CN106592654A - Monitoring method for perpendicularity of steel pipe pile - Google Patents

Monitoring method for perpendicularity of steel pipe pile Download PDF

Info

Publication number
CN106592654A
CN106592654A CN201611240355.3A CN201611240355A CN106592654A CN 106592654 A CN106592654 A CN 106592654A CN 201611240355 A CN201611240355 A CN 201611240355A CN 106592654 A CN106592654 A CN 106592654A
Authority
CN
China
Prior art keywords
steel pipe
pipe
steel
pipe pile
perpendicularity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611240355.3A
Other languages
Chinese (zh)
Inventor
张继红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201611240355.3A priority Critical patent/CN106592654A/en
Publication of CN106592654A publication Critical patent/CN106592654A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a monitoring method for the perpendicularity of a steel pipe pile in the field of foundation pit bracing engineering monitoring. The monitoring method comprises the following steps that (a) a protecting steel pipe (1) is connected with a steel pipe pile (2); (b) the protecting steel pipe (1) and the steel pipe pile (2) are sunk into a soil body together, and a fixing inclinometer pipe (3) is installed in the protecting steel pipe (1); (c) an inclinometer (4) is stored into the inclinometer pipe (3); (b) the perpendicularity or the perpendicularity change of each section of the steel pipe pile (2) is monitored by measuring the inclinometer pipe (3) in the piling or foundation pit excavating process; and (e) the perpendicularity after piling is completed or the deep horizontal displacement in the foundation pit excavating process of the steel pipe pile (2) is calculated. According to the monitoring method for the perpendicularity of the steel pipe pile, the implementation speed is quick, data are reliable, manufacturing cost is low, and quality is good.

Description

A kind of steel pipe pile verticality monitoring method
Technical field
The present invention relates to the Foundation Pit Support Engineering monitoring field in Geotechnical Engineering field.
Background technology
Steel-pipe pile and steel-pipe pile diaphragm wall as the full foundation pit enclosure structure for reclaiming realize all kinds of depth in weak soil or The full recovery of the foundation pit enclosure soil-baffling structure under all kinds of geological conditions such as pan soil, after the completion of piling and steel-pipe pile in use Perpendicularity and its monitoring of changing value be directly connected to engineering safety, be steel-pipe pile and steel-pipe pile diaphragm wall in foundation pit enclosure work Important step in journey field.
The content of the invention
The purpose of this reality invention is to provide a kind of steel pipe pile verticality monitoring method, and the steel pipe pile verticality monitoring method can Lateral displacement measurement of the steel-pipe pile in the soil body, monitoring cost during for the degree control and excavation of foundation pit during piling Low, degree of safety is high, reliable in quality.
The steel pipe pile verticality monitoring method is comprised the following steps:
A) protection steel pipe is connected with steel-pipe pile;
B) protection steel pipe is sunk to into the soil body together with steel-pipe pile, and fixed inclinometer pipe is installed in protection steel pipe;
C) inclinometer is inserted into inclinometer pipe;
D) each sectional vertical degree of the steel-pipe pile in piling or Excavation Process or vertical is monitored by measuring inclinometer pipe Degree change;
E) calculate deeply mixing cement-soil pile of the steel-pipe pile in the perpendicularity after the completion of piling or in Excavation Process.
The steel pipe pile verticality monitoring method of the present invention, it can be ensured that monitoring instrument is not broken in pile driving process with equipment It is bad, can calculate the perpendicularity of each section of steel-pipe pile, and the change calculations steel-pipe pile case of bending of each section of perpendicularity of steel-pipe pile can be passed through, Data acquisition reliability is high, low cost.
Description of the drawings
Fig. 1 is that the steel-pipe pile cross-sectional configuration with perpendicularity monitoring device used by one embodiment of the present of invention is illustrated Figure.
Specific embodiment
As present invention one embodiment as shown in Figure 1, the main steel pipe pile verticality monitoring method for introducing the present invention Implementation steps.At first of the present embodiment, protection steel pipe (1) is firmly connected with steel-pipe pile (2), welding manner can be taken Connection, i.e., be directly welded on protection steel pipe (1) on the side wall of steel-pipe pile (2).In this step, protect steel pipe (1) Ying Yugang The parallel laying of pile tube (2), it is vertical with steel-pipe pile (2) corresponding segment with the perpendicularity for guaranteeing each segmentation for protecting steel pipe (1) Degree be it is consistent, and should cause protect steel pipe (1) internal diameter more than inclinometer pipe (3) outline, in order to inclinometer pipe (3) place In protection steel pipe (1).Protection steel pipe (1) can be laid in the outside of steel-pipe pile (2), it is also possible to be laid in steel-pipe pile (2) Inner side.So as to complete the first step of the present embodiment, into second step.In this step, will protection steel pipe (1) and steel-pipe pile (2) The soil body is sunk to together, and the mode of sinking to can be completed using the one or more combination in vibratory drilling method, static pressure method or hammering method.Because of protection Steel pipe (1) is firmly connected with steel-pipe pile (2), therefore steel-pipe pile (2) synchronous with protection steel pipe (1) can become during the soil body is sunk to Shape or inclination.Can install solid in protection steel pipe (1) before steel-pipe pile (2) sink to the soil body or after steel-pipe pile (2) sinks to the soil body Location survey inclined tube (3), the one or more combination in can adopting with the following method between inclinometer pipe (3) and protection steel pipe (1) are fixed, the A kind of fixing meanss be by inclinometer pipe (3) be positioned in protection steel pipe (1), then, inclinometer pipe (3) and protection steel pipe (1) it Between inject cement mortar, after cement slurry sets, inclinometer pipe (3) will be fixed in protection steel pipe (1);Second fixing means can To be such, after steel-pipe pile (2) sinks to the soil body with protection steel pipe (1), inclinometer pipe (3) is inserted in protection steel pipe (1), then The charges of sand or other forms are inserted in space between protection steel pipe (1) and inclinometer pipe (3), so as to by inclinometer pipe (3) It is fixed with protection steel pipe (1).The second step of the present embodiment is completed, into the 3rd step.In this step, only need to be by inclinometer (4) Inclinometer pipe (3) is inserted, can start to determine the perpendicularity that inclinometer pipe (3) is respectively segmented.The 3rd step of the present embodiment is completed, into the 4th Step.In this step, by measuring the perpendicularity of each segmentation of inclinometer pipe (3), steel-pipe pile (2) can be calculated during piling Perpendicularity, it is also possible to the perpendicularity of each segmentation of steel-pipe pile (2) is monitored by the different time in Excavation Process, calculates steel The perpendicularity change that pile tube (2) is respectively segmented, so as to the deeply mixing cement-soil pile of steel-pipe pile (2) can be calculated.In the present embodiment, steel pipe Stake (2) can be the steel-pipe pile diaphragm wall for being connected with connector between stake (5).Complete the steel pipe pile verticality monitoring side of the present invention Method.
This patent includes but is not limited to alternative other construction methods for using of professional person in the art.

Claims (1)

1. a kind of steel pipe pile verticality monitoring method, the method are comprised the following steps:
A) protection steel pipe (1) is connected with steel-pipe pile (2);
B) soil body is sunk in protection steel pipe (1) together with steel-pipe pile (2), and fixed inclinometer pipe is installed in protection steel pipe (1) (3);
C) inclinometer (4) is inserted into inclinometer pipe (3);
D) each sectional vertical degree of the steel-pipe pile (2) in piling or Excavation Process or vertical is monitored by measuring inclinometer pipe (3) Straight degree change;
E) calculate deeply mixing cement-soil pile of the steel-pipe pile (2) in the perpendicularity after the completion of piling or in Excavation Process.
CN201611240355.3A 2016-12-28 2016-12-28 Monitoring method for perpendicularity of steel pipe pile Pending CN106592654A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611240355.3A CN106592654A (en) 2016-12-28 2016-12-28 Monitoring method for perpendicularity of steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611240355.3A CN106592654A (en) 2016-12-28 2016-12-28 Monitoring method for perpendicularity of steel pipe pile

Publications (1)

Publication Number Publication Date
CN106592654A true CN106592654A (en) 2017-04-26

Family

ID=58604906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611240355.3A Pending CN106592654A (en) 2016-12-28 2016-12-28 Monitoring method for perpendicularity of steel pipe pile

Country Status (1)

Country Link
CN (1) CN106592654A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108716912A (en) * 2018-04-16 2018-10-30 上海同济检测技术有限公司 Dual axis inclinometer verticality tracking measurement method
CN111236331A (en) * 2020-03-13 2020-06-05 中铁上海工程局集团有限公司 Deep foundation pit spliced precast pile inclinometer pipe mounting structure and application method thereof
CN111778964A (en) * 2020-07-24 2020-10-16 中国建筑第八工程局有限公司 Foundation pit hollow support pile, construction method thereof and foundation pit support structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1123265A (en) * 1997-06-30 1999-01-29 Shimadzu Corp Insertion type inclinometer
CN1690317A (en) * 2004-04-29 2005-11-02 宝山钢铁股份有限公司 Method for measuring pipe pile swing resulted from foundation ditch digging
CN205475366U (en) * 2016-01-21 2016-08-17 昆山市交通工程试验检测中心有限公司 Foundation pile hangs down strain detection device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1123265A (en) * 1997-06-30 1999-01-29 Shimadzu Corp Insertion type inclinometer
CN1690317A (en) * 2004-04-29 2005-11-02 宝山钢铁股份有限公司 Method for measuring pipe pile swing resulted from foundation ditch digging
CN205475366U (en) * 2016-01-21 2016-08-17 昆山市交通工程试验检测中心有限公司 Foundation pile hangs down strain detection device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姜引利: "深基坑支护钢板桩围堰仿真分析与监测", 《公路与汽运》 *
潘泓等: "广州猎德大桥钢板桩围堰的设计与监测", 《岩石力学与工程学报》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108716912A (en) * 2018-04-16 2018-10-30 上海同济检测技术有限公司 Dual axis inclinometer verticality tracking measurement method
CN108716912B (en) * 2018-04-16 2020-07-28 上海同济检测技术有限公司 Perpendicularity tracking and measuring method for double-shaft inclinometer
CN111236331A (en) * 2020-03-13 2020-06-05 中铁上海工程局集团有限公司 Deep foundation pit spliced precast pile inclinometer pipe mounting structure and application method thereof
CN111778964A (en) * 2020-07-24 2020-10-16 中国建筑第八工程局有限公司 Foundation pit hollow support pile, construction method thereof and foundation pit support structure
CN111778964B (en) * 2020-07-24 2022-04-12 中国建筑第八工程局有限公司 Foundation pit hollow support pile, construction method thereof and foundation pit support structure

Similar Documents

Publication Publication Date Title
KR101162918B1 (en) Method of measuring underground displacement using inclinometer
CN104329076B (en) A kind of deviational survey hole osmotic pressure counter device and installation method
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN110700293B (en) Rotary excavating leading hole steel sheet pile cofferdam construction method under deep water sloping rock environment
CN105019485B (en) A kind of excavation of foundation pit dead load test on pile foundation detection method
JP6296867B2 (en) Installation method of stratified settlement meter and stratified settlement measurement system
CN104047611B (en) Weak broken wall rock tunnel two serves as a contrast the best opportunity method of discrimination applied
CN103774690A (en) Grabbing, drilling and punching combined underground continuous wall grooving construction method
CN106592654A (en) Monitoring method for perpendicularity of steel pipe pile
CN105019431B (en) Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method
JP2009174178A (en) Method of constructing underground structure
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
Gao et al. Influence of Benoto bored pile construction on nearby existing tunnel: A case study
CN110174503A (en) A method of determining that country rock weakens development range based on tunnel deformation
CN202925575U (en) Pre-buried structure for core-drilling detection of foundation pile
CN110847809B (en) Pile foundation pore-forming method next to underground structure
CN111733841A (en) Lake bottom karst treatment method for deep-buried shield tunnel
Cheng et al. Alignment of vertical and inclined jet grout columns for waterproofing
Gandhi Observations on pile design and construction practices in India
Baker Jr et al. Caisson construction problems and correction in Chicago
CN105040699A (en) Drilling pile planting method
CN114059921A (en) Hole-forming construction process for cast-in-place pile in karst strong development area
Tan et al. Challenges in design and construction of deep excavation for KVMRT in Kuala Lumpur limestone formation
KR101437882B1 (en) Tunnel excavating method having various cross sectional shapes
Bjerrum et al. Measuring instruments for strutted excavations

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170426