CN106703070A - Construction method of roof photovoltaic strip foundation - Google Patents

Construction method of roof photovoltaic strip foundation Download PDF

Info

Publication number
CN106703070A
CN106703070A CN201611020380.0A CN201611020380A CN106703070A CN 106703070 A CN106703070 A CN 106703070A CN 201611020380 A CN201611020380 A CN 201611020380A CN 106703070 A CN106703070 A CN 106703070A
Authority
CN
China
Prior art keywords
template
concrete
construction
reinforcing bar
colligation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611020380.0A
Other languages
Chinese (zh)
Inventor
王晓压
杨世文
徐剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Engineering Co Of Power Construction Corp Of China
Original Assignee
Guizhou Engineering Co Of Power Construction Corp Of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Engineering Co Of Power Construction Corp Of China filed Critical Guizhou Engineering Co Of Power Construction Corp Of China
Priority to CN201611020380.0A priority Critical patent/CN106703070A/en
Publication of CN106703070A publication Critical patent/CN106703070A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention belongs to the field of building construction and particularly relates to a construction method of a roof photovoltaic strip foundation. The construction method of the roof photovoltaic strip foundation comprises the following steps: (1) preparing construction; (2) cleaning impurities on the roof; (3) surveying and setting out; (4) processing steel bars; (5) processing and mounting templates; (6) binding and checking the steel bars; (7) pouring concrete; and (8) curing the concrete and removing the templates.

Description

Roofing photovoltaic strip footing construction
Technical field
The invention belongs to the realm of building construction, and in particular to roofing photovoltaic strip footing construction.
Background technology
Photovoltaic foundation typically uses isolated footing and strip footing.It has been a maturation that strip footing is constructed on the ground Construction technology, but strip footing roofing construction appoint can so have the following disadvantages:1st, difficulty of construction is bigger, easily to room Face waterproof and structure sheaf are damaged, destroy it is serious even to lay waterproof layer again, this obviously to construction bring it is many not Just, it is also never to allow;2nd, construction procedure is cumbersome, and construction progress is slow;3rd, construction interference is more.
The content of the invention
Goal of the invention:The present invention makes improvement for the problem that above-mentioned prior art is present, i.e., the invention discloses roofing Photovoltaic strip footing construction.
Technical scheme:Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50~60m3/ h, part basis use people Work is poured, and is being poured simultaneously, and vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth The 2/3~3/4 of degree, speed is maintained at 12 beats/min, and when keeping vibrating for 4~5 seconds in concrete after insertion, vibrator must not be touched Template is hit, the fast theory inserted and pull out slowly should be observed, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Beneficial effect:Roofing photovoltaic strip footing construction disclosed by the invention has the advantages that:
By changing roofing photovoltaic base form, traditional independent shape basis is substituted with small-sized strip footing, solve biography System photovoltaic roof basis is uneven using the roofing load that isolated footing is brought, structure, waterproof layer destructible, and structure is not The shortcoming of stabilization, is not only improved in quality and roof structure stability, also reduces construction cost.
Carrying out photovoltaic roof construction using this engineering method makes the engineering time shorten 6 days;Skilled worker's saving of time 6X32=192 Man-hour, 192X180 units/man-hour=34560 yuan, general 6X8=48 man-hour of work saving of time, 48X150 units/man-hour=7200 yuan; Only labour cost just saves 41760 yuan of fund;Use strip footing instead also makes material used in construction (mixed instead of detached pier basis Solidifying soil, reinforcing bar, template) amount to 15000 yuan of reduction;Total makes cost reduce 55760 yuan.
Brief description of the drawings
Fig. 1 is the flow chart of roofing photovoltaic strip footing construction disclosed by the invention.
Specific embodiment:
Specific embodiment of the invention is described in detail below.
As shown in figure 1, roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50m3/ h, part basis are used and manually poured Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth The 2/3 of degree, speed is maintained at 12 beats/min, is kept when vibrating within 4 seconds in concrete after insertion, vibrator must not collision slab, should The slow theory pulled out is inserted in accordance with fast, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
The load that roofing can be transmitted superstructure using strip footing concrete, certain bottom surface is extended to by side Product, makes the compression for acting on substrate be equal to or less than the permitted bearing capacity of roofing, and the stress of basic internal should meet simultaneously Material intensity requirement in itself.
Roofing photovoltaic uses strip footing concrete, the pre-embedded steel slab in photovoltaic strip footing to increase supporting leg to solve The roof drainage gradient, it is ensured that photovoltaic panel is in same level.Roofing strip footing solves the buttress that traditional roof photovoltaic is used The discontinuity that isolated footing is brought, the shortcomings of local pressure is larger;Pre-embedded steel slab facilitates photovoltaic bracket to install on the basis of Shi Jinhang is welded.Thus unwrapping wire positioning in work progress to basis seems increasingly important.Additionally, the pendulum of strip footing concrete Put position and spacing also contributes to roofing stress.
Specific embodiment 2
Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 60m3/ h, part basis are used and manually poured Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth The 3/4 of degree, speed is maintained at 12 beats/min, is kept when vibrating within 5 seconds in concrete after insertion, vibrator must not collision slab, should The slow theory pulled out is inserted in accordance with fast, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Specific embodiment 3
Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 55m3/ h, part basis are used and manually poured Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth The 7/10 of degree, speed is maintained at 12 beats/min, and when keeping vibrating for 4.5 seconds in concrete after insertion, vibrator must not collide mould Plate, should observe the fast theory inserted and pull out slowly, and when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/ h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Embodiments of the present invention are elaborated above.But the present invention is not limited to above-mentioned implementation method, In the ken that art those of ordinary skill possesses, can also be done on the premise of present inventive concept is not departed from Go out various change.

Claims (3)

1. roofing photovoltaic strip footing construction, it is characterised in that comprise the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms that concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing meet Design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis position is indicated with red paint, And repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet design to steel bar meter at the scene It is required that;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and in mould The inner side brushing paraffin release agent of plate;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing and《Steel Muscle is welded and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50~60m3/ h, part basis are used and manually poured Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is total depth 2/3~3/4, speed is maintained at 12 beats/min, and when keeping vibrating for 4~5 seconds in concrete after insertion, vibrator must not collide mould Plate, should observe the fast theory inserted and pull out slowly, and when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/ h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, protected Warm moisture-keeping maintaining;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture state;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form is after intensity reaches 90% Form removal;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just followed and first torn open Non-bearing template, after tear the theory of bearing form open.
2. roofing photovoltaic strip footing construction according to claim 1, it is characterised in that setting base in step (3) Plinth absolute altitude is within 5mm.
3. roofing photovoltaic strip footing construction according to claim 1, it is characterised in that without conjunction in step (413) Lattice are demonstrate,proved and the reinforcing bar of report of dispatching from the factory forbids admission.
CN201611020380.0A 2016-11-17 2016-11-17 Construction method of roof photovoltaic strip foundation Pending CN106703070A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611020380.0A CN106703070A (en) 2016-11-17 2016-11-17 Construction method of roof photovoltaic strip foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611020380.0A CN106703070A (en) 2016-11-17 2016-11-17 Construction method of roof photovoltaic strip foundation

Publications (1)

Publication Number Publication Date
CN106703070A true CN106703070A (en) 2017-05-24

Family

ID=58940582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611020380.0A Pending CN106703070A (en) 2016-11-17 2016-11-17 Construction method of roof photovoltaic strip foundation

Country Status (1)

Country Link
CN (1) CN106703070A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109333799A (en) * 2018-11-09 2019-02-15 如皋汉府建筑科技有限公司 A kind of production technology of nonmetallic ore Tetramune
CN110687560A (en) * 2019-10-12 2020-01-14 中国电建集团贵州工程有限公司 Impeller combination rapid positioning method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006104770A (en) * 2004-10-05 2006-04-20 Hiroshi Ueno Installation implement for solar cell panel
CN202108169U (en) * 2011-05-26 2012-01-11 泰通(泰州)工业有限公司 Embedded roof structure with photovoltaic subassemblies
CN104264543A (en) * 2014-09-11 2015-01-07 北京铁五院工程机械有限公司 Method for constructing small-radius curve ballastless track
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure
CN104420478A (en) * 2013-08-22 2015-03-18 中国电力工程顾问集团华北电力设计院工程有限公司 Photovoltaic module support simple strip foundation structure in photovoltaic power station

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006104770A (en) * 2004-10-05 2006-04-20 Hiroshi Ueno Installation implement for solar cell panel
CN202108169U (en) * 2011-05-26 2012-01-11 泰通(泰州)工业有限公司 Embedded roof structure with photovoltaic subassemblies
CN104420478A (en) * 2013-08-22 2015-03-18 中国电力工程顾问集团华北电力设计院工程有限公司 Photovoltaic module support simple strip foundation structure in photovoltaic power station
CN104264543A (en) * 2014-09-11 2015-01-07 北京铁五院工程机械有限公司 Method for constructing small-radius curve ballastless track
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张原: "《土木工程施工(下册)》", 31 December 2008 *
杜日武: "《建筑施工技术》", 30 September 2014 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109333799A (en) * 2018-11-09 2019-02-15 如皋汉府建筑科技有限公司 A kind of production technology of nonmetallic ore Tetramune
CN110687560A (en) * 2019-10-12 2020-01-14 中国电建集团贵州工程有限公司 Impeller combination rapid positioning method

Similar Documents

Publication Publication Date Title
CN107989401B (en) Existing building outer wall reconstruction structure and construction method
CN101713237B (en) Construction method of large-volume original decorative large pier stud fair-faced concrete
CN103266767A (en) Construction method for preventing and treating cracks between concrete structure and filler wall
CN104846744A (en) Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN105484391A (en) Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks
CN104372890A (en) Construction method of bare concrete prefabricated box beam with complicated structure
CN101476382A (en) Construction method for large area concrete terrace angle steel corner protector dividing joint
CN103643603A (en) Ballastless track construction method with sleepers arranged firstly and rail panel assembled later
CN107882321A (en) Diameter Silo slding form operation engineering method
CN103821253A (en) Constructing technique for aerated concrete block filler wall
CN105666687A (en) Construction process for pre-stress reactive powder concrete box girder
CN102392549A (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN106368183B (en) Under horizontal steel-slag sand side sealing embedded part pour construction method for forming
CN104963289A (en) Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud
CN110396937A (en) The asynchronous construction of hollow thin-walled high pier binder pier beam
CN103603236A (en) Method for controlling cracks of double-block type ballastless track bed slabs
CN108532466A (en) A kind of bridge pier over-form construction technique
CN105442629B (en) A kind of large scale equipment T stage vibration isolation mounts construction
CN110093852A (en) Shaped form bridge pier Construction technology of fair-faced concrete
CN110952586A (en) Construction process for bearing platform below expressway
CN104894954A (en) Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge
CN106703070A (en) Construction method of roof photovoltaic strip foundation
CN110468638A (en) A kind of road bed board concreting and plastering technique
CN207829511U (en) A kind of existing building external wall reconstruction structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170524