CN111594188A - Shield starting and receiving method for subway open cut station - Google Patents

Shield starting and receiving method for subway open cut station Download PDF

Info

Publication number
CN111594188A
CN111594188A CN202010353794.5A CN202010353794A CN111594188A CN 111594188 A CN111594188 A CN 111594188A CN 202010353794 A CN202010353794 A CN 202010353794A CN 111594188 A CN111594188 A CN 111594188A
Authority
CN
China
Prior art keywords
shield
subway
station
starting
station body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010353794.5A
Other languages
Chinese (zh)
Inventor
齐明山
徐正良
王春凯
黄爱军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN202010353794.5A priority Critical patent/CN111594188A/en
Publication of CN111594188A publication Critical patent/CN111594188A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space
    • E21D19/04Provisional protective covers for working space for use in drifting galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a shield launching and receiving method for an open cut station of a subway; the shield is hoisted from the outer side of the subway station body, so that the shield does not occupy the current road; in the hoisting process, according to the arrangement of a station wind pavilion of the subway station body, hoisting holes of the shield are arranged on the side of the subway station body and outside a red line of a road; when a hoisting hole is constructed, the structure of the station wind box needs to be locally deepened to be flush with the elevation of the end well bottom plate of the subway station body; when starting, the shield is hung downwards through the shield hoisting hole, reaches the end well along the designed path direction, and then is translated and rotated by 90 degrees; then, entering a normal starting program; and during receiving, the direction of the transportation path of the shield during starting is opposite to that of the transportation path of the shield during starting, and the shield is hoisted out through the shield hoisting hole. The application of the invention can effectively solve a series of problems in construction, is economical and feasible, and has wide application prospect in subway engineering.

Description

Shield starting and receiving method for subway open cut station
Technical Field
The invention relates to the technical field of subway construction, in particular to a shield starting and receiving method for an open cut station of a subway.
Background
With the rapid development of urban rail transit, a large number of subway stations and regional tunnels are arranged below urban trunk roads, and more regional tunnels are constructed by adopting a shield method.
The traditional shield starting and receiving method comprises the following steps: after the subway station structure is completed, shield hoisting holes are reserved in the positions of a station top plate and a middle plate end well, soil holes are reserved in the middle of the station, starting and receiving of a shield tunneling machine are carried out through the hoisting holes, slag and duct piece hoisting in the shield tunneling process is carried out through the soil holes, and duct pieces and materials are stacked in the space above the completed station top plate.
The problems with this approach are: in the whole process of interval tunnel construction, hoisting holes, unearthing holes and material yards need to occupy the road surface all the time, and the interval tunnel construction period is long, thereby having great influence on road surface traffic and normal life of people.
In view of the above factors, how to provide the construction efficiency of the shield, and improve the application prospect of the shield in the subway engineering become technical problems to be solved urgently by technical personnel in the field.
Disclosure of Invention
In view of the defects in the prior art, the invention provides a shield launching and receiving method for an open cut station of a subway, which aims to effectively solve a series of problems in construction, is economical and feasible and has wide application prospect in subway engineering.
In order to achieve the purpose, the invention discloses a shield starting and receiving method for an open cut station of a subway; the shield is hoisted from the outer side of the subway station body, so that the shield does not occupy the current road;
in the hoisting process, according to the arrangement of a station wind pavilion of the subway station body, the hoisting hole of the shield is arranged on the side of the subway station body and outside a red road;
when the hoisting hole is constructed, the structure of the station wind box needs to be locally deepened to be flush with the elevation of the end well bottom plate of the subway station body;
when starting, the shield is hung downwards through the shield hoisting hole, reaches the end well along the direction of the designed path, and then is translated and rotated by 90 degrees;
then, entering a normal starting program;
and during receiving, the direction of the transportation path of the shield during starting is opposite to that of the transportation path of the shield during starting, and the shield is hoisted out through the shield hoisting hole.
Preferably, the duct pieces and the muck are hoisted and transported outside the subway station body, so that the existing road is not occupied;
in the hoisting process, according to the arrangement of the entrance and the exit of the subway station body, the unearthed holes are arranged on the side of the subway station body and outside the red line of the road;
when the soil outlet hole is constructed, the access structure needs to be locally deepened to be flush with the elevation of the bottom plate of the subway station body;
when the soil is excavated, the flat trolley is transported to the position of the soil-excavating hole along the direction of the designed path, and the residue soil is lifted out through the soil-excavating hole;
the segments are lifted to the flat trolley through the soil outlet and then transported to the shield position along the designed path direction for assembly;
the design path meets the turning radius requirement of the flat-bed trolley.
Preferably, a temporary upright post is arranged at the position where the subway station body conflicts with the designed path, and a station structural post is arranged at the conflict position after the shield construction is finished; and the corresponding temporary upright post is removed after the stress conversion is finished.
Preferably, the temporary upright column is in a steel pipe column or section steel column type.
The invention has the beneficial effects that:
the application of the invention can effectively solve a series of problems in construction, is economical and feasible, and has wide application prospect in subway engineering.
The conception, the specific structure and the technical effects of the present invention will be further described with reference to the accompanying drawings to fully understand the objects, the features and the effects of the present invention.
Drawings
Fig. 1 shows the arrangement of shield hoisting holes and shield transport paths in an embodiment of the present invention.
Fig. 2 shows an arrangement of the soil outlet holes, the segments and the muck transport path in an embodiment of the invention.
Fig. 3 is a schematic diagram illustrating the processing of the collision between the transportation path and the position of the structural column of the station according to an embodiment of the present invention.
Detailed Description
Examples
The shield is hoisted by the outer side of the station body, and does not occupy the road in the current situation.
As shown in figure 1, the arrangement of the station wind pavilion is combined, a shield hoisting hole is arranged on the side of a station and outside a red line of a road, and the structure of the station wind pavilion is locally deepened to be level with the elevation of a bottom plate of a station end.
When starting, the shield machine is hung downwards from the shield hoisting hole, and then moves and rotates for 90 degrees after reaching the station end well along the direction of the path shown in the figure, and then the normal starting procedure can be started.
The shield receiving is similar to the starting, except that the direction of the transportation path is opposite, and the shield machine is called out through the shield hoisting hole.
The segment and the muck are hoisted and transported outside the station body, and the segment and the muck do not occupy the road in the current situation.
As shown in fig. 2, in combination with the arrangement of the station access, the unearthed holes are arranged on the side of the station and outside the red line of the road, and the station access structure is locally deepened to be flush with the elevation of the station main body bottom plate.
When the platform trolley is unearthed, the platform trolley is transported to the position of the unearthed hole along the direction of the path shown in the figure and is lifted out of the unearthed hole.
And the segments are lifted to the flat trolley from the unearthed holes and then transported to the position of the shield tunneling machine along the direction of the path shown in the figure for assembly. When the transportation path is arranged, the turning radius requirement of the flat-bed trolley is met.
In the method for constructing the station structural column on the transportation path, as shown in fig. 3, the pipe piece and the muck transportation path must meet the turning radius requirement of the flat-bed trolley, so that the position conflict between the transportation path and the station structural column is inevitably caused.
The processing method comprises the following steps: and arranging a temporary stand column in a way of avoiding the collision position, constructing the station structure column at the collision position after the shield construction is finished, and removing the temporary stand column after the stress conversion is finished.
The temporary upright column is preferably in the form of a steel pipe column or a section steel column and the like, and is convenient and rapid to erect and dismantle.
The foregoing detailed description of the preferred embodiments of the invention has been presented. It should be understood that numerous modifications and variations could be devised by those skilled in the art in light of the present teachings without departing from the inventive concepts. Therefore, the technical solutions available to those skilled in the art through logic analysis, reasoning and limited experiments based on the prior art according to the concept of the present invention should be within the scope of protection defined by the claims.

Claims (4)

1. A shield starting receiving method of an open cut station of a subway; the shield is hoisted from the outer side of the subway station body, so that the shield does not occupy the current road;
in the hoisting process, according to the arrangement of a station wind pavilion of the subway station body, the hoisting hole of the shield is arranged on the side of the subway station body and outside a red road;
when the hoisting hole is constructed, the structure of the station wind box needs to be locally deepened to be flush with the elevation of the end well bottom plate of the subway station body;
when starting, the shield is hung downwards through the shield hoisting hole, reaches the end well along the direction of the designed path, and then is translated and rotated by 90 degrees;
then, entering a normal starting program;
and during receiving, the direction of the transportation path of the shield during starting is opposite to that of the transportation path of the shield during starting, and the shield is hoisted out through the shield hoisting hole.
2. The shield launching and receiving method for the subway open cut station as claimed in claim 1, wherein both the segments and the dregs are hoisted and transported outside the subway station body without occupying the current road;
in the hoisting process, according to the arrangement of the entrance and the exit of the subway station body, the unearthed holes are arranged on the side of the subway station body and outside the red line of the road;
when the soil outlet hole is constructed, the access structure needs to be locally deepened to be flush with the elevation of the bottom plate of the subway station body;
when the soil is excavated, the flat trolley is transported to the position of the soil-excavating hole along the direction of the designed path, and the residue soil is lifted out through the soil-excavating hole;
the segments are lifted to the flat trolley through the soil outlet and then transported to the shield position along the designed path direction for assembly;
the design path meets the turning radius requirement of the flat-bed trolley.
3. The shield starting and receiving method for the subway open cut station as claimed in claim 2, wherein a temporary upright post is provided at a position where the subway station body collides with the designed path, and a station structural post is provided at the position of the collision after the shield construction is completed; and the corresponding temporary upright post is removed after the stress conversion is finished.
4. The shield launching and receiving method for the subway open cut station as claimed in claim 3, wherein the temporary columns are steel pipe columns or section steel columns.
CN202010353794.5A 2020-04-29 2020-04-29 Shield starting and receiving method for subway open cut station Pending CN111594188A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010353794.5A CN111594188A (en) 2020-04-29 2020-04-29 Shield starting and receiving method for subway open cut station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010353794.5A CN111594188A (en) 2020-04-29 2020-04-29 Shield starting and receiving method for subway open cut station

Publications (1)

Publication Number Publication Date
CN111594188A true CN111594188A (en) 2020-08-28

Family

ID=72183785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010353794.5A Pending CN111594188A (en) 2020-04-29 2020-04-29 Shield starting and receiving method for subway open cut station

Country Status (1)

Country Link
CN (1) CN111594188A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10306697A (en) * 1997-04-28 1998-11-17 Okumura Corp Execution method of tunnel support and widening device of ring-shaped support member
CN103114857A (en) * 2013-02-26 2013-05-22 中铁十九局集团第二工程有限公司 Shield tunnel construction method
CN106593454A (en) * 2017-01-25 2017-04-26 北京市市政工程设计研究总院有限公司 Shield side original tunneling construction method and structure combined with subsurface excavated construction of original well and hoisting well

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10306697A (en) * 1997-04-28 1998-11-17 Okumura Corp Execution method of tunnel support and widening device of ring-shaped support member
CN103114857A (en) * 2013-02-26 2013-05-22 中铁十九局集团第二工程有限公司 Shield tunnel construction method
CN106593454A (en) * 2017-01-25 2017-04-26 北京市市政工程设计研究总院有限公司 Shield side original tunneling construction method and structure combined with subsurface excavated construction of original well and hoisting well

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
油新华: "风道始发盾构的创新与实践", 《都市快轨交通》 *

Similar Documents

Publication Publication Date Title
CN105370287B (en) Large Underground parking lot machinery excavating construction method
CN107119711B (en) Connecting structure for large-range adjacent existing transfer station and construction method
CN107558494B (en) Underground station structure for rail transit and construction method thereof
CN105822310B (en) Rapid low-risk subway station tunnel construction method
US11391004B1 (en) Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN105370300A (en) Two-layer or multi-layer underground space construction method
CN110439574B (en) Tunnel structure for shield lateral translation starting and slag discharging material conveying and construction method
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN111271074A (en) Tunnel slag tapping transfer station positioned on steep slope and transfer method
CN104818994A (en) Urban subway n-shaped double-shaft and double transverse passage plane arrangement system
CN204851266U (en) Secretly dig shaft structure directly over station
CN201762695U (en) Structure applicable to large and medium-sized mechanical device to enter long tunnel for overhaul
CN110439000B (en) Underground structure internal transportation system based on plate lower sliding chute and construction method
CN111594188A (en) Shield starting and receiving method for subway open cut station
CN107829408A (en) Rectangle aqueduct construction telescoping steel form
CN108397211B (en) A kind of section of jurisdiction that can be removed inside subway tunnel and construction method
CN204663535U (en) City underground π type twin shafts and two transverse passage-way layout system
CN215486018U (en) Subway transfer channel structure for receiving push bench by using station body
CN113463646B (en) Construction method under complex intersection condition of deep and large foundation pit and shallow tunnel
CN212454435U (en) External shield working well for subway shield tunnel construction under road
CN114961772A (en) Underground structure combining subway station and tunnel and construction method thereof
CN214118216U (en) A shelter from canopy for subway percolating water
CN215101586U (en) Earth vertical excavation transportation system in reverse construction method foundation pit engineering
CN205858373U (en) For tunnel, culvert or the repairing and reinforcement structure of box piping lane
CN213116321U (en) Conversion structure between double-layer TBM tunnel and single-layer TBM tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200828