CN106703056A - Method for connecting pipelines in underwater dry environment through utilizing steel-concrete connection well - Google Patents

Method for connecting pipelines in underwater dry environment through utilizing steel-concrete connection well Download PDF

Info

Publication number
CN106703056A
CN106703056A CN201611191691.3A CN201611191691A CN106703056A CN 106703056 A CN106703056 A CN 106703056A CN 201611191691 A CN201611191691 A CN 201611191691A CN 106703056 A CN106703056 A CN 106703056A
Authority
CN
China
Prior art keywords
double
layer plate
cuboid
pit shaft
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611191691.3A
Other languages
Chinese (zh)
Other versions
CN106703056B (en
Inventor
杨涛
李国洪
边江
黄峰
杨荔
王勇
沈文
魏斌
魏耀红
皮文强
徐雯婷
王雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central and Southern China Municipal Engineering Design and Research Institute Co Ltd filed Critical Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201611191691.3A priority Critical patent/CN106703056B/en
Publication of CN106703056A publication Critical patent/CN106703056A/en
Application granted granted Critical
Publication of CN106703056B publication Critical patent/CN106703056B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0069Welding

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a method for connecting pipelines in an underwater dry environment through utilizing a steel-concrete connection well. The method comprises the steps of S1, manufacturing a cuboid double-layer steel plate well shaft, and digging a foundation pit used for placing the cuboid double-layer steel plate well shaft underwater in the design position of the connection well; S2, conveying the manufactured cuboid double-layer steel plate well shaft to the foundation pit of the design connection well through flotation, and enabling the cuboid double-layer steel plate well shaft to sink in position; S3, backfilling the outer side of the cuboid double-layer steel plate well shaft in the foundation pit of the connection well to the design bottom elevation of immersed tubes; S4, cutting reserved vertical slots underwater, taking out the cut reserved vertical slots, enabling the immersed tubes to sink, and placing the vertical slots in home positions in the cuboid double-layer steel plate well shaft; and S5, pumping water in the connection well, and carrying out connection, pressing and backfilling on the immersed tubes. The method has the advantages that through the utilization of the method, the problem that the pipelines cannot be connected in the dry environment underwater is solved, and the problems that the supporting difficulty is high and the water sealing effect is poor due to the facts that the occupied water area of underwater immersed tube connection is large, time is long, and the surrounding environment and geology affect connection are solved.

Description

One kind connects well and carries out pipeline connection in dry environment under water using steel-concrete Engineering method
Technical field
It is specifically a kind of to be done under water using steel-concrete connection well the present invention relates to municipal works technical field The engineering method of pipeline connection is carried out in dry environment.
Background technology
According to country《Water prevention and cure of pollution action plan》Requirement, various regions are increasing water environment treatment, regional water supply etc. The building-up work of aspect, part engineering is related to immersed tube pipe's crossing of river, river, lake, but is usually present that the water surface is broad, and difficulty of construction is big Problem, and the safety of dykes and dams will also protect, and some pipelines need to be welded to connect in the following dry environment of the water surface.Therefore A kind of new engineering method is needed to be constructed.
At present, buried cross river pipeline typically excavates the modes such as pipe laying using push pipe, immersed tube or cofferdam.It is larger to the depth of water, have River, river, lake that navigation is required etc., should not excavate pipe laying using cofferdam.By surrounding enviroment condition, the requirement of dykes and dams, geological conditions Limitation, pressure pipeline need to be welded to connect below the water surface;At present, the method for being connected in dry environment under water is mainly adopted With method excavation constructions such as cofferdam, steel sheet pile supportings, greatly, the time is long for the method occupancy water surface area, has to environment and flood control Influence.
The content of the invention
In order to solve above-mentioned technological deficiency, present invention design is a kind of to connect well dry environment under water using steel-concrete In carry out the engineering method of pipeline connection, to solve to take, water area is big, the time is long, the problems such as influence environment is with flood control, while also gram Taken because the influence of surrounding enviroment, geological conditions etc. and caused by supporting difficulty it is big, the problem of water-stagnating effect difference.
One of the object of the invention is to provide and a kind of connect well using steel-concrete and carry out pipeline in dry environment under water The engineering method of connection, comprises the following steps:
S1, making cuboid double-layer plate pit shaft;Simultaneously in the design attitude of connection well, it is double that underwater excavation places cuboid The connection well foundation ditch a of layer steel plate pit shaft;
S2, cuboid double-layer plate pit shaft transportation by driving to the design that will be made connected and sink at well foundation ditch a, in place;Again in length Concrete perfusion b carries out back cover in cube double-layer plate pit shaft, and is filled in the second accommodating cavity of cuboid double-layer plate pit shaft Note concrete b, to form steel-concrete connection well;
S3, will be backfilled at immersed tube c designs bottom absolute altitude d in cuboid double-layer plate pit shaft outside in connection well foundation ditch a, and look for It is flat, to meet Immersed tunnel requirement;
S4, reserved vertical slot is cut and taken out under water, carried out the sinking of immersed tube c, the vertical slot that then will be taken out Frid bottom be cut into immersed tube c size identical semicircle e, then the vertical slot after cutting is positioned over cuboid double-layer plate pit shaft Interior original position so that immersed tube c is sticked in vertical slot bottom semicircular e, finally the concrete perfusion b in vertical slot;
S5, the water drained in connection well, then carry out being welded to connect of immersed tube c, pressure pipe and backfill.
The two of the object of the invention are to provide a kind of cuboid double-layer plate pit shaft, including:Two piece of first double-layer plate, two pieces Second double-layer plate, first double-layer plate is vertically arranged with second double-layer plate, per adjacent two pieces described first pair The second double-layer plate described in one is welded between layer steel plate so that two pieces of first double-layer plates, two pieces of second bilayers Steel plate collectively forms a cuboid double-layer plate pit shaft with the first accommodating cavity.
Wherein, the vertical slot being made up of steel plate is provided with second double-layer plate, the sinking for realizing immersed tube.
One kind connects well and carries out the engineering method of pipeline connection in dry environment under water using steel-concrete, and its advantage is: Solve the problems, such as that the following pipeline of the water surface cannot be attached in dry environment using steel-concrete connection well, reduce under water Immersed tube connection takes that water area is big, the time is long, and because the influence of surrounding enviroment, geology etc. and caused by supporting difficulty is big, sealing The problem of effect difference;
Furthermore, the structure design of vertical slot in the cuboid double-layer plate pit shaft used in the above method so that this method Environmental protection, flood control, it is feasible, effective.
Brief description of the drawings
Fig. 1 is steel of the invention-concrete connection well floor plan;
Fig. 2 is steel of the invention-concrete connection well profile figure;
Fig. 3 is the profile after steel of the invention-concrete connection well transportation by driving to design attitude;
Fig. 4 is the profile after steel of the invention-concrete connection well back cover, the backfill of well week and vertical slot cutting;
After Fig. 5 is steel of the invention-concrete connection well immersed tube sinking, vertical slot frid and steel plate pit shaft ectonexine steel plate Profile after welding;
Fig. 6 is to be drawn water in steel of the invention-concrete connection well well and be welded to connect two sections of immersed tube, carries out feature After pass the test, backfill cobble or rubble in well, the outer backfill of well, and the profile after the cutting of well top will be connected;
Wherein:
1st, the first double-layer plate, 11, outside plate, 12, inner side steel plate, 13, support angle steel, the 14, second accommodating cavity, 15, Second support column,
2nd, the second double-layer plate, the 3, first accommodating cavity, the 4, first support column, 5, vertical slot, 51, steel plate,
A, connection well foundation ditch, b, concrete, c, immersed tube, d, bottom absolute altitude, e, semicircle.
Specific embodiment
One kind is using the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment, including following step Suddenly:
S1, making cuboid double-layer plate pit shaft;Simultaneously in the design attitude of connection well, it is double that underwater excavation places cuboid The connection well foundation ditch a of layer steel plate pit shaft;
Preferably, in step S1, the design of cuboid double-layer plate pit shaft is risen higher than the water at design connection well foundation ditch a Position;
Preferably, in step S1, the vertical slot 5 of immersed tube c sinkings, and vertical slot 5 are reserved in the cuboid upper strata steel plate pit shaft Bottom is semicircle;
Preferably, in step S1, the bottom of the vertical slot 5 and side are constituted with steel plate so that the vertical slot 5 is double with cuboid Other parts isolation in layer steel plate pit shaft.
Preferably, in step S1, by the long-armed digging machine of boat-carrying or dredger excavation pit.
S2, cuboid double-layer plate pit shaft transportation by driving to the design that will be made connected and sink at well foundation ditch a, in place;Again in length Concrete perfusion b carries out back cover in cube double-layer plate pit shaft, and in the second accommodating cavity 14 of cuboid double-layer plate pit shaft Concrete perfusion b, to form steel-concrete connection well;
Preferably, in step S2, the interior not concrete perfusion of reserved vertical slot 5.
S3, will be backfilled at immersed tube c designs bottom absolute altitude d in cuboid double-layer plate pit shaft outside in connection well foundation ditch a, and look for It is flat, to meet Immersed tunnel requirement;
S4, reserved vertical slot 5 is cut and taken out under water, carried out the sinking of immersed tube c, the vertical slot that then will be taken out 5 frid bottoms be cut into immersed tube c size identical semicircle e, then the vertical slot 5 after cutting is positioned over cuboid double-layer plate well Original position in cylinder so that immersed tube c is sticked in the bottom semicircular e of vertical slot 5, finally the concrete perfusion b in vertical slot 5;
S5, the water drained in connection well, then carry out being welded to connect of immersed tube c, pressure pipe and backfill;
Preferably, in step S5, block immersed tube with doughnut-shaped steel plate and ring-shaped rubber pad and be connected connector institute shape on the outside of well Into space after, then drawn water;
Preferably, in step S5, the immersed tube c to connecting carries out functional trial, it is qualified after will connection well foundation ditch a it is inside and outside Backfill, and steel-concrete connection well on riverbed top and is met and partly carry out imderwater cutting, take below the riverbed of navigation channel requirement Go out, meet navigation and require, recover river bed original appearance.
According to Fig. 1, Fig. 2:Cuboid double-layer plate pit shaft, including:Two piece of first double-layer plate 1, two pieces second pair Layer steel plate 2, first double-layer plate 1 is vertically arranged with second double-layer plate 2, per adjacent two blocks first clad steels The second double-layer plate 2 described in one is welded between plate 1 so that two pieces of first double-layer plates, 1, two blocks of second clad steels Plate 2 collectively forms a cuboid double-layer plate pit shaft with the first accommodating cavity 3.
Preferably, the first support column of many of horizontally set 4 in the accommodating cavity 3 (specific radical as needed depending on);
Preferably, first double-layer plate 1 includes outside plate 11, inner side steel plate 12, at least one support angle steel 13, The outside plate 11 is connected by the support angle steel 13 with the inner side steel plate 12 so that the outside plate 11, inner side Steel plate 12 constitutes second accommodating cavity 14 of band, for the perfusion of concrete.
Further, first double-layer plate 1 also includes at least one second support column 15, for strengthening the outside Steel plate 11 is connected with the inner side steel plate 12.
Further, second double-layer plate 2 is identical with the structure of the first double-layer plate 1;
Preferably, it is provided with the vertical slot being made up of steel plate 51 in first double-layer plate 1 or second double-layer plate 2 5, the sinking for realizing immersed tube;Further, the bottom of the vertical slot 5 is semicircle, for the installation of immersed tube.
Specific embodiment is described further to invention below;
S1、
S11, the beach making cuboid double-layer plate pit shaft near immersed tube pipe's crossing of river, river, Hu Chu, concretely comprise the following steps: First double-layer plate 1 is welded to connect with the second double-layer plate 2, is allowed to enclose as a cuboid with the first accommodating cavity 3 is double-deck Steel plate pit shaft;Meanwhile, the first support column of many of horizontally set 4 (specific radical as needed depending on) in the first accommodating cavity 3, and Along the vertically arranged vertical slot 5 being made up of steel plate of cuboid double-layer plate pit shaft, and the bottom of vertical slot 5 is set to semicircle;
S12, excavated by the long-armed digging machine of boat-carrying or dredger underwater in riverbed bottom and place cuboid double-layer plate pit shaft Connection well foundation ditch a;
S13, step S11 design cuboid double-layer plate pit shaft are risen higher than the water at step S12 connections well foundation ditch a Position.
Sink at S2, the cuboid double-layer plate pit shaft transportation by driving that will be made to the foundation ditch a for designing connection well, (such as Fig. 3 in place It is shown);Concrete perfusion b carries out back cover in cuboid double-layer plate pit shaft again, and to the of cuboid double-layer plate pit shaft Concrete perfusion b in two accommodating cavities 14, to form steel-concrete connection well;And in step S2, do not irrigated in reserved vertical slot 5 Concrete;
S3, cuboid double-layer plate pit shaft outside is backfilled to immersed tube c design bottom absolute altitudes d places (as shown in Figure 4), and use Rubble is backfilled, and levelling, to meet Immersed tunnel requirement;
S4, reserved vertical slot 5 is cut and taken out (as shown in Figure 5) under water, carried out the sinking of immersed tube c, then By the frid bottom of vertical slot 5 of taking-up be cut into immersed tube c size identical semicircle e, then the vertical slot 5 after cutting is positioned over steel plate Original position in pit shaft, and outside plate with the second double-layer plate, inner side steel plate be respectively welded and be connected that (now vertical slot is arranged at institute State the second double-layer plate) so that immersed tube c is sticked in the bottom semicircular e of the vertical slot 5, finally the concrete perfusion b in vertical slot 5; (as shown in Figure 5)
S5, immersed tube is blocked with doughnut-shaped steel plate and ring-shaped rubber pad and the space that connector on the outside of well is formed is connected, drained Water in connection well, then carry out being welded to connect (such as Fig. 6) for two sections of immersed tube c;Immersed tube c to connecting carries out functional trial, closes The inside and outside backfills of a of well foundation ditch will be connected after lattice, and by steel-concrete connection well is on riverbed top and meets the riverbed that navigation channel requires Following part carries out imderwater cutting, takes out, and meets navigation and requires, recovers river bed original appearance.
The foregoing is only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all it is of the invention spirit and Within principle, any modification, equivalent substitution and improvements made etc. should be included within the scope of the present invention.

