CN103790590A - Technology for preventing and controlling underground floods in transitional period from surface mine to underground mine - Google Patents

Technology for preventing and controlling underground floods in transitional period from surface mine to underground mine Download PDF

Info

Publication number
CN103790590A
CN103790590A CN201410027231.1A CN201410027231A CN103790590A CN 103790590 A CN103790590 A CN 103790590A CN 201410027231 A CN201410027231 A CN 201410027231A CN 103790590 A CN103790590 A CN 103790590A
Authority
CN
China
Prior art keywords
underground
stage casing
transition
stage
open
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410027231.1A
Other languages
Chinese (zh)
Other versions
CN103790590B (en
Inventor
王运敏
汪为平
章林
孙丽军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority to CN201410027231.1A priority Critical patent/CN103790590B/en
Publication of CN103790590A publication Critical patent/CN103790590A/en
Application granted granted Critical
Publication of CN103790590B publication Critical patent/CN103790590B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)
  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The invention discloses a technology for preventing and controlling underground floods in the transitional period from a surface mine to an underground mine. The mining stage is divided into a surface mining stage (1), a transition stage (2) from surface to underground and an underground mining stage (3), wherein the transition stage (2) from surface to underground is divided into a linking production middle section (4) and an emergency middle section (5); the interior of the emergency middle section (5) is uniformly divided into rooms (13) and jambs (14); ore bodies on the lower layers of the rooms (13) are firstly extracted; upward drainage wells (6) are excavated in the rooms (13) to communicate with the linking production middle section (4); after extraction of a plurality of rooms (13) in the emergency middle section (5) is completed, places of underground rainwater in the water inrush period are formed; when rainstorm seasons come, rainwater floods into the rooms (13) of the emergency middle section (5), flows into a main sump via a drainage well (12) and then is drained to safe sections of surfaces via a water pump, thus solving the problem of insufficient underground preventing and draining capabilities in the transitional period from the surface mine to the underground mine in rainstorm seasons and providing guarantees for safe transition from the surface mine to the underground mine.

Description

Transition from open-pit underground mine transitional period down-hole flood Prevention Technique
Technical field
The present invention relates to transition from open-pit underground mining technology, be specifically related to the safety guarantee technology of the interior underground mining flood improvement of transitional period of transition from open-pit underground mining.Can extensive use in the non-coal solid mine transition from open-pit underground minings such as black, coloured, gold.
Background technology
Transition from open-pit underground mine is in order to maintain mine smooth transition within the transitional period, and most mines adopt combined surface and underground mining.Down-hole adopts Caving Method with Large Space exploitation can cause surface subsidence directly and open-air pit connects, the open-air pit of depression forms huge catchment area, in heavy rain season, a large amount of rainwater flow into underground mining stope via the roadway communicating with open-air pit and bed course space, lead to the well accident of flooding, transitional period flood prevention is a very important problem.
" discussion of transition from open-pit underground mining mine flood control and water drain " that the 3rd phase of " metallurgical mine design and construction " May in 1997 delivers, what delivered " technique of preparing net " on August 16th, 2008 " ventilates during transition from open-pit underground mining, cold-proof and flood control " and " after transition from open-pit underground mining, atmospheric precipitation disaster prevents technical research " article of delivering of " energy technology and management " the 5th phase in 2011, all emphasize the importance of transition from open-pit underground mine transitional period flood control and water drain, and mention the flood control and water drain measure that take in some mines, as: the outer excavation of boundary cut Great Gulch in the open, surface water beyond outdoor boundary and surface rock changing of the relative positions boundary line is drawn, on the security platform in hole, establish the pumping plant that dams in the open, the charge for remittance in open-air pit is displaced into beyond open-air pit and changing of the relative positions boundary, in suitable tunnel, down-hole (developing of general using next stage and development heading), the water dam of device with regulation gate valve, the lower water pump in hole should be arranged in the top bench that is easy to catchment as far as possible, etc.But lead off at heavy rain rainwater in season instantaneous time, the anti-drainage measure in earth's surface is difficult to stop, sump volume, the drainage plant ability of down-hole are also limited, rainwater cannot be stored or discharge earth's surface, flood that well accident is more difficult to be avoided.
Summary of the invention
Object of the present invention is exactly for the above-mentioned defect existing in prior art, and provides one to be suitable for transition from open-pit underground mine transitional period down-hole flood Prevention Technique, and this technology can realize the underground transitional safe working of transition from open-pit.
For realizing above-mentioned purpose of the present invention, transition from open-pit underground mine of the present invention transitional period down-hole flood Prevention Technique realizes by following scheme:
1) be divided into strip mining transformation stage, the underground transition stage of transition from open-pit, underground mining stage the mining stage.
Underground described transition from open-pit transition stage is further subdivided into and is connected production stage casing, emergent stage casing, and emergent stage casing is positioned at the bottom that is connected production stage casing; When mining phase enters latter stage, start to build underground developing system to being connected production stage casing in the open, the system of the mining phase that goes underground completely can complete in linking stages manufacturing process.Described linking production stage casing connects by being connected stage casing development drift and main shaft; Be connected the side lower part construction accessory system of production stage casing near main shaft, be connected stage casing development drift and connect by blind inclined shaft or perpendicular blind shaft, emergent stage casing development drift and the emergent stage casing of accessory system.
2) in emergent stage casing, evenly divide mineral building and ore pillar according to 14-16m, the high ore body of the first rooming 19-21m of lower floor, ore pillar wouldn't be exploited.
3) in mineral building, dig upwards drainage sump and be connected production stage casing and link up, after in emergent stage casing, multiple mineral building back production finish, this stage casing has formed the storage house of down-hole rainwater during gushing water, in the development drift of the emergent stage casing of accessory system, installs airtight waterproof door.
4), when heavy rain is interim season, rainwater pours in linking production stage casing through connecting channel, then flows into emergent stage casing through drainage sump; After linking production stage casing back production finishes, underground mining developing system also completes substantially, now rainwater in emergent stage casing can be flowed into the main sump that divide into by drainage sump, underground mining stage development drift by amount, then drains into safe location, earth's surface through water pump.
The height of the described underground transition stage of transition from open-pit is advisable with 100m~120m, is connected the height in production stage casing in 60m~80m scope.
The size in the emergent stage casing in the underground transition stage of described transition from open-pit is take 40m as good, and mineral building, ore pillar width 15m are good, and rooming lower floor ore body height is 20m.
Transition from open-pit underground mine of the present invention transitional period down-hole flood Prevention Technique has following good effect by above technical scheme:
1) dead zone forming after ore body back production in emergent stage casing as gushing water during the storage house of water burst, this volume is far longer than shaft sump volume, for underground mining provides safety guarantee;
2) in the underground transitional period of transition from open-pit, underground mining method choice is strengthened, and without considering flood impact, and abandons the Caving Method with Large Space that production capacity is larger.
Accompanying drawing explanation
Fig. 1 is transition from open-pit underground mine of the present invention transitional period down-hole flood Prevention Technique schematic diagram.
In figure, be labeled as:
1-strip mining transformation stage; The underground transition stage of 2-transition from open-pit; 3-underground mining stage; 4-linking production stage casing; 5-emergent stage casing; 6-drainage sump; 7-rock drilling lane/moat ditch; 8-rock drilling lane; 9-ore removal lane; 10-water door; 11-blind inclined shaft; 12-drainage sump; 13-mineral building; 14-ore pillar; 15-linking stage casing development drift; 16-emergent stage casing development drift; 17-underground mining stage development drift.
The specific embodiment
For further describing the present invention, below in conjunction with accompanying drawing, transition from open-pit underground mine of the present invention transitional period down-hole flood Prevention Technique is described in further detail.
The schematic diagram of the transition from open-pit underground mine transitional period down-hole flood Prevention Technique shown in Fig. 1 finds out, transition from open-pit underground mine is divided into three phases by the present invention: strip mining transformation stage 1, the underground transition stage 2 of transition from open-pit, underground mining stage 3.Turn underground transition stage in the open and be divided into again linking production stage casing 4 and emergent stage casing 5, emergent stage casing 5 is positioned at the bottom that is connected production stage casing 4.Emergent stage casing 5 is highly 40m, and being connected production stage casing 4 is highly 60m~80m.
Mining phase 1 closes before hole in the open, start to build Underground Mining System to being connected production stage casing 4, being connected the side lower part construction accessory system of production stage casing 4 near main shaft, be connected stage casing development drift 15 and connect with emergent stage casing 5 by the blind inclined shaft 11 of accessory system, emergent stage casing development drift 16.
In emergent stage casing 5, evenly divide mineral building 13 and ore pillar 14 according to 15m, first in the higher slice rock drilling lane of mineral building 13, correct position is dug drainage sump 6 and is connected production stage casing 4 and links up, then the compensation space while digging cutting well and cutting lane as back production in the end of mineral building 13, on the interior Drilling in rock drilling lane 7 to fanhole(s) back production lower floor ore body, adopt lower ore body and transport through the ore removal lane 9 that is positioned at mineral building 13, ore pillar 14 junctions, bottom, ore pillar 14 wouldn't be exploited.
After the ore body back production of the emergent stage casing 5 interior lower floor of interior all mineral buildings 13 finishes, this stage casing has formed the storage house of down-hole rainwater during gushing water, installs airtight waterproof door 10 at the correct position of the emergent stage casing of accessory system development drift 16.Interim season when heavy rain, rainwater pours in linking production stage casing 4 through connecting channel, then flows into emergent stage casings through drainage sump 6.After linking production stage casing 4 back production finish, underground mining developing system also completes substantially, now rainwater in emergent stage casing can be flowed into the main sump of dividing into by drainage sump 12, underground mining stage development drift 17 by amount, then drain into safe location, earth's surface through water pump.

Claims (3)

1. a transition from open-pit underground mine transitional period down-hole flood Prevention Technique, is divided into strip mining transformation stage (1), the underground transition stage of transition from open-pit (2), underground mining stage (3) by the mining stage, it is characterized in that by the following technical solutions:
1) underground described transition from open-pit transition stage (2) is further subdivided into and is connected production stage casing (4), emergent stage casing (5), emergent stage casing (5) is positioned at the bottom that is connected production stage casing (4); When mining phase (1) enters latter stage, start to build underground developing system to being connected production stage casing (4) in the open, described linking production stage casing (4) connects with main shaft by being connected stage casing development drift (15); Build accessory system at the side lower part that is connected the close main shaft in production stage casing (4), be connected stage casing development drift (15) and connect by blind inclined shaft (11) or perpendicular blind shaft, emergent stage casing development drift (16) and the emergent stage casing (5) of accessory system;
2) in emergent stage casing (5), evenly divide mineral building (13) and ore pillar (14) according to 14-16m, the high ore body of first rooming (13) 19-21m of lower floor, ore pillar (14) wouldn't be exploited;
3) in mineral building (13), dig upwards drainage sump (6) and be connected production stage casing (4) and link up, after in emergent stage casing (5), multiple mineral buildings (13) back production finishes, this stage casing has formed the storage house of down-hole rainwater during gushing water, installs airtight waterproof door (10) in the emergent stage casing of accessory system development drift (16);
4) when heavy rain is interim season, rainwater pours in linking production stage casing (4) through connecting channel, then flows into emergent stage casing (5) through drainage sump (6); After linking production stage casing (4) back production finishes, underground mining developing system also completes substantially, now the interior rainwater in the stage casing of meeting an urgent need (5) can be flowed into the main sump of dividing into by drainage sump (12), underground mining stage development drift (17) by amount, then drain into safe location, earth's surface through water pump.
2. transition from open-pit underground mine as claimed in claim 1 transitional period down-hole flood Prevention Technique, is characterized in that: the height of the underground transition stage of described transition from open-pit (2) is 100m~120m, and the height that is connected production stage casing (4) is 60m~80m.
3. transition from open-pit underground mine as claimed in claim 1 or 2 transitional period down-hole flood Prevention Technique, it is characterized in that: the emergent stage casing (5) in the underground transition stage of described transition from open-pit (2) is of a size of 40m, mineral building (12), ore pillar (13) width 15m, rooming (12) lower floor ore body height is 20m.
CN201410027231.1A 2014-01-22 2014-01-22 Transitional period down-hole, open air trestle mine flood prevention and controls Active CN103790590B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410027231.1A CN103790590B (en) 2014-01-22 2014-01-22 Transitional period down-hole, open air trestle mine flood prevention and controls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410027231.1A CN103790590B (en) 2014-01-22 2014-01-22 Transitional period down-hole, open air trestle mine flood prevention and controls

Publications (2)

Publication Number Publication Date
CN103790590A true CN103790590A (en) 2014-05-14
CN103790590B CN103790590B (en) 2015-09-09

Family

ID=50666601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410027231.1A Active CN103790590B (en) 2014-01-22 2014-01-22 Transitional period down-hole, open air trestle mine flood prevention and controls

Country Status (1)

Country Link
CN (1) CN103790590B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638891A (en) * 2017-02-13 2017-05-10 中钢集团马鞍山矿山研究院有限公司 Comprehensive water managing method in underground mining stage of open pit into underground mining
CN107083984A (en) * 2017-06-14 2017-08-22 陕西有色榆林煤业有限公司 A kind of colliery central water sump whole wind pressure ventilation system and design method
CN110206544A (en) * 2019-05-20 2019-09-06 中铁十九局集团矿业投资有限公司 A kind of hole bottom ore body stoping method behind open-pit slope landslide
CN110578552A (en) * 2019-10-16 2019-12-17 海南矿业股份有限公司 Connecting structure of mine drainage shaft and drainage roadway
CN111852553A (en) * 2020-07-06 2020-10-30 紫金矿业集团股份有限公司 Method for rapidly sinking and trenching open-pit mine with large water inrush quantity
CN111852554A (en) * 2020-07-06 2020-10-30 紫金矿业集团股份有限公司 Rapid trenching method for large water inrush quantity pit open-pit mine small-block full-section deep one-time blasting

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4059963A (en) * 1976-08-19 1977-11-29 Joy Manufacturing Company Method of mine backfilling and material therefor
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN1580490A (en) * 2004-05-19 2005-02-16 陈安琪 Open production method for lake bottom copper mine
CN101737047A (en) * 2008-11-19 2010-06-16 孙广义 Method for mining coal of steeply inclined thin seam
CN102606161A (en) * 2012-03-26 2012-07-25 中钢集团马鞍山矿山研究院有限公司 Outdoor underground three-period mining method of inclined, thick and large mineral deposit
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN102913246A (en) * 2012-10-30 2013-02-06 中国科学院地质与地球物理研究所 Solid potash ore open-pit mining method under condition of tropical monsoon climate
CN103089266A (en) * 2012-12-18 2013-05-08 鞍钢集团矿业公司 Drift-pillar-free sublevel barnyard caving mining method of open pit transferred underground transitional period

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4059963A (en) * 1976-08-19 1977-11-29 Joy Manufacturing Company Method of mine backfilling and material therefor
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN1580490A (en) * 2004-05-19 2005-02-16 陈安琪 Open production method for lake bottom copper mine
CN101737047A (en) * 2008-11-19 2010-06-16 孙广义 Method for mining coal of steeply inclined thin seam
CN102606161A (en) * 2012-03-26 2012-07-25 中钢集团马鞍山矿山研究院有限公司 Outdoor underground three-period mining method of inclined, thick and large mineral deposit
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN102913246A (en) * 2012-10-30 2013-02-06 中国科学院地质与地球物理研究所 Solid potash ore open-pit mining method under condition of tropical monsoon climate
CN103089266A (en) * 2012-12-18 2013-05-08 鞍钢集团矿业公司 Drift-pillar-free sublevel barnyard caving mining method of open pit transferred underground transitional period

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘志翔: "德兴铜矿铜厂露天矿排水系统", 《露天采矿技术》 *
周万忠: "拉拉铜矿中露天矿山防洪疏干系统浅析", 《采矿技术》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638891A (en) * 2017-02-13 2017-05-10 中钢集团马鞍山矿山研究院有限公司 Comprehensive water managing method in underground mining stage of open pit into underground mining
CN107083984A (en) * 2017-06-14 2017-08-22 陕西有色榆林煤业有限公司 A kind of colliery central water sump whole wind pressure ventilation system and design method
CN110206544A (en) * 2019-05-20 2019-09-06 中铁十九局集团矿业投资有限公司 A kind of hole bottom ore body stoping method behind open-pit slope landslide
CN110578552A (en) * 2019-10-16 2019-12-17 海南矿业股份有限公司 Connecting structure of mine drainage shaft and drainage roadway
CN111852553A (en) * 2020-07-06 2020-10-30 紫金矿业集团股份有限公司 Method for rapidly sinking and trenching open-pit mine with large water inrush quantity
CN111852554A (en) * 2020-07-06 2020-10-30 紫金矿业集团股份有限公司 Rapid trenching method for large water inrush quantity pit open-pit mine small-block full-section deep one-time blasting
CN111852554B (en) * 2020-07-06 2021-07-16 紫金矿业集团股份有限公司 Rapid trenching method for large water inrush quantity pit open-pit mine small-block full-section deep one-time blasting
CN111852553B (en) * 2020-07-06 2021-08-03 紫金矿业集团股份有限公司 Method for rapidly sinking and trenching open-pit mine with large water inrush quantity

Also Published As

Publication number Publication date
CN103790590B (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN103790590B (en) Transitional period down-hole, open air trestle mine flood prevention and controls
CN102562065B (en) Sublevel open-stop and delayed filling mining method
CN103790589B (en) Transition connection mining technique from outdoor mine to underground mine
CN109577980B (en) Underground longwall working face water-retaining coal mining method based on aquifer freezing
CN107524459B (en) Freezing water stop structure and method for vertical shaft and transverse passage of subway underground excavation station
CN104047623A (en) Large-span grotto excavation construction method
CN104847355A (en) Continuous mining method for hollow ground of medium-thickness steeply inclined ore body
CN104564074A (en) Method for implementing water-preserved coal mining of coal mining area
CN104373125A (en) Two-step upward high-layering bagging cut-and-filling stoping method
CN107829736A (en) A kind of colliery Striping noise and filling displacement coal column method
CN102080568B (en) Method for reducing water pressure of covering layer of mine transferred from opencast mine to underground mine
CN105804754A (en) Coal uncovering method for mining shaft with coal seam as main water-bearing layer
CN110067597A (en) A kind of mine angle of depression negative pressure visits the method for putting old dead zone ponding
CN106285731B (en) A kind of small courtyard radiant type of high Large chamber and the mixed construction method of step
CN107701229B (en) Surface mining landfill, which is administered, drains Synergistic method with underground head middle section goaf filling
CN207211100U (en) Vertical shaft type powerhouse of hydropower station structure
CN111594168B (en) Pseudo-goaf-layer supporting and sinking-limiting stoping method formed by matching rock waste with rock waste
CN103790587B (en) A kind of method of preventing and treating open air trestle exploitation transitional period down-hole flood
CN204676504U (en) The emptying maintenance structure of a kind of long tailwater tunnel group without gravity flow ejectment condition
CN103291307B (en) A kind of rich water rockhole Dewatering by leading level method
CN204899930U (en) Secretly dig leading dry out well in subway hole
CN107386222A (en) Vertical shaft type powerhouse of hydropower station structure
CN104088664B (en) A kind of mine wastewater treatment method and system of upwards filling mining
RU2010114898A (en) METHOD FOR STRUCTURE OF UNDERWATER TUNNELS
RU2465405C2 (en) Drainage method of open pit edges by means of systems of combined drainage devices

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Address before: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Patentee before: SINOSTEEL MAANSHAN INSTITUTE OF MINING RESEARCH Co.,Ltd.

CP01 Change in the name or title of a patent holder