CN106638625A - 一种锚索预应力失效后可再次张拉的施工方法 - Google Patents
一种锚索预应力失效后可再次张拉的施工方法 Download PDFInfo
- Publication number
- CN106638625A CN106638625A CN201610944821.XA CN201610944821A CN106638625A CN 106638625 A CN106638625 A CN 106638625A CN 201610944821 A CN201610944821 A CN 201610944821A CN 106638625 A CN106638625 A CN 106638625A
- Authority
- CN
- China
- Prior art keywords
- anchor cable
- failure
- tensioning
- construction method
- end socket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种锚索预应力失效后可再次张拉的施工方法:包括第一次施工中斜坡开挖→锚索孔定位→成孔→清孔→锚索制安→喷射混凝土→搭设脚手架的前序工作,还包括第一次施工中格构施工和预埋钢板→锚索张拉锁定→预制封头并预埋角钢→预制混凝土锚索封头→封头安装→焊缝处理的工作,预应力失效后再次张拉→重新安装封头。本发明中锚索预留长度700mm~800mm,为满足可以再次张拉的长度;本发明中当锚索预应力失效后,可以直接将封头打开,再次进行张拉、锁定和重新安装封头;本发明的方法操作简单、控制质量良好,很好的保证了边坡支护的稳定和安全。
Description
技术领域
本发明属于边坡工程施工领域,尤其涉及一种锚索预应力失效后可再次张拉的施工方法。
背景技术
目前于川贵地区的山体工程,由于山体大多属于喀斯特地貌,工程施工需要大量开挖山体,部分位置甚至需要垂直开挖,山体支护工作量较大。工程中山体支护采用的是预应力锚索加格构的支护方法,垂直开挖部分采用抗滑桩。鉴于预应力锚索施加张拉力后将长期埋置于潮湿的岩层或土体中,并持续承受高拉应力作用,其使用寿命将取决于锚索的耐久性。在工程实践中,锚固边坡失稳的事故时有发生、预应力锚索失效后,将无法保证边坡的稳定性和安全性,因此有必要对预应力锚索失效研究应对措施。
用常规方法进行锚索封锚存在的技术问题:由于锚索长期埋置于土层或岩层中,持续承受高拉应力作用,长此下去锚索的预应力将会失效。采用常规的封锚方法在预应力失效后,锚索将失去作用,无法保证边坡的稳定和安全。
申请号为201410144433.4的中国发明专利:公开了一种重复施加预应力的锚索支护方法,其提供一种在不扰动全长注浆凝固结构、并具有足够强度的锚固端的可重复施加预应力的锚索的支护方法;包括制作安装锚索、首次注浆锚固锚索锚固端、二次注浆、重复施加预应力的流程,其并没有解决边坡锚索封锚存在预应力失效的技术问题。
发明内容
本发明所要解决的技术问题是:提供一种锚索预应力失效后可再次张拉的施工方法。
为了解决上述技术问题,本发明公开了一种锚索预应力失效后可再次张拉的施工方法:包括第一次施工中斜坡开挖→锚索孔定位→成孔→清孔→锚索制安→喷射混凝土→搭设脚手架的前序工作,第一次施工还包括以下步骤:
步骤一,格构施工和预埋钢板:格构钢筋绑扎完成后,在锚索四周预埋钢板,随后进行模板安装和混凝土浇筑;
步骤二,锚索张拉锁定:根据设计的锚索张拉锁定值利用锚具和钢垫板进行锚索张拉并锁定,锚索预留长度700mm~800mm,多余部分切除;
步骤三,预制封头并预埋角钢:预制混凝土锚索封头,在封头中央预埋直径150mm镀锌钢管,同时在封口四周预埋角钢;
步骤四,封头安装:将外露锚索及锚具用黄油进行包裹,然后将封头套在外露锚索上,再把角钢和钢板焊接到一起;
步骤五,焊缝处理:将焊缝处理干净,角钢和钢板进行打磨除锈,然后涂抹黄油,最后用砂浆进行封闭;
锚索预应力失效后再次施工,包括以下步骤:
步骤六,锚索失效后再次张拉:锚索预应力失效后,打开砂浆封闭,割开焊缝,取下混凝土预制封头,再次对锚索进行张拉并锁定;
步骤七,重新安装封头:重复步骤四和步骤五。
进一步的,所述步骤二中锚索张拉锁定值为500KN~1000KN。
进一步的,所述步骤二中锚索张拉前在锚索中部预设有内应力传感器。
进一步的,所述步骤三种所用角钢为50角钢。
进一步的,所述步骤四中封头内壁涂有防腐涂层。
进一步的,所述防腐涂层为水性防腐涂料。
与现有技术相比,本发明可以获得以下技术效果:
1)本发明中锚索预留长度700mm~800mm,为满足可以再次张拉的长度。
2)本发明中当锚索预应力失效后,可以直接将封头打开,再次进行张拉、锁定和重新安装封头。
3)本发明的方法操作简单、控制质量良好,很好的保证了边坡支护的稳定和安全。
4)本发明中防腐涂层为水性防腐涂料,可以更好的保护锚索预留长度的性能。
附图说明
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1是本发明方法的流程示意图。
图2是本发明方法的结构示意图和局部放大图。
其中:1-钢垫板,2-锚具,3-钢管,4-预制封头,5-锚索,6-角钢,7-焊缝,8-钢板。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
下面结合附图及具体实施例对本发明的应用原理作进一步描述。
实施例一
如图1和图2所示,一种锚索预应力失效后可再次张拉的施工方法:包括第一次施工中斜坡开挖→锚索孔定位→成孔→清孔→锚索制安→喷射混凝土→搭设脚手架的前序工作,第一次施工还包括以下步骤:
步骤一,格构施工和预埋钢板:格构钢筋绑扎完成后,在锚索四周预埋钢板,随后进行模板安装和混凝土浇筑;
步骤二,锚索张拉锁定:根据设计的锚索张拉锁定值利用锚具和钢垫板进行锚索张拉并锁定,锚索预留长度700mm,多余部分切除;
步骤三,预制封头并预埋角钢:预制混凝土锚索封头,在封头中央预埋直径150mm镀锌钢管,同时在封口四周预埋角钢;
步骤四,封头安装:将外露锚索及锚具用黄油进行包裹,然后将封头套在外露锚索上,再把角钢和钢板焊接到一起;
步骤五,焊缝处理:将焊缝处理干净,角钢和钢板进行打磨除锈,然后涂抹黄油,最后用砂浆进行封闭;
锚索预应力失效后再次施工,包括以下步骤:
步骤六,锚索失效后再次张拉:锚索预应力失效后,打开砂浆封闭,割开焊缝,取下混凝土预制封头,再次对锚索进行张拉并锁定;
步骤七,重新安装封头:重复步骤四和步骤五。
其中:步骤二中锚索张拉锁定值为500KN;步骤二中锚索张拉前在锚索中部预设有内应力传感器;步骤三种所用角钢为50角钢;步骤四中封头内壁涂有防腐涂层;所述防腐涂层为水性防腐涂料。
实施例二
实施例二与实施例一操作步骤基本相同,不同之处在于步骤二中锚索预留长度为800mm,锚索张拉锁定值为1000KN。
实施例三
实施例三与实施例一操作步骤基本相同,不同之处在于步骤二中锚索预留长度为750mm,锚索张拉锁定值为700KN。
本发明的有益效果是这样实现的:
本发明中锚索预留长度700mm~800mm,为满足可以再次张拉的长度;本发明中当锚索预应力失效后,可以直接将封头打开,再次进行张拉、锁定和重新安装封头;本发明的方法操作简单、控制质量良好,很好的保证了边坡支护的稳定和安全;本发明中防腐涂层为水性防腐涂料,可以更好的保护锚索预留长度的性能。
Claims (6)
1.一种锚索预应力失效后可再次张拉的施工方法,包括第一次施工中斜坡开挖→锚索孔定位→成孔→清孔→锚索制安→喷射混凝土→搭设脚手架的前序工作,其特征在于,第一次施工还包括以下步骤:
步骤一,格构施工和预埋钢板:格构钢筋绑扎完成后,在锚索四周预埋钢垫板,随后进行模板安装和混凝土浇筑;
步骤二,锚索张拉锁定:根据设计的锚索张拉锁定值利用锚具和钢垫板进行锚索张拉并锁定,锚索预留长度700mm~800mm,多余部分切除;
步骤三,预制封头并预埋角钢:预制混凝土锚索封头,在封头中央预埋直径150mm镀锌钢管,同时在封口四周预埋角钢;
步骤四,封头安装:将外露锚索及锚具用黄油进行包裹,然后将封头套在外露锚索上,再把角钢和钢板焊接到一起;
步骤五,焊缝处理:将焊缝处理干净,角钢和钢板进行打磨除锈,然后涂抹黄油,最后用砂浆进行封闭;
锚索预应力失效后再次施工,包括以下步骤:
步骤六,锚索失效后再次张拉:锚索预应力失效后,打开砂浆封闭,割开焊缝,取下混凝土预制封头,再次对锚索进行张拉并锁定;
步骤七,重新安装封头:重复步骤四和步骤五。
2.根据权利要求1所述一种锚索预应力失效后可再次张拉的施工方法,其特征在于:所述步骤二中锚索张拉锁定值为500KN~1000KN。
3.根据权利要求1所述一种锚索预应力失效后可再次张拉的施工方法,其特征在于:所述步骤二中锚索张拉前在锚索中部预设有内应力传感器。
4.根据权利要求1所述一种锚索预应力失效后可再次张拉的施工方法,其特征在于:所述步骤三种所用角钢为50角钢。
5.根据权利要求1至5任一项所述一种锚索预应力失效后可再次张拉的施工方法,其特征在于:所述步骤四中封头内壁涂有防腐涂层。
