CN106638891A - Comprehensive water managing method in underground mining stage of open pit into underground mining - Google Patents

Comprehensive water managing method in underground mining stage of open pit into underground mining Download PDF

Info

Publication number
CN106638891A
CN106638891A CN201710075607.XA CN201710075607A CN106638891A CN 106638891 A CN106638891 A CN 106638891A CN 201710075607 A CN201710075607 A CN 201710075607A CN 106638891 A CN106638891 A CN 106638891A
Authority
CN
China
Prior art keywords
underground mining
pumping plant
underground
water
open
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710075607.XA
Other languages
Chinese (zh)
Inventor
王杰
汪为平
章林
陈继强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd, Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Priority to CN201710075607.XA priority Critical patent/CN106638891A/en
Publication of CN106638891A publication Critical patent/CN106638891A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a comprehensive water managing method in an underground mining stage of open pit into underground mining. The method comprises the steps of building a flood intercepting trench (13) outside an underground mining moving band range line (10), mounting a lower shaft pump station (3) inside an underground mining horizontal transportation lane (7) at the bottom of the underground mining lift shaft (1), at least adding an upper shaft pump station (2) inside the underground mining horizontal transportation lane (7) at the upper portion of the underground mining lift shaft (1), establishing a drainage opening (5) at the bottom of an open pit slope, and building an overflow well (4) in the underground mining horizontal transportation lane (7) arranged with the lower shaft pump station (3). According to the comprehensive water managing method in the underground mining stage of open pit into underground mining, multi-pronged comprehensive measures of severing, prevention, drainage, dredging and storage are adopted, water disasters in the underground mining stage of the open pit into underground mining can be effectively solved, and the method can be applied widely to water managing in the underground mining stage of the open pit into underground mining in industries of ferrous, non-ferrous, coal, chemical engineering and the like.

Description

A kind of underground mining stage integral harness method in open air trestle exploitation
Technical field
The present invention relates to a kind of integral harness method of mining, and in particular to underground in a kind of open air trestle exploitation The comprehensive control measures of mining phase surface water and groundwater, can be on the transition from open-pit of the industry such as black, coloured, coal, chemical industry ground Lower mining is extensively applied.
Background technology
During the open air trestle mining underground mining stage, top is the recessed open-air pit of depth of remaining.Open-air pit gathering ground Product is very big, often up to hundreds thousand of square metres.Atmospheric precipitation directly affects subdrainage, and during heavy rain, flood peak is swift and violent, short duration flood peak Amount is especially big, and open-air pit charge for remittance amount greatly, to underground mining serious threat is brought.Such as 1984, ShaoXing,ZheJiang drenches small piece of land surrounded by water iron ore to be occurred Because of storm flood, cause mine to be flooded;1969, Liaoning Huludao City pine tree fourth of the twelve Earthly Branches molybdenum ore in a rainfall, because of underground Water door problem, causes to flood well accident, stops production and processes up to more than a year.Underground mine being harnessed the river open air trestle recovery of subterranean of become One important topic of mining phase, by industry common concern.
Underground mining stage flood in order to solve the problems, such as open air trestle mining type,《Coloured mining and metallurgy》In August, 2010 " brief talking open air trestle exploitation Flood Control Problem " text delivered has been made to inquire into the open air trestle exploitation method of harnessing the river.By edge Subside excavate outside scope tidal channel, the important roadway in underground of excavating plant periphery and underground mining arranges the measures such as water dam and carries out Flood control is harnessed the river.《Metal mine》Describe in " Guilaizhuang ore deposit open air trestle safety and high efficiency " that 1st phase in 2012 delivers In the ore deposit open air trestle recovery process of Guilaizhuang, catch pit is arranged by earth's surface open-air pit bottom, water is set in the stage casing of down-hole point 3 Storehouse pumping drainage.
Above-mentioned existing method of prevent floods by water control is all locality and not into system, it is difficult to meet open air trestle mining underground Demand of the mining phase in heavy rain season integral harness, it is impossible to effectively prevent mine from flooding the generation of the water damages such as well.
The content of the invention
The purpose of the present invention is aiming at the problems referred to above of prior art presence and provides one kind collection section, anti-, row, thin, storage Various technologies of harnessing the river are integrated, and can not only effectively administer surface water, and can prevent and treat the open air trestle exploitation of underground water Middle underground mining stage integral harness method, can be prevented with the water damage in underground mining stage in the exploitation of effectively solving open air trestle Only mine floods the generation of the water damages such as well.
To realize the above-mentioned purpose of the present invention, underground mining stage integral harness in a kind of open air trestle exploitation of the invention Method is achieved through the following technical solutions:
1)Cut-off ditch is built outside underground mining moving belt scope line:In order to reduce openpit charge for remittance, in underground mining movement Cut-off ditch is built outside band scope line, and periodically repairerment maintenance is carried out to it, can so be allowed surface water to be concentrated and drain into openpit Outside, do not allow earth's surface charge for remittance to enter openpit, the arrangement of Cut-off ditch must be according to actual landform, and the size of Cut-off ditch is according to reality Border landform and the hydrological data with reference to catchment area and location are computed checking and determine after flood discharge capacity.
2)Catch pit is set in open-air pit bottom:Catch pit is set in open-air pit bottom, water pump is installed in catch pit, using water The charge for remittance collected in catch pit is drained into stope ground off-balancesheet by pump in real time;The size of the catch pit and the selection of water pump are according to outdoor The catchment area in hole and ore district hydrogeologic condition are calculated and determined.
3)Underground mining vertical shaft pumping drainage facility:In the underground mining horizontal transport lane of underground mining winding shaft bottom Interior installation lower shaft pumping plant;Because open air trestle mining is at the underground mining stage, usual mining depth is larger, A upper shaft pumping plant should be at least set up in the underground mining horizontal transport lane on underground mining winding shaft top, with alleviation The discharge pressure of portion's vertical shaft pumping plant;Underground water burst is drained into by stope earth's surface by lower shaft pumping plant, the relay of upper shaft pumping plant Outward.
Described lower shaft pumping plant, the draining of upper shaft pumping plant are set up defences must carry out storage row's EQUILIBRIUM CALCULATION FOR PROCESS, and meet The pit maximum flooding quantity of 24h storm frequencies is discharged in 20h, lower shaft pumping plant, the water pump of upper shaft pumping plant is determined therefrom that Number of units;Underground mining stage pit maximum flooding quantity is heavy rain runoff amount, the underground for importing open-air pit in open air trestle exploitation Swelling water yield sum.
4)Spilled water hole is arranged:In open-air pit highwall bottom position, spilled water hole is opened up, bottom and the underground mining of spilled water hole are carried The underground mining horizontal transport lane for rising silo bottom communicates, spilled water hole will open-air pit side slope charge for remittance concentrate under let out to being provided with bottom The underground mining horizontal transport lane of vertical shaft pumping plant.
5)Spilling water well is arranged:Spilling water well, spilling water are built in the underground mining horizontal transport lane for installing lower shaft pumping plant Between underground mining winding shaft, spilled water hole, the suitable for reading of spilling water well communicates well location with open-air pit bottom.When minimum pumping plant level Due to unpredictable flood, when unavoidably being flooded, water burst can be back to open-air pit bottom, it is to avoid underground mining by spilling water well More tunnels are flooded.
Water door is set up in underground mining horizontal transport lane between spilling water well and spilled water hole, can be closed in heavy rain season Close water door, protection down-hole visual plant, facility.
In heavy rain season, draining quantity of sand and mud is big, and in lower shaft pumping plant, upper shaft pumping plant pumping plant desilting is set up respectively System.
Underground mining stage integral harness method is adopted after above technical scheme in a kind of open air trestle exploitation of the present invention, Have the advantages that:Comprehensive employing is cut, prevents, arranging, dredging, storing up multi-pronged anti-aggregate measures of harnessing the river, and is mainly opened by underground Adopt Cut-off ditch outside moving belt scope line, the catch pit of open-air pit bottom, underground mining vertical shaft pumping drainage facility, spilling water well, The facilities such as spilled water hole composition integrated system come administer open air trestle exploitation in the underground mining stage surface water and groundwater.
Cut-off ditch wherein outside underground mining moving belt scope line can reduce openpit charge for remittance, effectively block periphery Water;The catch pit of open-air pit bottom is effectively reduced and drains into groundwater run off, reduces drainage underground pressure;Underground mining vertical shaft pumping plant Pumping equipment can will import the heavy rain runoff amount of open-air pit, underground water water burst and be ultimately discharged into earth's surface;Spilling water well can be inevitable When dangerous situation occurs, underground water burst is drained into into earth's surface;Water door is important water proof equipment, can protect down-hole visual plant, Facility is from water damage.
Description of the drawings
Fig. 1 is the mine vertical section of underground mining stage integral harness method in a kind of open air trestle exploitation of the invention Figure.
Reference is:1- underground mining winding shafts;2- upper shaft pumping plants;3- lower shaft pumping plants;4- spilling water wells; 5- spilled water holes;6- water doors;7- underground mining horizontal transports lane;8- stope earth's surfaces;9- has an opencast mining of the step to be formed;10- ground Lower exploitation moving belt scope line;11- ore bodies;12- catch pits;13- Cut-off ditch;14- open-air pits bottom.
Specific embodiment
To further describe the present invention, in exploiting to a kind of open air trestle of the invention with reference to the accompanying drawings and examples Lower mining phase integral harness method is described in further details.
The mine vertical profile of underground mining stage integral harness method in of the invention a kind of open air trestle exploitation shown in Fig. 1 Face figure finds out that it belongs to remaining Wall ore after strip mining transformation(Have an opencast mining of the underground ore bodies in side slope)Underground mining.This A kind of underground mining stage integral harness method in open air trestle exploitation is invented, first in underground mining moving belt scope line 10 Outer build Cut-off ditch 13, the size of Cut-off ditch 13 is according to actual landform and with reference to the hydrological data Jing meters of catchment area and location Calculation checked and determine after flood discharge capacity, meanwhile, Cut-off ditch should periodically repair maintenance.
Catch pit 12 is set in open-air pit bottom 14, water pump is installed in catch pit 12, using water pump in real time by catch pit 12 The charge for remittance of interior collection is drained into outside stope earth's surface 8;The gathering ground of the size of the catch pit 12 and the selection of water pump according to open-air pit Product and ore district hydrogeologic condition are calculated and determined.
Lower shaft pumping plant 3 is installed in the underground mining horizontal transport lane 7 of the bottom of underground mining winding shaft 1, on ground A upper shaft pumping plant 2 should be at least set up in the underground mining horizontal transport lane 7 on lower exploitation winding shaft 1 top, to alleviate The discharge pressure of lower shaft pumping plant 3.Underground water burst is drained into stope earth's surface by lower shaft pumping plant 3, the relay of upper shaft pumping plant 2 Outside 8.Lower shaft pumping plant 3, the draining of upper shaft pumping plant 2 are set up defences must carry out storage row's EQUILIBRIUM CALCULATION FOR PROCESS.It is existing at present according to China Row safety code specifies that lower shaft pumping plant 3, upper shaft pumping plant 2 must are fulfilled in 20h discharging the pit of 24h storm frequencies Maximum flooding quantity, determines therefrom that the water pump number of units of lower shaft pumping plant 3, upper shaft pumping plant 2.Heavy rain season, draining quantity of sand and mud Greatly, pumping plant desilting system should respectively be set up in lower shaft pumping plant 3, upper shaft pumping plant 2.
In open-air pit highwall bottom position, spilled water hole 5, bottom and the bottom of underground mining winding shaft 1 of spilled water hole 5 are opened up Underground mining horizontal transport lane 7 communicate, spilled water hole 5 will open-air pit side slope charge for remittance concentrate under let out to being provided with lower shaft pumping plant 3 underground mining horizontal transport lane 7;Spilling water well 4 is built in the underground mining horizontal transport lane 7 for installing lower shaft pumping plant 3, Between the exploitation winding shaft 1 located underground of spilling water well 4, spilled water hole 5, the suitable for reading of spilling water well 4 communicates with open-air pit bottom 14;Overflowing Water door 6 is set up in underground mining horizontal transport lane 7 between well 4 and spilled water hole 5.It is minimum when unpredictable flood occurs Underground mining horizontal transport lane 7 when unavoidably being flooded, water burst can be back to open-air pit bottom 14 by spilling water well 4, it is to avoid The more tunnels of underground mining are flooded.

Claims (4)

1. a kind of underground mining stage integral harness method during open air trestle is exploited, in underground mining moving belt scope line(10) Outer build Cut-off ditch(13), Cut-off ditch(13)Size is according to actual landform and with reference to catchment area and the hydrological data of location It is computed checks and determine after flood discharge capacity, it is characterised in that also including technical scheme below:
1)In open-air pit bottom(14)If catch pit(12), in catch pit(12)Interior installation water pump, will be catchmented in real time using water pump Hole(12)The charge for remittance of interior collection drains into stope earth's surface(8)Outward;The catch pit(12)Size and water pump selection according to outdoor The catchment area in hole and ore district hydrogeologic condition are calculated and determined;
2)In underground mining winding shaft(1)The underground mining horizontal transport lane of bottom(7)Interior installation lower shaft pumping plant(3), In underground mining winding shaft(1)The underground mining horizontal transport lane on top(7)Inside should at least set up a upper shaft pumping plant (2), lower shaft pumping plant(3), upper shaft pumping plant(2)Underground water burst is entered stope earth's surface by relay(8)Outward;
3)In open-air pit highwall bottom position, spilled water hole is opened up(5), spilled water hole(5)Bottom and underground mining winding shaft(1) The underground mining horizontal transport lane of bottom(7)Communicate, spilled water hole(5)Will open-air pit side slope charge for remittance concentrate under let out to being provided with bottom Vertical shaft pumping plant(3)Underground mining horizontal transport lane(7);
4)Lower shaft pumping plant is being installed(3)Underground mining horizontal transport lane(7)Inside build spilling water well(4), spilling water well(4)Position In underground mining winding shaft(1), spilled water hole(5)Between, spilling water well(4)It is suitable for reading with open-air pit bottom(14)Communicate.
2. underground mining stage integral harness method during a kind of open air trestle as claimed in claim 1 is exploited, its feature exists In:Described lower shaft pumping plant(3), upper shaft pumping plant(2)Draining set up defences and must carry out storage row's EQUILIBRIUM CALCULATION FOR PROCESS, and meet The pit maximum flooding quantity of 24h storm frequencies is discharged in 20h, lower shaft pumping plant is determined therefrom that(3), upper shaft pumping plant(2) Water pump number of units.
3. underground mining stage integral harness method during a kind of open air trestle as claimed in claim 1 or 2 is exploited, its feature It is:In spilling water well(4)With spilled water hole(5)Between underground mining horizontal transport lane(7)Inside set up water door(6).
4. underground mining stage integral harness method during a kind of open air trestle as claimed in claim 3 is exploited, its feature exists In:In lower shaft pumping plant(3), upper shaft pumping plant(2)Pumping plant desilting system is inside set up respectively.
CN201710075607.XA 2017-02-13 2017-02-13 Comprehensive water managing method in underground mining stage of open pit into underground mining Pending CN106638891A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710075607.XA CN106638891A (en) 2017-02-13 2017-02-13 Comprehensive water managing method in underground mining stage of open pit into underground mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710075607.XA CN106638891A (en) 2017-02-13 2017-02-13 Comprehensive water managing method in underground mining stage of open pit into underground mining

Publications (1)

Publication Number Publication Date
CN106638891A true CN106638891A (en) 2017-05-10

Family

ID=58844785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710075607.XA Pending CN106638891A (en) 2017-02-13 2017-02-13 Comprehensive water managing method in underground mining stage of open pit into underground mining

Country Status (1)

Country Link
CN (1) CN106638891A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107701229A (en) * 2017-09-29 2018-02-16 华北理工大学 Surface mining landfill is administered and underground head stage casings goaf filling draining Synergistic method
CN109736411A (en) * 2019-01-23 2019-05-10 马钢集团矿业有限公司 A kind of method of openpit dredging and mud disposition
CN110714798A (en) * 2019-09-03 2020-01-21 海南矿业股份有限公司 Drainage distribution method for sill pillar-free mine stope
CN113338938A (en) * 2021-04-21 2021-09-03 紫金矿业集团股份有限公司 Safety control method for open-pit and underground collaborative mining of metal mine

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4059963A (en) * 1976-08-19 1977-11-29 Joy Manufacturing Company Method of mine backfilling and material therefor
CN1042966A (en) * 1988-12-01 1990-06-13 韦斯普里米森本亚克 The underground space is the water discharge method in mining area particularly
CN1114712A (en) * 1994-06-04 1996-01-10 崔正洙 Mining and ore dressing process new modle for mine
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN103790590A (en) * 2014-01-22 2014-05-14 中钢集团马鞍山矿山研究院有限公司 Technology for preventing and controlling underground floods in transitional period from surface mine to underground mine
CN103790587A (en) * 2014-01-22 2014-05-14 中钢集团马鞍山矿山研究院有限公司 Method for preventing and controlling underground floods in transitional period from surface mining to underground mining
RU2569145C1 (en) * 2014-08-06 2015-11-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Кемеровский государственный университет" (КемГУ) Set of mechanical and hydraulic recultivation of disturbed lands

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4059963A (en) * 1976-08-19 1977-11-29 Joy Manufacturing Company Method of mine backfilling and material therefor
CN1042966A (en) * 1988-12-01 1990-06-13 韦斯普里米森本亚克 The underground space is the water discharge method in mining area particularly
CN1114712A (en) * 1994-06-04 1996-01-10 崔正洙 Mining and ore dressing process new modle for mine
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN103790590A (en) * 2014-01-22 2014-05-14 中钢集团马鞍山矿山研究院有限公司 Technology for preventing and controlling underground floods in transitional period from surface mine to underground mine
CN103790587A (en) * 2014-01-22 2014-05-14 中钢集团马鞍山矿山研究院有限公司 Method for preventing and controlling underground floods in transitional period from surface mining to underground mining
RU2569145C1 (en) * 2014-08-06 2015-11-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Кемеровский государственный университет" (КемГУ) Set of mechanical and hydraulic recultivation of disturbed lands

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘景秀: "深凹露天转地下开采矿山防排水措施的探讨", 《非金属矿》 *
李定欧: "露天转地下开采矿山防洪排水的探讨", 《冶金矿山设计与建设》 *
杨福海等: "露天转地下开采的若干特殊技术问题", 《河北冶金》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107701229A (en) * 2017-09-29 2018-02-16 华北理工大学 Surface mining landfill is administered and underground head stage casings goaf filling draining Synergistic method
CN109736411A (en) * 2019-01-23 2019-05-10 马钢集团矿业有限公司 A kind of method of openpit dredging and mud disposition
CN110714798A (en) * 2019-09-03 2020-01-21 海南矿业股份有限公司 Drainage distribution method for sill pillar-free mine stope
CN113338938A (en) * 2021-04-21 2021-09-03 紫金矿业集团股份有限公司 Safety control method for open-pit and underground collaborative mining of metal mine

Similar Documents

Publication Publication Date Title
CN111577383B (en) Method for treating tunnel leakage water in alpine region
CN106638891A (en) Comprehensive water managing method in underground mining stage of open pit into underground mining
CN107524459A (en) A kind of Underground Subway Station vertical shaft and transverse passage-way freeze water sealing structure and method
Reynolds et al. The construction of a drainage tunnel as part of glacial lake hazard mitigation at Hualcán, Cordillera Blanca, Peru
CN208533546U (en) A kind of series-parallel underground stereo drainage system suitable for side landslide engineering
CN104612753B (en) What maokou limestone underground grouting dammed closes the anti-method of harnessing the river that stifled lean phase combines
CN111322111A (en) Mine gushing cement sand sedimentation structure
CN103790590A (en) Technology for preventing and controlling underground floods in transitional period from surface mine to underground mine
CN105133618A (en) Construction method of deep foundation pit penetrating through underground permeable layer
CN113027522B (en) Coal mine drainage same-layer recharging method
CN110593949B (en) Mine sluicing wind shielding structure
CN110578552B (en) Connecting structure of mine drainage shaft and drainage roadway
CN213448534U (en) Sealing and lowering combined pressure-bearing water control system
CN105178648A (en) Shore-side plant structure for hydropower station in easy-to-seep mountainous area
CN103790587B (en) A kind of method of preventing and treating open air trestle exploitation transitional period down-hole flood
CN205046886U (en) A bank factory building structure for exchanging ooze mountain area power station
Younger ‘Making water’: the hydrogeological adventures of Britain’s early mining engineers
CN110552737A (en) Flow guiding device for mine drainage roadway
CN210768907U (en) Mine sluicing air door device
CN214460675U (en) Construction structures is used safely to old basement
Šubaranović et al. Multi-Attribute Scenario Analysis of Protection of Drmno Open Pit Mine against Groundwater
CN205046530U (en) Mountain area power station is with bank factory building structure
CN210768904U (en) Flow guiding device for mine drainage roadway
CN208585629U (en) A kind of coal store inflatable protective device
Baimirzaev et al. Substantiation and Selection of Optimal Method of Angren Section Field Drainage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510