CN106592620A - Construction method of coordination device for guaranteeing pile-soil co-action - Google Patents

Construction method of coordination device for guaranteeing pile-soil co-action Download PDF

Info

Publication number
CN106592620A
CN106592620A CN201611165359.XA CN201611165359A CN106592620A CN 106592620 A CN106592620 A CN 106592620A CN 201611165359 A CN201611165359 A CN 201611165359A CN 106592620 A CN106592620 A CN 106592620A
Authority
CN
China
Prior art keywords
pressure
bearing steel
soil
steel case
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611165359.XA
Other languages
Chinese (zh)
Inventor
尹骥
魏建华
俞海洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Geotechnical Investigations and Design Institute Co Ltd
Original Assignee
Shanghai Geotechnical Investigations and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Geotechnical Investigations and Design Institute Co Ltd filed Critical Shanghai Geotechnical Investigations and Design Institute Co Ltd
Priority to CN201611165359.XA priority Critical patent/CN106592620A/en
Publication of CN106592620A publication Critical patent/CN106592620A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method of a coordination device for guaranteeing pile-soil co-action. The construction method comprises the following steps: sequentially constructing an engineering pile and a pressure-bearing steel box located above the engineering pile from bottom to top in foundation soil, and installing a reserved grouting pipe at the top of the pressure-bearing steel box; and constructing a foundation slab and an upper structure above the pressure-bearing steel box, enabling the pressure-bearing steel box to generate compressive deformation with the foundation soil due to a vertical load generated by the foundation slab and the upper structure, and grouting in the pressure-bearing steel box through the reserved grouting pipe when the foundation soil is compressed to a limit value, thus realizing the pile-soil co-action. The construction method disclosed by the invention has the advantages of being simple in structure, simple and convenient to construct, convenient to calculate, high in reliability, and capable of reliably realizing the pile-soil co-action.

Description

A kind of conditioning unit construction method for guaranteeing pile soil common action
Technical field
The invention belongs to the realm of building construction, and in particular to a kind of conditioning unit for guaranteeing pile soil common action is constructed Method.
Background technology
Pile foundation is a kind of traditional base form, and more universal method for designing is all by work by upper load at present Journey stake is undertaking, and does not consider the carrying effect of foundation soil under basis.In recent years, with the continuous accumulation of engineering experience, ground The bearing capacity of soil is gradually paid attention to, and how to play the bearing capacity of foundation soil, reduces the quantity of engineering engineering pile, so as to save work Journey cost is the new problem that current engineering circles are explored.
To ensure pile soil common action, pile soil common action is realized, the implementation method of the pile soil common action for proposing at present It is numerous, displacement method, stiffness equivalent method, pre-add displacement method etc. are such as compensated, especially by reserved headroom, mattress layer is set, is arranged soft Property the method such as material realize.As various material mechanical performances differ greatly, calculate inaccurate, the reason such as constructional difficulties is most of It is unable to reach the purpose of stake soil pile soil common action.
The content of the invention
The purpose of the present invention is according in place of above-mentioned the deficiencies in the prior art, there is provided a kind of to be used to guarantee pile soil common action Conditioning unit construction method, the construction method by between engineering pile and sole plate arrange can be under vertical uniform load q The pressure-bearing steel case that compression occurs jointly with foundation soil realizes pile soil common action with reliable.
The object of the invention is realized being completed by technical scheme below:
A kind of conditioning unit construction method for guaranteeing pile soil common action, it is characterised in that comprise the following steps:In ground In soil, construction work stake and the pressure-bearing steel case being positioned above successively from bottom to top, and pacify at the top of the pressure-bearing steel case The reserved Grouting Pipe of dress;Construct above the pressure-bearing steel case sole plate and superstructure, the vertical loads produced by both Make the pressure-bearing steel case that compression occur jointly with the foundation soil, when the foundation soil is compressed to ultimate value, by institute Reserved Grouting Pipe is stated to slip casting inside the pressure-bearing steel case, pile soil common action is realized.
The pressure-bearing steel case includes cylindrical sidewall, upper sealing plate and lower shrouding;The upper sealing plate and the lower shrouding are opened It is provided with the reserved circular hole that some connection reinforcing bars for the engineering pile are passed through.
The cross section of the cylindrical sidewall is similar round or class rectangle.
The connection reinforcing bar in the engineering pile sequentially passes through the described pre- of the lower shrouding and the upper envelope steel plate Circular hole is stayed, the engineering pile, the pressure-bearing steel case and the sole plate are connected structure.
The wall thickness of the pressure-bearing steel case is controlled, so that the surrender bearing capacity of the pressure-bearing steel case is corresponding to by the basic bottom Upper load and compression deformation of ground soil ultimate value that plate is applied with the superstructure.
It is an advantage of the invention that simple structure, easy construction, be easy to calculate, reliability it is big, can reliably realize stake soil Collective effect.
Description of the drawings
Fig. 1 is the side view of the pile foundation structure in the present invention;
Fig. 2 is the top view of the pressure-bearing steel case in the present invention;
Fig. 3 is the side view after the completion of the Construction of Engineering Pile in the present invention;
Fig. 4 is the side view after the pressure-bearing steel case installation in the present invention;
Fig. 5 is sole plate and the side view after the completion of Superstructure Construction in the present invention.
Specific embodiment
The feature and other correlated characteristics of the present invention is described in further detail by embodiment below in conjunction with accompanying drawing, with It is easy to the understanding of technical staff of the same trade:
Such as Fig. 1-5, in figure, labelling 1-12 is respectively:Engineering pile 1, pressure-bearing steel case 2, sole plate 3, slip casting implant 4, tubular side Wall 5, upper sealing plate 6, lower shrouding 7, connection reinforcing bar 8, reserved circular hole 9, reserved injected hole 10, reserved Grouting Pipe 11, superstructure 12.
Embodiment:As shown in figure 1, the present embodiment is specifically related to a kind of conditioning unit for guaranteeing pile soil common action applying Work method, the method are comprised the following steps:
1)As shown in Figure 1,3, the construction work stake 1 in foundation soil;The top of engineering pile 1 is provided with the connection steel for extending upward Muscle 8, connecting reinforcing bar 8 is used to connect the sole plate 3 of subsequent construction;After the completion of engineering pile 1 is constructed, need to each engineering pile 1 pile crown carries out leveling, it is ensured that each 1 uniform force of engineering pile.
2)As shown in Fig. 1,2,4, pressure-bearing steel case 2 is installed on the top of engineering pile 1;Pressure-bearing steel case 2 include cylindrical sidewall 5, Upper sealing plate 6 and lower shrouding 7;It is reserved that upper sealing plate 6 and lower shrouding 7 offer that the connection reinforcing bar 8 of some confession engineering piles 1 passes through Circular hole 9;9 a diameter of 20mm to 35mm of reserved circular hole;The cross section of cylindrical sidewall 5 is similar round or class rectangle;In installation process, Connection reinforcing bar 8 in engineering pile 1 sequentially passes through the reserved circular hole 9 of lower shrouding 7 and upper sealing plate 6;It is further opened with upper sealing plate 6 Reserved injected hole 10, the bottom for reserving Grouting Pipe 11 insert the inside of pressure-bearing steel case 2 from reserved injected hole 10, reserve Grouting Pipe 11 Top higher than 3 upper surface of sole plate height.
3)As shown in Fig. 1,2,5, construct above pressure-bearing steel case 2 sole plate 3 and superstructure 12, sole plate 3 It is fixedly connected with the connection reinforcing bar 8 extended to above pressure-bearing steel case 2;After the completion of construction, 12 institute of sole plate 3 and superstructure The vertical load of generation makes the foundation soil below pressure-bearing steel case 2 generation compression, and sole plate 3 also in vertical uniform load q Lower generation compression further produces certain settling amount, that is to say, that pressure-bearing steel case 2 occurs compression jointly with foundation soil; When ground soil pressure is reduced to ultimate value, the foundation soil for being compressed into ultimate value can be with shared top pressure-bearing steel case 2 The effect of load, by reserved Grouting Pipe 11 to the 2 inside slip casting of pressure-bearing steel case so that pressure-bearing steel case 2 forms solid stable stake Body, so as to realize pile soil common action, additionally, the pressure-bearing steel case 2 that side wall occurs compression also can accordingly increase its stake Side friction, and then improve its bearing capacity in foundation soil;After the completion of slip casting, the reserved Grouting Pipe 11 of closing proceeds Construction.
It should be noted that when pressure-bearing steel case 2 is made, by adjusting the wall thickness of its cylindrical sidewall 5 so that it is determined that pressure-bearing The surrender bearing capacity of steel case 2;That is, the wall thickness of the cylindrical sidewall 5 on pressure-bearing steel case 2 should be according to upper load and the foundation soil limit Deformation values are determined, so that when the upper load by produced by sole plate 3 and superstructure 12 reaches pressure-bearing steel case 2 Surrender bearing capacity and foundation soil when being not up to ultimate deformation value, pressure-bearing steel case 2 produces compression, in company with foundation soil body altogether With generation compression.
The Advantageous Effects of the present embodiment are:Simple structure, easy construction, be easy to calculate, reliability it is big, can be reliable Realize pile soil common action.

Claims (5)

1. a kind of conditioning unit construction method for guaranteeing pile soil common action, it is characterised in that comprise the following steps:On ground In base soil, construction work stake and the pressure-bearing steel case being positioned above successively from bottom to top, and at the top of the pressure-bearing steel case Reserved Grouting Pipe is installed;Construct above the pressure-bearing steel case sole plate and superstructure, the vertical lotuses produced by both Load makes the pressure-bearing steel case that compression occur jointly with the foundation soil, when the foundation soil is compressed to ultimate value, passes through The reserved Grouting Pipe realizes pile soil common action to slip casting inside the pressure-bearing steel case.
2. a kind of conditioning unit construction method for guaranteeing pile soil common action according to claim 1, its feature exist In:The pressure-bearing steel case includes cylindrical sidewall, upper sealing plate and lower shrouding;If the upper sealing plate and the lower shrouding are offered The reserved circular hole that the dry connection reinforcing bar for the engineering pile is passed through.
3. a kind of conditioning unit construction method for guaranteeing pile soil common action according to claim 2, its feature exist In:The cross section of the cylindrical sidewall is similar round or class rectangle.
4. a kind of conditioning unit construction method for guaranteeing pile soil common action according to claim 2, its feature exist In:The connection reinforcing bar in the engineering pile sequentially passes through the described reserved circle of the lower shrouding and the upper envelope steel plate Hole, the engineering pile, the pressure-bearing steel case and the sole plate are connected structure.
5. a kind of conditioning unit construction method for guaranteeing pile soil common action according to claim 1, its feature exist In:Control the wall thickness of the pressure-bearing steel case so that the surrender bearing capacity of the pressure-bearing steel case corresponding to by the sole plate with Upper load and compression deformation of ground soil ultimate value that the superstructure applies.
CN201611165359.XA 2016-12-16 2016-12-16 Construction method of coordination device for guaranteeing pile-soil co-action Pending CN106592620A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611165359.XA CN106592620A (en) 2016-12-16 2016-12-16 Construction method of coordination device for guaranteeing pile-soil co-action

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611165359.XA CN106592620A (en) 2016-12-16 2016-12-16 Construction method of coordination device for guaranteeing pile-soil co-action

Publications (1)

Publication Number Publication Date
CN106592620A true CN106592620A (en) 2017-04-26

Family

ID=58801857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611165359.XA Pending CN106592620A (en) 2016-12-16 2016-12-16 Construction method of coordination device for guaranteeing pile-soil co-action

Country Status (1)

Country Link
CN (1) CN106592620A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101487267A (en) * 2009-01-14 2009-07-22 南京工业大学 Support stiffness-adjustable pile-raft foundation and construction process
CN101608455A (en) * 2008-06-17 2009-12-23 上海江欢成建筑设计有限公司 Cavity backfill type pile soil bearing capacity adjusting device
JP2013019248A (en) * 2011-07-14 2013-01-31 Takenaka Komuten Co Ltd Piled raft method
CN203559427U (en) * 2013-10-30 2014-04-23 济南中建建筑设计院有限公司 Settlement-adjustable piled raft foundation structure under combined action of pile and soil

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101608455A (en) * 2008-06-17 2009-12-23 上海江欢成建筑设计有限公司 Cavity backfill type pile soil bearing capacity adjusting device
CN101487267A (en) * 2009-01-14 2009-07-22 南京工业大学 Support stiffness-adjustable pile-raft foundation and construction process
JP2013019248A (en) * 2011-07-14 2013-01-31 Takenaka Komuten Co Ltd Piled raft method
CN203559427U (en) * 2013-10-30 2014-04-23 济南中建建筑设计院有限公司 Settlement-adjustable piled raft foundation structure under combined action of pile and soil

Similar Documents

Publication Publication Date Title
CN202466569U (en) Integrated solid-hollow concrete pile
CN208219303U (en) A kind of high-speed railway cast-in-situ bored pile frame-type road structure
CN206233276U (en) A kind of pretest pile static pressure bringing device
CN206829211U (en) The foundation reinforcing structure passively rectified a deviation for building
CN103541377B (en) Overall process controllable type displacement adjustment device
CN110188499A (en) A kind of compound single pile settlement calculation method of extruding-enlarging branch tray grouting behind shaft or drift lining bored concrete pile
CN202543966U (en) Pile-supported cantilever retaining wall
CN205501843U (en) Consolidate rigid framed arch bridge
CN102493472B (en) Deepwater soft soil foundation reverse construction method low pile cap composite foundation construction process for bridge
CN202595757U (en) Grouting type reinforced filling pile foundation structure
CN207295756U (en) Coating subgrade strengthening structure
CN202787222U (en) Deep stratum reinforcement rammer
CN206308701U (en) A kind of important actor back taper basis high
CN110607801A (en) Improve fan cushion cap subassembly of stake resistance to plucking bearing capacity
CN206418515U (en) It is a kind of to be used to ensure the conditioning unit of pile soil common action
CN106592620A (en) Construction method of coordination device for guaranteeing pile-soil co-action
CN202595758U (en) Batter post foundation structure for overhead transmission line
CN107246037A (en) A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course
CN211257051U (en) Improve fan cushion cap subassembly of stake resistance to plucking bearing capacity
CN215759136U (en) Concrete silo box type foundation
CN205776320U (en) Electric power pylon
CN106836324A (en) A kind of blower foundation reinforcement means for setting up oblique tension reinforcement
CN204645025U (en) A kind of device utilizing soil bearing capacity between grout pile
CN204645071U (en) A kind of device utilizing soil bearing capacity between PHC pipe pile
CN204676591U (en) Trough rim construction elevator basis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426