CN203559427U - Settlement-adjustable piled raft foundation structure under combined action of pile and soil - Google Patents

Settlement-adjustable piled raft foundation structure under combined action of pile and soil Download PDF

Info

Publication number
CN203559427U
CN203559427U CN201320673436.8U CN201320673436U CN203559427U CN 203559427 U CN203559427 U CN 203559427U CN 201320673436 U CN201320673436 U CN 201320673436U CN 203559427 U CN203559427 U CN 203559427U
Authority
CN
China
Prior art keywords
pile
foundation
raft
soil
cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320673436.8U
Other languages
Chinese (zh)
Inventor
张健
孙学锋
冀科锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhong Jian Architecture Design Institute Jinan Co Ltd
CSCEC Jinan Architectural Design Institute Co Ltd
Original Assignee
Zhong Jian Architecture Design Institute Jinan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhong Jian Architecture Design Institute Jinan Co Ltd filed Critical Zhong Jian Architecture Design Institute Jinan Co Ltd
Priority to CN201320673436.8U priority Critical patent/CN203559427U/en
Application granted granted Critical
Publication of CN203559427U publication Critical patent/CN203559427U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a settlement-adjustable piled raft foundation structure under the combined action of a pile and soil. The structure comprises a pile foundation, a raft plate and a pile cap, wherein the pile cap is arranged between the pile foundation and the raft plate, consists of an inner cylinder cavity formed by arranging annular stirrups, side protective nets and a pile cap cover plate, and is used for adjusting differential settlement of the pile foundation and the raft plate; and the height of the cavity is greater than the maximum settlement value of a superstructure. The structure has the benefits that the structure can sufficiently exert a bearing potential of foundation soil, can reduce the pile number, is easy and simple to operate and high in reliability, and has a better popularization prospect.

Description

A kind of pile soil common action sedimentation adjustable type pile-raft foundation structure
Technical field
The utility model relates to a kind of optimal design of pile-raft foundation, particularly, relates to a kind of pile soil common action sedimentation adjustable type pile-raft foundation structure.
Technical background
Along with the high speed development of economic construction, infrastructure is more and more, and pile foundation is because the reliability aspect settlement Control and bearing capacity is subject to increasing attention, and pile foundation theory has also had significant progress and development.Generally, there is the difference of the order of magnitude in the support stiffness of stake, soil, and therefore, under identical load level, the distortion of stake soil is also inharmonious, and both are difficult to as an overall work.Also just for these reasons, ordinary pile foundation designs by all transferring to pile foundation to bear superstructure load at present, do like this and not only easily make raft plate of building and foundation soil come to nothing, cause certain hidden danger to durability and the safety of building foundation, more seriously the bearing capacity of foundation soil cannot be brought into play, and causes larger waste.Bearing capacity of foundation soil is higher, wastes larger.Therefore consider how to utilize the supporting capacity of foundation soil self, the acting in conjunction that realizes stake soil is a problem in the urgent need to address.
Pile soil common action problem is one of key problem of theory of pile foundation research, the essence of its problem is exactly the bearing capacity that how to make full use of stake and foundation soil, make two kinds of diverse materials of mechanical property can bear superstructure load, and Deformation control within the range of permission simultaneously.For eliminating the modified difference of stake soil, guarantee pile soil common action, from realizing the prerequisite of pile soil common action, the implementation method of the pile soil common action that current engineering circles is occurred is roughly divided into three major types, is specially: compensate for displacement method, rigidity are adjusted method and adds in advance displacement method.Above method major part has also rested on theoretical side at present, the drawback that has design calculation theory imperfection, method is immature, construction cost is higher and is difficult to realization.
Summary of the invention
Technical problem to be solved in the utility model is for above-mentioned the deficiencies in the prior art, and provide a kind of pile soil common action sedimentation adjustable type pile-raft foundation to construct, the utility model can fully play potential bearing capacity, a minimizing stake number, cost-saving for foundation soil, it is a kind of both economical applicable new structure structure, easy and simple to handle, reliability is strong, has stronger promotion prospect.
For achieving the above object, the utility model is by the following technical solutions: a kind of pile soil common action sedimentation adjustable type pile-raft foundation structure, comprise pile foundation, raft plate, pile cover, described pile cover is arranged between pile foundation and raft plate, by forming by the inner core cavity that ring-shaped stirrup, side shield net and pile cover cover plate form is set, be used for regulating the differential settlement of pile foundation and raft plate, cavity height is greater than the greatest measure that superstructure is sunk.
Further, in described inner core cavity, be provided with vertical reinforcement, between its top and pile cover cover plate, there is certain space, its bottom is connected with pile foundation, its Main Function is after second pouring, pile foundation and raft plate to be reconnected in aggregates, after assurance stiffness tuning, the resistance to plucking ability of pile foundation is not less than ordinary pile foundation, and owing to having certain space between its top and pile cover cover plate, the situation of bending reinforcing bar in the time of therefore effectively preventing the sedimentation of raft plate.
Further, described inner core cavity bottom and pile foundation junction are provided with sealing ring, and it can effectively prevent that soil from advancing into cavity inside in slip casting.
Further, Grouting Pipe and anti-slurry pipe are installed on described pile cover cover plate, and anti-slurry in pipe is provided with settlement measurement bar, and settlement measurement bar is through anti-slurry pipe, its bottom is connected with pile foundation, it exposes outside anti-slurry pipe, for measuring the relative deformation of pile foundation and raft plate, when the stressed generation sedimentation of raft plate, stake is now not stressed, measuring stick stretches out the corresponding increase of raft plate length, and available meter ruler is measured the length of increase, records raft plate settling amount.
Further, raft plate top is extended in described Grouting Pipe and anti-one end, top of starching pipe, the other end of Grouting Pipe is positioned at the bottom of pile cover inner chamber, and the counter other end of starching pipe is concordant with the bottom surface of pile cover cover plate, anti-main exhaust passage when starching pipe and being secondary pressure cement injection slurry.
As preferably, the external margin of the junction of pile cover and raft plate and pile cover, raft plate is provided with pile cover arrangement of reinforcement, for strengthening the fastening degree of pile cover and raft plate.
Described a kind of pile soil common action sedimentation adjustable type pile-raft foundation structure and construction technology, generally be suitable for better area of soil property, as low compression soil such as sands, the settling amount that different soil properties completed in construction period has very large difference, generally for sand, can think that construction period its final settlement has completed more than 80%, for other low compressibility soil, can think and complete the 50%-80% of final settlement, for middle compressibilty soil, can think and complete 20%-50%, for high-compressibility soil, can think and complete 5%-20%, during design, need to estimate the foundation deformation value of building within the scope of design load, so that the height of reserved pile cover cavity, when foundation soil is born part superstructure load, with stake, bear total settlement and the relative settlement of residue load and control building.In this applicable novel specific design process, should note the value of bearing capacity of foundation slab,
The reasonable value of bearing capacity of foundation slab is the importance can rigidity mode pile-raft foundation successfully designing, also determined to a great extent the cost on whole basis, when the foundation soil destruction of loses stability not, and s is also just within permissible range [S] time in distortion, the design of ground is most economical, in order to make full use of the bearing capacity of foundation soil, when carrying out the calculating of bearing capacity of foundation slab, just can not be confined to all the time elastic stage.Concrete bearing capacity of foundation slab get surely should according to test in situ and with due regard to the dimensional effect of raft plate determine, that is also should control the bearing capacity of determining foundation soil by allowable strain.
The beneficial effects of the utility model are: can fully play foundation soil potential bearing capacity, reduce a stake number, easy and simple to handle, reliability is strong, has stronger promotion prospect.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the utility model is described further
Fig. 1 is the structural profile schematic diagram of pile cover of the present invention.
Fig. 2 is the structural reinforcement intention of pile cover of the present invention.
Fig. 3 is the structural plan schematic diagram of pile cover of the present invention.
Fig. 4 is the floor map of pile cover cover plate.
In figure: 1, pile cover, 2, vertical reinforcement, 3, side shield net, 4, steel hoop, 5, settlement measurement bar, 6, Grouting Pipe, 7, raft plate, 8, anti-slurry pipe, 9, pile cover cover plate, 10, pile cover arrangement of reinforcement, 11, sealing ring.
The specific embodiment
A kind of pile soil common action sedimentation adjustable type pile-raft foundation structure, it is to implement like this, 12 pile foundation constructions are complete, and through acceptance(check), the pile crown of 12 pile foundations cleared up and chipping, at 12 pile foundation tops, 11 sealing rings are set around, then at 11 sealing ring edges, 4 steel hoops are set, then 3 side shield nets are fixed on 4 steel hoops, on 12 pile foundation top pile crowns, 2 vertical reinforcements are set, the height of 2 vertical reinforcements is lower than the inner core cavity height that is intended to arrange, then 5 settlement measurement bars are vertically fixed in 12 pile foundations, 5 settlement measurement bars stretch out outside 7 raft plates, at the external margin of inner core cavity, the external margin of pile cover arranges 10 pile cover arrangements of reinforcement, 6 Grouting Pipe and 8 anti-slurry pipes are installed on 9 pile cover cover plates, one end, bottom of 8 anti-slurry pipes is concordant with 9 pile cover cover plate bottom surfaces, 7 raft plates are extended in one end, top, 7 raft plates are stretched out in one end of 6 Grouting Pipe, the other end extends to the bottom of inner core cavity, then 9 pile cover cover plates are covered on 4 steel hoops, now because 8 anti-slurry pipes are identical with the position of 5 settlement measurement bars, 5 settlement measurement bars expose outside 7 raft plates through 8 anti-slurry pipes, now 1 pile cover construction is complete, cast pile cover concrete, at the external margin of raft plate and with the junction of pile cover, 10 pile cover arrangements of reinforcement are set, then pour into a mould raft board concrete, when foundation deformation reaches after limiting design value, by 6 Grouting Pipe, to the cement slurry that pours into a high strength grade in pile cover, 2 vertical reinforcements of 12 pile foundations are connected in aggregates with 7 raft plates.
Obviously, above-mentioned embodiment is only better embodiment of the present utility model, and the simple modifications of then carrying out on this basis, all belongs to protection domain of the present utility model.

Claims (3)

1. a pile soil common action sedimentation adjustable type pile-raft foundation is constructed, comprise pile foundation, raft plate, pile cover, it is characterized in that pile cover is arranged between pile foundation and raft plate, the inner core cavity being formed by ring-shaped stirrup, side shield net and pile cover cover plate forms, be used for regulating the differential settlement of pile foundation and raft plate, cavity height is greater than the greatest measure that superstructure is sunk.
2. a kind of pile soil common action sedimentation adjustable type pile-raft foundation according to claim 1 is constructed, it is characterized in that on pile cover cover plate, Grouting Pipe being installed manages with anti-slurry, in anti-slurry pipe, be provided with settlement measurement bar, settlement measurement bar bottom is connected with pile foundation, and it exposes outside anti-slurry pipe.
3. a kind of pile soil common action sedimentation adjustable type pile-raft foundation according to claim 1 is constructed, it is characterized in that being provided with vertical reinforcement in inner core cavity, between its top and pile cover cover plate, have certain space, its bottom is connected with pile foundation, and inner core cavity bottom and pile foundation junction are provided with sealing ring.
CN201320673436.8U 2013-10-30 2013-10-30 Settlement-adjustable piled raft foundation structure under combined action of pile and soil Expired - Fee Related CN203559427U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320673436.8U CN203559427U (en) 2013-10-30 2013-10-30 Settlement-adjustable piled raft foundation structure under combined action of pile and soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320673436.8U CN203559427U (en) 2013-10-30 2013-10-30 Settlement-adjustable piled raft foundation structure under combined action of pile and soil

Publications (1)

Publication Number Publication Date
CN203559427U true CN203559427U (en) 2014-04-23

Family

ID=50509158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320673436.8U Expired - Fee Related CN203559427U (en) 2013-10-30 2013-10-30 Settlement-adjustable piled raft foundation structure under combined action of pile and soil

Country Status (1)

Country Link
CN (1) CN203559427U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839657A (en) * 2016-04-20 2016-08-10 叶香雄 Raft foundation
CN106592620A (en) * 2016-12-16 2017-04-26 上海岩土工程勘察设计研究院有限公司 Construction method of coordination device for guaranteeing pile-soil co-action
CN109083143A (en) * 2018-09-27 2018-12-25 上海勘察设计研究院(集团)有限公司 A kind of preexisting hole burried pipe grouting aperture slurry seal construction method and constructing device
CN111335316A (en) * 2020-03-04 2020-06-26 珠海市规划设计研究院 Differential settlement control method for rigid pile composite foundation
CN113931213A (en) * 2021-10-19 2022-01-14 济南市规划设计研究院 Pile foundation flexible connection node only used for uplift resistance and construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839657A (en) * 2016-04-20 2016-08-10 叶香雄 Raft foundation
CN106592620A (en) * 2016-12-16 2017-04-26 上海岩土工程勘察设计研究院有限公司 Construction method of coordination device for guaranteeing pile-soil co-action
CN109083143A (en) * 2018-09-27 2018-12-25 上海勘察设计研究院(集团)有限公司 A kind of preexisting hole burried pipe grouting aperture slurry seal construction method and constructing device
CN111335316A (en) * 2020-03-04 2020-06-26 珠海市规划设计研究院 Differential settlement control method for rigid pile composite foundation
CN113931213A (en) * 2021-10-19 2022-01-14 济南市规划设计研究院 Pile foundation flexible connection node only used for uplift resistance and construction method
CN113931213B (en) * 2021-10-19 2022-12-27 济南市规划设计研究院 Pile foundation flexible connection node only used for uplift resistance and construction method

Similar Documents

Publication Publication Date Title
CN203559427U (en) Settlement-adjustable piled raft foundation structure under combined action of pile and soil
CN205000256U (en) Cast -in -place case roof beam of high mound of bridge construction support system
CN104746422A (en) Bridge prefabricated hollow pier column post-poured connecting structure and construction method
CN204609908U (en) A kind of pressure water work tunnel concrete anticracking liner structure
CN1952273A (en) Digging foundation with baffle and its construction method
CN103233432B (en) Bailey beam reverse lifting support system and construction method thereof
CN101775783A (en) Construction method by using sandbox as temporary support for continuous beam
CN205501843U (en) Consolidate rigid framed arch bridge
CN104878786A (en) Inclined-straight alternating group piles-soil-structure interaction experiment model
CN202730783U (en) Water sealing device between steel cofferdam and concrete
CN104612142B (en) Integral abutment bridge structure based on composite flexible piles and construction method thereof
CN101285302B (en) Method for reinforcing caisson of concrete dam
CN203066052U (en) Geogrid component applicable to abutment of bridge and culvert
CN203373769U (en) Draught fan foundation ring supporting structure arranged on soft soil foundation
CN201605533U (en) Continuous beam temporary support
CN201169781Y (en) Cap digging pit structure
CN216142062U (en) Abutment foundation structure
CN202644549U (en) Single-wall steel hanging box cofferdam
CN205617162U (en) Novel sleeper
CN205530400U (en) Batter pile test model steel reinforcement cage cushion inclines
CN219219284U (en) Sedimentation repair structure of rain sewage inspection well
CN205444262U (en) A pile head for dead load compression test
CN204199177U (en) Interior constraint reinforcing bar protection apparatus
CN204662629U (en) A kind of overflow well derrick
CN203475833U (en) Surcharge preloading structural member for high and large formwork supporting system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140423

Termination date: 20141030

EXPY Termination of patent right or utility model