Claims (10)

1. a kind of using the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment, it is characterised in that: Comprise the following steps
S1, making cuboid double-layer plate pit shaft;Simultaneously in the design attitude of connection well, underwater excavation places cuboid clad steel The connection well foundation ditch a of plate pit shaft;
S2, cuboid double-layer plate pit shaft transportation by driving to the design that will be made connected and sink at well foundation ditch a, in place;Again in cuboid Concrete perfusion b carries out back cover in double-layer plate pit shaft, and to filling in second accommodating cavity (14) of cuboid double-layer plate pit shaft Note concrete b, to form steel-concrete connection well;
S3, will be backfilled at immersed tube c designs bottom absolute altitude d in cuboid double-layer plate pit shaft outside in connection well foundation ditch a, and it is levelling, To meet Immersed tunnel requirement;
S4, reserved vertical slot (5) is cut and taken out under water, carried out the sinking of immersed tube c, the vertical slot that then will be taken out (5) frid bottom be cut into immersed tube c size identical semicircle e, then the vertical slot (5) after cutting is positioned over cuboid clad steel Original position in plate pit shaft so that immersed tube c is sticked in vertical slot (5) bottom semicircular e, finally in the interior concrete perfusion b of vertical slot (5);
S5, the water drained in connection well, then carry out being welded to connect of immersed tube c, pressure pipe and backfill.
2. engineering method according to claim 1, it is characterised in that:In step S1, the design of cuboid double-layer plate pit shaft is risen Higher than the water level at design connection well foundation ditch a.
3. engineering method according to claim 1, it is characterised in that:In step S1, reserved in the cuboid upper strata steel plate pit shaft The vertical slot (5) of immersed tube c sinkings, and vertical slot (5) bottom is semicircle.
4. engineering method according to claim 1, it is characterised in that:In step S2, the interior not concrete perfusion of reserved vertical slot (5).
5. engineering method according to claim 1, it is characterised in that:In step S5, it is heavy to be blocked with doughnut-shaped steel plate and ring-shaped rubber pad Pipe be connected the space that connector on the outside of well is formed after, then drawn water.
6. engineering method according to claim 1, it is characterised in that:In step S5, the immersed tube c to connecting carries out functional trial, The inside and outside backfills of a of well foundation ditch will be connected after qualified, and by steel-concrete connection well is on riverbed top and meets the river that navigation channel requires Bed is following partly to carry out imderwater cutting, takes out, and meets navigation and requires, recovers river bed original appearance.
7. the cuboid double-layer plate pit shaft in any engineering method of claim 1 to 6, it is characterised in that:Including two pieces First double-layer plate (1), two piece of second double-layer plate (2), first double-layer plate (1) and second double-layer plate (2) It is vertically arranged, is welded with the second double-layer plate (2) described between every adjacent two pieces first double-layer plates (1) so that two The first double-layer plate (1), two pieces of second double-layer plates (2) collectively form one with the rectangular of the first accommodating cavity (3) described in block Body double-layer plate pit shaft;
Wherein:The vertical slot being made up of steel plate 51 is provided with first double-layer plate (1) or second double-layer plate (2) (5), for realizing the sinking of immersed tube.
8. cuboid double-layer plate pit shaft according to claim 7, it is characterised in that:Vertical slot (5) bottom is semicircle, For the installation of immersed tube.
9. cuboid double-layer plate pit shaft according to claim 7, it is characterised in that:First double-layer plate (1) includes Outside plate (11), inner side steel plate (12), at least one support angle steel (13), the outside plate (11) is by the strut angle Steel (13) is connected with the inner side steel plate (12) so that the outside plate (11), inner side steel plate (12) constitute a band second and hold Chamber (14) is put, for the perfusion of concrete.
10. cuboid double-layer plate pit shaft according to claim 7, it is characterised in that:Second double-layer plate (2) and institute State the first double-layer plate (1) structure, pattern identical.
CN201611191691.3A 2016-12-21 2016-12-21 It is a kind of to utilize the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment Active CN106703056B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611191691.3A CN106703056B (en) 2016-12-21 2016-12-21 It is a kind of to utilize the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611191691.3A CN106703056B (en) 2016-12-21 2016-12-21 It is a kind of to utilize the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment

Publications (2)

Publication Number Publication Date
CN106703056A true CN106703056A (en) 2017-05-24
CN106703056B CN106703056B (en) 2019-04-19

Family

ID=58938772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611191691.3A Active CN106703056B (en) 2016-12-21 2016-12-21 It is a kind of to utilize the engineering method that pipeline connection is carried out in steel-concrete connection well under water dry environment

Country Status (1)

Country Link
CN (1) CN106703056B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1018229A (en) * 1996-06-28 1998-01-20 Fujita Corp Cofferdam construction method of existing underwater structure
CN102604000A (en) * 2012-03-26 2012-07-25 华东理工大学华昌聚合物有限公司 Synthetic method and application of epoxy vinyl ester resin with high bromine content
CN202359566U (en) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 Cofferdam for deep-water soft soil foundation construction of bridge
CN103741725A (en) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 Immersed tunnel final joint and shoreside dry-work construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1018229A (en) * 1996-06-28 1998-01-20 Fujita Corp Cofferdam construction method of existing underwater structure
CN202359566U (en) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 Cofferdam for deep-water soft soil foundation construction of bridge
CN102604000A (en) * 2012-03-26 2012-07-25 华东理工大学华昌聚合物有限公司 Synthetic method and application of epoxy vinyl ester resin with high bromine content
CN103741725A (en) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 Immersed tunnel final joint and shoreside dry-work construction method thereof

Also Published As

Publication number Publication date
CN106703056B (en) 2019-04-19

Similar Documents

Publication Publication Date Title
CN1837512B (en) Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN102345300A (en) Construction method of underground structures of seacoasts and artificial islands
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN104234056A (en) Construction method for preventing deformation of utility tunnel at high-water-level liquefaction region
CN104762982B (en) The construction method that a kind of rich water red sandstone geology level of ground water controls
CN105220703A (en) A kind of sand flat enclosure-type deep water construction method under weighing apparatus method condition based on returning
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN203429664U (en) Grout blocking and locking device of immersed tube section grouting foundation
CN104929142A (en) Combined cofferdam structure and building construction method thereof
CN114482099A (en) Steel sheet pile cofferdam construction method
JP4979228B2 (en) Additional construction method of impermeable layer
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN107761668B (en) Coastal shore reservoir land-building type revetment structure and construction method thereof
CN107190709B (en) Method for building river channel in newly dredged soil reclamation land-enclosed area
CN103898915A (en) Anti-floating and waterstop construction method for small-area deep foundation pit of building
CN104727325B (en) A kind of method of construction of polder sea wall
CN104612128B (en) Vacuum preloading reinforcement construction method applicable to underwater silt environment
CN110939150A (en) Emergency rescue method for rapidly constructing large-hydraulic-slope-drop-ratio thin-wall structure in confined water inrush accident state
CN105484229A (en) Overlying mud layer seal vacuum pre-pressing method suitable for water area soft foundation
CN106703056A (en) Method for connecting pipelines in underwater dry environment through utilizing steel-concrete connection well
CN107587484B (en) Panel rock-fill dam with toe board under small stress
CN204780965U (en) Complicated geology and existing system construction structures that struts of environment access subway
CN217710783U (en) Occupy full section cofferdam of river course structure and break stream structure not
CN216407913U (en) Water taking pipe jacking structure crossing near-river railway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant