CN106597208A - Breaker failure start loop detection device and method - Google Patents

Breaker failure start loop detection device and method Download PDF

Info

Publication number
CN106597208A
CN106597208A CN201710055154.4A CN201710055154A CN106597208A CN 106597208 A CN106597208 A CN 106597208A CN 201710055154 A CN201710055154 A CN 201710055154A CN 106597208 A CN106597208 A CN 106597208A
Authority
CN
China
Prior art keywords
detection
contact
breaker failure
later time
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710055154.4A
Other languages
Chinese (zh)
Inventor
呼建礼
王天民
魏民
郭鹏伟
王晓琳
乔崇宏
宋建辉
王晓辉
彭超
王若洋
佘林娟
李星婕
杨雪
郭世嘉
李江坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Hua Xin Electric Applicance Co Ltd
Anyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Zhengzhou Hua Xin Electric Applicance Co Ltd
Anyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Hua Xin Electric Applicance Co Ltd, Anyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Zhengzhou Hua Xin Electric Applicance Co Ltd
Priority to CN201710055154.4A priority Critical patent/CN106597208A/en
Publication of CN106597208A publication Critical patent/CN106597208A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • G01R31/66Testing of connections, e.g. of plugs or non-disconnectable joints
    • G01R31/67Testing the correctness of wire connections in electric apparatus or circuits

Abstract

A breaker failure start loop detection device comprises a detection module, a man-machine interaction module and a power module; the detection module is provided with a wiring terminal, wherein the wiring terminal is connected with a breaker failure start loop wiring port through an acquisition line; the detection module is connected with the man-machine interaction module; the power module powers the detection module and the man-machine interaction module. The breaker failure start loop detection method comprises the following steps: using the acquisition line to connect the wiring terminal on the detection module with the corresponding wiring port of the breaker failure start loop; using the man-machine interaction module to input detection current determine contact point or protect motion contact point signals into the detection module; allowing the detection module to use the acquisition line to obtain a signal in the breaker failure start loop, and determining whether the current determine contact point or protect motion contact point are conducted or not according to existence of the signal; determining the wiring is normal if the contact point is conducted, and determining the wiring is wrong if not conducted.

