CN106567463B - 华夫板施工缝防漏浆施工方法 - Google Patents
华夫板施工缝防漏浆施工方法 Download PDFInfo
- Publication number
- CN106567463B CN106567463B CN201610988363.XA CN201610988363A CN106567463B CN 106567463 B CN106567463 B CN 106567463B CN 201610988363 A CN201610988363 A CN 201610988363A CN 106567463 B CN106567463 B CN 106567463B
- Authority
- CN
- China
- Prior art keywords
- construction
- construction joint
- concrete
- flat panel
- wafer board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6806—Waterstops
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明涉及厂房建筑施工领域,具体是华夫板施工缝防漏浆施工方法;其特征是:包括按照施工缝位置,在平板模板上固定模板,采用C30细石混凝土浇筑;将平板模板切开,钢筋绑扎对施工缝位置进行固定;在混凝土浇筑时,配备一台高压水枪,对施工缝外的飞溅泥浆、渗漏浆进行及时冲洗;在施工缝一侧华夫板浇筑完毕后,取出收口网上口方钢管,检查上口混凝土边缘情况,必要时进行切割修边,底部平板模板上预设的冲洗口在二次浇筑侧混凝土浇筑前进行封口,封口时采用原先切割预留的模板条进行塞缝,完成后进行二次侧混凝土浇筑。采用上述施工方法能够简单、有效、快捷地进行华夫板施工缝防渗漏施工处理,并且,成型后的混凝土表面也具有美观、平整和连续的效果。
Description
技术领域
本发明涉及厂房建筑施工领域,具体是华夫板施工缝防漏浆施工方法。
背景技术
洁净厂房的洁净楼板(即华夫板)存在板厚、面积大、施工进度紧凑的特点。因此要将华夫板分成若干区域进行跳仓法施工,这样的施工方法将造成大量的分仓施工缝,而如何进行施工缝的防漏浆处理是华夫板施工的一大难点。
发明内容
本发明的目的在于,提供一种简化漏浆处理、有利于混凝土观感及成型质量的华夫板施工缝防漏浆施工方法。
为了达到上述目的,本发明是这样实现的:
一种华夫板施工缝防漏浆施工方法,包括
步骤1、当平板模板抄平完毕后,在平板模板上对轴线进行放样,通过对轴线框对角线长度的测量进行复核;
步骤2、对奇氏桶中心线进行放样,按照施工图及施工方案的要求,在现场实际放样出施工缝的位置;
步骤3、按照施工缝位置,在平板模板上按照100mm宽度固定模板,厚度30mm,采用C30细石混凝土浇筑;其中,浇筑前应对模板浇水湿润,浇筑完毕后覆盖土工布浇水养护;
步骤4、在施工缝外延300mm处采用切割机,将平板模板切开,切开部位宽度为100mm,切割好的模板放置在切缝部位边缘,以备后续封堵使用;
步骤5、在钢筋绑扎完毕浇筑混凝土前,对施工缝位置的井字梁进行固定,固定方式为将该梁与其交越的梁钢筋进行焊接固定,以防止浇筑时混凝土的侧压力将井字梁挤偏,造成下一板块奇氏桶无法安装的情况;
步骤6、在施工缝位置井字梁的靠浇筑一侧,固定安装快易收口网,收口网底部与模板脱开10mm,与浇筑的混凝土挡条交越20mm,保证拆模后混凝土观感质量;
步骤7、快易收口网安装完毕后,在收口网上部,贴近混凝土板面处安装方钢管,用以约束收口网上端及控制混凝土边缘高度;其中,方钢管采用电焊法固定,固定前对方管上皮标高进行抄测复核;
步骤8、在混凝土浇筑时,配备一台高压水枪,对施工缝外的飞溅泥浆、渗漏浆进行及时冲洗;
步骤9、在施工缝一侧华夫板浇筑完毕后,取出收口网上口方钢管,检查上口混凝土边缘情况,必要时进行切割修边,底部平板模板上预设的冲洗口在二次浇筑侧混凝土浇筑前进行封口,封口时采用原先切割预留的模板条进行塞缝,完成后进行二次侧混凝土浇筑。
采用上述施工方法能够简单、有效、快捷地进行华夫板施工缝防渗漏施工处理,并且,成型后的混凝土表面也具有美观、平整和连续的效果。
附图说明
图1为本施工方法施工示意图一。
图2为本施工方法施工示意图二。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1、图2所示,一种华夫板施工缝防漏浆施工方法,包括
步骤1、当平板模板抄平完毕后,在平板模板上对轴线进行放样,通过对轴线框对角线长度的测量进行复核;
步骤2、对奇氏桶中心线进行放样,按照施工图及施工方案的要求,在现场实际放样出施工缝的位置;
步骤3、按照施工缝位置,在平板模板上按照100mm宽度固定模板,厚度30mm,采用C30细石混凝土浇筑;其中,浇筑前应对模板浇水湿润,浇筑完毕后覆盖土工布浇水养护;
步骤4、在施工缝外延300mm处采用切割机,将平板模板切开,切开部位宽度为100mm,切割好的模板放置在切缝部位边缘,以备后续封堵使用;
步骤5、在钢筋绑扎完毕浇筑混凝土前,对施工缝位置的井字梁进行固定,固定方式为将该梁与其交越的梁钢筋进行焊接固定,以防止浇筑时混凝土的侧压力将井字梁挤偏,造成下一板块奇氏桶无法安装的情况;
步骤6、在施工缝位置井字梁的靠浇筑一侧,固定安装快易收口网,收口网底部与模板脱开10mm,与浇筑的混凝土挡条交越20mm,保证拆模后混凝土观感质量;
步骤7、快易收口网安装完毕后,在收口网上部,贴近混凝土板面处安装方钢管,用以约束收口网上端及控制混凝土边缘高度;其中,方钢管采用电焊法固定,固定前对方管上皮标高进行抄测复核;
步骤8、在混凝土浇筑时,配备一台高压水枪,对施工缝外的飞溅泥浆、渗漏浆进行及时冲洗;
步骤9、在施工缝一侧华夫板浇筑完毕后,取出收口网上口方钢管,检查上口混凝土边缘情况,必要时进行切割修边,底部平板模板上预设的冲洗口在二次浇筑侧混凝土浇筑前进行封口,封口时采用原先切割预留的模板条进行塞缝,完成后进行二次侧混凝土浇筑。
采用上述施工方法能够简单、有效、快捷地进行华夫板施工缝防渗漏施工处理,并且,成型后的混凝土表面也具有美观、平整和连续的效果。
Claims (1)
1.一种华夫板施工缝防漏浆施工方法,其特征是:包括
步骤1、当平板模板抄平完毕后,在平板模板上对轴线进行放样,通过对轴线框对角线长度的测量进行复核;
步骤2、对奇氏桶中心线进行放样,按照施工图及施工方案的要求,在现场实际放样出施工缝的位置;
步骤3、按照施工缝位置,在平板模板上以平板模板边缘为参照,然后在距离该参照100mm的位置固定模板,厚度30mm,采用C30细石混凝土浇筑;其中,浇筑前应对模板浇水湿润,浇筑完毕后覆盖土工布浇水养护;
步骤4、在施工缝外延300mm处采用切割机,将平板模板切开,切开部位宽度为100mm,切割好的模板放置在切缝部位边缘,以备后续封堵使用;
步骤5、在钢筋绑扎完毕浇筑混凝土前,对施工缝位置的井字梁进行固定,固定方式为将该梁钢筋与其交越的梁钢筋进行焊接固定,以防止浇筑时混凝土的侧压力将井字梁挤偏,造成下一板块奇氏桶无法安装的情况;
步骤6、在施工缝位置井字梁的靠浇筑一侧,固定安装快易收口网,快易收口网底部与模板脱开10mm,与浇筑的混凝土挡条交越20mm,保证拆模后混凝土观感质量;
步骤7、快易收口网安装完毕后,在快易收口网上部,贴近混凝土板面处安装方钢管,用以约束快易收口网上端及控制混凝土边缘高度;其中,方钢管采用电焊法固定,固定前对方钢管上皮标高进行抄测复核;
步骤8、在混凝土浇筑时,配备一台高压水枪,对施工缝外的飞溅泥浆、渗漏浆进行及时冲洗;
步骤9、在施工缝一侧华夫板浇筑完毕后,取出快易收口网上口方钢管,检查上口混凝土边缘情况,必要时进行切割修边,底部平板模板上预设的冲洗口在二次浇筑侧混凝土浇筑前进行封口,封口时采用原先切割预留的模板条进行塞缝,完成后进行二次侧混凝土浇筑。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610988363.XA CN106567463B (zh) | 2016-11-10 | 2016-11-10 | 华夫板施工缝防漏浆施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610988363.XA CN106567463B (zh) | 2016-11-10 | 2016-11-10 | 华夫板施工缝防漏浆施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106567463A CN106567463A (zh) | 2017-04-19 |
CN106567463B true CN106567463B (zh) | 2019-03-15 |
Family
ID=58540968
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610988363.XA Active CN106567463B (zh) | 2016-11-10 | 2016-11-10 | 华夫板施工缝防漏浆施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106567463B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110173052A (zh) * | 2019-05-17 | 2019-08-27 | 武汉一冶建筑安装工程有限责任公司 | 施工缝施工方法 |
CN110344538A (zh) * | 2019-06-28 | 2019-10-18 | 上海宝冶集团有限公司 | 井字梁阴角的防开裂方法 |
CN114135077A (zh) * | 2021-11-08 | 2022-03-04 | 中建四局第六建设有限公司 | 一种混凝土超筑复位切割的免分仓条结构地坪施工方法 |
CN113982116A (zh) * | 2021-11-22 | 2022-01-28 | 中建科工集团有限公司 | 一种高层钢结构住宅不等高施工屋面构造方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5898550A (ja) * | 1981-12-07 | 1983-06-11 | ショボンド建設株式会社 | プレキヤスト床版の継手構造 |
CN101328745A (zh) * | 2004-06-03 | 2008-12-24 | 奇美实业股份有限公司 | 一种无尘室厂房的混凝土楼板预留开孔的施工方法 |
CN102359272A (zh) * | 2011-08-15 | 2012-02-22 | 中国建筑第八工程局有限公司 | 用奇氏筒作留孔模具的华夫板施工方法 |
CN102677898A (zh) * | 2011-03-17 | 2012-09-19 | 中铁二局股份有限公司 | 大面积钢筋混凝土楼板跳仓法施工方法 |
CN205329988U (zh) * | 2016-02-03 | 2016-06-22 | 深圳卓诺中科科技发展有限公司 | 一种华夫板的施工结构 |
-
2016
- 2016-11-10 CN CN201610988363.XA patent/CN106567463B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5898550A (ja) * | 1981-12-07 | 1983-06-11 | ショボンド建設株式会社 | プレキヤスト床版の継手構造 |
CN101328745A (zh) * | 2004-06-03 | 2008-12-24 | 奇美实业股份有限公司 | 一种无尘室厂房的混凝土楼板预留开孔的施工方法 |
CN102677898A (zh) * | 2011-03-17 | 2012-09-19 | 中铁二局股份有限公司 | 大面积钢筋混凝土楼板跳仓法施工方法 |
CN102359272A (zh) * | 2011-08-15 | 2012-02-22 | 中国建筑第八工程局有限公司 | 用奇氏筒作留孔模具的华夫板施工方法 |
CN205329988U (zh) * | 2016-02-03 | 2016-06-22 | 深圳卓诺中科科技发展有限公司 | 一种华夫板的施工结构 |
Also Published As
Publication number | Publication date |
---|---|
CN106567463A (zh) | 2017-04-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106567463B (zh) | 华夫板施工缝防漏浆施工方法 | |
CN105064579B (zh) | 一种保证卫生间止水坎台浇筑成型的施工方法 | |
CN109322505A (zh) | 一种屋面预留洞口混凝土封堵装置及其制作方法 | |
CN109577377A (zh) | 地下室后浇带结构及其施工方法 | |
CN104264700A (zh) | 一种地下建筑轻型降水井点后浇带的防渗漏施工方法 | |
CN114482424B (zh) | 一种暗藏企口的女儿墙二次浇筑施工方法 | |
CN108638322B (zh) | 一种装配式建筑中预制柱混凝土浇筑方法 | |
CN206844138U (zh) | 一种坡形独立基础的钢筋结构 | |
CN207212356U (zh) | 一种隧道二次衬砌端头折叠模板 | |
CN209620278U (zh) | 一种具有可周转钢筋内衬的混凝土反坎模板结构 | |
CN208604640U (zh) | 一种外墙后浇带快速建造结构 | |
CN204174629U (zh) | 一种地下建筑轻型降水井点后浇带多道设防封堵结构 | |
CN205875714U (zh) | 一种用于固定圈梁模板的加固卡具 | |
CN107299649A (zh) | 一种用于丰沛地下水位的后浇带超前止水施工方法 | |
CN208202554U (zh) | 一种楼面的后浇带模板支设结构 | |
CN105986671A (zh) | 一种建筑混凝土浇注工艺 | |
CN108385981A (zh) | 一种室外地下室顶板后浇带防渗漏施工方法 | |
CN209082573U (zh) | 一种沉降后浇带预先封闭构造 | |
CN209703720U (zh) | 池壁施工缝多重防水结构 | |
CN102322146A (zh) | 剪力墙结构连梁施工缝的处理方法 | |
CN206829094U (zh) | 一种便于安装盖板的混凝土沟结构 | |
CN109914571A (zh) | 一种地下室排水沟模架体系、浇筑系统及施工方法 | |
CN201962948U (zh) | 一种顶部带有预埋件的混凝土梁浇注模板 | |
CN206309016U (zh) | 一种后浇带侧模及防水结构 | |
CN206428583U (zh) | 一种用于半预制钢筋混凝土墙式护栏的护栏预制挂板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |