CN106638678A - Underground structure lining wall and underground continuous wall overlapped surface structure and construction method thereof - Google Patents

Underground structure lining wall and underground continuous wall overlapped surface structure and construction method thereof Download PDF

Info

Publication number
CN106638678A
CN106638678A CN201510736401.8A CN201510736401A CN106638678A CN 106638678 A CN106638678 A CN 106638678A CN 201510736401 A CN201510736401 A CN 201510736401A CN 106638678 A CN106638678 A CN 106638678A
Authority
CN
China
Prior art keywords
profiled sheet
diaphram wall
underground structure
underground
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510736401.8A
Other languages
Chinese (zh)
Other versions
CN106638678B (en
Inventor
朱世友
贺维国
江水德
于勇
谭宁波
江婕瑞
徐韬
朱剑平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN201510736401.8A priority Critical patent/CN106638678B/en
Publication of CN106638678A publication Critical patent/CN106638678A/en
Application granted granted Critical
Publication of CN106638678B publication Critical patent/CN106638678B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

The invention belongs to the field of underground engineering construction, and in particular, relates to an underground structure lining wall and underground continuous wall overlapped surface structure and a construction method thereof. The structure is characterized by comprising an underground structure lining wall and an underground continuous wall; the underground continuous wall is constructed on the outer side of the underground structure lining wall to serve as a surrounding structure; profiled steel sheets are paved between the underground structure lining wall and the underground continuous wall, and are concave-convex; concrete protection layers are arranged between the profiled steel sheets and vertical reinforcements on the inner side of the underground continuous wall; the adjacent profiled steel sheets are joined with each other; fixed pieces are arranged between the profiled steel sheets and the vertical reinforcements on the inner side of the underground continuous wall; the profiled steel sheets are connected with the fixed pieces; and the fixed pieces are fixedly welded with reinforcement cages of the underground continuous wall. As the profiled steel sheets are arranged on the inner side of the underground continuous wall, the underground structure lining wall and the underground continuous wall form an overall stress structure component; and meanwhile, the profiled steel sheets serve as waterproof units of the underground structure lining wall.

Description

A kind of underground structure inwall overlaps surface construction and its construction method with diaphram wall
Technical field
The invention belongs to underground engineering construction field, more particularly to a kind of underground structure inwall and diaphram wall overlapping surface construction and its construction method of construction of underground structure suitable for subway station, underground parking garage and skyscraper.
Background technology
When underground structure inwall outside has performed diaphram wall as its foundation pit enclosure structure, structure design is usually descended to consider that diaphram wall participates in underground structure stress, it is normal at present to carry out calculating design by composite wall or overlapping wall.Overlapping wall is that diaphram wall is poured with after underground structure inwall to form a whole force structure component, i.e. by manually diaphram wall inner side being dug into male and fomale(M&F) or arranging steel tie makes diaphram wall couple together with underground structure inwall, and structure roof, the tension reinforcement of middle plate and base plate is attached by embedded bar connector and diaphram wall, positive pressure and shearing can be transmitted between diaphram wall and underground structure inwall, general underground structure liner wall thickness can use 400mm, the bending rigidity of overlapping wall is larger, and the arrangement of reinforcement on the outside of underground structure inwall is less.
Composite wall to be referred to and be provided with watertight insulation between diaphram wall and underground structure inwall, diaphram wall, underground structure inwall are two independent primary structure members, underground structure liner wall thickness generally requires 700mm-800mm, the bending rigidity of composite wall is less, and arrangement of reinforcement is more on the outside of underground structure inwall;Watertight insulation on the outside of inwall forms an entirety with structure roof waterproof layer, base plate waterproofing, and the water resistance of composite wall is preferable.Diaphram wall only undertakes the support action in construction stage engineering, and two components not Transfer of Shear, the steel bar stress of structure roof, middle plate and base plate need not be connected with diaphragm wall;In operational phase, diaphram wall participates in structural anti-buoyancy effect.
According to《Urban track traffic design specification》, when superposed surfaces do not match somebody with somebody lacing wire, diaphram wall medial surface dabbing is required:Dig out green stone to show up, male and fomale(M&F) mean depth 20mm.Diaphram wall medial surface digs male and fomale(M&F), needs a large amount of manpowers.Face is poured due to there is new-old concrete between diaphram wall and structure inwall, crack easily occurs in structure inwall, cause structure inwall percolating water, structure reinforcing bars easily to corrode, reduce the durability of structure.In the built subway station by overlapping wall design, much there is structural percolating water, later stage Treatment Measures to Leakage is costly.
The content of the invention
Perform manpower needed for male and fomale(M&F), solve the deficiency of underground structure inwall percolating water to save diaphram wall, it is an object of the invention to provide a kind of underground structure inwall overlaps surface construction and its construction method with diaphram wall.
The technical solution adopted in the present invention is:
A kind of underground structure inwall overlaps surface construction with diaphram wall, it is characterised in that:Including underground structure inwall, diaphram wall, the underground structure inwall outside has performed diaphram wall as its building enclosure, the underground structure inwall, profiled sheet is equipped between diaphram wall, the profiled sheet is in concave-convex, the diaphram wall inner side is provided with diaphram wall inner side vertical reinforcement, concrete cover is provided between the profiled sheet and diaphram wall inner side vertical reinforcement, mutually overlap between the adjacent profiled sheet, fixture is provided between the profiled sheet and diaphram wall inner side vertical reinforcement, the profiled sheet is connected with fixture, the fixture is welded and fixed with the steel reinforcement cage of diaphram wall.
The fixture is cableway or shaped steel.
Profiled sheet structure roof top surface absolute altitude located underground is between the absolute altitude of underground structure bottom plate bottom surface.
The profiled sheet indention.
The profiled sheet undulate, the peak line of the profiled sheet, hollow line are horizontally disposed with.
The profiled sheet is rolled using galvanized steel plain sheet or general steel plate.
Profiled sheet wave height >=the 10mm, is connected between the profiled sheet using pulling rivet.
By welding or securing member connection between the profiled sheet and fixture.
A kind of underground structure inwall overlaps the construction method of surface construction with diaphram wall, it is characterised in that comprise the following steps:(1)First make diaphram wall steel reinforcement cage by usual method, then some fixtures are set in steel reinforcement cage top surface, by being welded and fixed between fixture and diaphram wall steel reinforcement cage, finally profiled sheet is laid on fixture, mutually overlap between profiled sheet, connected using pulling rivet between profiled sheet, by welding or securing member connection between profiled sheet and fixture;(2)Soil body stage excavation in foundation ditch, often excavates one layer of earthwork, and diaphram wall inner side profiled sheet surface is cleaned, and rubber strip is laid between underground continuous wall connector or so profiled sheet, and rubber strip is overlapped with profiled sheet, and using fluid sealant adhering and sealing.
The step(2)In, transverse joint or vertical abutment joint are using welding or sealant sealing between the continuous profiled sheet within the walls of each width.
Beneficial effects of the present invention are:
1st, diaphram wall inner side is provided with concavo-convex profiled sheet, diaphram wall inner side self-assembling formation male and fomale(M&F), it is not necessary to artificial chisel diaphram wall superposed surfaces in the present invention;
2nd, than artificial chisel male and fomale(M&F) reliability, shear bond strength bearing capacity is significantly improved the quality of underground structure inwall and diaphram wall superposed surfaces;
3rd, profiled sheet defines the steel plate waterproof layer on the outside of underground structure inwall, solves current underground structure overlapping wall and percolating water phenomenon easily occurs.
Description of the drawings
Fig. 1 is the structural representation of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings the invention will be further described:
In figure, 1- diaphram walls, 2- underground structure inwalls, 3- profiled sheets, 4- diaphram walls inner side vertical reinforcement, 5- fixtures, 6- concrete covers, 7- pulling rivets.
Embodiment 1
As shown in Figure 1, the outside of underground structure inwall 2 has performed diaphram wall 1, the joint form of diaphram wall 1 adopts cross steel plate, from from underground structure top board top surface absolute altitude+0.1m between the absolute altitude -0.1m of underground structure bottom plate bottom surface, the inner side of diaphram wall 1 is equipped with profiled sheet 3, the inner side of diaphram wall 1 is provided with diaphram wall inner side vertical reinforcement 4, the waveform of the concave-convex surface of profiled sheet 3, profiled sheet 3 is vertically continuous, the peak line and hollow line of profiled sheet 3 is level, 30mm concrete covers 6 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, profiled sheet 3 is rolled using galvanized steel plain sheet, wave height 28mm of profiled sheet 3, mutually overlap between adjacent profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3;Some fixtures 5 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, fixture 5 selects cableway, cableway diameter 14mm, cableway is welded and fixed with the steel reinforcement cage of diaphram wall 1, and profiled sheet 3 is with cableway by being welded to connect.
Construction procedure:(1) first by the steel reinforcement cage of usual method making diaphram wall 1, then cableway is set in steel reinforcement cage top surface laterally spaced 0.7m, by being welded and fixed between the steel reinforcement cage of cableway and diaphram wall 1, finally some pieces of profiled sheets 3 are laid on cableway, 20mm is overlapped between profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3, spacing 0.25m of pulling rivet 7;(2) soil body stage excavation in foundation ditch, often excavate one layer of earthwork, the surface of profiled sheet 3 of the inner side of diaphram wall 1 is cleaned, vertical abutment joint adopts sealant sealing between the profiled sheet 3 of the inner side of each width diaphram wall 1, rubber strip is laid between the joint both sides profiled sheet 3 of diaphram wall 1, rubber strip is with the mutually overlap joint of profiled sheet 3 and bonding by fluid sealant, because the inner side of diaphram wall 1 is provided with profiled sheet 3, so that the concavo-convex wavy surface of the inner surface self-assembling formation of diaphram wall 1, diaphram wall 1 forms overall force structure component with underground structure inwall 2, while waterproof unit of the profiled sheet 3 as underground structure inwall 2.
Embodiment 2
As shown in Figure 1, the outside of underground structure inwall 2 has performed diaphram wall 1, the joint form of diaphram wall 1 adopts cross steel plate, from from underground structure top board top surface absolute altitude+0.1m between the absolute altitude -0.1m of underground structure bottom plate bottom surface, the inner side of diaphram wall 1 is equipped with profiled sheet 3, the inner side of diaphram wall 1 is provided with diaphram wall inner side vertical reinforcement 4, the zigzag of the concave-convex surface of profiled sheet 3, profiled sheet 3 is vertically continuous, the peak line and hollow line of profiled sheet 3 is level, 25mm concrete covers 6 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, profiled sheet 3 is rolled using general steel plate, wave height 30mm of profiled sheet 3, mutually overlap between adjacent profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3;Some fixtures 5 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, fixture 5 selects shaped steel, and shaped steel is equal leg angle, angle steel length of side 25mm, shaped steel is welded and fixed with the steel reinforcement cage of diaphram wall 1, and profiled sheet 3 is connected with shaped steel by securing member.
Construction procedure:(1) first by the steel reinforcement cage of usual method making diaphram wall 1, then shaped steel is set in steel reinforcement cage top surface laterally spaced 0.5m, by being welded and fixed between the steel reinforcement cage of shaped steel and diaphram wall 1, finally some pieces of profiled sheets 3 are laid on shaped steel, 25mm is overlapped between profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3, spacing 0.30m of pulling rivet 7;(2) soil body stage excavation in foundation ditch, often excavate one layer of earthwork, the surface of profiled sheet 3 of the inner side of diaphram wall 1 is cleaned, vertical abutment joint adopts sealant sealing between the profiled sheet 3 of the inner side of each width diaphram wall 1, rubber strip is laid between the joint both sides profiled sheet 3 of diaphram wall 1, rubber strip is with the mutually overlap joint of profiled sheet 3 and bonding by fluid sealant, because the inner side of diaphram wall 1 is provided with profiled sheet 3, so that the concavo-convex hackly surface of the inner surface self-assembling formation of diaphram wall 1, diaphram wall 1 forms overall force structure component with underground structure inwall 2, while waterproof unit of the profiled sheet 3 as underground structure inwall 2.
Embodiment 3
As shown in Figure 1, the outside of underground structure inwall 2 has performed diaphram wall 1, the joint form of diaphram wall 1 adopts cross steel plate, from from underground structure top board top surface absolute altitude+0.1m between the absolute altitude -0.1m of underground structure bottom plate bottom surface, the inner side of diaphram wall 1 is equipped with profiled sheet 3, the inner side of diaphram wall 1 is provided with diaphram wall inner side vertical reinforcement 4, the waveform of the concave-convex surface of profiled sheet 3, profiled sheet 3 is vertically continuous, the peak line and hollow line of profiled sheet 3 is level, 35mm concrete covers 6 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, profiled sheet 3 is rolled using general steel plate, wave height 18mm of profiled sheet 3, mutually overlap between adjacent profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3;Some fixtures 5 are provided between profiled sheet 3 and diaphram wall inner side vertical reinforcement 4, fixture 5 selects cableway, cableway diameter 18mm, cableway is welded and fixed with the steel reinforcement cage of diaphram wall 1, and profiled sheet 3 is with cableway by being welded to connect.
Construction procedure:(1) first by the steel reinforcement cage of usual method making diaphram wall 1, then cableway is set in steel reinforcement cage top surface laterally spaced 0.9m, by being welded and fixed between the steel reinforcement cage of cableway and diaphram wall 1, finally some pieces of profiled sheets 3 are laid on cableway, 15mm is overlapped between profiled sheet 3, connected using pulling rivet 7 between profiled sheet 3, spacing 0.20m of pulling rivet 7;(2) soil body stage excavation in foundation ditch, often excavate one layer of earthwork, the surface of profiled sheet 3 of the inner side of diaphram wall 1 is cleaned, vertical abutment joint adopts sealant sealing between the profiled sheet 3 of the inner side of each width diaphram wall 1, rubber strip is laid between the joint both sides profiled sheet 3 of diaphram wall 1, rubber strip is with the mutually overlap joint of profiled sheet 3 and bonding by fluid sealant, because the inner side of diaphram wall 1 is provided with profiled sheet 3, so that the concavo-convex wavy surface of the inner surface self-assembling formation of diaphram wall 1, diaphram wall 1 forms overall force structure component with underground structure inwall 2, while waterproof unit of the profiled sheet 3 as underground structure inwall 2.
3 embodiments of the present invention have been described in detail above, but the content is only presently preferred embodiments of the present invention, it is impossible to it is considered as the practical range for limiting the present invention.All impartial changes made according to the present patent application scope and improvement etc., all should still belong within the patent covering scope of the present invention.

Claims (10)

1. a kind of underground structure inwall overlaps surface construction with diaphram wall, it is characterised in that:Including underground structure inwall, diaphram wall, the underground structure inwall outside has performed diaphram wall as its building enclosure, the underground structure inwall, profiled sheet is equipped between diaphram wall, the profiled sheet is in concave-convex, concrete cover is provided between the profiled sheet and diaphram wall inner side vertical reinforcement, mutually overlap between the adjacent profiled sheet, fixture is provided between the profiled sheet and diaphram wall inner side vertical reinforcement, the profiled sheet is connected with fixture, the fixture is welded and fixed with the steel reinforcement cage of diaphram wall.
2. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:The fixture is cableway or shaped steel.
3. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:Profiled sheet structure roof top surface absolute altitude located underground is between the absolute altitude of underground structure bottom plate bottom surface.
4. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:The profiled sheet indention.
5. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:The profiled sheet undulate, the peak line of the profiled sheet, hollow line are horizontally disposed with.
6. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:The profiled sheet is rolled using galvanized steel plain sheet or general steel plate.
7. a kind of underground structure inwall according to claim 5 overlaps surface construction with diaphram wall, it is characterised in that:Profiled sheet wave height >=the 10mm, is connected between the profiled sheet using pulling rivet.
8. a kind of underground structure inwall according to claim 1 overlaps surface construction with diaphram wall, it is characterised in that:By welding or securing member connection between the profiled sheet and fixture.
9. a kind of underground structure inwall and diaphram wall overlap the construction method of surface construction, it is characterised in that comprise the following steps:(1)First make diaphram wall steel reinforcement cage by usual method, then fixture is set in steel reinforcement cage top surface, by being welded and fixed between fixture and diaphram wall steel reinforcement cage, finally profiled sheet is laid on fixture, mutually overlap between profiled sheet, connected using pulling rivet between profiled sheet, profiled sheet is connected with fixture;(2)Soil body stage excavation in foundation ditch, often excavates one layer of earthwork, and diaphram wall inner side profiled sheet surface is cleaned, and rubber strip is laid between underground continuous wall connector or so profiled sheet, and rubber strip is overlapped with profiled sheet, and using fluid sealant adhering and sealing.
10. a kind of underground structure inwall according to claim 9 and diaphram wall overlap the construction method of surface construction, it is characterised in that:The step(2)In, transverse joint or vertical abutment joint are using welding or sealant sealing between the continuous profiled sheet within the walls of each width.
CN201510736401.8A 2015-11-03 2015-11-03 A kind of underground structure inwall and diaphram wall overlapping surface construction and its construction method Active CN106638678B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510736401.8A CN106638678B (en) 2015-11-03 2015-11-03 A kind of underground structure inwall and diaphram wall overlapping surface construction and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510736401.8A CN106638678B (en) 2015-11-03 2015-11-03 A kind of underground structure inwall and diaphram wall overlapping surface construction and its construction method

Publications (2)

Publication Number Publication Date
CN106638678A true CN106638678A (en) 2017-05-10
CN106638678B CN106638678B (en) 2018-10-16

Family

ID=58810422

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510736401.8A Active CN106638678B (en) 2015-11-03 2015-11-03 A kind of underground structure inwall and diaphram wall overlapping surface construction and its construction method

Country Status (1)

Country Link
CN (1) CN106638678B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756322A (en) * 2021-09-01 2021-12-07 珠海华发城市研究院有限公司 Construction method for reserved occlusal surface of underground engineering laminated structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07166539A (en) * 1993-12-17 1995-06-27 Takenaka Komuten Co Ltd Construction method for steel framed reinforced concrete continuous underground wall
CN101096850A (en) * 2006-06-29 2008-01-02 邹新建 Plastics water discharge plate application method for underground engineering wall surface, bottom plating and top board
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit support device and construction method
CN103015431A (en) * 2012-12-04 2013-04-03 北京建材地质工程公司 Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN103669698A (en) * 2013-12-24 2014-03-26 初明进 Prefabricated concrete component with connecting rings
CN203583493U (en) * 2013-09-29 2014-05-07 中国一冶集团有限公司 Combined lattice steel frame spray anchoring foundation pit supporting structure
CN205100244U (en) * 2015-11-03 2016-03-23 中铁隧道勘测设计院有限公司 Underground structure inwall and underground continuous wall coincide face structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07166539A (en) * 1993-12-17 1995-06-27 Takenaka Komuten Co Ltd Construction method for steel framed reinforced concrete continuous underground wall
CN101096850A (en) * 2006-06-29 2008-01-02 邹新建 Plastics water discharge plate application method for underground engineering wall surface, bottom plating and top board
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit support device and construction method
CN103015431A (en) * 2012-12-04 2013-04-03 北京建材地质工程公司 Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN203583493U (en) * 2013-09-29 2014-05-07 中国一冶集团有限公司 Combined lattice steel frame spray anchoring foundation pit supporting structure
CN103669698A (en) * 2013-12-24 2014-03-26 初明进 Prefabricated concrete component with connecting rings
CN205100244U (en) * 2015-11-03 2016-03-23 中铁隧道勘测设计院有限公司 Underground structure inwall and underground continuous wall coincide face structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756322A (en) * 2021-09-01 2021-12-07 珠海华发城市研究院有限公司 Construction method for reserved occlusal surface of underground engineering laminated structure

Also Published As

Publication number Publication date
CN106638678B (en) 2018-10-16

Similar Documents

Publication Publication Date Title
CN110094213B (en) Space combined supporting structure and supporting method for water-rich broken stratum tunnel
CN206874310U (en) One kind is applied to high pressure water enrichment tunnel decompression drainage arrangement
CN101761096B (en) Anti-crack and anti-leak construction method of arranging tower crane foundation below waterproof baseplate
CN108547645B (en) Assembled tunnel supporting device and method capable of realizing prestress
CN211037072U (en) Piping lane bottom plate waterproof construction
CN105256810A (en) Construction method for round underground continuous wall two-in-one structure
CN103603368A (en) Construction method for reverse construction of continuous wall encountering underground pipeline
CN101476470B (en) Water-proof drainage house cover process for tunnel
CN205100244U (en) Underground structure inwall and underground continuous wall coincide face structure
CN110005438B (en) Large-deformation tunnel cast-in-place structure design and construction method for crossing movable fault
CN105113435A (en) Culvert mouth of corrugated steel pipe culvert
CN108547316B (en) Double-layer corrugated steel structure for underground comprehensive pipe gallery
CN203904971U (en) Reinforcement cage protective device capable of controlling necking, bar leakage and mud inclusion of underground diaphragm wall
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN106638678A (en) Underground structure lining wall and underground continuous wall overlapped surface structure and construction method thereof
CN111156036A (en) Novel plate anchor structure
CN110593320A (en) Early sealing structure for outer wall post-cast strip and construction method thereof
CN217107046U (en) Corrugated steel plate self-plugging structure for highway tunnel transverse passage
CN113187487B (en) Construction method of double-layer full-section frozen underground excavation station structure of subway
CN211395768U (en) Outer wall post-cast strip is enclosed construction in advance
CN104727276B (en) The manufacture method of the double; two water sealing structure of concrete extension joint
CN207143996U (en) A kind of underground structure spare interface temporary plugging structure
CN105317021A (en) Connection method and structure for variable-section continuous rigid frame aqueducts
CN114263215B (en) Construction method for building waterproof structure at storey-added connection part of subway station by combined excavation and excavation
CN114991222B (en) Shock absorption disposal method for subway station structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190214

Address after: 300000 Tianjin Free Trade Test Zone (Airport Economic Zone) No. 36 West Central Road

Patentee after: CHINA RAILWAY LIUYUAN GROUP CO., LTD.

Address before: No. 1 Hebei street, Hongqiao District, Tianjin City, Tianjin

Patentee before: Zhongtie Tunnel Survey and Design Inst., Ltd.

TR01 Transfer of patent right