Description

Breaker failure starting-up later time detector and detection method
Technical field
The present invention relates to a kind of detector, more particularly to a kind of breaker failure starting-up later time detector and detection method.
Background technology
Increasingly sophisticated with electrical network, the security of electrical network becomes more and more important, and electrical network band is given in the tripping of relay protection The harm for coming is increasing.Wherein primary cut-out is used as the Special electric that high-tension circuit is switched on or switched off under normal or failure condition Device, plays the security guards effect of electrical networks at different levels.When line failure, if because there is breaker tripping in circuit breaker failure Phenomenon, will make fault spread, and the tripping operation that causes to bypass the immediate leadership causes large-area power-cuts, in addition cause power equipment to burn, personal injury etc. Serious consequence.And breaker fail protection can cut off other breakers on the bus of stoppage circuit breaker place with the shorter time limit, Power failure range is reduced, ensure the stable operation of whole electrical network, it can be seen that breaker fail protection has in power system Critically important effect.At present, 220kV and above transformer station and 110kV transformer stations that some are important have installed breaker failure Protection.But not enough fasten because secondary line often occurs in Jing, loop wrong position, to have breakage, contact obstructed in the middle of cable etc. various Reason causes unsuccessful reason loop easily to go wrong.This is accomplished by us and detection mistake is had in the middle of the work of each regular inspection The correctness of clever starting-up later time.Can use without relevant speciality instrument in field inspection process, traditional artificial node can only be adopted The method of measurement is detected to breaker failure starting-up later time, and there is the method for traditional artificial contact measurement instrument to simulate The shortcomings of repeated high, easy generation is leaked item, needs many people to coordinate, along with measurement meter and the error of manual measurement so that traditional Breaker failure starting-up later time verification and measurement ratio it is relatively low, extend route protection time between predetermined repairs, and then when increased line outage Between.If testing result is not inconsistent with expection in checking process, it may be possible to which breaker failure starting-up later time occurs in that wiring error Or there is parasitic loop, this is accomplished by staff and detects confirmation again to the associated contacts in whole loop, and which section finds out is Circuit connection between contact is wrong or there is parasitic loop, and searching wiring error and parasitic loop overlong time can also affect line Protect time between predetermined repairs in road.
The content of the invention
Present invention offer is a kind of can to significantly improve the disconnected of operating efficiency, reduction operating personnel's labour intensity and cost of labor Road device unsuccessful reason loop detector, to solve the problems, such as prior art.
To solve above-mentioned technical problem, the present invention is employed the following technical solutions:
Breaker failure starting-up later time detector, including detection module, human-machine exchange module and power module, set on detection module It is equipped with the binding post being connected by gathering line with breaker failure starting-up later time Wiring port, detection module and man-machine interaction mould Block connects, and power module is that detection module and human-computer interaction module are powered.
The detection module includes CPU, and power supply interface is connected with CPU, is also associated with detecting the open circuit that gathering line is obtained The circuit for detecting connecting point of signal in device unsuccessful reason loop, and the contact conversion electricity that the detection object of pair of wire connection terminals is changed Road.
Also include rechargeable battery, rechargeable battery is connected with power module and external power source.
The gathering line is aviation plug with the interface of detector, and the interface being connected with breaker failure starting-up later time is spiral shell Wire form accesses terminal.
Binding post on detection module is connected by gathering line with the respective terminal mouth of breaker failure starting-up later time Connect;The signal of detection current judgement contact or protection act contact, detection are input into detection module by human-machine exchange module Module obtains the signal in breaker failure starting-up later time by gathering line, according to the presence or absence of signal, judges current judgement contact Or protection act contact is turned on or is not turned on, conducting then judges that wiring is normal, is not turned on, and judges that wiring is wrong.
When detecting to current judgement contact, current judgement contact is sent to detection module by human-machine exchange module The signal of detection, the CPU of detection module is received after signal, to the node change-over circuit sending signal being connected with CPU, makes to be protected The binding post of shield action connection point detection is disconnected with CPU, while being input into A phases or B phases in breaker failure starting-up later time Or C phase currents, judge whether the nodal test circuit connected with CPU receives and A phases or B phases or C phases loop is corresponding adopts The signal of line concentration, if receiving signal, judges that the current node connection of the phase is normal, and the current node for otherwise judging the phase connects Connect abnormal.
When detecting to protection act contact, protection act contact is sent to detection module by human-machine exchange module The signal of detection, the CPU of detection module is received after signal, to the node change-over circuit sending signal being connected with CPU, makes to carry out electricity Stream differentiates that the binding post of contact detection is disconnected with CPU, while being input into A phases or B phases in breaker failure starting-up later time Or C phase currents, judge whether the circuit for detecting connecting point connected with CPU receives and A phases or B phases or C phases loop is corresponding adopts The signal of line concentration, if receiving signal, judges that the protection contact connection of the phase is normal, and the protection node for otherwise judging the phase connects Connect abnormal.
It is described when carrying out current judgement contact or protection act contact and detecting, while carry out the detection of parasitic loop, such as Fruit detects parasitic loop, then shown in the display screen of human-machine exchange module.
The connection diagram of breaker failure starting-up later time, and loop are shown on the display screen of the human-machine exchange module Upper each contact can be according to the display methods for pre-setting, and the signal of the circuit for detecting connecting point detection obtained according to CPU is carried out automatically Contact connection shows and does not connect display with contact.
Beneficial effects of the present invention:After the present invention is by the interface connection of gathering line, examined by human-computer interaction module The operation and display of survey, is remarkably improved operating efficiency topic and reduces operating personnel's labour intensity and cost of labor.
Description of the drawings
Fig. 1 is breaker failure starting-up later time detector material object layout.
Fig. 2 is the interface diagram that detector is connected with breaker failure starting-up later time.
Fig. 3 is A phase protection act contact overhaul flow charts.
Fig. 4 is A judgment by phase current contact overhaul flow charts.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and detailed description.
As shown in figure 1, the breaker failure starting-up later time detector that the present invention is provided, including detection module, human-computer exchange Module and power module, are provided with the Wiring port detected in breaker failure starting-up later time by adopting on detection module The binding post of line concentration connection, and the Wiring port detected in breaker failure starting-up later time is breaker protection screen terminal A part of interface in row.Detection module is connected with human-computer interaction module, and power module is detection module and human-computer interaction module Power supply.Human-computer interaction module includes display screen and button, and button can be touch-screen button.During connection, binding post and relay The contact in terminal block after device protection screen is attached.
Above-mentioned detection module includes CPU, and system power supply interface, clock, serial interface, system power supply are connected with CPU Interface is used for and power module connection is powered.It is also associated with detecting that the breaker failure that gathering line is obtained starts back on CPU The circuit for detecting connecting point of signal in road, and the contact change-over circuit that the gathering line break-make of the connection of pair of wire connection terminals is changed. By key-press input signal, selection carries out detecting or protection act contact is detected to current judgement contact, by pressing After key input, the break-make of the binding post that node change-over circuit is connected by conversion with gathering line carries out the acquisition of signal.
Above-mentioned circuit for detecting connecting point may be selected existing signal deteching circuit, in breaker failure starting-up later time Whether detected with signal.I.e. by gathering line connecting detection instrument and the detection contact of breaker failure starting-up later time, Gathering line obtains the signal of detection contact and is sent to circuit for detecting connecting point, and according to circuit for detecting connecting point signal whether is detected, and examines Judge that contact is normal if measuring, otherwise judge contact failure, then the display screen in human-computer interaction module is shown.And connect Point change-over circuit then may be selected to use relay circuit, and by the contact of relay break-make control is realized.
Present invention additionally comprises rechargeable battery, rechargeable battery is connected with power module and external power source.It is by external power source It is rechargeable battery powered, then powered for power module by rechargeable battery.
The interface of gathering line and detector is secondary aviation plug, and with dust cap design, prevents dust from entering, and disconnected Device unsuccessful reason loop-coupled interface in road is that screw type accesses terminal.
As shown in Fig. 2 being the schematic diagram that detector is connected with malfunction of the electric relay starting-up later time.
It is of the invention the contact of the various pieces in unsuccessful reason loop is detected respectively by intelligent chip control, And operated by touch-screen human-computer exchange and show testing result.
Detector has six binding posts, and gathering line, the end after six gathering lines and relay protection screen are connected respectively Six contact connections of 8D21,8D23,8D24,8D25,8D26, the 8D30 in loop in son row are detected;Detector is safe, It is by isolated from power, protection device is completely isolated with detector inside.Detector is simple to operate, small volume, easy to carry.
8D21 in Fig. 2,8D23,8D24,8D25,8D25,8D30,1D30,1D31,1D32,1D37,1D38,1D39, 1D29,1D36,4D129,4D128,4D126 are the terminal block numbering in route protection screen.When the present invention is detected, connection Six test points of 8D21,8D23,8D24,8D25,8D25,8D30, carry out respectively current judgement contact, the inspection of protection act contact Survey.
And number [01], 011,012,013,014,020 be breaker protection screen in cable connection loop numbering; 8SLP1,1SLP1,1SLP2,1SLP3,2SLP1,2SLP2,2SLP3,4SLP1 are the hard pressing plate in route protection screen;SLA-2、 SLB-2, SLC-2, SL2-2 are the current judgement contact in breaker auxiliary protection device:2TIA、2TJB、2TJC、1TJA、 1TJB, 1TJC, 1TJQ, 1TJR, 2TJQ, 2TJR are the protection act contact of line protective devices.
The present invention also provides a kind of breaker failure starting-up later time detection method, line is carried out first, i.e., by gathering line Binding post on detection module is connected with the respective terminal mouth of breaker failure starting-up later time.When needs are detected When, the signal of detection current judgement contact or protection act contact, detection are input into detection module by human-machine exchange module Module obtains the signal in breaker failure starting-up later time by gathering line, according to the presence or absence of signal, judges current judgement contact Or protection act contact is turned on or is not turned on, conducting then judges that wiring is normal, is not turned on, and judges that wiring is wrong.
Specifically, the process for carrying out current judgement contact or the detection of protection act connection point on-off is as follows:
When detecting to current judgement contact, electric current is sent to the CPU of detection module by the button of human-machine exchange module Differentiate the signal of contact detection, the CPU of detection module is received after signal, to the contact change-over circuit sending signal being connected with CPU, The binding post for carrying out protection act contact detection is set to disconnect with CPU, while being input into A in breaker failure starting-up later time Phase or B phases or C phase currents, judge whether the circuit for detecting connecting point being connected with CPU receives and A phases or B phases or C phase current contacts The signal of conducting, if receiving signal, judges that the electric current contact connection of the phase is normal, and the current node for otherwise judging the phase connects Connect abnormal.
As shown in Fig. 2 when the detection of current judgement contact is carried out, causing to be connected with 8D30 interfaces by contact change-over circuit The corresponding Wiring port signal of gathering line disconnect, and the corresponding binding post of 8D21,8D23,8D24,8D25,8D25,8D26 Signal is connected.As shown in figure 4, by taking A phases as an example, A phase currents are input into in breaker failure starting-up later time, then judge whether only Have in SLA-2 junction closures, i.e. 8D23,8D24,8D25,8D26 whether only the gathering line of connection 8D23 collects signal, such as If fruit is, then it represents that output is correct, otherwise, output error, and the letter of the gathering line to 8D24,8D25,8D26 connection are represented Number it is acquired, judges actual circuit-closing contacts, and shows on a display screen.
When detecting to protection act contact, protection act contact is sent to detection module by human-machine exchange module The signal of detection, the CPU of detection module is received after signal, to the node change-over circuit sending signal being connected with CPU, makes to carry out electricity Stream differentiates that the binding post of contact detection is disconnected with CPU, while transmission line simulation A phases or B phases or C phase transient faults, Judge whether receive the collection corresponding with A phases or B phases or C phases loop with the protection act circuit for detecting connecting point of CPU connections The signal of line, if receiving signal, judges that the protection contact connection of the phase is normal, otherwise judges the protection contact connection of the phase It is abnormal.
As shown in Fig. 2 when the detection of protection act contact is carried out, causing to be connected with 8D21 interfaces by contact change-over circuit The corresponding Wiring port signal of gathering line disconnect, and the corresponding binding post of 8D23,8D24,8D25,8D25,8D26,8D30 Signal is connected.As shown in figure 3, by taking A phases as an example, with relay-protection tester current analog A phase protection acts, then judgement is Only whether the gathering line of connection 8D23 is collected in no only 1TJA, 2TJA junction closure, i.e. 8D23,8D24,8D25,8D26 Signal, if it does, then representing that output is correct, otherwise, represents output error, and to the collection of 8D24,8D25,8D26 connection The signal of line is acquired, and judges actual circuit-closing contacts, and shows on a display screen.
In the design of the present invention, the connection that breaker failure starting-up later time is shown on the display screen of human-machine exchange module is shown It is intended to, and each contact can be according to the display methods for pre-setting on loop, the letter of the circuit for detecting connecting point detection obtained according to CPU Number, contact connection display is carried out automatically does not connect display with contact.For example, the contact for needing detection is represented using yellow, then During test, connect with and correct contact is shown in green, connect still incorrect contact shown in red.Facilitate testing staff Viewing judges.
When current judgement contact is carried out or protection act contact is detected, while the detection of parasitic loop is carried out, if inspection Parasitic loop is measured, is then shown in the display screen of human-machine exchange module.If detecting the presence of parasitic loop, accordingly Contact can change color and show parasitic loop contact, and personal observations immediately can learn it is which bar circuit branch has parasitic loop, Inspection of the personnel to each branch road is saved, the checkability of parasitic loop is improved.
Binding post on detection module is connected to breaker failure and is opened by the present invention in detection by six roots of sensation gathering line In dynamic loop, by the current judgement contact in detection breaker failure starting-up later time or the break-make of protection act contact, and then Detection current judgement contact or the correctness of protection act contact wiring, and judge whether deposited in breaker failure starting-up later time In parasitic loop.
The present invention with breaker failure starting-up later time detector to the current judgement contact of breaker failure starting-up later time, Parasitic loop in protection act contact and whole loop is accurately detected successively, in contact misoperation and loop is detected Parasitic loop when, breaker failure starting-up later time detector can accurately be detected and shown.The measurement of Traditional Man universal meter Method at least needs the instrument simulated failure of 74 times to measure, and breaker failure starting-up later time detector saves the same of manual measurement When, completing entirely to check work by only needing fault simulation 25 times, breaker failure starting-up later time inspection detection time can shorten Complete in 15 minutes, and can accurately detect parasitic loop, the directionality of parasitic loop can also be shown.
Above-described is only the preferred embodiment of the present invention, it is noted that for a person skilled in the art, Under the premise of without departing from general idea of the present invention, some changes and improvements can also be made, these should also be considered as the present invention's Protection domain.

Claims (9)

1. breaker failure starting-up later time detector, it is characterised in that:Including detection module, human-machine exchange module and power supply mould Block, is provided with the binding post being connected by gathering line with breaker failure starting-up later time Wiring port on detection module, detection Module is connected with human-computer interaction module, and power module is that detection module and human-computer interaction module are powered.
2. breaker failure starting-up later time detector according to claim 1, it is characterised in that:The detection module includes Power supply interface is connected with CPU, CPU, is also associated with detecting in the breaker failure starting-up later time that gathering line is obtained that signal connects Point detection circuit, and the contact change-over circuit that the detection object of pair of wire connection terminals is changed.
3. breaker failure starting-up later time detector according to claim 1, it is characterised in that:Also include rechargeable battery, Rechargeable battery is connected with power module and external power source.
4. breaker failure starting-up later time detector according to claim 1, it is characterised in that:The gathering line and detection The interface of instrument is aviation plug, and the interface being connected with breaker failure starting-up later time is that screw type accesses terminal.
5. breaker failure starting-up later time detection method, it is characterised in that:Binding post on detection module is passed through into gathering line It is connected with the respective terminal mouth of breaker failure starting-up later time;By human-machine exchange module to detection module input detection electric current Differentiate the signal of contact or protection act contact, detection module obtains the letter in breaker failure starting-up later time by gathering line Number, according to the presence or absence of signal, judging current judgement contact or the conducting of protection act contact or be not turned on, conducting then judges wiring Normally, it is not turned on, judges that wiring is wrong.
6. breaker failure starting-up later time detection method according to claim 5, it is characterised in that:Current judgement is being connect When point is detected, the signal of current judgement contact detection is sent to detection module by human-machine exchange module, detection module CPU is received after signal, to the node change-over circuit sending signal being connected with CPU, makes the wiring for carrying out protection act contact detection Terminal is disconnected with CPU, while being input into A phases or B phases or C phase currents in breaker failure starting-up later time, judges to connect with CPU Whether the nodal test circuit for connecing receives the signal of the gathering line corresponding with A phases or B phases or C phases loop, if received Signal, judges that the current node connection of the phase is normal, otherwise judges that the current node malunion of the phase is normal.
7. breaker failure starting-up later time detection method according to claim 5, it is characterised in that:Protection act is being connect When point is detected, the signal of protection act contact detection is sent to detection module by human-machine exchange module, detection module CPU is received after signal, to the node change-over circuit sending signal being connected with CPU, makes the wiring for carrying out current judgement contact detection Terminal is disconnected with CPU, while being input into A phases or B phases or C phase currents in breaker failure starting-up later time, judges to connect with CPU Whether the circuit for detecting connecting point for connecing receives the signal of the gathering line corresponding with A phases or B phases or C phases loop, if received Signal, judges that the protection contact connection of the phase is normal, otherwise judges that the protection node malunion of the phase is normal.
8. the breaker failure starting-up later time detection method according to claim 6 or 7, it is characterised in that:It is described to carry out When current judgement contact or protection act contact are detected, while the detection of parasitic loop is carried out, if detecting parasitic loop, Shown in the display screen of human-machine exchange module.
9. breaker failure starting-up later time detection method according to claim 8, it is characterised in that:
The connection diagram of breaker failure starting-up later time is shown on the display screen of the human-machine exchange module, and it is each on loop Contact can be according to the display methods for pre-setting, and the signal of the circuit for detecting connecting point detection obtained according to CPU carries out contact automatically Connection shows and does not connect display with contact.
CN201710055154.4A 2017-01-24 2017-01-24 Breaker failure start loop detection device and method Pending CN106597208A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710055154.4A CN106597208A (en) 2017-01-24 2017-01-24 Breaker failure start loop detection device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710055154.4A CN106597208A (en) 2017-01-24 2017-01-24 Breaker failure start loop detection device and method

Publications (1)

Publication Number Publication Date
CN106597208A true CN106597208A (en) 2017-04-26

Family

ID=58586056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710055154.4A Pending CN106597208A (en) 2017-01-24 2017-01-24 Breaker failure start loop detection device and method

Country Status (1)

Country Link
CN (1) CN106597208A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110542826A (en) * 2019-09-23 2019-12-06 深圳供电局有限公司 On-site calibration method for failure protection starting circuit of power grid transmission line breaker
CN113341240A (en) * 2021-04-21 2021-09-03 广州亚美信息科技有限公司 Function test equipment and method for vehicle-mounted electronic product

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103630789A (en) * 2013-12-19 2014-03-12 国家电网公司 Auxiliary experiment device for breaker failure protection
CN203535152U (en) * 2013-07-15 2014-04-09 深圳供电局有限公司 Recessive defect detecting device for external starting contacts of failure protection equipment
WO2014124660A1 (en) * 2013-02-12 2014-08-21 Abb Technology Ltd Method and device for detection of a fault in a protected unit
CN204241580U (en) * 2014-05-28 2015-04-01 国网山西省电力公司电力科学研究院 Relay-protection tester
CN105954626A (en) * 2016-06-22 2016-09-21 国网山东省电力公司莱芜供电公司 Portable microcomputer bus protection apparatus tester

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014124660A1 (en) * 2013-02-12 2014-08-21 Abb Technology Ltd Method and device for detection of a fault in a protected unit
CN203535152U (en) * 2013-07-15 2014-04-09 深圳供电局有限公司 Recessive defect detecting device for external starting contacts of failure protection equipment
CN103630789A (en) * 2013-12-19 2014-03-12 国家电网公司 Auxiliary experiment device for breaker failure protection
CN204241580U (en) * 2014-05-28 2015-04-01 国网山西省电力公司电力科学研究院 Relay-protection tester
CN105954626A (en) * 2016-06-22 2016-09-21 国网山东省电力公司莱芜供电公司 Portable microcomputer bus protection apparatus tester

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李锐: "继电保护实验仪校验装置研制", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110542826A (en) * 2019-09-23 2019-12-06 深圳供电局有限公司 On-site calibration method for failure protection starting circuit of power grid transmission line breaker
CN113341240A (en) * 2021-04-21 2021-09-03 广州亚美信息科技有限公司 Function test equipment and method for vehicle-mounted electronic product

Similar Documents

Publication Publication Date Title
CN105375572B (en) A kind of intelligent detection device of electric vehicle alternating-current charging pile
CN105553421B (en) A kind of online IV curve testing devices of photovoltaic generating system and method for testing
CN102243286B (en) Apparatus for detecting and displaying grounding state of equipment or socket
CN104198867B (en) Detection Apparatus and method for for arc light protecting device
CN103995172B (en) Method for on-line monitoring of load current of GIS bus of substation
CN104749487B (en) A kind of method in check protection device and its loop under circuit no cut-off condition
CN107064693A (en) A kind of protective relaying device outlet matrix test device and test method
CN110061473A (en) A kind of transformer digital protection equipment and method based on pressure list amount information
CN103983895B (en) The online N line multipoint earth faults detection method of PT secondary circuit
CN106597208A (en) Breaker failure start loop detection device and method
CN201130227Y (en) Portable DC earthing seeking instrument
CN102944762B (en) Debugging method of phase sequences of loops at two sides of synchronization point before commissioning of generator set
CN202453445U (en) Testing device for stage difference coordination of transformer substation direct-current system
CN206431231U (en) Breaker failure starting-up later time detector
CN211426651U (en) Relay protection device export check-up instrument
CN107861004A (en) A kind of prepared auto restart Auto-Test System
CN209561923U (en) Intelligent railway weak electric system power lightning protection distribution device
CN202057749U (en) Instrument for detecting and displaying ground state of equipment or socket
CN103353557A (en) Main transformer protection tripping matrix exit auxiliary tester
CN106771841B (en) A kind of through-flow system of substation S type and method
CN206657055U (en) A kind of switch cubicle phase checking device
CN109683015A (en) Intelligent electric energy meter
CN213843487U (en) Device for confirming whether secondary circuit is in short circuit correctness in case of electrification of primary equipment
CN104062616B (en) DC earthing and exchange string direct current simulator
CN202903864U (en) Electric leakage current detection device of single-phase AC power supply circuit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426