CN106505509A - A kind of 500kV cable systems transition joint mounting process - Google Patents

A kind of 500kV cable systems transition joint mounting process Download PDF

Info

Publication number
CN106505509A
CN106505509A CN201610993023.6A CN201610993023A CN106505509A CN 106505509 A CN106505509 A CN 106505509A CN 201610993023 A CN201610993023 A CN 201610993023A CN 106505509 A CN106505509 A CN 106505509A
Authority
CN
China
Prior art keywords
cable
copper
insulation
heat
transition joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610993023.6A
Other languages
Chinese (zh)
Inventor
杨丽伟
滕兆丰
倪穗
盛宇杰
蒋国杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Cable Co Ltd
Original Assignee
Hangzhou Cable Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Cable Co Ltd filed Critical Hangzhou Cable Co Ltd
Priority to CN201610993023.6A priority Critical patent/CN106505509A/en
Publication of CN106505509A publication Critical patent/CN106505509A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G15/00Cable fittings
    • H02G15/08Cable junctions
    • H02G15/18Cable junctions protected by sleeves, e.g. for communication cable
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G15/00Cable fittings
    • H02G15/08Cable junctions

Landscapes

  • Cable Accessories (AREA)

Abstract

The present invention relates to extra-high-tension cable systems technology field, discloses a kind of 500kV cable systems transition joint mounting process, including:1) construction condition confirms;2) prepare before installing;3) transition joint major insulation stress cone is installed;4) process of cable and joint external screen;5) installation of copper shell;6) grounding.The present invention proposes a whole set of 500kV cable system transition joint mounting process, and the effective specification installation procedure of joint, it is to avoid randomness that joint is installed, so that ensure stability and the safety of cable system.

Description

A kind of 500kV cable systems transition joint mounting process
Technical field
A kind of the present invention relates to extra-high-tension cable systems technology field, more particularly to 500kV cable systems transition joint peace Dress technique.
Background technology
With the continuous dilatation of China's super-large city, transmission distance and power consumption are constantly increasing, existing 220kV cities Power transmission network increasingly can not meet the power reguirements of super-large city, therefore, using limited space, using jumbo 500kV electric power transmissions cable system enters big city, has become inevitable development trend.In recent years, although China is high in 500kV Achieve not little progress in terms of voltage cable and adnexa production, the product performance index that produces can meet national standard and IEC standard, yet with the immature, unstable and lack of standardization of attachment tab process, also gap compared with foreign countries, So that China 500kV power cable systems still rely on external producer.
The Chinese patent of Application No. CN200910060410.4 is disclosed in a kind of high voltage power cable rubber-like indirectly Head installation method and device, certain depth in cable major insulation is inserted in transition joint, in transition joint inner chamber and cable major insulation Surface is passed through gases at high pressure, move to precalculated position stop inflation, transition joint before cable is inserted in, initially with Hough set The method of transition joint is inserted in, two pairs of Hough sets is inserted in the inner chamber of transition joint two ends respectively, then two ends is carried Hough set Transition joint be inserted in cable major insulation by gases at high pressure, one end Hough set being wherein first inserted in is with sealing ring and filling Pore, after two sections of cable connections are finished, restart to inflate, and the dynamic transition joint of reverse push, move to specified location and stop Only inflate, the tool device such as two pairs of Hough sets of unloading, transition joint is that elasticity is held tightly in cable main.Using foregoing invention, Transition joint installation effectiveness is substantially increased, and operation is simple and reliable, be particularly well-suited to the installation of 110kV power cables.
But foregoing invention just in the cable of 110kV, therefore need badly a kind of specification ground, safely, stably and It is directed to the installation method of the cable system transition joint of 500kV.
Content of the invention
In order to solve above-mentioned technical problem, the invention provides a kind of 500kV cable systems transition joint mounting process.This Flow process and points for attention in invention specification transition joint installation process, random when effectively avoiding transition joint from installing Property, so as to improve 500kV cable systems safety and stability.
The present invention concrete technical scheme be:
A kind of 500kV cable systems transition joint mounting process, comprises the following steps:
1) construction condition confirms:
1.1) product standard and type is checked;
1.2) confirm that installation outfit is complete;
1.3) in-site installation purifies paulin and mobile air conditioner, it is ensured that, at 0-35 DEG C, air is relative for the temperature control of erecting bed Humidity≤70%;
2) prepare before installing:
2.1) cable two ends are in place, heat alignment pretreatment, remove mechanical stress;
2.1.1) two end cables to be installed are put, and long end, the short end direction of cable is determined according to field requirement;
2.1.2) required according to process, remove oversheath, the metallic sheath of two end cables, retain waterstop, here mistake Guarantee in journey that cable semi-conductive layer is not damaged;
2.1.3) will be clean for cable metal set removing surface, metallic sheath port is expanded into horn mouth with specific purpose tool, is used Horn mouth is processed rounding by file;
2.1.4) cable end is removed the part heating alignment of metallic sheath with heating coalignment;By wrapped for heating tape Outside waterstop, it is more than 6 hours 80 ± 5 DEG C of heat time heating times that heating-up temperature is, it is ensured that the cable after heating can reach alignment to be needed Will, after heating terminates, cable to be fixed with aluminum corner brace plate, allow cable to be cooled to ambient temperature, the time is no less than 8 hours;Alignment palintrope Curvature is per 400mm cable segment lengths≤2mm gaps.
2.2) exploitation of cable semi-conductive layer and cable surface are processed;
2.2.1 cable metal sheath incision position is retained the long waterstops of 15mm), remaining removal;
2.2.2) cable external shield is divested according to technological requirement size, process semi-conductive layer and insulating barrier;
2.2.3) cable insulation surface treatment:Successively with 400 mesh, 600 mesh, 1500 mesh sand paperings, make cable master exhausted Edge layer surface does not have cut and conductive particle, constantly at the uniform velocity moves in axial direction and peripheral direction in bruting process, it is to avoid in local Position long-time polishing forms insulating surface depression, persistently checks insulating surface quality with glare light electric torch, after polishing during polishing Size meet technological requirement, and keep clean with protecting film winding;
2.2.4) insulation screen process:Insulation screen fracture is vertical with cable axis, smooth, disconnected in insulation screen Mouth scrapes the groove of 70 ± 5mm, and is extremely seamlessly transitted with insulation with 400 mesh, 600 mesh, 1500 mesh sand paperings successively, this process It should be specifically noted that being unable to Damage to insulation, the sand paper of semi-conductive layer of polishing is without being used further to insulating barrier of polishing.
3) transition joint major insulation stress cone is installed:
3.1) parts suit and adapter body are installed;
3.1.1) the cable major insulation external diameter and adapter body stress cone internal diameter in orthogonal two direction are measured, outside cable major insulation Footpath is bigger by 20 ± 5% than adapter body stress cone internal diameter;
3.1.2) as requested heat-shrink tube, copper shell, sealing ring are sequentially sleeved on cable;
3.1.3 locating clip is installed at long end), main body stress cone inner surface is cleaned clean and is dried up with blowing hot wind, use Buddhist nun Imperial rod uniform application silicone oil, does interim protection with preservative film;Remove the preservative film on cable, be directed to head and be mounted in long end line core On, and the insulating surface at long end, Semiconducting surface are cleaned are dried up with heat gun, and one layer four is wound on semiconductive face Fluorothene band, is then uniformly coating multiple ester for filling, is smearing silicone oil for lubricating, be interim guarantor with preservative film Shield, then makes stress cone be inserted in long end by loading instrument, slowly divests preservative film during being inserted in, until cable length end Insulation is unloaded guide head and loads instrument after exposing 50mm.
3.2) connecting tube is crimped;
3.2.1) remove guide head, expose cable core, to straight two end cable;
3.2.2) connecting tube is put, after determining conductor thread core docking in place, selection pressure is touched and crimped with 75t pressure, is pressed The sharp edge burr cleaning that rubs with the hands in connecting tube with file after connecing is dried up, and this operation will guarantee to crimp centrally located.
3.3) radome is installed;
3.3.1 copper braid over braid and connecting tube, radome are connected by screw fastening first), two pieces of radomes is buckled in In connecting tube after through crimping, then interim fixation is done with PVC bands, remove PVC bands when main body pulls on radome;Copper braid over braid will Covered by radome completely, it is ensured that the round and smooth docking dislocation-free impulse- free robustness of radome;
3.3.2) make telltale mark:Length K of the adapter body stress cone being enclosed within cable is measured, from aluminium hydraulic pressed connecting pipe center K/2 is measured to cable short end direction and makees telltale mark;
3.3.3, after) drying up cable insulation, semi-conductive layer and radome surface cleaning, disposable glove is worn in cable Surface of insulating layer uniformly coats multiple ester and smears silicone oil;
3.3.4) according to step 3.1.3) adapter body is pulled to cable short end telltale mark position by method, long end wound Tetrafluoroethene band remove.
4) process of cable and joint external screen:
4.1) start to wind two-layer semi-conductive tape to adapter body two ends external shield end from cable two ends protective metal shell respectively Mouthful, 55mm is overlapped, two ends protective metal shell overlaps 50mm;
4.2) start overlap joint winding copper mesh to 50mm on other end protective metal shell, two ends copper from cable metal sheath one end Silk is tightened;
4.3) 6-8 layer insulating self-adhesive bands are wound outside copper mesh, wind one layer of PVC tape afterwards;
5) installation of copper shell:
5.1) sealing ring is loaded in the seal groove on copper housing flange, two ends copper shell is tightened together with bolt;
5.2) by copper shell encapsulating mouth upward, the space between copper shell tail end and protective metal shell is filled with fire-proof mud, to copper Shell two ends carry out encapsulation process with cable metal sheath;
5.2.1) frosting treatment is carried out in copper shell tail end and cable metal sheath sealing lead region with steel brush;
5.2.2) bottoming process is carried out to the sealing lead position of cable metal sheath with aluminum strip first, reusable lead bar is to copper shell tail End seal lead position carries out bottoming process;
5.2.3) sealing lead being carried out with leads, smearing uniform, compacting during sealing lead, length is not less than 120mm, and sealing lead process can not More than 30 minutes, it is to avoid scald cable.
5.3) afterbody is processed;
5.3.1) water blocking tape and fluid sealant are twined and cable cover(ing) between at the sealing lead of copper shell two ends, water blocking tape is at least overlapped The 150mm on cable jacket, by heat-shrink tube heat shrink, the wrapped fluid sealant of lap-joint, water blocking tape, waterproof at heat-shrink tube two ends Strengthen sealing with outer wrapped black PVC adhesive tape;
5.3.2) by one group of A, B high tension cable fluid sealant with volume 1:2 ratio is poured in agitator and is stirred, from copper Till shell encapsulating mouth is filled;
5.3.3 encapsulating mouth and copper housing flange are covered according to technological requirement), 3-4 layer water blocking tapes are wound;Covered with heat-shrinkable T bush Lid flange and encapsulating mouth, heat shrink wind 3-4 layer water blocking tapes at heat-shrink tube two-port, wind 2 layers of black outside water blocking tape PVC tape.
6) grounding:
Earth cable insulating stripping is removed, length is divested and is met technological requirement, the copper that bare exposed conductor inserts two bronze medal shells is connect Compressed in pipe, and earth cable is crimped place's good seal with copper connecting tube with band, heat-shrinkable T bush, passed through ground protection case Or grounding box is grounded.
It is compared with the prior art, the invention has the beneficial effects as follows:Patented technology specification of the present invention transition joint was installed Flow process and points for attention in journey, randomness when effectively avoiding transition joint from installing, so that improve 500kV cable systems peace Complete and stability.So as to realize that high tension cable (500kV cable systems) domesticizes, break International Power giant to field of cables Technical monopoly, reduce high tension cable price, seize extra-high-tension cable technology commanding elevation.
Description of the drawings
Fig. 1 be step 2.1.4 of the present invention) in heating alignment after flexibility requirement schematic diagram;
Fig. 2 be step 2.2 of the present invention) in cable semi-conductive layer exploitation and cable surface process schematic diagram;
Fig. 3 be step 3 of the present invention) in transition joint major insulation stress cone scheme of installation;
Fig. 4 is step 4 of the present invention) in cable and joint external screen process schematic diagram.
Reference is:The part 1 of cable end removal metallic sheath, protective metal shell 2, semi-conductive layer 3, insulating barrier 4, cable Long end 5, main body stress cone 6, radome 7, copper braid over braid 8, connecting tube 9, cable short end 10, telltale mark 11, adapter body 12, Copper mesh 13, insulating self-adhesive band 14.
Specific embodiment
With reference to embodiment, the invention will be further described.
Embodiment 1
A kind of 500kV cable systems transition joint mounting process, comprises the following steps:
1) construction condition confirms:
1.1) product standard and type is checked;
1.2) confirm that installation outfit is complete;
1.3) in-site installation purifies paulin and mobile air conditioner, it is ensured that, at 0-35 DEG C, air is relative for the temperature control of erecting bed Humidity≤70%;
2) prepare before installing:
2.1) cable two ends are in place, heat alignment pretreatment, remove mechanical stress;
2.1.1) two end cables to be installed are put, and long end, the short end direction of cable is determined according to field requirement;
2.1.2) required according to process, remove oversheath, the metallic sheath of two end cables, retain waterstop, here mistake Guarantee in journey that cable semi-conductive layer is not damaged;
2.1.3) will be clean for cable metal set removing surface, metallic sheath port is expanded into horn mouth with specific purpose tool, is used Horn mouth is processed rounding by file;
2.1.4 Fig. 1) is combined, alignment is heated in the part 1 that cable end removes metallic sheath with heating coalignment;To add The torrid zone is wrapped outside waterstop, and it is more than 6 hours 80 ± 5 DEG C of heat time heating times that heating-up temperature is, it is ensured that the cable energy after heating Alignment needs being reached, after heating terminates, cable being fixed with aluminum corner brace plate, allow cable to be cooled to ambient temperature, the time is little no less than 8 When;After alignment, flexibility is per 400mm cable segment lengths≤2mm gaps.
2.2) exploitation of cable semi-conductive layer and cable surface are processed;In conjunction with Fig. 2
2.2.1 2 incision position of cable metal sheath is retained the long waterstops of 15mm), remaining removal;
2.2.2) cable external shield is divested according to technological requirement size, process semi-conductive layer 3 and insulating barrier 4;
2.2.3) cable insulation surface treatment:Successively with 400 mesh, 600 mesh, 1500 mesh sand paperings, make cable master exhausted Edge layer surface does not have cut and conductive particle, constantly at the uniform velocity moves in axial direction and peripheral direction in bruting process, it is to avoid in local Position long-time polishing forms insulating surface depression, persistently checks insulating surface quality with glare light electric torch, after polishing during polishing Size meet technological requirement, and keep clean with protecting film winding;
2.2.4) insulation screen process:Insulation screen fracture is vertical with cable axis, smooth, disconnected in insulation screen Mouth scrapes the groove of 70 ± 5mm, and is extremely seamlessly transitted with insulation with 400 mesh, 600 mesh, 1500 mesh sand paperings successively, this process It should be specifically noted that being unable to Damage to insulation, the sand paper of semi-conductive layer of polishing is without being used further to insulating barrier of polishing.
3) transition joint major insulation stress cone is installed:In conjunction with Fig. 3
3.1) parts suit and adapter body are installed;
3.1.1) the cable major insulation external diameter and adapter body stress cone internal diameter in orthogonal two direction are measured, outside cable major insulation Footpath is bigger by 20 ± 5% than adapter body stress cone internal diameter;
3.1.2) as requested heat-shrink tube, copper shell, sealing ring are sequentially sleeved on cable;
3.1.3 locating clip is installed at cable length end 5), 6 inner surface of main body stress cone cleaning totally and is used hot blow wind Dry, with nylon rod uniform application silicone oil, interim protection is done with preservative film;Remove the preservative film on cable, be directed to head and be mounted in electricity On the long end line core of cable, and the insulating surface at cable length end, Semiconducting surface are cleaned are dried up with heat gun, and in semiconductive One layer of tetrafluoroethene band is wound on face, is then uniformly being coated multiple ester for filling, is being smeared silicone oil for lubricating, with guarantor Fresh film does interim protection, then makes stress cone be inserted in cable length end by loading instrument, slow by preservative film during being inserted in Divest, guide head is unloaded after 50mm is exposed in the insulation of cable length end and load instrument.
3.2) connecting tube is crimped;
3.2.1) remove guide head, expose cable core, to straight two end cable;
3.2.2) connecting tube 9 is put, and after determining conductor thread core docking in place, selection pressure is touched and crimped with 75t pressure, is pressed The sharp edge burr cleaning that rubs with the hands in connecting tube with file after connecing is dried up, and this operation will guarantee to crimp centrally located.
3.3) radome 7 is installed;
3.3.1 copper braid over braid 8 and connecting tube, radome are connected by screw fastening first), two pieces of radomes is buckled in In connecting tube after through crimping, then interim fixation is done with PVC bands, remove PVC bands when main body pulls on radome;Copper braid over braid will Covered by radome completely, it is ensured that the round and smooth docking dislocation-free impulse- free robustness of radome;
3.3.2) make telltale mark:Length K of the adapter body stress cone being enclosed within cable is measured, from aluminium hydraulic pressed connecting pipe center K/2 is measured to 10 direction of cable short end and makees telltale mark 11;
3.3.3, after) drying up cable insulation, semi-conductive layer and radome surface cleaning, disposable glove is worn in cable Surface of insulating layer uniformly coats multiple ester and smears silicone oil;
3.3.4) according to step 3.1.3) adapter body is pulled to cable short end telltale mark position by method, long end wound Tetrafluoroethene band remove.
4) process of cable and joint external screen:In conjunction with Fig. 4
4.1) start to wind two-layer semi-conductive tape to 12 two ends external shield of adapter body from cable two ends protective metal shell respectively Port, overlaps 55mm, and two ends protective metal shell overlaps 50mm;
4.2) start overlap joint winding copper mesh 13 to 50mm on other end protective metal shell from cable metal sheath one end, two ends are used Copper wire is tightened;
4.3) winding 6-8 layers insulating self-adhesive band 14 outside copper mesh, winds one layer of PVC tape afterwards;
5) installation of copper shell:
5.1) sealing ring is loaded in the seal groove on copper housing flange, two ends copper shell is tightened together with bolt;
5.2) by copper shell encapsulating mouth upward, the space between copper shell tail end and protective metal shell is filled with fire-proof mud, to copper Shell two ends carry out encapsulation process with cable metal sheath;
5.2.1) frosting treatment is carried out in copper shell tail end and cable metal sheath sealing lead region with steel brush;
5.2.2) bottoming process is carried out to the sealing lead position of cable metal sheath with aluminum strip first, reusable lead bar is to copper shell tail End seal lead position carries out bottoming process;
5.2.3) sealing lead being carried out with leads, smearing uniform, compacting during sealing lead, length is not less than 120mm, and sealing lead process can not More than 30 minutes, it is to avoid scald cable.
5.3) afterbody process;
5.3.1) water blocking tape and fluid sealant are twined and cable cover(ing) between at the sealing lead of copper shell two ends, water blocking tape is at least overlapped The 150mm on cable jacket, by heat-shrink tube heat shrink, the wrapped fluid sealant of lap-joint, water blocking tape, waterproof at heat-shrink tube two ends Strengthen sealing with outer wrapped black PVC adhesive tape;
5.3.2) by one group of A, B high tension cable fluid sealant with volume 1:2 ratio is poured in agitator and is stirred, from copper Till shell encapsulating mouth is filled;
5.3.3 encapsulating mouth and copper housing flange are covered according to technological requirement), 3-4 layer water blocking tapes are wound;Covered with heat-shrinkable T bush Lid flange and encapsulating mouth, heat shrink wind 3-4 layer water blocking tapes at heat-shrink tube two-port, wind 2 layers of black outside water blocking tape PVC tape.
6) grounding:
Earth cable insulating stripping is removed, length is divested and is met technological requirement, the copper that bare exposed conductor inserts two bronze medal shells is connect Compressed in pipe, and earth cable is crimped place's good seal with copper connecting tube with band, heat-shrinkable T bush, passed through ground protection case Or grounding box is grounded.
Raw materials used in the present invention, equipment, unless otherwise noted, is conventional raw material, the equipment of this area;In the present invention Method therefor, unless otherwise noted, is the conventional method of this area.
The above, is only presently preferred embodiments of the present invention, not the present invention is imposed any restrictions, every according to the present invention Any simple modification, change and equivalent transformation that technical spirit is made to above example, still fall within the technology of the present invention side The protection domain of case.

Claims (8)

1. a kind of 500kV cable systems transition joint mounting process, it is characterised in that:Comprise the following steps:
1) construction condition confirms:
1.1) product standard and type is checked;
1.2) confirm that installation outfit is complete;
1.3) in-site installation purifies paulin and mobile air conditioner, it is ensured that the temperature control of erecting bed at 0-35 DEG C, relative air humidity ≤ 70%;
2) prepare before installing:
2.1) cable two ends are in place, heat alignment pretreatment, remove mechanical stress;
2.2) exploitation of cable semi-conductive layer and cable surface are processed;
3) transition joint major insulation stress cone is installed:
3.1) parts suit and adapter body are installed;
3.2) connecting tube is crimped;
3.3) radome is installed;
4) process of cable and joint external screen:
4.1) start to wind two-layer semi-conductive tape to adapter body two ends external shield port from cable two ends protective metal shell respectively, take 55mm is met, two ends protective metal shell overlaps 50mm;
4.2) start overlap joint winding copper mesh to 50mm on other end protective metal shell from cable metal sheath one end, two ends are pricked with copper wire Tightly;
4.3) 6-8 layer insulating self-adhesive bands are wound outside copper mesh, wind one layer of PVC tape afterwards;
5) installation of copper shell:
5.1) sealing ring is loaded in the seal groove on copper housing flange, two ends copper shell is tightened together with bolt;
5.2) by copper shell encapsulating mouth upward, the space between copper shell tail end and protective metal shell is filled with fire-proof mud, to copper shell Two ends carry out encapsulation process with cable metal sheath;
5.3) afterbody is processed;
6) grounding:
Earth cable insulating stripping is removed, length is divested and is met technological requirement, bare exposed conductor is inserted in the copper connecting tube of two bronze medal shells Compressed, and earth cable is crimped place's good seal with copper connecting tube with band, heat-shrinkable T bush, passed through ground protection case or connecing Ground case is grounded.
2. a kind of 500kV cable systems transition joint mounting process as claimed in claim 1, it is characterised in that step 2.1) Specifically include:
2.1.1) two end cables to be installed are put, and long end, the short end direction of cable is determined according to field requirement;
2.1.2) required according to process, remove oversheath, the metallic sheath of two end cables, retain waterstop, in the process Guarantee that cable semi-conductive layer is not damaged;
2.1.3) will be clean for cable metal set removing surface, metallic sheath port is expanded into horn mouth with specific purpose tool, file is used Horn mouth is processed rounding;
2.1.4) cable end is removed the part heating alignment of metallic sheath with heating coalignment;Blocking water wrapped for heating tape Band outside, it is more than 6 hours 80 ± 5 DEG C of heat time heating times that heating-up temperature is, it is ensured that the cable after heating can reach alignment needs, plus After accumulation of heat beam, cable being fixed with aluminum corner brace plate, allowing cable to be cooled to ambient temperature, the time is no less than 8 hours;After alignment, flexibility is every 400mm cables segment length≤2mm gaps.
3. a kind of 500kV cable systems transition joint mounting process as claimed in claim 1 or 2, it is characterised in that step 2.2) specifically include:
2.2.1 cable metal sheath incision position is retained the long waterstops of 15mm), remaining removal;
2.2.2) cable external shield is divested according to technological requirement size, process semi-conductive layer and insulating barrier;
2.2.3) cable insulation surface treatment:Successively with 400 mesh, 600 mesh, 1500 mesh sand paperings, cable main insulating layer is made Surface does not have cut and conductive particle, constantly at the uniform velocity moves in axial direction and peripheral direction, it is to avoid in local location in bruting process Long-time polishing forms insulating surface depression, persistently checks insulating surface quality, the chi after polishing with glare light electric torch during polishing Very little meet technological requirement, and keep clean with protecting film winding;
2.2.4) insulation screen process:Insulation screen fracture is vertical with cable axis, smooth, scrapes in insulation screen fracture Go out the groove of 70 ± 5mm, and extremely seamlessly transitted with insulation with 400 mesh, 600 mesh, 1500 mesh sand paperings successively, this process Ying Te Damage to insulation Zhu Yi be unable to, the sand paper of semi-conductive layer of polishing is without being used further to insulating barrier of polishing.
4. a kind of 500kV cable systems transition joint mounting process as claimed in claim 1, it is characterised in that step 3.1) Specifically include:
3.1.1) the cable major insulation external diameter and adapter body stress cone internal diameter in orthogonal two direction, cable major insulation external diameter ratio are measured Adapter body stress cone internal diameter big 20 ± 5%;
3.1.2) as requested heat-shrink tube, copper shell, sealing ring are sequentially sleeved on cable;
3.1.3 locating clip is installed at long end), main body stress cone inner surface is cleaned clean and is dried up with blowing hot wind, use nylon rod Uniform application silicone oil, does interim protection with preservative film;Remove the preservative film on cable, be directed to head and be mounted in the long end line core of cable On, and the insulating surface at cable length end, Semiconducting surface are cleaned are dried up with heat gun, and one is wound on semiconductive face Layer tetrafluoroethene band, is then uniformly coating multiple ester for filling, is smearing silicone oil for lubricating, make of preservative film temporarily Protection, then makes stress cone be inserted in cable length end by loading instrument, slowly divests preservative film, Zhi Dao electricity during being inserted in The insulation of cable length end is unloaded guide head after exposing 50mm and loads instrument.
5. a kind of 500kV cable systems transition joint mounting process as described in claim 1 or 4, it is characterised in that step 3.2) specifically include:
3.2.1) remove guide head, expose cable core, to straight two end cable;
3.2.2) connecting tube is put, after determining conductor thread core docking in place, selection pressure is touched and crimped with 75t pressure, after crimping The sharp edge burr cleaning that rubs with the hands in connecting tube with file is dried up, and this operation will guarantee to crimp centrally located.
6. a kind of 500kV cable systems transition joint mounting process as claimed in claim 4, it is characterised in that step 3.3) Specifically include:
3.3.1 copper braid over braid and connecting tube, radome are connected by screw fastening first), two pieces of radomes are buckled in and have been pressed In connecting tube after connecing, then interim fixation is done with PVC bands, remove PVC bands when main body pulls on radome;Copper braid over braid will be completely Covered by radome, it is ensured that the round and smooth docking dislocation-free impulse- free robustness of radome;
3.3.2) make telltale mark:Length K of the adapter body stress cone being enclosed within cable is measured, from aluminium hydraulic pressed connecting pipe center to electricity Cable short end direction measures K/2 and makees telltale mark;
3.3.3, after) drying up cable insulation, semi-conductive layer and radome surface cleaning, disposable glove is worn in cable insulation Layer surface uniformly coats multiple ester and smears silicone oil;
3.3.4) according to step 3.1.3) adapter body is pulled to cable short end telltale mark position by method, four that long end is wound Fluorothene band removes.
7. a kind of 500kV cable systems transition joint mounting process as claimed in claim 1, it is characterised in that step 5.2) Specifically include:
5.2.1) frosting treatment is carried out in copper shell tail end and cable metal sheath sealing lead region with steel brush;
5.2.2) bottoming process is first carried out to the sealing lead position of cable metal sheath with aluminum strip, and reusable lead bar is sealed to copper shell tail end Lead position carries out bottoming process;
5.2.3) sealing lead being carried out with leads, smearing uniform, compacting during sealing lead, length is not less than 120mm, and sealing lead process is no more than 30 minutes, it is to avoid scald cable.
8. a kind of 500kV cable systems transition joint mounting process as described in claim 1 or 7, it is characterised in that step 5.3) specifically include:
5.3.1) water blocking tape and fluid sealant are twined and cable cover(ing) between at the sealing lead of copper shell two ends, water blocking tape at least snaps into electricity 150mm on cable oversheath, by heat-shrink tube heat shrink, the wrapped fluid sealant of lap-joint, water blocking tape at heat-shrink tube two ends, outside water blocking tape Sealing strengthened by wrapped black PVC adhesive tape;
5.3.2) by one group of A, B high tension cable fluid sealant with volume 1:2 ratio is poured in agitator and is stirred, from copper shell Till encapsulating mouth is filled;
5.3.3 encapsulating mouth and copper housing flange are covered according to technological requirement), 3-4 layer water blocking tapes are wound;Use heat-shrinkable T bush cladding process Blue and encapsulating mouth, heat shrink wind 3-4 layer water blocking tapes at heat-shrink tube two-port, wind 2 layers of black PVC glue outside water blocking tape Band.
CN201610993023.6A 2016-11-11 2016-11-11 A kind of 500kV cable systems transition joint mounting process Pending CN106505509A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610993023.6A CN106505509A (en) 2016-11-11 2016-11-11 A kind of 500kV cable systems transition joint mounting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610993023.6A CN106505509A (en) 2016-11-11 2016-11-11 A kind of 500kV cable systems transition joint mounting process

Publications (1)

Publication Number Publication Date
CN106505509A true CN106505509A (en) 2017-03-15

Family

ID=58324024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610993023.6A Pending CN106505509A (en) 2016-11-11 2016-11-11 A kind of 500kV cable systems transition joint mounting process

Country Status (1)

Country Link
CN (1) CN106505509A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107658834A (en) * 2017-09-29 2018-02-02 常州安凯特电缆有限公司 A kind of combination presetting system transition joint of high-tension cable and its installation method
CN108134343A (en) * 2017-12-22 2018-06-08 宁波东方电缆股份有限公司 A kind of emergency repair method of three-core cable
CN108199334A (en) * 2017-12-20 2018-06-22 国网北京市电力公司 CA cable assembly
CN109167327A (en) * 2018-08-29 2019-01-08 天津科博电缆科技发展有限公司 A kind of welding machine Special integrated cable and its manufacturing method
CN109301768A (en) * 2018-10-27 2019-02-01 中国海洋石油集团有限公司 A kind of emergency repair method of seabed three-core cable
CN109962442A (en) * 2019-03-21 2019-07-02 上海三原电缆附件有限公司 A kind of sealing structure of plastic-aluminum combined sheath high-voltage cable joint
CN109167327B (en) * 2018-08-29 2024-06-04 天津科博电缆科技发展有限公司 Special integrated cable for welding machine and manufacturing method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1667897A (en) * 2005-02-18 2005-09-14 夏云杰 On-site crosslinked polyethylene cable joint welding technique
WO2012083984A1 (en) * 2010-12-22 2012-06-28 Prysmian S.P.A. Jointing assembly for electrical cables
CN102664380A (en) * 2012-04-19 2012-09-12 中天科技海缆有限公司 Flexible joint for 220kV crosslinked polyethylene submarine cables and method for manufacturing flexible joint
CN103259240A (en) * 2013-05-13 2013-08-21 哈尔滨理工大学 Stress control body for plastic insulation high-voltage and direct-current cable connector
CN103972825A (en) * 2014-05-15 2014-08-06 国家电网公司 Method for manufacturing wrapped type intermediate joint
CN104967066A (en) * 2015-06-11 2015-10-07 天津送变电工程公司 Crosslinked cable prefabricated intermediate joint installation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1667897A (en) * 2005-02-18 2005-09-14 夏云杰 On-site crosslinked polyethylene cable joint welding technique
WO2012083984A1 (en) * 2010-12-22 2012-06-28 Prysmian S.P.A. Jointing assembly for electrical cables
CN102664380A (en) * 2012-04-19 2012-09-12 中天科技海缆有限公司 Flexible joint for 220kV crosslinked polyethylene submarine cables and method for manufacturing flexible joint
CN103259240A (en) * 2013-05-13 2013-08-21 哈尔滨理工大学 Stress control body for plastic insulation high-voltage and direct-current cable connector
CN103972825A (en) * 2014-05-15 2014-08-06 国家电网公司 Method for manufacturing wrapped type intermediate joint
CN104967066A (en) * 2015-06-11 2015-10-07 天津送变电工程公司 Crosslinked cable prefabricated intermediate joint installation method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107658834A (en) * 2017-09-29 2018-02-02 常州安凯特电缆有限公司 A kind of combination presetting system transition joint of high-tension cable and its installation method
CN108199334A (en) * 2017-12-20 2018-06-22 国网北京市电力公司 CA cable assembly
CN108134343A (en) * 2017-12-22 2018-06-08 宁波东方电缆股份有限公司 A kind of emergency repair method of three-core cable
CN109167327A (en) * 2018-08-29 2019-01-08 天津科博电缆科技发展有限公司 A kind of welding machine Special integrated cable and its manufacturing method
CN109167327B (en) * 2018-08-29 2024-06-04 天津科博电缆科技发展有限公司 Special integrated cable for welding machine and manufacturing method thereof
CN109301768A (en) * 2018-10-27 2019-02-01 中国海洋石油集团有限公司 A kind of emergency repair method of seabed three-core cable
CN109962442A (en) * 2019-03-21 2019-07-02 上海三原电缆附件有限公司 A kind of sealing structure of plastic-aluminum combined sheath high-voltage cable joint

Similar Documents

Publication Publication Date Title
CN106505509A (en) A kind of 500kV cable systems transition joint mounting process
CN103178482B (en) A kind of cable is around packet mode joint and preparation method thereof
CN103972825A (en) Method for manufacturing wrapped type intermediate joint
CN207426656U (en) A kind of high-voltage cable middle joint
CN107294014A (en) A kind of low-voltage cable joint prosthetic device and low-voltage cable joint restorative procedure
CN108683149A (en) A kind of crosslinked cable hot melting connector and preparation method thereof
CN101252266A (en) Mounting process of three-core cable shrink terminal
KR20120057823A (en) Electrical power cable formed nylon sheath
CN105185482A (en) Manufacturing method of cable having waterproof outer sheath structure
CN108471092A (en) The single-phase dry packet restorative procedure of high-tension cable
CN101800093B (en) Externally-sleeved insulated sleeve
CN208190228U (en) A kind of crosslinked cable hot melting connector
CN116093845A (en) Cable outdoor terminal installation process
CN114227162B (en) Hot melting connection process for 25 type passenger car box body and pipeline heat tracing band
CN206992665U (en) A kind of cable accessory
CN206922409U (en) The buried separable connector of silicon rubber
CN107196242A (en) 110kV cross-linked power cable insulation transition joint manufacture crafts
RU2190913C1 (en) Junction box for power cable covered with cross- linked polyethylene and method for box installation and wiring
CN210517718U (en) Be suitable for overhead conductor lag tube 10kV and below
CN114360764A (en) Manufacturing method of high-pressure submarine cable factory joint
CN110379541A (en) A kind of manufacturing process of fusing type cable connector
CN109378775B (en) Optimized manufacturing method for sealing and water-blocking of cable cold-shrinkage type joint
CN209844528U (en) Joint structure suitable for 35kV and following well low voltage cable
CN106340850A (en) Cable intermediate joint with high waterproof performance, and installation method thereof
CN219626899U (en) Waterproof joint for aluminum wire shielding aluminum core cable

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170315