6.根据权利要求5所述一种锚索预应力失效后可再次张拉的施工方法,其特征在于:所述防腐涂层为水性防腐涂料。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610944821.XA CN106638625B (zh) | 2016-11-02 | 2016-11-02 | 一种锚索预应力失效后可再次张拉的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610944821.XA CN106638625B (zh) | 2016-11-02 | 2016-11-02 | 一种锚索预应力失效后可再次张拉的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106638625A true CN106638625A (zh) | 2017-05-10 |
CN106638625B CN106638625B (zh) | 2018-08-17 |
Family
ID=58821235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610944821.XA Active CN106638625B (zh) | 2016-11-02 | 2016-11-02 | 一种锚索预应力失效后可再次张拉的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638625B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109235490A (zh) * | 2018-11-16 | 2019-01-18 | 青岛业高建设工程有限公司李沧分公司 | 挡土墙及其施工方法 |
CN109356158A (zh) * | 2018-10-30 | 2019-02-19 | 中铁二院贵阳勘察设计研究院有限责任公司 | 一种预应力锚索可补张拉封锚结构 |
CN110792097A (zh) * | 2019-11-28 | 2020-02-14 | 聂磊 | 一种预应力监测可调的衡重式组合挡土墙及施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001032273A (ja) * | 1999-07-27 | 2001-02-06 | Ohbayashi Corp | グラウンドアンカーの耐凍上定着構造 |
KR100741405B1 (ko) * | 2006-03-09 | 2007-07-20 | 심석래 | 타이케이블 결속장치 |
CN103883339A (zh) * | 2014-04-11 | 2014-06-25 | 衢州市优德工业设计有限公司 | 一种重复施加预应力的锚索支护方法 |
CN204435373U (zh) * | 2015-04-17 | 2015-07-01 | 辽宁有色勘察研究院 | 一种永久型边坡可重复利用锚头封固装置 |
CN204703160U (zh) * | 2015-06-17 | 2015-10-14 | 万军利 | 双锚固段预应力锚索结构 |
CN205475220U (zh) * | 2015-12-29 | 2016-08-17 | 大陆交通建设集团有限公司 | 一种预应力锚索结构 |
-
2016
- 2016-11-02 CN CN201610944821.XA patent/CN106638625B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001032273A (ja) * | 1999-07-27 | 2001-02-06 | Ohbayashi Corp | グラウンドアンカーの耐凍上定着構造 |
KR100741405B1 (ko) * | 2006-03-09 | 2007-07-20 | 심석래 | 타이케이블 결속장치 |
CN103883339A (zh) * | 2014-04-11 | 2014-06-25 | 衢州市优德工业设计有限公司 | 一种重复施加预应力的锚索支护方法 |
CN204435373U (zh) * | 2015-04-17 | 2015-07-01 | 辽宁有色勘察研究院 | 一种永久型边坡可重复利用锚头封固装置 |
CN204703160U (zh) * | 2015-06-17 | 2015-10-14 | 万军利 | 双锚固段预应力锚索结构 |
CN205475220U (zh) * | 2015-12-29 | 2016-08-17 | 大陆交通建设集团有限公司 | 一种预应力锚索结构 |
Non-Patent Citations (2)
Title |
---|
张志亮: "预应力锚索耐腐蚀性及失效研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
蔡启龙等: "无粘结预应力锚索的腐蚀与防护", 《人民长江》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109356158A (zh) * | 2018-10-30 | 2019-02-19 | 中铁二院贵阳勘察设计研究院有限责任公司 | 一种预应力锚索可补张拉封锚结构 |
CN109235490A (zh) * | 2018-11-16 | 2019-01-18 | 青岛业高建设工程有限公司李沧分公司 | 挡土墙及其施工方法 |
CN109235490B (zh) * | 2018-11-16 | 2024-05-03 | 青岛业高建设工程有限公司 | 挡土墙及其施工方法 |
CN110792097A (zh) * | 2019-11-28 | 2020-02-14 | 聂磊 | 一种预应力监测可调的衡重式组合挡土墙及施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106638625B (zh) | 2018-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020173100A1 (zh) | 加固装置及富水砂砾地层中深基坑局部冷冻加固施工方法 | |
CN106400813B (zh) | 一种基坑支护系统及其施工方法 | |
CN106050266A (zh) | 富水砂卵石地层隧道内盾构区间联络通道暗挖的施工方法 | |
CN103410161A (zh) | 斜向控制注浆钢锚管框架及其施工方法 | |
CN103306289A (zh) | 基坑桩锚护壁混凝土锚索冠梁结构及其施工方法 | |
CN107524174B (zh) | 一种设有遇水膨胀止水条的连续墙工字钢接头 | |
CN106638625B (zh) | 一种锚索预应力失效后可再次张拉的施工方法 | |
CN106498943A (zh) | 一次性高压旋喷型扩大头预应力土锚杆施工方法 | |
CN108149692B (zh) | 一种适用于非闭合基坑的支护结构 | |
CN104213509A (zh) | 一种缆索吊装锚索式锚碇施工方法 | |
CN102808422A (zh) | 灌注钢筋混凝土结构有粘结后张预应力工法 | |
CN108266207B (zh) | 一种适用于深厚富水砂层地区的顶管进出洞止水方法及装置 | |
CN108005097B (zh) | 高陡边坡坡顶建构/筑物锚筏基础构造及施工方法 | |
CN202970719U (zh) | 一种超长管幕无中继间顶进施工装置 | |
CN105714819A (zh) | 一种新型预应力锚索外锚头多重防护装置及其固定方法 | |
CN109706941B (zh) | 一种基坑复合支护技术的施工方法和锚固装置 | |
CN115717397A (zh) | 拉森钢板桩与预应力锚索组合支护施工方法 | |
CN109930610A (zh) | 受限环境基坑采用混凝土加钢管混合斜撑支护的施工方法 | |
US7033114B2 (en) | Method for installing reinforcements around a cylindrical underground pipeline | |
CN105937248B (zh) | 主体结构分段施工与临时封堵墙相接处处理方法 | |
CN205662920U (zh) | 一种带锚索孔的地下装配式预制桩 | |
CN114934791A (zh) | 一种隧道约束锚固索及提高初期支护结构稳定性的方法 | |
CN110318419B (zh) | 下穿式管廊一衬门洞支护的施工方法 | |
CN108277798A (zh) | 预应力型钢支护桩及其施工方法 | |
JPH0813495A (ja) | 土留め壁及びその構築工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |