CN106500112B - Incinerator charging gear - Google Patents

Incinerator charging gear Download PDF

Info

Publication number
CN106500112B
CN106500112B CN201611213828.0A CN201611213828A CN106500112B CN 106500112 B CN106500112 B CN 106500112B CN 201611213828 A CN201611213828 A CN 201611213828A CN 106500112 B CN106500112 B CN 106500112B
Authority
CN
China
Prior art keywords
guide channel
material guide
rubbish
incinerator
collecting tray
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611213828.0A
Other languages
Chinese (zh)
Other versions
CN106500112A (en
Inventor
于公满
张武军
赵方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Hong Chau Xingye Environmental Protection Technology Co Ltd
Original Assignee
Beijing Hong Chau Xingye Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Hong Chau Xingye Environmental Protection Technology Co Ltd filed Critical Beijing Hong Chau Xingye Environmental Protection Technology Co Ltd
Priority to CN201611213828.0A priority Critical patent/CN106500112B/en
Publication of CN106500112A publication Critical patent/CN106500112A/en
Application granted granted Critical
Publication of CN106500112B publication Critical patent/CN106500112B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/44Details; Accessories
    • F23G5/442Waste feed arrangements
    • F23G5/444Waste feed arrangements for solid waste
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/02Incineration of waste; Incinerator constructions; Details, accessories or control therefor with pretreatment
    • F23G5/04Incineration of waste; Incinerator constructions; Details, accessories or control therefor with pretreatment drying
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2201/00Pretreatment
    • F23G2201/20Dewatering by mechanical means
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2205/00Waste feed arrangements
    • F23G2205/10Waste feed arrangements using ram or pusher

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The present invention provides incinerator charging gears, are related to incinerator technical field, and incinerator charging gear includes material guide channel, and the output end of material guide channel is communicated with the feed inlet of incinerator;Draining collecting tray is set in the material guide channel along the length direction of material guide channel, and the material guide channel is equipped with several drainage holes being connected with the draining collecting tray;Material-pulling device acts on the input terminal of material guide channel, and one end of material-pulling device is arranged in material guide channel.The present invention is during material guide channel conveying garbage is to incinerator, by the partial moisture in rubbish by squeezing discharge, reduce the water content of rubbish itself, the burning for being rubbish in incinerator creates good condition, present apparatus structure is simple simultaneously, manufacturing cost is low, can cooperate with all incinerators, suitable for promoting the use of a large area.

Description

Incinerator charging gear
Technical field
The present invention relates to incinerator design fields, more particularly, to a kind of incinerator charging gear.
Background technique
It is also stepped up with the improvement of people's living standards, the production quantity of domestic waste with the development of the city, city City's house refuse has become the public hazards of many big and medium-sized cities, therefore the further development for constraining city solves garbage-surrounded city Problem has been put in face of many city managers.In the method for all multiprocessing domestic wastes, waste incineration remove the evil, Minimizing and energy recovery etc. all have apparent advantage compared with other processing modes, and therefore, waste incineration has become The prefered method of domestic waste pollution problem is solved for the big and medium-sized cities of modernization.
In order to ensure municipal refuse in incinerator normal combustion, need to meet enough Lower heat value, and component of refuse In water content will affect Lower heat value, it is therefore desirable to control the moisture content into furnace rubbish, house refuse before burning all Need to carry out a degree of draining process, in order to reduce the moisture content in rubbish, it is common practice to ferment certainly using stockpiling and storing The method of right draining, i.e., stack rubbish 5~7 days, the organic matter in rubbish is more, since organic matter will do it hair in warehouse Ferment so that organic matter in garbage it is interior it is aqueous become outside water, the outside water of generation can lean on the gravity of moisture itself to leach, still Always some can not be leached.
Existing incinerator charging gear is for can not achieve drain function to incinerator conveying garbage, therefore, Remaining moisture can be transported in incinerator in rubbish, influence burning effect.
Summary of the invention
The purpose of the present invention is to provide a kind of incinerator charging gears, to solve problems of the prior art.
A kind of incinerator charging gear provided by the invention, comprising:
Material guide channel, the output end of the material guide channel are communicated with the feed inlet of incinerator;
Draining collecting tray, the draining collecting tray are set in the material guide channel along the length direction of the material guide channel On, the material guide channel is equipped with several drainage holes being connected with the draining collecting tray, and the draining collecting tray is equipped with Water outlet for draining;
The input terminal of the material guide channel is arranged in material-pulling device, the material-pulling device, can will enter the guide and lead to Rubbish in road pushes delivery outlet to from the input port of the material guide channel.
Further, circumference uniform distribution is equipped with several drainings being connected with the draining collecting tray in the material guide channel Hole.
It further, further include that the output end of the material guide channel is set and is formed during pusher for controlling The single or double acting door of rubbish internal pressure size.
Further, the single or double acting door includes being rotatably arranged on the output end of the material guide channel and stopping rubbish row Into door-plate, be provided with for providing the spring of elastic pressure on the free end of the door-plate.
Further, the door-plate is arranged on the output end of the material guide channel by rotation axis, and the rotation Axis is vertical with the direction of travel of rubbish.
Further, the rotation axis is arranged in the upper end wall of the material guide channel.
Further, the material-pulling device uses piston structure, and the piston structure is equipped with an annular notch, described Annular notch and the piston structure are coaxially disposed, and the middle section position of the piston structure and close is arranged in the annular notch The draining collecting tray.
Further, the output end of the material guide channel uses conical pipeline, and the input terminal of the material guide channel Cross-sectional area is greater than the cross-sectional area of the output end of the material guide channel.
The present invention provides a kind of incinerator charging gears, will during material guide channel conveying garbage is to incinerator Partial moisture in rubbish reduces the water content of rubbish itself, is burning wound of the rubbish in incinerator by squeezing discharge Good condition is made, while present apparatus structure is simple, manufacturing cost is low, can be used cooperatively, be suitable for all incinerators It promotes the use of a large area.
Detailed description of the invention
In order to illustrate more clearly of the technical solution in the specific embodiment of the invention, specific embodiment will be retouched below Attached drawing needed in stating is briefly described, it should be apparent that, the accompanying drawings in the following description is some realities of the invention Mode is applied, it for those of ordinary skill in the art, without creative efforts, can also be attached according to these Figure obtains other attached drawings.
Fig. 1 is the incinerator charging gear schematic diagram that the embodiment of the present invention 1 provides;
Material-pulling device promotes the schematic diagram of a period of time in the incinerator charging gear that Fig. 2 provides for the embodiment of the present invention 1;
Fig. 3 is the incinerator charging gear schematic diagram that the embodiment of the present invention 2 provides.
Icon: 1- material guide channel;2- draining collecting tray;3- material-pulling device;4- door-plate;5- spring;6- annular lacks Mouthful.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " connected " " connects Connect " it shall be understood in a broad sense, for example, it may be being fixedly connected, it may be a detachable connection, or be integrally connected;It can be machine Tool connection, is also possible to be electrically connected;It can be directly connected, two members can also be can be indirectly connected through an intermediary Connection inside part.For the ordinary skill in the art, above-mentioned term can be understood in the present invention with concrete condition Concrete meaning.
According to Fig. 1 to Fig. 3, incinerator charging gear provided by the invention, including material guide channel 1, draining collecting tray 2 With material-pulling device 3.
The output end of material guide channel 1 is communicated with the feed inlet of incinerator;Material guide channel is for giving incinerator conveying garbage, rubbish After rubbish enters material guide channel, under the promotion of material-pulling device, the feed inlet of incinerator is transported to by output end, finally convey into Enter incinerator to be burned.
Draining collecting tray 2 is set in material guide channel 1 along the length direction of material guide channel 1, is laid in material guide channel 1 Several drainage holes being connected with draining collecting tray 3, the draining collecting tray are equipped with the water outlet for draining;Material guide channel On be arranged with draining collecting tray, the drainage hole on the conduit wall of the material guide channel in draining collecting tray package range is for being discharged rubbish The moisture that rubbish squeezes in transmission process in material guide channel, moisture flow into draining collecting tray from drainage hole, effectively realization rubbish Draining, reduce the water content of rubbish itself, the moisture flowed into draining collecting tray passes through water outlet realization draining collecting tray Draining, guarantee that moisture will not accumulate spill-over in draining collecting tray and go out, to guarantee the normal work of draining collecting tray and continue It uses.
The setting of drainage hole can be in the following way in this programme.
Circumference uniform distribution is equipped with several drainage holes being connected with draining collecting tray in material guide channel, that is to say, that draining confluence Slot is set in material guide channel, and draining collecting tray is arranged on the conduit wall of the material guide channel in the range of package along material guide channel Length direction on circumference be equipped with several drainage holes, in this case, push squeeze during, extra moisture can be from each A orientation is overflowed, and is flowed into draining collecting tray under gravity, and structure is simple and easy to implement, and drainage efficiency is high.
Material-pulling device 3 acts on the input terminal of material guide channel 1, and one end of material-pulling device 3 is arranged in material guide channel 1. The front end face of material-pulling device is located at the input terminal of material guide channel, and there are the space that rubbish enters, rubbish enters for the front of front end face After material guide channel, by applying thrust to rubbish, the push to rubbish can be effectively realized, simultaneously as in conveying garbage During, it is to be carried out by pushing material-pulling device, the thrust that driving means acts on rubbish can make rubbish generate internal pressure Power, and then the effect of rubbish draining can be generated.
In the present apparatus, rubbish is pushed by material-pulling device, so that rubbish is generated interior pressure using thrust, realizes rubbish draining Effect, later, further through the drainage hole in material guide channel by the water effective leached in rubbish be discharged, finally flow into draining remittance In chute, the draining purpose of rubbish is realized.
Material-pulling device uses following implementation in this programme, and specific embodiment is as follows.
According to Fig. 1 to Fig. 3, material-pulling device uses piston structure, is provided with annular notch 6 on piston structure, annular Notch 6 and piston structure are coaxially disposed, and annular notch 6 is arranged in the middle section position of piston structure and close to draining collecting tray.? In the present embodiment, material-pulling device is formed with the piston structure of annular notch using centre, to form the cross section at intermediate position Product is less than the configuration state of the cross-sectional area at both ends, that is to say, that is formed in the middle section of material-pulling device a part of hollow Space, this segment space form certain spatial cache, can will be extra in rubbish during material-pulling device pushes rubbish Moisture squeezes out, be possible to if moisture is more can by the gap between material guide channel and material-pulling device to exosmosis, Not only it be easy to cause pollution also unhygienic, still, the structure design in the present embodiment forms certain spatial cache, even if past Exosmosis when reaching annular notch i.e. when spatial cache, would not be further continued for toward excessive, if spatial cache is not full of Too big pressure would not be formed, during push, moisture will be directly discharged into draining collecting tray by drainage hole, avoid Moisture overflows the case where material-pulling device in extrusion process.
Embodiment one
The effect that generates between thrust when relying solely on the resistance that material guide channel generates rubbish and push rubbish makes If rubbish generates interior pressure, interior pressure is smaller, and the moisture contained in organic matter in rubbish can not also drain, and also can not just obtain To optimal draining effect.
To solve the above problems, using following proposal in the present invention.
According to Fig.3, the output end of material guide channel uses conical pipeline, and the cross-sectional area of the input terminal of material guide channel Greater than the cross-sectional area of the output end of material guide channel.
The conical design of material guide channel, during extruding, bore constantly reduces, and the resistance that rubbish is advanced will become Greatly, under the action of material-pulling device, the internal pressure generated in rubbish can be made to increase, to improve the draining effect of rubbish.
Embodiment two
Different rubbish, what is needed needs different interior pressure to carry out draining, the sectional dimension and charging of material guide channel Mouthful the interior pressure that generates when all can influence conveying garbage of bore, but plant bulk is changed it is very not convenient, and More cost of idleness uses under type such as in order to handle different rubbish, in the present invention and solves.
According to Fig. 1 to Fig. 2, the present apparatus further includes the output end of material guide channel being arranged in and for controlling pusher mistake The rubbish internal pressure size single or double acting door formed in journey.In the present apparatus, change rubbish propelling resistance using single or double acting door, it can Cooperate with material-pulling device, allows rubbish to generate different internal pressures, and then meet different types of rubbish demand.
In the present solution, single or double acting door includes the door-plate for being rotatably arranged on the output end of material guide channel and rubbish being stopped to be advanced 4, it is provided with for providing the spring 5 of elastic pressure on the free end of door-plate.In the present solution, door-plate is led by being rotatably arranged on Material channel output end may be implemented to rotate, naturally it is also possible to needed to be arranged to other angles according to conveying, rubbish not yet When reaching the output end of material guide channel, the direct vertical barrier of door-plate lives the output end of material guide channel, plays temporarily to block and lead The effect for expecting channel, after rubbish reaches at door-plate, material-pulling device pushes rubbish to offset with single or double acting door, when rubbish is to single or double acting door When thrust is greater than initial elastic force, that is, pretightning force of single or double acting door, single or double acting door is opened, and completes the conveying of rubbish.
The initial elastic force of single or double acting door can be adjusted according to different rubbish, so that when handling different rubbish, Optimal draining effect can be reached.
During rubbish conveying, before the pressure that rubbish is born does not reach the pretightning force of spring, rubbish is in one In a closed space, since material-pulling device gives rubbish one thrust at rear, rubbish is in compressed process at this time, is formed The interior pressure of rubbish, so that whole volume can reduce, and rubbish can be such that the moisture in it is forced out under the action of interior pressure, Achieve the effect that draining;When the pressure that rubbish is born reaches initial tension of spring, rubbish integrally starts to move, at this point, leading portion Resistance be greater than back segment resistance, when the thrust of material-pulling device be greater than single or double acting door generate resistance when, single or double acting door is opened, rubbish into Enter incinerator burning.
The setting requirements of the initial elastic force of single or double acting door be the moisture in rubbish can be drained as far as possible it is net, that is, Say, when in rubbish there are also moisture or moisture is more burning standard is not achieved when, single or double acting door should not be opened, if bullet at this time Spring door opens, then just illustrating that the initial elastic force of single or double acting door is inadequate, needs to be adjusted.That is, the pressure of single or double acting door It needs to be adjusted according to the water content of rubbish.
Rotation axis is arranged in the upper end wall of material guide channel.In the present solution, the upper of material guide channel is arranged in rotation axis On end wall, structure is simple and setting is convenient, satisfies the use demand, naturally it is also possible to be arranged in other angles and positions, only Meet squeezing action, herein with no restrictions.
The setting of single or double acting door can be changed the interior pressure of rubbish generation by the elastic force of spring, and then be adapted to not of the same race The demand of class rubbish.
In the present solution, using spring as elastic barrier power, naturally it is also possible to use other elastic materials, not do herein It limits.
The water outlet of draining collecting tray 2 can be set funnel or be arranged to other convenient for the shape of circulation.At this In scheme, funnel is arranged in the water outlet of draining collecting tray, and moisture can be made to collect in time after flowing into draining collecting tray In lower end, to be discharged or smoothly be drained conducive to the drainage hole of upper end in time.
The water outlet of draining collecting tray 2 is equipped with valve, can also be not provided with valve.The water outlet of draining collecting tray is provided with If valve, the moisture of storage can be discharged by opening valve when the moisture in draining collecting tray is that will be filled with Go working in order to draining collecting tray.
The water outlet of draining collecting tray 2 can also be connected to wastewater disposal basin by pipeline.In the present solution, draining collecting tray Water outlet is connected to wastewater disposal basin by pipeline, and the moisture that can be thus discharged into draining collecting tray is directly arranged by pipeline It out without being stored in draining collecting tray, avoids the occurrence of and has stored up full water in draining collecting tray, material-pulling device also exists Continue conveying garbage, to influence the conveying effect of whole device.
A kind of incinerator charging gear provided by the invention will during material guide channel conveying garbage is to incinerator Partial moisture in rubbish reduces the water content of rubbish itself, is burning wound of the rubbish in incinerator by squeezing discharge Good condition has been made, while realizing feed draining function, has also acted the effect in sealed material guide channel, while the present apparatus Structure is simple, and manufacturing cost is low, suitable for promoting the use of a large area.
The present apparatus can further remove the moisture in rubbish during charging, while can be according to the moisture of removing Judge the moisture content in rubbish, provides reference for the control of burning;The present apparatus can not change original process flow, not change Become the type of furnace, do not change the device configuration of system, do not change in furnace and used in the case where Combustion System, by the setting for assisting draining Improve the reliability of operational process;The present apparatus is arranged between feed hopper and incinerator, it can be ensured that the leakproofness of burner hearth, in addition By squeezing by external force rubbish, the dynamics of draining is increased, there is a possibility that reducing garbage storing holding capacity of bin.By leading The conical design for expecting channel can increase the resistance generated when rubbish push, and then increase the interior pressure that rubbish generates, further Improve the effect that draining is carried out to rubbish;By the way that single or double acting door is arranged in the end of material guide channel, can easily adjust All kinds of rubbish are had good adaptability by required interior pressure when to rubbish progress draining.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (6)

1. a kind of incinerator charging gear characterized by comprising
Material guide channel, the output end of the material guide channel are communicated with the feed inlet of incinerator;
It further include that the output end of the material guide channel is set and for controlling the rubbish internal pressure size formed during pusher Single or double acting door;
Draining collecting tray, the draining collecting tray are set in the material guide channel along the length direction of the material guide channel, institute Material guide channel is stated equipped with several drainage holes being connected with the draining collecting tray, the draining collecting tray is equipped with for arranging The water outlet of water;Circumference uniform distribution is equipped with several drainage holes being connected with the draining collecting tray in the material guide channel;
The input terminal of the material guide channel is arranged in material-pulling device, the material-pulling device, can will enter in the material guide channel Rubbish push delivery outlet to from the input port of the material guide channel.
2. incinerator charging gear according to claim 1, which is characterized in that the single or double acting door includes being rotatably arranged on institute It states the output end of material guide channel and stops the door-plate of rubbish traveling, be provided on the free end of the door-plate for providing elasticity The spring of pressure.
3. incinerator charging gear according to claim 2, which is characterized in that the door-plate is arranged by rotation axis in institute It states on the output end of material guide channel, and the rotation axis is vertical with the direction of travel of rubbish.
4. incinerator charging gear according to claim 2, which is characterized in that the rotation axis setting is logical in the guide In the upper end wall in road.
5. incinerator charging gear according to claim 1, which is characterized in that the material-pulling device uses piston structure, The piston structure is equipped with annular notch, and the annular notch and the piston structure are coaxially disposed, and the annular notch is set Set the middle section position in the piston structure and close to the draining collecting tray.
6. incinerator charging gear according to claim 1, which is characterized in that the output end of the material guide channel is using cone Shape pipeline, and the cross-sectional area of the input terminal of the material guide channel is greater than the cross-sectional area of the output end of the material guide channel.
CN201611213828.0A 2016-12-23 2016-12-23 Incinerator charging gear Active CN106500112B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611213828.0A CN106500112B (en) 2016-12-23 2016-12-23 Incinerator charging gear

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611213828.0A CN106500112B (en) 2016-12-23 2016-12-23 Incinerator charging gear

Publications (2)

Publication Number Publication Date
CN106500112A CN106500112A (en) 2017-03-15
CN106500112B true CN106500112B (en) 2019-04-19

Family

ID=58333794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611213828.0A Active CN106500112B (en) 2016-12-23 2016-12-23 Incinerator charging gear

Country Status (1)

Country Link
CN (1) CN106500112B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106940018A (en) * 2017-04-06 2017-07-11 桂林市宏远能源科技服务有限公司 The incinerator for the treatment of time can be shortened
CN109253455A (en) * 2017-07-12 2019-01-22 上海明华电力技术工程有限公司 A kind of house refuse feeding system
CN108006663A (en) * 2018-01-04 2018-05-08 利百川环保科技有限公司 A kind of feed arrangement and mode
CN111336524A (en) * 2020-03-06 2020-06-26 嵊州市星丰环保节能设备厂 Incineration integrated equipment based on heat-accumulating type recyclable waste gas treatment
CN112254135A (en) * 2020-10-13 2021-01-22 云南蓝恒环保科技有限公司 Novel air return type garbage pyrolysis furnace
CN113120479B (en) * 2021-04-21 2024-02-06 湖北专力汽车科技有限公司 Energy-saving environment-friendly municipal garbage truck

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2774630Y (en) * 2005-04-01 2006-04-26 包文婷 Powder material screw feeder for reactor
CN102631869A (en) * 2012-03-31 2012-08-15 赵旭荣 Organic solid waste spiral charge pump
CN204534597U (en) * 2015-04-01 2015-08-05 西华师范大学 A kind of changing food waste CIU
CN205679042U (en) * 2016-06-17 2016-11-09 山东一鸣工贸有限公司 Material automatic charging device
CN206280977U (en) * 2016-12-23 2017-06-27 北京鸿洲兴业环保科技有限公司 Incinerator charging gear

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2774630Y (en) * 2005-04-01 2006-04-26 包文婷 Powder material screw feeder for reactor
CN102631869A (en) * 2012-03-31 2012-08-15 赵旭荣 Organic solid waste spiral charge pump
CN204534597U (en) * 2015-04-01 2015-08-05 西华师范大学 A kind of changing food waste CIU
CN205679042U (en) * 2016-06-17 2016-11-09 山东一鸣工贸有限公司 Material automatic charging device
CN206280977U (en) * 2016-12-23 2017-06-27 北京鸿洲兴业环保科技有限公司 Incinerator charging gear

Also Published As

Publication number Publication date
CN106500112A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN106500112B (en) Incinerator charging gear
CN103600950B (en) The compression system of garbage transfer station
CN108758637B (en) A kind of rubbish solid-liquid separation pyrolyzing device of easy to clean
CN204869735U (en) High -efficient rubbish wringing machine
CN209225909U (en) A kind of urban waste disposal equipment
CN204054720U (en) Suction-type sewer scavenger spiral separating device
CN109605800A (en) A kind of feeding garbage squeezes broken machine
CN202764243U (en) Solid-liquid separating equipment for dinning room and kitchen waste
CN206280977U (en) Incinerator charging gear
CN103754531A (en) Waste-compressing garbage can
CN201154324Y (en) Wet-type automatic sorting device for organic refuse
CN203823771U (en) Feeding airlock working together with dry-process rotary kiln to treat domestic wastes and sludge
CN205949458U (en) Garbage treatment device
CN102220232B (en) Mechanical material discharge acidification anaerobic tank
CN208377958U (en) A kind of conveying device of sorting rubbish efficient transportation
CN209649543U (en) A kind of feeding garbage squeezes broken machine
CN206088023U (en) City domestic waste compressor device
CN209042406U (en) A kind of house refuse centralized processor
CN211551608U (en) Garbage pyrolysis device
CN204544953U (en) Garbage as resource utilizes device
CN210617373U (en) Landfill leachate drainage guide device
CN106824991A (en) A kind of solid refuse dries bulk material device
CN209603940U (en) paraffin removal device of oil collecting pipeline
CN111791525A (en) Shaftless spiral channel conveying garbage compression box
CN202598542U (en) Feeding device for garbage incinerator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant