CN107761668B - Coastal shore reservoir land-building type revetment structure and construction method thereof - Google Patents
Coastal shore reservoir land-building type revetment structure and construction method thereof Download PDFInfo
- Publication number
- CN107761668B CN107761668B CN201710979077.1A CN201710979077A CN107761668B CN 107761668 B CN107761668 B CN 107761668B CN 201710979077 A CN201710979077 A CN 201710979077A CN 107761668 B CN107761668 B CN 107761668B
- Authority
- CN
- China
- Prior art keywords
- slope
- layer
- filling layer
- filling
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/12—Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
本发明提供了一种滨海滨库造地型护岸结构,包括沿护岸基础坡面设置的填土界面台阶、覆盖在该填土界面台阶上的透水填土层、覆盖在所述透水填土层上的不透水填土层;所述不透水填土层沿护岸基础坡面自下而上设置成多级台阶结构,在每级不透水填土层台阶的整个底部也设置有透水填土层;所述透水填土层和所述不透水填土层之间均设置有防渗土工布;所述透水填土层由砂砾石填筑而成,所述不透水填土层由粘性土体分层填筑而成。本发明形成一个保障滨海滨库岸坡稳定并同时新增土地的填土结构,有效保护滨海滨库地带地质环境,促进岸坡土地资源开发利用。
The invention provides a revetment structure of coastal waterfront reservoir building type, comprising a soil filling interface step arranged along the slope of a bank protection foundation, a permeable soil filling layer covering the filling interface step, and a permeable soil filling layer covering the permeable soil layer. The impervious filling layer on the top of the water-proof filling layer; the impermeable filling layer is arranged in a multi-step structure from bottom to top along the slope of the bank protection foundation, and a permeable filling layer is also arranged at the entire bottom of the steps of each impervious filling layer. between the permeable soil filling layer and the impermeable soil filling layer are provided with anti-seepage geotextiles; the permeable soil filling layer is filled with sand and gravel, and the impermeable soil filling layer is made of cohesive soil Layered filling. The invention forms a filling structure that ensures the stability of the bank slope of the coastal reservoir and simultaneously increases the land, effectively protects the geological environment of the coastal reservoir area, and promotes the development and utilization of land resources on the bank slope.
Description
技术领域technical field
本发明涉及滨海滨库的护岸设计及建造领域,具体为一种滨海滨库造地型护岸结构及其建筑方法。The invention relates to the field of bank protection design and construction of a coastal waterfront silo, in particular to a land-building type revetment structure and a construction method thereof.
背景技术Background technique
近三十年来,为了大力开发水电资源,兼顾防洪需求与区域性水资源调配,兴建了大量大型及特大型水库。据不完全统计,80~90%的水库滑坡与库水活动有关,岸坡破坏既与岸坡物质结构有关,又与水库海洋水位变化有关。据初步统计,我国滨海滨库聚集着大量城集镇,如三峡库区有巴东、秭归、宜昌、巫山、奉节、开州、云阳、万州、忠县、丰都等60余个城集镇位于滨库地带,居民数量超过1000万人。作为地质灾害高发区,滨海滨库城市的基础建设和岸坡地质灾害治理必须高度融合、协调发展。In the past 30 years, in order to vigorously develop hydropower resources, taking into account the needs of flood control and regional water resources allocation, a large number of large and extra-large reservoirs have been built. According to incomplete statistics, 80-90% of reservoir landslides are related to reservoir water activities, and bank slope damage is not only related to the material structure of the bank slope, but also to changes in the ocean water level of the reservoir. According to preliminary statistics, there are a large number of urban market towns in the coastal reservoirs in my country. For example, there are more than 60 urban market towns in Badong, Zigui, Yichang, Wushan, Fengjie, Kaizhou, Yunyang, Wanzhou, Zhongxian and Fengdu in the Three Gorges Reservoir area. The Binku area has more than 10 million inhabitants. As a high-incidence area of geological disasters, the infrastructure construction and the management of geological disasters on the bank slope must be highly integrated and developed in a coordinated manner.
坡式护岸结构是将建筑材料或构件直接铺护在堤防或滩岸临水坡面,形成连续的覆盖层,防止水流、风浪的侵蚀、冲刷。这种防护形式顺水流方向布置,对水流的影响较小,也不影响航运,因此被广泛采用。中国长江中下游河势比较稳定,在水深流急处、险要堤段、重要城市、港埠码头广泛采用坡式护岸。然而现有技术中的坡式护岸结构为了控制河势和滨海滨库的防洪安全,着力于运用块石、混凝土等硬质材料的结构设计从而导致护岸硬化现象严重,硬化的护岸结构破坏了河床与河岸生态系统的联系,割断了水域中的生物、微生物与陆域的接触,同时,硬化型河岸使得水生植物无法生长,严重影响滨海滨库的生态系统;另外,常规的硬质护岸结构还可能造成冲刷与侵蚀问题的转移,减弱滨海河流削减流水能量的能力,对下游造成更严重的侵蚀。The slope type bank protection structure is to directly protect the building materials or components on the embankment or the water-facing slope of the beach to form a continuous covering layer to prevent the erosion and scouring of water flow, wind and waves. This form of protection is arranged in the direction of the water flow, which has less impact on the water flow and does not affect shipping, so it is widely used. The rivers in the middle and lower reaches of the Yangtze River in China are relatively stable, and slope-type revetments are widely used in places with deep water and rapid currents, dangerous embankment sections, important cities, and ports and wharves. However, in order to control the river situation and the flood control safety of the coastal reservoir, the slope-type revetment structure in the prior art focuses on the structural design of hard materials such as block stone and concrete, which leads to a serious phenomenon of hardening of the revetment. The hardened revetment structure damages the river bed. The connection with the riparian ecosystem cuts off the contact between organisms and microorganisms in the water and the land. At the same time, the hardened riparian makes the aquatic plants unable to grow, which seriously affects the ecosystem of the coastal reservoir; in addition, the conventional hard revetment structure also May cause diversion of scour and erosion problems, reduce the ability of coastal rivers to reduce the energy of running water, and cause more severe erosion downstream.
以工程治理区域岸坡稳定安全为目标,从地质灾害治理角度进行岸坡防护工程设计施工是国内外岸坡地质灾害防治目前唯一的技术路径,但治理工程导致不能满足治理区域土地资源开发利用,甚至为后续城市基础设施建设带来诸多不利因素。换言之,滨海滨库岸坡地质灾害治理与土地资源开发利用一体化具有重要实用意义。Aiming at the stability and safety of the bank slope in the engineering control area, the design and construction of the bank slope protection project from the perspective of geological disaster control is the only technical path for the prevention and control of the bank slope geological disaster at home and abroad. It even brings many unfavorable factors to the subsequent urban infrastructure construction. In other words, the integration of geological hazard management and land resource development and utilization on the bank slope of the coastal reservoir has important practical significance.
发明内容SUMMARY OF THE INVENTION
针对现有技术中的缺陷,本发明提供一种滨海滨库造地型护岸结构及其建筑方法以形成一个保障滨海滨库岸坡稳定并产生面积为“B×护岸工程长度”新增土地的填土结构。Aiming at the defects in the prior art, the present invention provides a shore-side reservoir building-type revetment structure and a construction method thereof, so as to ensure the stability of the bank slope of the shore-side reservoir and generate new land with an area of "B×the length of the revetment project". fill structure.
为实现上述目的本发明提供一种滨海滨库造地型护岸结构,其关键在于:包括沿护岸基础坡面设置的填土界面台阶、覆盖在该填土界面台阶上的透水填土层、覆盖在所述透水填土层上的不透水填土层;所述不透水填土层沿护岸基础坡面自下而上设置成多级台阶结构,在每级不透水填土层台阶的整个底部也设置有透水填土层;所述透水填土层和所述不透水填土层之间均设置有防渗土工布;所述透水填土层由砂砾石填筑而成,所述不透水填土层由粘性土体分层填筑而成。In order to achieve the above-mentioned purpose, the present invention provides a revetment structure of coastal waterfront reservoir building type, the key of which is that it includes a filling interface step arranged along the slope of the bank protection foundation, a permeable filling layer covering the filling interface step, and a covering layer. The impermeable fill layer on the permeable fill layer; the impermeable fill layer is arranged in a multi-step structure from bottom to top along the slope of the bank protection foundation, and the entire bottom of the steps of each impermeable fill layer is at the bottom A permeable soil filling layer is also provided; an anti-seepage geotextile is provided between the permeable soil filling layer and the impermeable soil filling layer; the permeable soil filling layer is filled with sand and gravel, and the impermeable soil filling layer is The filling layer is made up of layers of cohesive soil.
进一步的,所述填土界面台阶坡面角θ为30°,台阶平盘宽度为100cm,在所述填土界面台阶坡面上设置有排水孔,所述排水孔与所述台阶坡底线的夹角为10°~30°。Further, the slope angle θ of the step slope of the filling interface is 30°, the width of the step plate is 100cm, and a drainage hole is provided on the step slope of the filling interface, and the drainage hole and the bottom line of the step slope are separated. The included angle is 10°~30°.
进一步的,所述透水填土层由砂砾石填筑压实而成,压实度不小于85%。Further, the permeable soil filling layer is formed by filling and compacting with sand and gravel, and the compaction degree is not less than 85%.
进一步的,所述不透水填土层由粘性土体分层填筑压实而成,分层厚度为20-30cm,压实度不小于85%。Further, the impervious filling layer is formed by layering and compacting of cohesive soil, the layered thickness is 20-30 cm, and the compaction degree is not less than 85%.
进一步的,所述不透水填土层台阶高度h为300-500cm,台阶平盘宽度a为200cm,沿护岸基础坡面自下而上最后一级台阶的上部平盘宽度B为300-600cm。Further, the step height h of the impermeable filling layer is 300-500cm, the width a of the step plate is 200cm, and the upper plate width B of the last step from bottom to top along the revetment foundation slope is 300-600cm.
进一步的,每级不透水填土层台阶底部的透水填土层厚度为30-50cm。Further, the thickness of the permeable soil layer at the bottom of the steps of each impermeable soil layer is 30-50cm.
进一步的,还包括锚固系统,所述锚固系统包括锚杆和锚杆格钩,在所述护岸基础坡面下部的不透水填土层台阶坡面上固定有所述锚杆,该锚杆锚固在岸坡土体中;所述锚杆格钩钩挂在不透水填土层台阶坡面形成锚杆与不透水填土层台阶坡面的稳固连接。Further, an anchoring system is also included. The anchoring system includes an anchor rod and an anchor rod lattice hook. In the bank slope soil body; the anchor rod lattice hook is hung on the stepped slope surface of the impermeable filling layer to form a stable connection between the anchor rod and the stepped slope surface of the impermeable filling soil layer.
本发明的另一目的在于提供一种建筑滨海滨库造地型护岸结构的方法,其关键在于,包括步骤:Another object of the present invention is to provide a method for building a waterfront bank revetment structure, the key of which is to include the steps:
a、根据滨海滨库地质、地貌条件确定护岸结构的建筑部位;a. Determine the building position of the bank protection structure according to the geological and geomorphological conditions of the coastal reservoir;
b、在建筑部位沿护岸基础坡面开挖填土界面台阶,在该台阶坡面上设置排水孔,在所述填土界面台阶覆盖透水填土层,所述透水填土层采用砂砾石按照国家相关技术标准填筑压实、压实度不小于85%;b. Excavate a soil-fill interface step along the slope of the bank protection foundation at the building site, set drainage holes on the slope of the step, and cover the permeable soil fill layer on the soil-fill interface step, and the permeable soil layer is made of sand and gravel according to the The relevant national technical standards are filled with compaction, and the compaction degree is not less than 85%;
c、在所述透水填土层表面铺设防渗土工布,防渗土工布上填筑不透水填土层,该不透水填土层采用粘性土体分层填筑而成,沿护岸基础坡面自下而上设置成台阶结构,并且在每级不透水填土层台阶的整个底部也设置透水填土层;c. Lay anti-seepage geotextiles on the surface of the permeable soil layer, and fill the impermeable soil layers on the anti-seepage geotextiles. The surface is set into a step structure from bottom to top, and a permeable fill layer is also set at the entire bottom of the steps of each impervious fill layer;
d、在护岸基础坡面下部的不透水填土层坡面上设置锚固系统将不透水填土层锚固。d. An anchoring system is installed on the slope of the impervious fill layer at the lower part of the slope of the bank protection foundation to anchor the impermeable fill layer.
基于上述技术方案,本发明的优点是:Based on the above technical solutions, the advantages of the present invention are:
本发明由填土界面台阶、透水填土层、不透水填土层、锚固系统组成,形成一个保障滨海滨库岸坡稳定并同时产生面积为“B×护岸工程长度”新增土地的填土结构。该发明设置填土界面台阶并在该台阶坡面设置排水孔,在填土界面台阶开挖区覆盖透水填土层,所述透水填土层采用砂砾石将填土界面台阶开挖区回填压实,解决了造地型填土结构与岸坡原始坡面之间粘结强度低的难题,将造地型的填土体设置成透水填土层和不透水填土层,并且透水填土层回填覆盖在所述界面台阶上,解决了库水位降落过程中岸坡同步排水问题,消除了地下水渗透作用对填土结构稳定性的不利影响,而在护岸基础坡面下部的不透水填土层坡面上设置锚固系统将不透水填土层锚固,解决了填土岸坡的整体稳定问题。The present invention is composed of a soil filling interface step, a permeable soil filling layer, an impermeable soil filling layer, and an anchoring system, and forms a filling soil that guarantees the stability of the bank slope of the coastal waterfront reservoir and at the same time generates new land with an area of "B × the length of the bank protection project". structure. In the invention, a soil filling interface step is arranged and drainage holes are arranged on the slope surface of the step, and a permeable soil filling layer is covered in the step excavation area of the filling soil interface. It solves the problem of low bonding strength between the land-forming fill structure and the original slope surface of the bank slope. The backfill is covered on the interface steps, which solves the problem of synchronous drainage of the bank slope in the process of the reservoir water level falling, and eliminates the adverse effect of groundwater infiltration on the stability of the fill structure. An anchoring system is set on the layer slope to anchor the impervious fill layer, which solves the overall stability of the fill bank slope.
本发明提供了一种既能保障滨海滨库岸坡稳定,又能新增土地的填土结构。与传统护岸结构相比,本发明不但能有效保护滨海滨库岸坡稳定,而且能很好地保护滨海滨库地质环境,促进岸坡土地资源的开发利用。The invention provides a filling structure which can not only ensure the stability of the bank slope of the coastal reservoir, but also increase the land. Compared with the traditional bank protection structure, the invention can not only effectively protect the stability of the bank slope of the coastal reservoir, but also can well protect the geological environment of the coastal reservoir and promote the development and utilization of land resources on the bank slope.
附图说明Description of drawings
为了更清楚地说明本发明具体实施方式中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍。在所有附图中,类似的元件或部分一般由类似的附图标记标识。附图中,各元件或部分并不一定按照实际的比例绘制。In order to illustrate the technical solutions in the specific embodiments of the present invention more clearly, the following will briefly introduce the accompanying drawings that are required to be used in the specific embodiments or the description of the prior art. Similar elements or parts are generally identified by similar reference numerals throughout the drawings. In the drawings, each element or section is not necessarily drawn to actual scale.
图1为本发明的结构示意图;Fig. 1 is the structural representation of the present invention;
附图中:1-岸坡土体;2-护岸基础坡面;3-岸坡潜在破坏面;4-填土界面台阶;5-排水孔;6-不透水填土层;7-透水填土层;8-传统护岸坡线;9-锚杆格钩;10-锚杆;11-防渗土工布;12-低水位;13-高水位。In the attached drawings: 1-bank slope soil; 2-bank protection foundation slope; 3-potential damage surface of bank slope; 4-fill interface step; 5-drainage hole; 6-impervious filling layer; 7-permeable filling Soil layer; 8-traditional bank protection slope line; 9-anchor rod grid hook; 10-anchor rod; 11-impermeable geotextile; 12-low water level; 13-high water level.
具体实施方式Detailed ways
下面结合附图对本发明的实施例作进一步详细说明。The embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.
在本实施例中,术语“上”“下”“左”“右”“前”“后”“上端”“下端”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造或操作,因此不能理解为对本发明的限制。In this embodiment, the azimuth or positional relationship indicated by the terms "upper", "bottom", "left", "right", "front", "rear", "upper end", "lower end", etc. are based on the azimuth or positional relationship shown in the accompanying drawings, It is only for the convenience of description, rather than indicating or implying that the referred device or element must have a particular orientation, be constructed or operate in a particular orientation, and therefore should not be construed as a limitation of the present invention.
实施例1Example 1
如图1所示,本发明提供一种滨海滨库造地型护岸结构,包括沿护岸基础坡面2设置的填土界面台阶4、覆盖在该填土界面台阶4上的透水填土层7、覆盖在所述透水填土层7上的不透水填土层6;所述不透水填土层6沿护岸基础坡面2自下而上设置成多级台阶结构,在每级不透水填土层台阶的整个底部也设置有透水填土层7;所述透水填土层和所述不透水填土层之间均设置有防渗土工布11;所述透水填土层7由砂砾石填筑而成,所述不透水填土层6由粘性土体分层填筑而成。As shown in FIG. 1 , the present invention provides a revetment structure of coastal waterfront reservoir building type, comprising a filling interface step 4 arranged along the bank
进一步的,所述填土界面台阶4坡面角θ为30°,台阶平盘宽度为100cm,在所述填土界面台阶坡面上设置有排水孔5,所述排水孔5与所述台阶坡底线的夹角为10°~30°。Further, the slope angle θ of the step 4 at the filling interface is 30°, the width of the step plate is 100 cm, and a
进一步的,所述透水填土层7由砂砾石填筑压实而成,压实度不小于85%。Further, the permeable
进一步的,所述不透水填土层6由粘性土体分层填筑压实而成,分层厚度为20-30cm,压实度不小于85%。Further, the impermeable soil filling layer 6 is formed by layered filling and compaction of cohesive soil, the layered thickness is 20-30 cm, and the compaction degree is not less than 85%.
进一步的,所述不透水填土层台阶高度h为300-500cm,台阶平盘宽度a为200cm,沿护岸基础坡面自下而上最后一级台阶的上部平盘宽度为B。Further, the step height h of the impermeable filling layer is 300-500cm, the width a of the step plate is 200cm, and the width of the upper plate of the last step from bottom to top along the revetment foundation slope is B.
进一步的,每级不透水填土层台阶底部的透水填土层厚度为30-50cm。Further, the thickness of the permeable soil layer at the bottom of the steps of each impermeable soil layer is 30-50cm.
进一步的,所述滨海滨库造地型护岸结构还包括锚固系统,所述锚固系统包括锚杆10和锚杆格钩9,在所述护岸基础坡面2下部的不透水填土层台阶坡面上固定有所述锚杆10,该锚杆锚固在岸坡土体1中;所述锚杆格钩钩挂在不透水填土层台阶坡面形成锚杆与不透水填土层台阶坡面的稳固连接。Further, the revetment structure of the coastal waterfront reservoir construction type also includes an anchoring system, and the anchoring system includes an
实施例2Example 2
本发明还提供一种建筑滨海滨库造地型护岸结构的方法,包括如下步骤:The present invention also provides a method for building a waterfront bank revetment structure, comprising the following steps:
a、根据滨海滨库地质、地貌条件确定护岸结构的建筑部位。a. Determine the building position of the bank protection structure according to the geological and geomorphological conditions of the Binhai Reservoir.
b、在建筑部位沿护岸基础坡面开挖填土界面台阶,在该台阶坡面上设置排水孔,在所述填土界面台阶覆盖透水填土层,所述透水填土层采用砂砾石按照国家相关技术标准填筑压实、压实度不小于85%。b. Excavate a soil-fill interface step along the slope of the bank protection foundation at the building site, set drainage holes on the slope of the step, and cover the permeable soil fill layer on the soil-fill interface step, and the permeable soil layer is made of sand and gravel according to the The relevant national technical standards are filled with compaction and the degree of compaction is not less than 85%.
c、在所述透水填土层表面铺设防渗土工布,防渗土工布上填筑不透水填土层,该不透水填土层采用粘性土体分层填筑而成,沿护岸基础坡面自下而上设置成台阶结构,并且在每级不透水填土层台阶的整个底部也设置透水填土层。c. Lay anti-seepage geotextiles on the surface of the permeable soil layer, and fill the impermeable soil layers on the anti-seepage geotextiles. The surface is arranged in a step structure from bottom to top, and a permeable filling layer is also arranged at the entire bottom of the steps of each impervious filling layer.
具体地,沿护岸基础坡面自下而上逐级建造造地型台阶:采用砂砾石回填压实所述填土界面台阶→覆盖一层砂砾石与回填的砂砾石融为一体→在不透水填土层台阶的底部覆盖一层砂砾石→在砂砾石层表面铺设防渗土工布→防渗土工布上采用粘性土分层填筑不透水填土层。Specifically, build the steps from bottom to top along the slope of the revetment foundation: use sand and gravel to backfill and compact the backfill interface step → cover a layer of sand and gravel to integrate with the backfilled sand and gravel → in the impermeable Cover the bottom of the steps of the filling layer with a layer of sand and gravel → lay an impermeable geotextile on the surface of the sand and gravel layer → use cohesive soil to fill the impermeable soil layer on the impermeable geotextile.
d、在护岸基础坡面下部的不透水填土层坡面上设置锚固系统将不透水填土层锚固。d. An anchoring system is installed on the slope of the impervious fill layer at the lower part of the slope of the bank protection foundation to anchor the impermeable fill layer.
本发明由填土界面台阶4、透水填土层7、不透水填土层6、锚固系统组成,形成一个保障滨海滨库岸坡稳定并同时产生面积为“B×护岸工程长度”新增土地的填土结构。该发明设置填土界面台阶4并在该台阶坡面设置排水孔5,在填土界面台阶开挖区覆盖透水填土层7,所述透水填土层采用砂砾石将填土界面台阶开挖区回填压实,解决了造地型填土结构与岸坡原始坡面之间粘结强度低的难题;将造地型的填土体设置成透水填土层7和不透水填土层6,并且透水填土层7回填覆盖在所述填土界面台阶4上,解决了库水位降落过程中岸坡同步排水问题,消除了地下水渗透作用对填土结构稳定性的不利影响;而在护岸基础坡面2下部的不透水填土层6坡面上设置锚固系统将不透水填土层锚固,解决了填土岸坡的整体稳定问题。The present invention is composed of a filling interface step 4, a
如图1所示,如果采用传统护岸坡线8,护岸结构将不能新增土地;并且水库低水位12、高水位13交替变化(水库水位变化)容易导致传统护岸坡线8侵蚀和冲刷,岸坡潜在破坏面3容易受到破坏。相比传统的护岸结构,本发明提供了一种既能保障滨海滨库岸坡稳定,又能新增土地的填土结构。本发明不但能有效保护滨海滨库岸坡稳定,而且能很好地保护滨海滨库地质环境,促进岸坡土地资源的开发利用。As shown in Figure 1, if the traditional bank protection slope line 8 is used, the bank protection structure will not be able to add new land; and the alternating change of the
最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解;其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明实施例技术方案的范围,其均应涵盖在本发明的权利要求和说明书的范围当中。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand; Modifications are made to the technical solutions recorded in the foregoing embodiments, or some or all of the technical features thereof are equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention. It should be covered within the scope of the claims and description of the present invention.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710979077.1A CN107761668B (en) | 2017-10-19 | 2017-10-19 | Coastal shore reservoir land-building type revetment structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710979077.1A CN107761668B (en) | 2017-10-19 | 2017-10-19 | Coastal shore reservoir land-building type revetment structure and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107761668A CN107761668A (en) | 2018-03-06 |
CN107761668B true CN107761668B (en) | 2020-01-10 |
Family
ID=61269703
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710979077.1A Expired - Fee Related CN107761668B (en) | 2017-10-19 | 2017-10-19 | Coastal shore reservoir land-building type revetment structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107761668B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108399305B (en) * | 2018-03-12 | 2021-06-29 | 自然资源部第三海洋研究所 | Design method for maintenance of beach on exposed bank section with strong erosion |
CN109315183B (en) * | 2018-11-08 | 2023-12-05 | 北京场道市政工程集团有限公司 | Garden engineering slope greening structure |
CN110656775B (en) * | 2019-09-15 | 2021-07-30 | 义乌市高洋建筑工程有限公司 | Special cast-in-place concrete separator for CL |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101097379B1 (en) * | 2010-12-16 | 2011-12-23 | 주식회사 서영엔지니어링 | Leak protection system for leak and its construction method |
CN202530351U (en) * | 2012-03-01 | 2012-11-14 | 长沙理工大学 | Carbon mudstone-soil layered staggered embankment filling structure |
CN202809559U (en) * | 2012-09-20 | 2013-03-20 | 徐国东 | Gangue-filled riverway dike |
CN203393676U (en) * | 2013-08-15 | 2014-01-15 | 江苏山水环境建设集团股份有限公司 | Cast-in-situ inverted filtration vegetative concrete ecological slope protection system |
CN205917704U (en) * | 2016-07-11 | 2017-02-01 | 黑龙江工程学院 | Novel multi -functional highway bank protection |
CN206173893U (en) * | 2016-11-16 | 2017-05-17 | 中国电建集团贵阳勘测设计研究院有限公司 | Fast and efficient slope fixing structure |
CN206428709U (en) * | 2017-01-05 | 2017-08-22 | 刘学生 | A kind of highway slope protection |
-
2017
- 2017-10-19 CN CN201710979077.1A patent/CN107761668B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101097379B1 (en) * | 2010-12-16 | 2011-12-23 | 주식회사 서영엔지니어링 | Leak protection system for leak and its construction method |
CN202530351U (en) * | 2012-03-01 | 2012-11-14 | 长沙理工大学 | Carbon mudstone-soil layered staggered embankment filling structure |
CN202809559U (en) * | 2012-09-20 | 2013-03-20 | 徐国东 | Gangue-filled riverway dike |
CN203393676U (en) * | 2013-08-15 | 2014-01-15 | 江苏山水环境建设集团股份有限公司 | Cast-in-situ inverted filtration vegetative concrete ecological slope protection system |
CN205917704U (en) * | 2016-07-11 | 2017-02-01 | 黑龙江工程学院 | Novel multi -functional highway bank protection |
CN206173893U (en) * | 2016-11-16 | 2017-05-17 | 中国电建集团贵阳勘测设计研究院有限公司 | Fast and efficient slope fixing structure |
CN206428709U (en) * | 2017-01-05 | 2017-08-22 | 刘学生 | A kind of highway slope protection |
Non-Patent Citations (2)
Title |
---|
《浅谈风积砂路基施工过程控制》;王旭传;《工程建设与管理》;20080401(第7期);第162-163页 * |
《高变幅水库岸坡造地型护岸结构修筑关键技术研究及应用》;何晓英;《中国优秀硕士学位论文全文数据库》;20120415;第46、52-53页 * |
Also Published As
Publication number | Publication date |
---|---|
CN107761668A (en) | 2018-03-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Chu et al. | Geosynthetic tubes and geosynthetic mats: Analyses and applications | |
CN105178245A (en) | Large filling bag ecological embankment and revetment building method for river lake channel | |
CN204282308U (en) | Gabion composite dam adapting to deep covering layer | |
CN103233444B (en) | Underwater dumped rockfill bedding and side slope Anti-scouring structure and construction method thereof | |
CN103015399B (en) | The quake evaluation system of Liquefaction Foundation and method for processing foundation | |
CN107761668B (en) | Coastal shore reservoir land-building type revetment structure and construction method thereof | |
CN113818402A (en) | Reinforcement and reinforcement structure of clay core rockfill dam and its construction method | |
CN104141285A (en) | Seepage-proofing seawall | |
CN216275518U (en) | Reinforcing and reinforcing structure of clay core rockfill dam | |
CN102286961B (en) | Overflow dam for waste tires | |
CN104695455B (en) | High-flow and high-head antiscour and anti-seepage overflow cofferdam structure and construction method thereof | |
CN113338315B (en) | Earth-rock cofferdam structure of silt soft soil foundation and construction method thereof | |
CN215252686U (en) | Construction structure of earth-rock dam on deep silt layer | |
CN212641379U (en) | Stone slag dam | |
CN211312563U (en) | Anti-seepage and anti-impact overflow cofferdam structure | |
CN107761700A (en) | The ballast method of soft soil foundation | |
CN203188174U (en) | Underwater riprap foundation bed and side-slope erosion prevention structure | |
CN112030877A (en) | Bank protection engineering construction method and bank protection structure thereof | |
CN216041253U (en) | Soft soil foundation earth-rock cofferdam structure of silt matter | |
Sitharam et al. | Geotechnical considerations for coastal reservoirs | |
CN105155478B (en) | A kind of new damming dam reinforces Application way | |
CN112962516B (en) | Design and construction method of a hazard-removing reinforcement measure for suppressing the swell of the embankment foundation | |
CN104947630A (en) | Over-current slag collecting weir for water conservancy and hydropower engineering and construction method thereof | |
CN217026896U (en) | River sluice flood control dyke structure | |
CN103835296B (en) | The safeguard structure of polder area deep foundation pit support and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200110 |