CN106677437A CN201710153700.8A CN201710153700A CN106677437A CN 106677437 A CN106677437 A CN 106677437A CN 201710153700 A CN201710153700 A CN 201710153700A CN 106677437 A CN106677437 A CN 106677437A
Authority
CN
China
Prior art keywords
grout sleeve
hole
grout
standby
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710153700.8A
Other languages
Chinese (zh)
Other versions
CN106677437B (en
Inventor
孟捷
马涛
苗启松
李文峰
隆玉来
刘大兴
徐建伟
段世昌
孙瑜峰
常政
何西令
刘少军
陈曦
张胜
张汎
周建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CN106677437A publication Critical patent/CN106677437A/en
Application granted granted Critical
Publication of CN106677437B publication Critical patent/CN106677437B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention relates to a rebar connecting grout sleeve with standby holes and a sleeve connection quality detecting method. The grout sleeve with the standby holes comprises a grout sleeve body, a grout filling hole and a grout discharge hole, wherein the grout filling hole and the grout discharging hole are formed in the grout sleeve body. The standby holes capable of being opened without damage and a blocking structure used for blocking the standby holes are formed in the grout sleeve body in advance. The blocking structure is used for blocking the standby holes in the grouting process, so that a through channel required for grouting is formed in the grout sleeve body. The blocking structure is taken out without damage after grouting is completed. By adoption of the sleeve, the application quality of the rebar connecting grout sleeve in the building construction process can be finally detected. The sleeve and method can be widely applied to construction of fabricated structures of constructional engineering.

Description

Bar connecting grout sleeve with standby hole and sleeve connection quality determining method
Technical field
The application provides a kind of grout sleeve and sleeve connection quality determining method.
Background technology
Assembled architecture is the developing direction of building trade industrialization upgrading, is connected by sleeve between assembled architecture component Connect, therefore, quality is to ensure that the key point of assembled architecture quality at link position.At present, assembled architecture still belongs in China In new technology, in the popularization of each new technology, need research and formulate a series of domestic quality control body of adaptation China The new standard of system.Such as design standard, acceptance of engineering quality standard, correlated quality is there is no to control standard at present.
At present, the control after the project delivery method acceptance criteria of our countries is mainly process control and is finally completed. Used as a kind of product, the corresponding standard of national regulation is current grout sleeve structure grout sleeve《Bar connecting grouting set Cylinder》JG/T398-2012.Standard is pointed out to be divided into full grout sleeve (both sides are grouting) and half grouting set according to version Cylinder (one section is mechanically connected one section for grouting).As shown in figure 1, grout sleeve has the grout sleeve body 1 of elongated hollow, its Grout hole 3 and plasma discharge hole 2 are formed with wall, reinforcing bar 4 is passed through when hollow space connects for prefabricated building components.To filling in standard There are clearly description, grout hole 3 in slurry hole 3 and plasma discharge hole 2:For plus cementing and grouting material entrance, usually unthreaded hole, spiral Hole.Plasma discharge hole 2:For adding when cementing and grouting material, the unnecessary grouting material after ventilating and filling discharges discharge gate, usually Unthreaded hole, threaded hole.This grout sleeve structure functions only as connection function, it is impossible to realize in work progress to process control.For Solve to realize the control to construction quality, the application have developed a kind of Novel sleeve on the basis of existing sleeve, such as apply Grout sleeve structure described in numbers 201610323531.3 patent application, this tube-in-tube structure can be realized in practice of construction The method of various procedures control, such as observe filling speed, plumpness of grouting etc., but lacks the inspection after engineering is finally completed Solidification situation of slurries inside means such as measuring set of cylinder etc..
In addition, sleeve has its product standard and the method for inspection as a kind of product.Fabricated component is used in sleeve When middle, due to the encirclement of reinforced concrete at sleeve in, environment is extremely complex, be difficult with existing test mode, overcomes difficulties Quality condition inside cylinder.
The content of the invention
In view of above-mentioned technical problem, a kind of set of the filling with standby hole bar connecting grout sleeve of the application offer, its purpose It is by changing tube-in-tube structure, realizing to the monitoring and measurement of sleeve connection part interior construction after the completion of engineering, so as to realize Assembled architecture final mass is detected.
Its concrete technical scheme is as follows:
A kind of bar connecting grout sleeve with standby hole, the grout sleeve includes grout sleeve body, and is formed at Grout hole thereon and plasma discharge hole, it is characterised in that:Offer in advance on the grout sleeve body can lossless unlatching it is standby Hole and the plugging structure in the closure standby hole, the plugging structure blocks the standby hole in filling process and makes the grouting Sleeve body forms the through channel needed for grouting, and grouting terminates lossless taking-up of the rear plugging structure and formed and the grouting set Cylinder this inside and outside insertion passage.
The plugging structure includes containment vessel, prevents structure, limit body and opening device, the containment vessel from being connected to described The described standby hole site of grout sleeve body outer wall, the prevention structure is formed positioned at the containment vessel and the standby hole In cavity, its one end stretches into the grout sleeve sheet in vivo, and the limit body limits the prevention structure and the grout sleeve There is relative displacement in body, the opening device is defaulted in the prevention structure for the prevention structure during slip casting It is lossless with the standby hole to separate.
The prevention structure is hollow or solid.
When the prevention structure is hollow, the standby hole may act as plasma discharge hole or grout hole.
To make solidification slurries and the prevention structure form entirety, its inner wall coarse when the prevention structure is hollow.
The prevention structure is smooth with the positive contact surface of slurries in the grout sleeve body.
The prevention structure can be along the prevention structure with the position of the positive contact surface of slurries in the grout sleeve body Axis trimming.
When the prevention structure for it is hollow when, can using its it is hollow make the hollow tunnel become plasma discharge hole, and in the sky The prevention body of exhaust not plasma discharge is provided with heart duct.
The standby hole is at least one.
The application has the advantages that relative to prior art:
Standby hole is arranged in sleeve body, and it is not only the simple perforate in sleeve body, but is needed again Design tube-in-tube structure, makes sleeve meet the requirements of the standard opening up standby hole after sleeve others mechanical property, and realizes lossless Open and close.It carries out that destructive perforate is also different from after the completion of grouting to place testing equipment, and destructive perforate cannot The reset condition for keeping sleeve inner is also impossible to judge grouting effect, and the standby hole for opening up in advance can be realized keeping set In the case of the in-built reset condition of cylinder, in-built quality is detected.
Standby hole is, to provide the means of a kind of detection mode and reinforcement in grout sleeve use, to provide after the completion of grouting The situation of sleeve inner is checked a kind of means after the completion of engineering.
Install on standby hole and prevent body, process control and the inspection of final construction quality are realized simultaneously using same sleeve Survey.
Prevent structure smooth with the positive contact surface of grout sleeve, after slurry curing, when opening standby hole, if sleeve inner slurry Material is formed and the shape for preventing the positive contact surface of structure from matching, then can be determined that grouting meets and require, otherwise may determine that grouting It is unsatisfactory for requiring.The prevention structure of closing can adjust the position for stretching into sleeve inner, so can observe reinforcement location etc. its Its situation.
Prevent structure for it is hollow when, its inwall be formed with rough surface its effect be sleeve construction need exhaust Or slip casting.
It is another object of the invention to provide the bar connecting grout sleeve quality of connection detection in a kind of assembled architecture Method, forms the omnibearing quality control and inspection standard of assembled architecture.
Its concrete technical scheme is as follows:
Bar connecting grout sleeve quality of connection detection method is carried out using above-mentioned grout sleeve, it is characterised in that: After the completion of grouting, the standby hole is opened, electronic inductor is sent into into the grout sleeve sheet by the standby hole internal Detection grout sleeve internal structure, or sampler is sent into into the grout sleeve sheet internal portion thing in vivo by the standby hole Matter is sampled, or after the problem of the grout sleeve body interior construction is found, reinforcement of being in the milk again.
If being provided with prevention body in the prevention structure of hollow grout sleeve, on the basis of the detection of above-mentioned final mass, Can also realize in filling process, by change of the prevention body phase to the spacing observation panel position slurries being observed simultaneously The real-time detection process detection of perfusion degree and velocity interpolation slip casting process.
The technical program has the advantages that compared with prior art:
At present the detection method fabricated construction complicated for environment cannot accomplish in real time accurately detection, and the application only passes through The detection and construction of the i.e. achievable filling process medium velocity of structure and plumpness that change sleeve completes the inspection of after sleeve inner structure Survey, method is simple, workable, testing result accurately, is provided for work progress and final mass and in real time, accurately examined Survey result.
Description of the drawings
Fig. 1 is existing tube-in-tube structure;
Fig. 2 is with a kind of embodiment of standby borehole jack barrel structure;
Fig. 3 is with standby second embodiment of borehole jack barrel structure;
Fig. 4 is with standby the third embodiment of borehole jack barrel structure;
Fig. 5 is with the 4th kind of embodiment of standby borehole jack barrel structure;
Fig. 6 is to take out the standby hole for preventing structure from being formed;
Fig. 7 is the embodiment of the standby borehole jack cylinder with body is prevented;
Fig. 8 is grout sleeve use state figure;
Reference:1- grout sleeve bodies, 2- plasma discharges hole, 3- grout holes, 4- reinforcing bars, the standby holes of 5-, 6- containment vessels, 7- Prevent structure, 8- limiting sections, 9- closure parts, 10- grooves, 11- locating parts, the hollow middle tubes of 12-, 13- opening devices, 14- resistances Only body, 15- steam vents, 16- reinforced concrete members, 17- electronic inductors.
Specific embodiment
To make goal of the invention, technical scheme and the beneficial effect of the present invention of greater clarity, below in conjunction with the accompanying drawings to this Inventive embodiment is illustrated, it should be noted that in the case where not conflicting, in the embodiment and embodiment in the application Feature can mutually be combined.
Embodiment as shown in Fig. 2 Fig. 2 provides a kind of bar connecting grout sleeve with standby hole 5, itself and existing skill Provided in art Fig. 1 grout sleeve difference be offer in advance on the grout sleeve body 1 can lossless unlatching it is standby Hole 5 and the plugging structure in the closure standby hole 5, the plugging structure blocks the standby hole in filling process and makes the filling Slurry sleeve body forms the through channel needed for grouting, grouting terminate after the lossless taking-up of the plugging structure (part is taken out, wherein Containment vessel be retained in standby hole) formed and the passage of this inside and outside insertion of the grout sleeve.
Referring to Fig. 3 to Fig. 7, plugging structure includes containment vessel 6, prevents structure 7, limit body 8 and open the plugging structure Device 13, the containment vessel 6 is connected to the position of described standby hole 5 of the outer wall of grout sleeve body 1, the prevention structure 7 In the cavity that the containment vessel 6 and the standby hole 1 are formed, its one end is stretched in the grout sleeve body 1, the limit Position body 8 limits the prevention structure 7 and relative displacement, the unlatching dress occurs during slip casting with the grout sleeve body 1 Put 13 and default in the prevention structure 7 and prevent that structure 7 is lossless with the standby hole 5 separates for described.
Referring to Fig. 3 to Fig. 6, in the specific implementation, the prevention structure can be hollow or solid.When the prevention structure 7 for it is hollow when, the standby hole 5 may act as plasma discharge hole or grout hole, or be served as by the existing plasma discharge hole of sleeve or grout hole Standby hole, realizes that a hole is dual-purpose.To make solidification slurries and the prevention structure 7 form entirety, when the prevention structure 7 is hollow When its inner wall coarse such as saw-tooth grooves or indenture.It is complete in order to ensure sleeve inner structure, the prevention structure 7 and the filling The positive contact surface of slurries (preventing structure from stretching into the end face in grout sleeve body 1) is smooth in slurry sleeve body 1.According to detecting position The difference put, the prevention structure 7 can be along the prevention structure 7 with the position of the positive contact surface of slurries in the grout sleeve body Axis trimming.
Referring to Fig. 7, in the specific implementation, when the prevention structure 7 for it is hollow when, hollow can make the hollow tunnel using its Become plasma discharge hole, and the prevention body 14 for being vented not plasma discharge is provided with the hollow tunnel, the prevention body is fixed on prevention The outer end (i.e. with positive contact surface opposite end) of structure 7, is provided with steam vent 15 in it.
In the specific implementation, structure 7 is prevented to be cored screw or hollow middle tube etc..
In the specific implementation, opening device 13 can be plug etc..
During specific embodiment, the quantity in standby hole and position require to determine according to detection, can be one or more.
Fig. 8 is the use state figure of the grout sleeve with standby hole, and grout sleeve is wrapped up positioned at reinforced concrete member 16 Inside, it is used to connecting and protecting reinforcing bar, offer in advance on grout sleeve body 1 can lossless unlatching standby hole 5 and envelope The plugging structure in the standby hole 5 is blocked up, plugging structure includes containment vessel 6, prevents structure 7, limit body 8 and opening device 13, figure In illustrate that take out opening device 13 state, prevent structure 7 outward flange it is concordant with the outward flange of reinforced concrete member 16, Inner to be connected in the hole that grout sleeve body 1 is connected with standby hole position, during grouting, standby hole 5 is blocked entirely by preventing structure 7, Grouting terminates, and by opening device structure lossless taking-up from standby hole 5 will be prevented, and forms electronic inductor 17 or/and mends Slurry passage.
The above-mentioned grout sleeve with standby hole may be implemented in the detection of assembled architecture construction middle sleeve final mass, its side Method is after the completion of grouting, to open the standby hole, and electronic inductor is sent into into the grout sleeve by the standby hole This vivo detection grout sleeve inner structure.
In the specific implementation, the electronic inductor includes endoscope, probe etc..
In the specific implementation, the content of detection include, the packing in reinforcement location, grout sleeve and state of cure.
When be provided with the prevention structure of the standby borehole jack cylinder of band prevent body when, can also realize in filling process pair may be used also To realize in filling process, by change of the prevention body phase to the spacing observation panel position slurry filling being observed simultaneously The real-time detection process detection of degree and velocity interpolation slip casting process.
What above-described embodiment only explanation present invention content was done enumerates, and the protection domain of the application is not limited by it System, still the content by the application claims is defined.It is easily understood that in other embodiments, this professional technology people Member can be modified according to this professional routine techniques and general knowledge, and above-mentioned change each falls within the protection domain of the application.

Claims (11)

1. a kind of bar connecting grout sleeve with standby hole, the grout sleeve includes grout sleeve body, and is formed at it On grout hole and plasma discharge hole, it is characterised in that:Offer in advance on the grout sleeve body can lossless unlatching standby hole With the plugging structure for blocking the standby hole, the plugging structure blocks the standby hole in filling process covers the grouting Cylinder body forms the through channel needed for grouting, and lossless taking-up of the plugging structure after terminating of being in the milk is formed and the grout sleeve The passage of this inside and outside insertion.
2. bar connecting grout sleeve according to claim 1, it is characterised in that:The plugging structure include containment vessel, Structure, limit body and opening device, the containment vessel is prevented to be connected to the described standby hole position of the grout sleeve body outer wall Put, described to prevent structure from being located in the cavity that the containment vessel and the standby hole are formed, its one end stretches into the grout sleeve This is internal, and the limit body limits the prevention structure and relative displacement occurs during slip casting with the grout sleeve body, The opening device is defaulted in the prevention structure and prevents that structure is lossless with the standby hole separates for described.
3. bar connecting grout sleeve according to claim 2, it is characterised in that:The prevention structure is hollow or real The heart.
4. bar connecting grout sleeve according to claim 3, it is characterised in that:When the prevention structure is hollow, The standby hole may act as plasma discharge hole or grout hole.
5. the bar connecting grout sleeve according to claim 3 or 4, it is characterised in that:To make solidification slurries and the resistance Only structure forms entirety, its inner wall coarse when the prevention structure is hollow.
6. bar connecting grout sleeve according to claim 5, it is characterised in that:The prevention structure and the grouting set The positive contact surface of slurries is smooth in cylinder body.
7. bar connecting grout sleeve according to claim 6, it is characterised in that:The prevention structure and the grouting set The position of the positive contact surface of slurries can be along the axis trimming of the prevention structure in cylinder body.
8. bar connecting grout sleeve according to claim 5, it is characterised in that:When the prevention structure is hollow, Can be using its hollow prevention for making the hollow tunnel become plasma discharge hole, and exhaust not plasma discharge being provided with the hollow tunnel Body.
9. bar connecting grout sleeve according to claim 1, it is characterised in that:The standby hole is at least one.
10., using the bar connecting grout sleeve quality of connection detection method as described in claim 1 to 9 any one, it is special Levy and be:After the completion of grouting, the standby hole is opened, electronic inductor is sent into into the grouting set by the standby hole Cylinder this vivo detection grout sleeve internal structure, or sampler is internal by the standby hole feeding grout sleeve sheet Inner material is sampled, or after the problem of the grout sleeve body interior construction is found, reinforcement of being in the milk again.
11. bar connecting grout sleeve quality of connection detection methods as claimed in claim 10, it is characterised in that:It had been in the milk Cheng Zhong, by change of the prevention body phase to the spacing observation panel position slurry filling degree and velocity interpolation slip casting are observed The real-time detection process of process.
CN201710153700.8A 2017-01-20 2017-03-15 Steel bar connection grouting sleeve with standby holes and sleeve connection quality detection method Active CN106677437B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201720077747 2017-01-20
CN2017200777476 2017-01-20

Publications (2)

Publication Number Publication Date
CN106677437A true CN106677437A (en) 2017-05-17
CN106677437B CN106677437B (en) 2023-12-29

Family

ID=58829129

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201720251117.6U Active CN206554394U (en) 2017-01-20 2017-03-15 Bar connecting grout sleeve with standby hole
CN201710153700.8A Active CN106677437B (en) 2017-01-20 2017-03-15 Steel bar connection grouting sleeve with standby holes and sleeve connection quality detection method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201720251117.6U Active CN206554394U (en) 2017-01-20 2017-03-15 Bar connecting grout sleeve with standby hole

Country Status (1)

Country Link
CN (2) CN206554394U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288268A (en) * 2017-06-27 2017-10-24 浙江大学 Endoscope detects the structure and its method of grouting behind shaft or drift lining plug-in type sleeve reinforced bar joint
CN107938947A (en) * 2017-12-13 2018-04-20 周建 Combined reinforced bar connects grout sleeve and application method
CN108152297A (en) * 2018-01-31 2018-06-12 昆山市建设工程质量检测中心 Inside peep the device and method of water flood detection reinforcing bar half grout sleeve grouting plumpness
CN108277926A (en) * 2018-01-31 2018-07-13 昆山市建设工程质量检测中心 Slurry anchor connection part with detection hole and grouting plumpness detection method and benefit paste-making method
CN108331260A (en) * 2018-01-31 2018-07-27 昆山市建设工程质量检测中心 Half grout sleeve with detection hole and grouting plumpness detection method and benefit paste-making method
CN108593721A (en) * 2018-05-11 2018-09-28 中国建筑科学研究院有限公司 Method and device for detecting whether full grouting sleeve is full by resistance method
CN109339343A (en) * 2018-09-27 2019-02-15 北京市建筑设计研究院有限公司 Precast concrete grout sleeve
CN109342265A (en) * 2018-11-05 2019-02-15 中交三航局第三工程有限公司 Grouting quality detection device in grouting pipe in assembled vertical member
CN110907630A (en) * 2019-10-24 2020-03-24 中建科技有限公司 Sleeve grouting fullness detection device and application method thereof
CN112523431A (en) * 2020-12-07 2021-03-19 邯郸市倚道金属制品有限公司 Connector with positioning pin and detection device thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206554394U (en) * 2017-01-20 2017-10-13 周建 Bar connecting grout sleeve with standby hole
CN109322444B (en) * 2018-10-23 2023-12-22 周建 Novel steel bar connection full grouting sleeve and construction method thereof
CN110514466B (en) * 2019-08-26 2020-04-17 昆山市建设工程质量检测中心 Method for drilling grouting material core sample from reinforcing steel bar sleeve grouting connection node

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5383740A (en) * 1993-08-02 1995-01-24 Richmond Screw Anchor Company Combination mechanical/grout sleeve coupling for concrete reinforcement bars
KR101498616B1 (en) * 2014-07-03 2015-03-04 아이에스동서 주식회사 Sleeve for connection of reinforcing steels
CN204876355U (en) * 2015-08-24 2015-12-16 刘运林 Reinforcing bar grout sleeve seals external device
CN105781022A (en) * 2016-05-17 2016-07-20 北京结研特工程技术有限公司 Blocking valve, grouting sleeve and prefabricated component connecting method
CN105908974A (en) * 2016-04-13 2016-08-31 江苏华江建设集团有限公司 Method of steel-bar sleeve grouting connection construction for vertical precast concrete component
CN206554394U (en) * 2017-01-20 2017-10-13 周建 Bar connecting grout sleeve with standby hole

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5383740A (en) * 1993-08-02 1995-01-24 Richmond Screw Anchor Company Combination mechanical/grout sleeve coupling for concrete reinforcement bars
KR101498616B1 (en) * 2014-07-03 2015-03-04 아이에스동서 주식회사 Sleeve for connection of reinforcing steels
CN204876355U (en) * 2015-08-24 2015-12-16 刘运林 Reinforcing bar grout sleeve seals external device
CN105908974A (en) * 2016-04-13 2016-08-31 江苏华江建设集团有限公司 Method of steel-bar sleeve grouting connection construction for vertical precast concrete component
CN105781022A (en) * 2016-05-17 2016-07-20 北京结研特工程技术有限公司 Blocking valve, grouting sleeve and prefabricated component connecting method
CN206554394U (en) * 2017-01-20 2017-10-13 周建 Bar connecting grout sleeve with standby hole

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288268A (en) * 2017-06-27 2017-10-24 浙江大学 Endoscope detects the structure and its method of grouting behind shaft or drift lining plug-in type sleeve reinforced bar joint
CN107938947A (en) * 2017-12-13 2018-04-20 周建 Combined reinforced bar connects grout sleeve and application method
CN107938947B (en) * 2017-12-13 2023-09-22 周建 Combined steel bar connection grouting sleeve and use method thereof
CN108331260B (en) * 2018-01-31 2019-09-03 昆山市建设工程质量检测中心 Half grout sleeve grouting plumpness detection method with detection hole
CN108331260A (en) * 2018-01-31 2018-07-27 昆山市建设工程质量检测中心 Half grout sleeve with detection hole and grouting plumpness detection method and benefit paste-making method
CN108277926B (en) * 2018-01-31 2019-09-03 昆山市建设工程质量检测中心 Slurry anchor connection part grouting plumpness detection method with detection hole
CN108277926A (en) * 2018-01-31 2018-07-13 昆山市建设工程质量检测中心 Slurry anchor connection part with detection hole and grouting plumpness detection method and benefit paste-making method
CN108152297B (en) * 2018-01-31 2019-10-22 昆山市建设工程质量检测中心 Inside peep the method for water flood detection half grout sleeve of reinforcing bar grouting plumpness
CN108152297A (en) * 2018-01-31 2018-06-12 昆山市建设工程质量检测中心 Inside peep the device and method of water flood detection reinforcing bar half grout sleeve grouting plumpness
CN108593721A (en) * 2018-05-11 2018-09-28 中国建筑科学研究院有限公司 Method and device for detecting whether full grouting sleeve is full by resistance method
CN109339343A (en) * 2018-09-27 2019-02-15 北京市建筑设计研究院有限公司 Precast concrete grout sleeve
CN109342265A (en) * 2018-11-05 2019-02-15 中交三航局第三工程有限公司 Grouting quality detection device in grouting pipe in assembled vertical member
CN110907630A (en) * 2019-10-24 2020-03-24 中建科技有限公司 Sleeve grouting fullness detection device and application method thereof
CN112523431A (en) * 2020-12-07 2021-03-19 邯郸市倚道金属制品有限公司 Connector with positioning pin and detection device thereof
CN112523431B (en) * 2020-12-07 2022-06-10 邯郸市倚道金属制品有限公司 Connector detection device with locating pin

Also Published As

Publication number Publication date
CN106677437B (en) 2023-12-29
CN206554394U (en) 2017-10-13

Similar Documents

Publication Publication Date Title
CN206554394U (en) Bar connecting grout sleeve with standby hole
CN106501495B (en) The detection device and detection method of grouting material compactness in a kind of sleeve
CN108761049B (en) Device and method for detecting grouting fullness of steel bar connecting sleeve through preformed hole
CN108331260A (en) Half grout sleeve with detection hole and grouting plumpness detection method and benefit paste-making method
CN208255027U (en) A kind of sleeve grouting plumpness detection device based on pre-buried steel wire hubbing
WO2018054290A1 (en) Pre-embedded pile tip foundation detection system
CN110714769B (en) Installation device and installation method for monitoring meter
CN110261403A (en) A kind of device and method for grouting construction stage detection sleeve grouting full weight
CN111519843A (en) Grouting sleeve with double inspection holes and application method
CN105671232A (en) Online installation process of iron-smelting blast furnace thermocouple
CN105624354A (en) Mounting method of blast furnace hearth bottom temperature thermocouple
CN210032352U (en) Steel bar sleeve with grouting quality monitoring device
CN107938947A (en) Combined reinforced bar connects grout sleeve and application method
CN110260166A (en) A kind of underground piping air tightness checking device and its application method
CN108808594B (en) Grouting-sealed cable wall bushing structure and construction method thereof
CN212026863U (en) Take half grout sleeve of inspection hole
CN206770864U (en) A kind of pipe end rubber plugging device of municipal works closed-water test
CN209293296U (en) A kind of detachable injected hole protection screw
CN206113880U (en) Concrete freeze thawing inflation strain sensor
CN206034513U (en) Pre -buried type stake end foundation detecting system
CN208950065U (en) A kind of pulp noodle detection of grout sleeve and the assembly node for mending sizing device and prefabricated component
CN211817426U (en) Plugging assembly for grouting connection or slurry anchor connection of assembled sleeve
CN207779462U (en) A kind of guarding against theft type hydrologic monitoring instrument apparatus for placing
CN110424571A (en) A kind of grout sleeve wall body structure and its quality determining method
CN207863312U (en) Slurry anchor connection part with detection hole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant