CN106593454B - The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure - Google Patents

The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure Download PDF

Info

Publication number
CN106593454B
CN106593454B CN201710060553.XA CN201710060553A CN106593454B CN 106593454 B CN106593454 B CN 106593454B CN 201710060553 A CN201710060553 A CN 201710060553A CN 106593454 B CN106593454 B CN 106593454B
Authority
CN
China
Prior art keywords
well
shield
lifting
construction
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710060553.XA
Other languages
Chinese (zh)
Other versions
CN106593454A (en
Inventor
杜博
邹彪
邢旺
范祚文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201710060553.XA priority Critical patent/CN106593454B/en
Publication of CN106593454A publication Critical patent/CN106593454A/en
Application granted granted Critical
Publication of CN106593454B publication Critical patent/CN106593454B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Abstract

The shield side combined the present invention relates to a kind of boring construction starting well and lifting well originates tunneling construction method and structure, pass through tunneling engineering method construction launching shaft and lifting well, it is connected between the two by dark-excavated passageway, siding is set in lifting well and starting well associated channel, lifts the opposite side setting equipment reentrant pathway of well.Before shield launching, shield machine is lifted in place by starting well, Backup system is hung to by lifting underground in interface channel, and is connect in place with shield machine;It after shield launching, is slagged tap by lifting well, handling section of jurisdiction, until the construction of shield section finishes.The present invention can be effectively prevented from interference of traditional shield well construction to traffic above-ground, pipeline, greatly shorten the period of shield launching, so as to improve the efficiency of shield-tunneling construction, reduce the destruction to urban environment.

Description

Boring construction starting well and lifting well combine shield side originate tunneling construction method and Structure
Technical field
The present invention relates to the construction methods of shield-tunneling construction in city track traffic engineering.
Background technology
It is national with investment of the government's increasing in recent years to infrastructure, especially Construction of Urban Rail Traffic field Build that tide is like a raging fire, how safety, economic, the efficient rail traffic for building out a rule high quality, always into To take part in building, each side is constantly considering the problems of.Important component of the section as city track traffic engineering also be unable to do without peace Entirely, selection economic, efficiently etc., since shield method has, ground adaptability is strong, and surface subsidence is controllable, during tunneling construction Effect on environment is small, it is safe the advantages that, as section construction a kind of common engineering method, more and more by the blueness of engineering staff It looks at.
But the starting well for originating needs and building the big scale of construction by open-cut right over section of shield machine, shield pick Into also need to be slagged tap by the well in the process, the operations such as handling section of jurisdiction, cause not closing in the starting well short time and extensive Multiple environment.It is simple for environment, such as the volume of traffic is small, pipeline is few and closes on area of the well location without important construction of structures influence factor Domain, starting well basic feasible solution of constructing.But the section environment in city is often positioned in that heavy traffic, pipeline is numerous and is disposed with The region of important construction of structures can not set traditional starting well at all, so as to cause this safe and efficient engineering method of shield without Method uses.When section boring construction is grown up in our helpless selections, need that the measures such as precipitation, advance support, slip casting is taken Ensure construction safety, but engineering accident also happens occasionally.
How in the region of environment complexity setting starting well using shield construction, annoying subway always and take part in building respectively Side.
Invention content
The shield side combined the object of the present invention is to provide a kind of boring construction starting well and lifting well originates tunneling construction Method and structure, to solve to be effectively reduced complex environment using shield construction in the region of environment complexity setting starting well Influence to shield-tunneling construction considerably increases the adaptability of shield method, effectively promotes the safety of Subway Tunnel engineering construction The technical problems such as property, high efficiency.
The purpose of the present invention is what is be achieved by the following technical programs:
The shield side that a kind of boring construction starting well and lifting well combine originates tunneling construction method, is applied by tunneling engineering method Work, the volume of traffic is small, pipeline is few and region setting launching shaft and lifting well without influence factors such as important constructions of structures, It is connected between the two by dark-excavated passageway, siding is set in lifting well and starting well associated channel, by shield machine by originating Well lifting is in place, shield machine is transported to environment complex region by originating channel, Backup system is hung to by lifting underground It is by lifting well and originating interface channel between channel that shield Backup system is in place in interface channel, and and shield machine Connection is in place;Then, it shield machine is completed in channel originates originating, it is another by interface channel and lifting well in tunneling process The reentrant pathway completion of side is slagged tap, section of jurisdiction handling work, until the construction of shield section finishes.
The shield side that a kind of boring construction starting well and lifting well combine originates structure, it includes:Starting well 1, originate it is logical Road 2, lifting well 3, interface channel 4 and reentrant pathway 5;Starting well 1 and lifting well 3 are respectively positioned on the periphery vacant lot far from complex environment On, meet originating channel 2 and lifting well 3 by meeting the connection of shield Backup system demand in place for shield machine demand in place Channel 4 is connected, and the slagging tap of driving, 3 opposite side of lifting well of handling section of jurisdiction demand setting guarantee haulage vehicle is turned back meeting The reentrant pathway 5 of demand.
The invention has the advantages that and good effect:
1) engineering construction risk is reduced, reduces construction cost and the pump drainage to underground water
By taking Beijing Metro section as an example, selected by the ratio of tunneling, shield scheme, structural cost list linear meter(lin.m.) tunneling is compared with shield Increase about 10,000, the total precipitation tunneling increases compared with shield not less than 300,000 sides, and boring construction need to take advance support, slip casting etc. auxiliary Measure is helped to ensure safety.
Final this section of section originates shield construction using side, reduces construction investment, underground water pump drainage and reduces Engineering risk.
2) field monitoring result verification
Section penetrates through safely, and surface subsidence is satisfied by design control requirement.
3) economical effect analysis
Standard section single line mining sectbn increases expense about 10,000 compared with shield section per linear meter(lin.m.) structure, and shield well cost is about 12000000 or so.The length about 1km (single line length about 2km) in usual segment standard section, then two engineering method difference about 20,000,000, is detained After shield well expense, shield section reduces investment ten thousand about more than 800 compared with mining sectbn, and after considering precipitation expense, difference can bigger.
4) society, environmental effect analysis
Shield method, should be widely used as a kind of safety, economic, efficient engineering method, is limited by ground complex environment It influences, it, can not reasonable selection in some regions.The release of side Originating Technique can be that shield method widely uses creation just The condition of profit, so as to create more environmentally-friendly, safe etc. construction environment, the safety of guarantee people's lives and properties advantageously.
Description of the drawings
Fig. 1 is floor map of the present invention;
Fig. 2 is starting well of the present invention and originates channel expansion diagrammatic cross-section;
Fig. 3 is shield launching channel cross-section schematic diagram of the present invention.
It is numbered in attached drawing:Starting well 1 originates channel 2, lifting well 3, interface channel 4, reentrant pathway 5, shield machine 6, shield Afterwards mating 7, shield section 8 to be tunneled, ground line 9.
Specific embodiment
The present invention is further illustrated below in conjunction with the accompanying drawings.
The shield side that a kind of boring construction starting well and lifting well combine originates tunneling construction method, is applied by tunneling engineering method Work, the volume of traffic is small, pipeline is few and region setting launching shaft and lifting well without influence factors such as important constructions of structures, It is connected between the two by dark-excavated passageway, siding is set in lifting well and starting well associated channel, by shield machine by originating Well lifting is in place, shield machine is transported to environment complex region by originating channel, Backup system is hung to by lifting underground It is by lifting well and originating interface channel between channel that shield Backup system is in place in interface channel, and and shield machine Connection is in place;Then, it shield machine is completed in channel originates originating, it is another by interface channel and lifting well in tunneling process The reentrant pathway completion of side is slagged tap, section of jurisdiction handling work, until the construction of shield section finishes.
The shield side that a kind of boring construction starting well and lifting well combine originates structure, it includes:Starting well 1, originate it is logical Road 2, lifting well 3, interface channel 4 and reentrant pathway 5;Starting well 1 and lifting well 3 are respectively positioned on the periphery vacant lot far from complex environment On, meet originating channel 2 and lifting well 3 by meeting the connection of shield Backup system demand in place for shield machine demand in place Channel 4 is connected, and the slagging tap of driving, 3 opposite side of lifting well of handling section of jurisdiction demand setting guarantee haulage vehicle is turned back meeting The reentrant pathway 5 of demand.
As shown in Figure 1, 2, 3, the concrete application of technical scheme of the present invention and feature are as follows:
1) starting well, lifting well itself construction are small to surrounding environment influence
Well location addressing generally may be provided at that surrounding enviroment are simple, the small region of construction infection, while pass through in work progress Set up totally enclosed construction shed can effectively influence of the control noise to environment, shaft excavation finds that ground sinks from existing engineering It drops fully controllable.Well location construction can be effectively reduced to surrounding enviroment by well location addressing, noise control, settlement Control etc. It influences.
2) each passage construction effect on environment is small
Passage construction using subsurface excavation method, has little effect surface line, traffic, will not generally generate noise dirt Dye.During ground settlement and tunnel, the timely and effective use of strict control items working measure, interface channel, reentrant pathway are accomplished Supporting construction is closed soon;It originates channel and selects rational pre-reinforcement measure according to surrounding enviroment, ensure that surface subsidence is controllable.
3) shield launching restraining factors greatly reduce
Small region is influenced since starting well, lifting well may be disposed at environment, shield launching in channel mainly by turning Fortune is realized in place, it is entirely avoided traditional originating mode by the situation of restriction, substantially reduce the restraining factors of shield launching.
4) shield driving is safe efficient
Such as using traditional originating mode, more region can only generally select subsurface excavation method to replace shield to some controlled factordiseases Method, speed of application is slow, and safety coefficient is low compared with shield method.After originating engineering method using side, for same condition section, the speed of tunneling construction The speed of the more artificial tunneling of degree greatly improves, while safety is also more secure.

Claims (2)

1. the shield side that a kind of boring construction starting well and lifting well combine originates tunneling construction method, which is characterized in that passes through Tunneling engineering method is constructed, the volume of traffic is small, pipeline is few and region setting launching shaft without important construction of structures influence factor and Well is lifted, is connected between the two by dark-excavated passageway, siding is set in lifting well and starting well associated channel, shield machine is led to It is in place to cross starting well lifting, shield machine is transported to environment complex region by originating channel, Backup system is by lifting well Under be hung in interface channel, it is by lifting well and originating interface channel between channel that shield Backup system is in place, and with Shield machine connection is in place;Then, it shield machine is completed in channel originates originating, in tunneling process, by interface channel and hang The reentrant pathway completion of dress well opposite side is slagged tap, section of jurisdiction handling work, until the construction of shield section finishes.
2. the shield side that a kind of boring construction starting well and lifting well combine originates structure, which is characterized in that it includes:Starting well (1), originate channel(2), lifting well(3), interface channel(4)And reentrant pathway(5);Starting well(1)And lifting well(3)It is respectively positioned on On periphery vacant lot far from complex environment, meet shield machine demand in place originates channel(2)And lifting well(3)By meeting shield The interface channel of structure Backup system demand in place(4)Be connected, meet driving slag tap, the lifting well of handling section of jurisdiction demand (3)Opposite side setting ensures the reentrant pathway of the demand of turning back of haulage vehicle(5).
CN201710060553.XA 2017-01-25 2017-01-25 The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure Active CN106593454B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710060553.XA CN106593454B (en) 2017-01-25 2017-01-25 The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710060553.XA CN106593454B (en) 2017-01-25 2017-01-25 The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure

Publications (2)

Publication Number Publication Date
CN106593454A CN106593454A (en) 2017-04-26
CN106593454B true CN106593454B (en) 2018-06-19

Family

ID=58585487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710060553.XA Active CN106593454B (en) 2017-01-25 2017-01-25 The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure

Country Status (1)

Country Link
CN (1) CN106593454B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111594188A (en) * 2020-04-29 2020-08-28 上海市城市建设设计研究总院(集团)有限公司 Shield starting and receiving method for subway open cut station
CN111927477B (en) * 2020-08-24 2022-02-11 上海市城市建设设计研究总院(集团)有限公司 Shield overall launching and receiving method for ultra-deep long-distance tunnel
CN116201563B (en) * 2023-04-27 2023-07-25 中建交通建设集团有限公司 Rapid soil discharging and feeding method for lateral vertical shaft of transverse passage for shield construction

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3434782B2 (en) * 2000-05-15 2003-08-11 鹿島建設株式会社 Starting method and starting device for shield machine
CN103114857A (en) * 2013-02-26 2013-05-22 中铁十九局集团第二工程有限公司 Shield tunnel construction method
CN103711499A (en) * 2014-01-08 2014-04-09 中铁十三局集团第六工程有限公司 Shield tunneling machine split starting construction method
CN104594911B (en) * 2015-02-16 2016-08-24 中建交通建设集团有限公司 Shield launching stage or reception stage wear down the construction method of operating line
CN104818994A (en) * 2015-04-30 2015-08-05 中铁二十二局集团第一工程有限公司 Urban subway n-shaped double-shaft and double transverse passage plane arrangement system
CN204663535U (en) * 2015-04-30 2015-09-23 中铁二十二局集团第一工程有限公司 City underground π type twin shafts and two transverse passage-way layout system
CN205477629U (en) * 2016-02-02 2016-08-17 中铁十九局集团轨道交通工程有限公司 T -shaped undercut tunnel shield constructs owner's machine translation system that goes into well
CN105545313A (en) * 2016-02-02 2016-05-04 中铁十九局集团轨道交通工程有限公司 T-shaped concealed excavated tunnel shield tunneling machine backup trolley lowering translation system and method thereof
CN205387937U (en) * 2016-02-02 2016-07-20 中铁十九局集团轨道交通工程有限公司 T -shaped undercut tunnel shield constructs supporting platform truck in machine back translation system of going into well

Also Published As

Publication number Publication date
CN106593454A (en) 2017-04-26

Similar Documents

Publication Publication Date Title
CN104102525B (en) A kind of risk stratification control method for passing through city track traffic engineering
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN106593454B (en) The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure
CN104563158B (en) Existing subway station realizes the construction method of transfer with new subway station platform layer
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN101328811B (en) TGRM subsection moving-on type advanced deep hole grouting construction process
CN204457792U (en) A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building
CN104481546B (en) A kind of soft rock tunnel inclined shaft enters the construction method of the double curvature arch in positive hole
CN103114857A (en) Shield tunnel construction method
CN107130613A (en) Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN104074524B (en) A kind of construction method of shallow embedding underpass of freeways large cross-section tunnel
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN108843338A (en) A kind of integrated excavation construction method of Construction of Silo channel conversion large cross-section tunnel
CN105332710A (en) Construction method suitable for up-down overlapped tunnel with small clear space and long distance under weak geological condition
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN106014424A (en) Blasting excavation method for shallowly-overburdened and shallowly-buried bored tunnel
CN105370288A (en) Construction method of shallow-buried large-span tunnels
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN106988760A (en) Facility-sliding strata tunnel portal reinforcing construction and construction method
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN106930318A (en) A kind of buried Room platform channel design in interface water condition subway station and its construction method
CN206409239U (en) A kind of hypogee modular construction system
CN108798676A (en) A kind of Subway Tunnel main track surface vertical shaft start tunneling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant