CN106522251A - 地质钻孔承压水喷涌水头平衡施工方法 - Google Patents
地质钻孔承压水喷涌水头平衡施工方法 Download PDFInfo
- Publication number
- CN106522251A CN106522251A CN201610969928.XA CN201610969928A CN106522251A CN 106522251 A CN106522251 A CN 106522251A CN 201610969928 A CN201610969928 A CN 201610969928A CN 106522251 A CN106522251 A CN 106522251A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- water
- construction method
- geotechnical boring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Earth Drilling (AREA)
Abstract
本发明公开了地质钻孔承压水喷涌水头平衡施工方法,包括如下步骤:S1:施工场地准备,大直径钢管施工前,清除地质钻孔附近泥沙,不对地质钻孔进行封堵,桩机停放场地选择在基坑外的路边;S2:钢管桩机进场,根据钢管重量及长度选择桩机,桩机进入设定位置;S3:测量放样,在钢管施打位置测量放样,并标明位置;S4:钢管起吊、就位,钢管桩机将钢管吊至上述标明位置的正上方,人工配合扶正;S5:钢管施打到位,钢管桩机对钢管进行施打,将钢管施打至设定位置,使地质钻孔位于钢管内。该方法可有效的解决基坑底地质钻孔承压水喷涌的问题,并且该方法操作简便,实施效果良好,可有效避免地下水对基坑施工的影响。
Description
技术领域
本发明涉及地质钻孔,尤其涉及地质钻孔承压水喷涌水头平衡施工方法。
背景技术
随着我国城市化和工业化步伐的不断加快,带动各种高层、超高层建筑拔地而起,各种大型地下空间也得到越来越多的开发利用。地下工程建设过程中,不可避免地会受到地下水的干扰。如果地下水的问题处理不当将对基坑开挖及周边建筑环境带来重大风险。
现有技术中,地质钻孔承压水喷涌的处理方法,主要分为三类:
(1)注浆封堵,通过注浆与土体结合形成强度高、渗透性小的结合体,改善土体性质,解决基坑开挖过程中承压水的突涌。该方法取材容易,配置简单,无环境污染等,目前在实际工程中应用比较广泛。但是采用该方法,在注浆封堵前,需要对涌水部位进行回填反压、临时封堵,若遇上涌水量大时,单独采用注浆效果难以达到,还需配合抽水减压。
(2)井点降水,通过降低承压水水头,使基底上覆土层重量与承压水的水压力达到平衡,避免发生突涌。该方法在降水前,也需对突涌部位进行回填反压。同时,在承压水水头较大时,降水工作量大,需在附近建筑物旁边地层中用回灌水法以控制地层沉降,保护建筑设施。
(3)有序引流,通过设置引流装置的方法,能较好地解决地下水流入基坑内的问题。但采用该方法,需对引流周边进行处理,地下水引流至集水井之后,仍需抽离基坑,消耗人力物力。此外,涌水量较大时,也造成地下水大量流失。
发明内容
为了克服现有技术的不足,本发明的目的在于提供地质钻孔承压水喷涌水头平衡施工方法,该方法可有效的解决基坑底地质钻孔承压水喷涌的问题,并且该方法操作简便,实施效果良好,可有效避免地下水对基坑施工的影响。
本发明的目的采用以下技术方案实现:
地质钻孔承压水喷涌水头平衡施工方法,包括如下步骤:
S1:施工场地准备,大直径钢管施工前,清除地质钻孔附近泥沙,不对钻孔进行封堵,桩机停放场地选择在基坑外的路边;
S2:钢管桩机进场,根据钢管重量及长度选择桩机,桩机进入设定位置;
S3:测量放样,在钢管施打位置测量放样,并标明位置;
S4:钢管起吊、就位,钢管桩机将钢管吊至上述标明位置的正上方,人工配合扶正;
S5:钢管施打到位,钢管桩机对钢管进行施打,将钢管施打至设定位置,使地质钻孔位于钢管内。
优选地,地质钻孔直径为108mm,采用内径为800mm的无缝钢管,钢管壁厚为10mm,钢管的长度L≥8200mm。
优选地,钢管的长度L为9000mm。
优选地,将钢管的下端打入基坑底以下2.5m。
优选地,使用线锤将钢管垂直度偏差控制在1%内。
相比现有技术,本发明的有益效果在于:通过在涌水钻孔位置施打一根大直径钢管,将喷涌出的地下水储存于钢管内,平衡基坑内外水头高度,避免地下水喷涌,并且,采用该方法,避免了使用复杂机械设备进行抽水,操作非常简单,节约了大量的成本,经济效用高,可有效减少地下水的流失,避免了地下水对基坑施工的影响,避免了因地下水流失造成土质干裂基坑下沉的危险。
附图说明
图1为本发明地质钻孔承压水喷涌水头平衡施工方法的施工流程图;
图2为本发明地质钻孔承压水喷涌水头平衡施工方法的示意图;
图中:1、基坑;2、钢管;3、地质钻孔。
具体实施方式
下面,结合附图以及具体实施方式,对本发明做进一步描述:
如图1和图2所示,地质钻孔承压水喷涌水头平衡施工方法,包括如下步骤:
S1:施工场地准备,大直径钢管2施工前,清除地质钻孔3附近泥沙,不对地质钻孔进行封堵,桩机停放在基坑1外。
S2:钢管2桩机进场,根据钢管2重量及长度选择桩机,桩机进入设定位置。
S3:测量放样,在钢管2施打位置测量放样,并标明位置。
S4:钢管2起吊、就位,钢管2桩机将钢管2吊至上述标明位置的正上方,人工配合扶正;具体地,在钢管2的顶端开两个孔,用钢丝绳穿过两孔,然后通过钢管2桩机将钢管2吊装至标明位置的正上方。
S5:钢管2施打到位,钢管2桩机对钢管2进行施打,将钢管2施打至设定位置,使地质钻孔位于钢管内;在施打钢管2的过程中,应随时检查其管身是否垂直,若发生倾斜,应立即纠正或者将钢管2拔起重新施打。
如此,通过在涌水钻孔3位置施打一根大直径钢管2,将喷涌出的地下水储存于钢管2内,间接降低了地下承压水头高度,减小了地下水的浮力,避免地下水喷涌,并且,采用该方法,避免了使用复杂机械设备进行抽水,操作非常简单,节约了大量的成本,经济效用高,可有效减少地下水的流失,避免了地下水对基坑1施工的影响。
地质钻孔3直径为108mm,由于地质钻孔3破坏原始工程地质条件,钻孔3周边有部分地下水涌出,涌水位置不一定局限于钻孔3范围内,因此,为了确保喷涌出的地下水能全部储存于钢管2内,根据现场实际涌水情况,钢管2直径大于地质钻孔3直径,优选地,采用内径为800mm的无缝钢管2,钢管2壁厚为10mm,钢管2的长度L≥8200mm。
为了进一步防止水从钢管2的上端涌出,优选地,钢管2的长度L为9000mm。
直径DN800钢管2,壁厚10mm,长度9000mm,每1000mm钢管2重量为200kg,总重量1.8t,选择三一405型钢板桩机。
为了保证钢管2在工作过程中的稳定性,将钢管2的下端打入基坑1底以下2.5m。
为了保证钢管2的垂直度,使用线锤将钢管2垂直度偏差控制在1%内。
对本领域的技术人员来说,可根据以上描述的技术方案以及构思,做出其它各种相应的改变以及形变,而所有的这些改变以及形变都应该属于本发明权利要求的保护范围之内。
Claims (5)
1.地质钻孔承压水喷涌水头平衡施工方法,其特征在于,包括如下步骤:
S1:施工场地准备,大直径钢管施工前,清除地质钻孔附近泥沙,不对地质钻孔进行封堵,桩机停放场地选择在基坑外的路边;
S2:钢管桩机进场,根据钢管重量及长度选择桩机,桩机进入设定位置;
S3:测量放样,在钢管施打位置测量放样,并标明位置;
S4:钢管起吊、就位,钢管桩机将钢管吊至上述标明位置的正上方,人工配合扶正;
S5:钢管施打到位,钢管桩机对钢管进行施打,将钢管施打至设定位置,使地质钻孔位于钢管内。
2.根据权利要求1所述的地质钻孔承压水喷涌水头平衡施工方法,其特征在于,地质钻孔直径为108mm,采用内径为800mm的无缝钢管,钢管壁厚为10mm,钢管的长度L≥8200mm。
3.根据权利要求2所述的地质钻孔承压水喷涌水头平衡施工方法,其特征在于,钢管的长度L为9000mm。
4.根据权利要求3所述的地质钻孔承压水喷涌水头平衡施工方法,其特征在于,将钢管的下端打入基坑底以下2.5m。
5.根据权利要求1所述的地质钻孔承压水喷涌水头平衡施工方法,其特征在于,使用线锤将钢管垂直度偏差控制在1%内。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610969928.XA CN106522251A (zh) | 2016-10-28 | 2016-10-28 | 地质钻孔承压水喷涌水头平衡施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610969928.XA CN106522251A (zh) | 2016-10-28 | 2016-10-28 | 地质钻孔承压水喷涌水头平衡施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106522251A true CN106522251A (zh) | 2017-03-22 |
Family
ID=58326148
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610969928.XA Pending CN106522251A (zh) | 2016-10-28 | 2016-10-28 | 地质钻孔承压水喷涌水头平衡施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106522251A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958433A (zh) * | 2017-05-09 | 2017-07-18 | 中铁二十四局集团南昌铁路工程有限公司 | 一种岩溶区动水处理装置及处理方法 |
CN110374093A (zh) * | 2019-07-16 | 2019-10-25 | 深圳市市政工程总公司 | 高承压裂隙水地层钻孔灌注桩施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19525590A1 (de) * | 1995-07-13 | 1997-01-16 | Zueblin Ag | Herstellung einer Baugrube mit Verankerungen unterhalb des Grundwasserspiegels |
US5911546A (en) * | 1989-03-03 | 1999-06-15 | University Of Waterloo | In-ground barrier |
CN101205721A (zh) * | 2007-12-03 | 2008-06-25 | 中铁大桥局集团第四工程有限公司 | 深水低桩承台施工中用钢围堰结合高压旋喷桩围水的方法 |
CN102926409A (zh) * | 2011-08-09 | 2013-02-13 | 上海建工五建集团有限公司 | 一种防止水土流失的施工方法 |
CN103643690A (zh) * | 2013-12-12 | 2014-03-19 | 南京工业大学 | 一种深基坑勘探孔涌水处理方法 |
CN105155564A (zh) * | 2015-08-07 | 2015-12-16 | 中建三局第二建设工程有限责任公司 | 深基坑薄弱隔水层防突涌的施工方法 |
-
2016
- 2016-10-28 CN CN201610969928.XA patent/CN106522251A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5911546A (en) * | 1989-03-03 | 1999-06-15 | University Of Waterloo | In-ground barrier |
DE19525590A1 (de) * | 1995-07-13 | 1997-01-16 | Zueblin Ag | Herstellung einer Baugrube mit Verankerungen unterhalb des Grundwasserspiegels |
CN101205721A (zh) * | 2007-12-03 | 2008-06-25 | 中铁大桥局集团第四工程有限公司 | 深水低桩承台施工中用钢围堰结合高压旋喷桩围水的方法 |
CN102926409A (zh) * | 2011-08-09 | 2013-02-13 | 上海建工五建集团有限公司 | 一种防止水土流失的施工方法 |
CN103643690A (zh) * | 2013-12-12 | 2014-03-19 | 南京工业大学 | 一种深基坑勘探孔涌水处理方法 |
CN105155564A (zh) * | 2015-08-07 | 2015-12-16 | 中建三局第二建设工程有限责任公司 | 深基坑薄弱隔水层防突涌的施工方法 |
Non-Patent Citations (1)
Title |
---|
龙三文: ""防护堤减压井的施工"", 《广东水利水电》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958433A (zh) * | 2017-05-09 | 2017-07-18 | 中铁二十四局集团南昌铁路工程有限公司 | 一种岩溶区动水处理装置及处理方法 |
CN110374093A (zh) * | 2019-07-16 | 2019-10-25 | 深圳市市政工程总公司 | 高承压裂隙水地层钻孔灌注桩施工方法 |
CN110374093B (zh) * | 2019-07-16 | 2021-07-06 | 深圳市市政工程总公司 | 高承压裂隙水地层钻孔灌注桩施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102454167B (zh) | 大型超深沉井的施工方法 | |
CN104196034B (zh) | 一种利用钢板桩作为支护围堰的基坑施工方法 | |
CN102691294B (zh) | 一种地下连续墙的施工方法 | |
CN113445498A (zh) | 复杂地质岩溶孔桩基础施工工艺 | |
CN203846485U (zh) | 长桩冲击钻成孔施工装置 | |
CN101560767A (zh) | 地下连续墙施工中槽段连接的方法 | |
CN106836206A (zh) | 护筒旋挖成桩施工方法 | |
CN102720186B (zh) | 变截面钻孔灌注桩水下一次成型浇筑法 | |
CN108589707A (zh) | 一种全套管长螺旋钻与旋挖钻组合式施工工法 | |
CN104563098A (zh) | 一种超大直径全钢护筒干作业成孔灌注桩施工方法 | |
CN105155516B (zh) | 在全面清理地下障碍物前施工钻孔灌注桩的方法 | |
CN105275381A (zh) | 富水卵石地层中冲击钻成孔施工方法 | |
CN110629747A (zh) | 复杂地质条件下桩基础全套管全回转施工工艺 | |
CN103114599A (zh) | 深基坑封闭降水装置及其施工方法 | |
CN209741847U (zh) | 一种钻孔灌注桩用导向支架 | |
CN112030956A (zh) | 一种岩溶地层钻孔灌注桩施工方法 | |
CN112482364A (zh) | 滨海地区强腐蚀性软弱地质条件下的旋挖灌注桩施工工艺 | |
CN110158579A (zh) | 一种钻孔灌注桩施工方法 | |
CN104762982A (zh) | 一种富水红砂岩地质地下水位控制的施工方法 | |
CN102535490A (zh) | 一种利用钻孔灌注桩进行基坑降水的方法 | |
CN101761069B (zh) | 三墙合一地下连续墙施工方法 | |
CN106522251A (zh) | 地质钻孔承压水喷涌水头平衡施工方法 | |
CN204401612U (zh) | 一种超大直径全钢护筒干作业成孔灌注桩施工装置 | |
CN206143760U (zh) | 一种联排式水上灌注桩装置 | |
CN212052725U (zh) | 溶洞区桩施工结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170322 |