CN106499193A - A kind of installation method of Ecology umbrella single-layer lattice shell steel construction - Google Patents
A kind of installation method of Ecology umbrella single-layer lattice shell steel construction Download PDFInfo
- Publication number
- CN106499193A CN106499193A CN201610925584.2A CN201610925584A CN106499193A CN 106499193 A CN106499193 A CN 106499193A CN 201610925584 A CN201610925584 A CN 201610925584A CN 106499193 A CN106499193 A CN 106499193A
- Authority
- CN
- China
- Prior art keywords
- steel truss
- steel
- heaven
- vault
- umbrella
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Specifically a kind of installation method of Ecology umbrella single-layer lattice shell steel construction of the present invention;It is characterized in that:Including umbrella single-layer latticed shell is divided into umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss part, on-site consolidation:Respectively will be assembled in place successively according to assembled order on ground for each lifting elements of umbrella footpath steel truss, collar tie beam steel construction and the vault of heaven steel truss;The lifting of umbrella footpath steel truss;The lattice temporary support of the vault of heaven steel truss bottom is installed;Installing ring joist steel structure;The vault of heaven steel truss is installed;Short covering welding;Remove temporary support.This installation method carries out the installation of special-shaped single-layer latticed shell by modular division twice, method that is pre-assembled and lifting respectively and carry out overall splicing in high-altitude;The problem that single-layer lattice shell steel structural overhead welding capacity in bulk is big, homework precision is poor and security risk is high is overcome, and causes this construction method that also there is short construction period as clear and definite, single lifting operation difficulty of dividing the work in advance is little.
Description
Technical field
The present invention relates to the construction applications of irregular building, specifically a kind of installation of Ecology umbrella single-layer lattice shell steel construction
Method.
Background technology
Conventional single layer reticulated shell steel construction has when high-altitude is installed that welding capacity is big, welding precision is poor and security risk is high asks
Topic, and when the single-layer lattice shell steel construction for needing to build bionical umbrella, the problems referred to above are even more and project.
Content of the invention
It is an object of the invention to, there is provided one kind can build Ecology umbrella single-layer lattice shell steel fast, efficient, safely
The installation method of structure.
In order to achieve the above object, the present invention is realized in:
A kind of installation method of Ecology umbrella single-layer lattice shell steel construction, including
Step 1, umbrella single-layer latticed shell is divided into umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss portion
Point,
Step 2, that umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss part are divided into multiple liftings again is single
Unit;
Step 3, on-site consolidation:Respectively by each lifting elements of umbrella footpath steel truss, collar tie beam steel construction and the vault of heaven steel truss on ground
Assembled in place successively according to assembled order;
Step 4, the lifting of umbrella footpath steel truss:Umbrella footpath steel truss each several part segmental hoisting is gone forward side by side to designed elevation using tower crane
Welding short covering between row section and section;
Step 5, temporary support:The lattice temporary support of the vault of heaven steel truss bottom is installed on the basis of the steel truss of umbrella footpath;
Step 6, installing ring joist steel structure:Collar tie beam steel construction part is averagely divided into 4 sections of installations;
Step 7, installation the vault of heaven steel truss:The vault of heaven steel truss is averagely divided into 21 units and is lifted successively, opened from an axis
Begin, lift to both sides successively;
Step 8, short covering welding:After the completion of the girder truss lifting of the vault of heaven steel truss, carry out the rod member short covering between piecemeal and weld
Connect;
Step 9, dismounting temporary support:Entirety when umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss part
All after installation, temporary support is removed.
The installation method of described Ecology umbrella single-layer lattice shell steel construction, before step 4, step 6 and step 7 are implemented
Whole Process Simulation Installation Validation is carried out using finite element analysis software.
This installation method by modular division twice, and further division after module be finely divided again, pre-assembled
The method for lifting respectively and carrying out overall splicing in high-altitude carries out the installation of special-shaped single-layer latticed shell;So as to overcome
The problem that single-layer lattice shell steel structural overhead welding capacity in bulk is big, homework precision is poor and security risk is high, and due to the division of labor in advance
Clearly, single lifting operation difficulty is little causes this construction method that also there is short construction period.
Description of the drawings
Fig. 1 is the schematic diagram of umbrella single-layer lattice shell steel construction.
Fig. 2 is the sequence of construction figure of this construction method.
Fig. 3 is the dividing elements schematic diagram in umbrella footpath.
Fig. 4 is the dividing elements schematic diagram of collar tie beam.
Fig. 5 is the dividing elements schematic diagram in the vault of heaven.
Fig. 6 is the schematic diagram of step 401-408 in this construction method.
Fig. 7 is the schematic diagram of step 409-414 in this construction method.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in Figure 1 and Figure 2, it is umbrella footpath 101, collar tie beam 102, the vault of heaven 104 by 1 point of umbrella reticulated shell steel truss and realizes peace
The temporary support 103 of dress, erection sequence is as shown in Figure 2:101 steel truss part of umbrella footpath is installed first, secondly installs interim
The vault of heaven 104 installed by support 103 and collar tie beam 102, last subdivision.
As shown in figure 3, the lifting elements in umbrella footpath 101 divide schematic diagram, which is divided into 4 lifting elements J01 ~ J04, each
Lifting elements are divided into 3 assembled rigid units again;As shown in figure 4, the lifting elements of collar tie beam 102 divide schematic diagram, including 4 sections
Rectangular tube L01 ~ L04 for 900mm × 400mm × 30mm × 30mm;As shown in figure 5, the lifting elements in the vault of heaven 104 are divided illustrating
Figure, including 21 lifting elements in annular distribution, each lifting elements is made up of 3 assembled rigid units again.
Fig. 6 ~ Fig. 7 is the construction procedure schematic diagram of the present invention;As shown in Figure 6 and Figure 7, the lifting construction of the steel roofing
Method is realized by following steps:
Step 401:After the completion of built-in fitting construction, 101 steel truss of umbrella footpath march into the arena after preassembling lifting elements J01, then overall pacify
Dress J01 units;
Step 402:Preassembling lifting elements J02, after the completion of install J02 units, while to covering between J02 and J01;
Step 403:Preassembling lifting elements J03, after the completion of install J03 units, while to covering between J03 and J03;
Step 404:Preassembling lifting elements J04, after the completion of install J04 units, while to covering between J04 and J03;
Step 405:Temporary support 103 is installed, including the crossbeam at the top of lattice column, lattice column;
Step 406:Lifting elements L01 of collar tie beam 102 are installed;
Step 407:Lifting elements L02 of collar tie beam 102 are installed, lifting elements L02 and L01 are covered;
Step 408:Lifting elements L03 of collar tie beam 102 are installed, lifting elements L03 and L02 are covered;
Step 409:Lifting elements L04 of collar tie beam 102 are installed, lifting elements L04 and L03, L04 and L01 are covered;
Step 410:The 104 first piece steel truss lifting elements of the vault of heaven being made up of assembled rigid unit Q7, Q28 and Q49 are installed, after the completion of
Main chord of the closing between Q7, Q28, Q49;
Step 411:Second piece and three piece steel truss of the vault of heaven 104 first piece steel truss both sides, second piece steel truss are lifted respectively
Frame is made up of assembled rigid unit Q8, Q29 and Q50, and the 3rd steel truss is made up of assembled rigid unit Q27, Q48 and Q69;
Step 412:Closing Q8, Q29, Q50 and Q27, the main chord between Q48, Q69, short covering second, the 3rd steel truss with
Web member between first piece steel truss;
Step 413:The steel truss in the vault of heaven 104 is installed in propulsion successively, closes the web member between main chord, short covering steel truss;
Step 414:Remove lattice temporary support 103, each point data of whole detection roofing;
By this construction method, most of work high above the ground is transferred to ground construction, operating efficiency is improved, and construction quality is easy to control
System, construction precision are improved, and security risk reduces, and construction period is relative to be shortened, and reduces hoisting process, temporary support and unloading
Impact of the process deflection to overall structure alignment error, solves coordinate setting and hoisting process, temporary support and unloading
The problem that deflection is predicted in advance, is that whole installation process is smoothed out there is provided scientific basis.Meanwhile, this construction method enters one
Step carries out overall process using computer carries out dynamic analog trace analysis, steel construction is assembled by the analogue data of computer,
Lifted, closed up, being unloaded overall process and adjusted and changed so that the assembled up-to-standard rate of whole steel construction reaches 100%, respectively
Item index is satisfied by design requirement.
Claims (2)
1. a kind of installation method of Ecology umbrella single-layer lattice shell steel construction, is characterized in that:Including
Step 1, umbrella single-layer latticed shell is divided into umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss portion
Point,
Step 2, that umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss part are divided into multiple liftings again is single
Unit;
Step 3, on-site consolidation:Respectively by each lifting elements of umbrella footpath steel truss, collar tie beam steel construction and the vault of heaven steel truss on ground
Assembled in place successively according to assembled order;
Step 4, the lifting of umbrella footpath steel truss:Umbrella footpath steel truss each several part segmental hoisting is gone forward side by side to designed elevation using tower crane
Welding short covering between row section and section;
Step 5, temporary support:The lattice temporary support of the vault of heaven steel truss bottom is installed on the basis of the steel truss of umbrella footpath;
Step 6, installing ring joist steel structure:Collar tie beam steel construction part is averagely divided into 4 sections of installations;
Step 7, installation the vault of heaven steel truss:The vault of heaven steel truss is averagely divided into 21 units and is lifted successively, opened from an axis
Begin, lift to both sides successively;
Step 8, short covering welding:After the completion of the girder truss lifting of the vault of heaven steel truss, carry out the rod member short covering between piecemeal and weld
Connect;
Step 9, dismounting temporary support:Entirety when umbrella footpath steel truss part, collar tie beam steel construction part and the vault of heaven steel truss part
All after installation, temporary support is removed.
2. the installation method of Ecology umbrella single-layer lattice shell steel construction according to claim 1, is characterized in that:Step 4,
Step 6 and step 7 carry out Whole Process Simulation Installation Validation using finite element analysis software before implementing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610925584.2A CN106499193A (en) | 2016-10-30 | 2016-10-30 | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610925584.2A CN106499193A (en) | 2016-10-30 | 2016-10-30 | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106499193A true CN106499193A (en) | 2017-03-15 |
Family
ID=58319458
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610925584.2A Pending CN106499193A (en) | 2016-10-30 | 2016-10-30 | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106499193A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237515A (en) * | 2017-05-31 | 2017-10-10 | 中国二十冶集团有限公司 | The support meanss and its application method of circular steel truss structure |
CN107620428A (en) * | 2017-09-29 | 2018-01-23 | 江苏沪宁钢机股份有限公司 | The c-type support column and its installation method of a kind of steel building |
CN107747357A (en) * | 2017-11-30 | 2018-03-02 | 江苏沪宁钢机股份有限公司 | A kind of closed annular steel construction and its installation method for building external |
CN108049666A (en) * | 2017-12-15 | 2018-05-18 | 陕西建工机械施工集团有限公司 | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction |
CN108166660A (en) * | 2017-11-07 | 2018-06-15 | 中国二十冶集团有限公司 | A kind of curved surface single-layer latticed shell installation method |
CN109281477A (en) * | 2018-03-14 | 2019-01-29 | 江苏恒久钢构有限公司 | A kind of hoisting Design method of steel construction in engineering |
CN111139962A (en) * | 2019-12-18 | 2020-05-12 | 北京城建集团有限责任公司 | Roof steel structure buffer system |
CN113323153A (en) * | 2021-06-08 | 2021-08-31 | 中国建筑第八工程局有限公司 | Bending-twisting aluminum alloy structure in existing complex space and construction method |
CN113404199A (en) * | 2021-08-19 | 2021-09-17 | 中铁建工集团有限公司 | Installation method of umbrella-shaped roof structure |
CN113431193A (en) * | 2021-06-09 | 2021-09-24 | 中交第三航务工程局有限公司 | Quick installation process of special-shaped membrane system for stretching large-span bionic tree |
CN114232802A (en) * | 2022-01-05 | 2022-03-25 | 北钢建设集团股份有限公司 | Steel structure dome latticed shell structure and sectional construction method thereof |
CN114961282A (en) * | 2022-05-26 | 2022-08-30 | 中铁建工集团有限公司 | Construction method of single-layer latticed shell structure streamer with middle cylinder column |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06101348A (en) * | 1992-09-18 | 1994-04-12 | Shimizu Corp | Method for constructing tower |
CN101451378A (en) * | 2007-11-29 | 2009-06-10 | 上海市机械施工有限公司 | 'Drip shaped' radial monolayer steel pipe reticulated shell block and installation method |
CN103938875A (en) * | 2013-01-18 | 2014-07-23 | 上海宝冶集团有限公司 | Ground single body tensioning lifting construction method of single layer suspendome |
CN105480002A (en) * | 2016-01-05 | 2016-04-13 | 江苏沪宁钢机股份有限公司 | Single-layer steel structure decoration tree and mounting method thereof |
CN105649206A (en) * | 2016-01-05 | 2016-06-08 | 江苏沪宁钢机股份有限公司 | Single-layer latticed shell steel structure roof and installation method thereof |
-
2016
- 2016-10-30 CN CN201610925584.2A patent/CN106499193A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06101348A (en) * | 1992-09-18 | 1994-04-12 | Shimizu Corp | Method for constructing tower |
CN101451378A (en) * | 2007-11-29 | 2009-06-10 | 上海市机械施工有限公司 | 'Drip shaped' radial monolayer steel pipe reticulated shell block and installation method |
CN103938875A (en) * | 2013-01-18 | 2014-07-23 | 上海宝冶集团有限公司 | Ground single body tensioning lifting construction method of single layer suspendome |
CN105480002A (en) * | 2016-01-05 | 2016-04-13 | 江苏沪宁钢机股份有限公司 | Single-layer steel structure decoration tree and mounting method thereof |
CN105649206A (en) * | 2016-01-05 | 2016-06-08 | 江苏沪宁钢机股份有限公司 | Single-layer latticed shell steel structure roof and installation method thereof |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237515A (en) * | 2017-05-31 | 2017-10-10 | 中国二十冶集团有限公司 | The support meanss and its application method of circular steel truss structure |
CN107620428B (en) * | 2017-09-29 | 2023-02-28 | 江苏沪宁钢机股份有限公司 | C-shaped support column of steel structure building and installation method thereof |
CN107620428A (en) * | 2017-09-29 | 2018-01-23 | 江苏沪宁钢机股份有限公司 | The c-type support column and its installation method of a kind of steel building |
CN108166660A (en) * | 2017-11-07 | 2018-06-15 | 中国二十冶集团有限公司 | A kind of curved surface single-layer latticed shell installation method |
CN108166660B (en) * | 2017-11-07 | 2020-09-25 | 中国二十冶集团有限公司 | Installation method of curved surface single-layer latticed shell structure |
CN107747357A (en) * | 2017-11-30 | 2018-03-02 | 江苏沪宁钢机股份有限公司 | A kind of closed annular steel construction and its installation method for building external |
CN108049666A (en) * | 2017-12-15 | 2018-05-18 | 陕西建工机械施工集团有限公司 | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction |
CN109281477A (en) * | 2018-03-14 | 2019-01-29 | 江苏恒久钢构有限公司 | A kind of hoisting Design method of steel construction in engineering |
CN111139962A (en) * | 2019-12-18 | 2020-05-12 | 北京城建集团有限责任公司 | Roof steel structure buffer system |
CN113323153A (en) * | 2021-06-08 | 2021-08-31 | 中国建筑第八工程局有限公司 | Bending-twisting aluminum alloy structure in existing complex space and construction method |
CN113431193A (en) * | 2021-06-09 | 2021-09-24 | 中交第三航务工程局有限公司 | Quick installation process of special-shaped membrane system for stretching large-span bionic tree |
CN113404199A (en) * | 2021-08-19 | 2021-09-17 | 中铁建工集团有限公司 | Installation method of umbrella-shaped roof structure |
CN114232802A (en) * | 2022-01-05 | 2022-03-25 | 北钢建设集团股份有限公司 | Steel structure dome latticed shell structure and sectional construction method thereof |
CN114961282A (en) * | 2022-05-26 | 2022-08-30 | 中铁建工集团有限公司 | Construction method of single-layer latticed shell structure streamer with middle cylinder column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106499193A (en) | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction | |
CN104480862B (en) | A kind of erection method of cable stayed bridge end bay steel truss girder | |
CN104947942B (en) | Hypervelocity arch grid structure architecture computer controls the installation method extending out accumulation lifting | |
CN101630344B (en) | Gradual recursion method for determining initial equilibrium state of cable dome | |
CN103696494B (en) | The computer of complex space trussed construction controls hydraulic synchronizing lifting construction method | |
CN103556836B (en) | Spherical reticulated shells assembling and construction method under restricted clearance condition | |
CN102691420A (en) | Installation and construction method for multilayer large-span steel truss | |
CN105178609A (en) | High-altitude bulk construction method for steel-structure grid | |
CN102425260A (en) | Annular single-point installation method for large-span hemispherical roof steel-structured net rack | |
CN104675125A (en) | Large-span roof high bracket supporting system with inclination angle and slide moving construction method thereof | |
CN105780925A (en) | Method for installation construction of truss-hanging combination system | |
CN103938875A (en) | Ground single body tensioning lifting construction method of single layer suspendome | |
CN105040986A (en) | Modular mounting technology for steel-structure door type frame roof system | |
CN107620472A (en) | A kind of portal-rigid frames steel construction Earthquake response integral hoisting method | |
CN100480398C (en) | Self-hoisting construction method and furnace top crane for general overhaul of blast furnace | |
CN111255075B (en) | Construction method of arched evacuated bolt ball latticed shell structure | |
US10738499B2 (en) | Concrete towers manufacturing method for wind turbines and concrete tower for wind turbine | |
CN108049666A (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
CN103046758B (en) | Method for constructing multichannel interval load-carrying mega truss door structure | |
CN104060841A (en) | Large-span steel girder installation construction method | |
CN206562827U (en) | A kind of modularization steel-frame structure for tower equipment | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
CN204401995U (en) | Encorbelment support system in a kind of center of installing for dome structure | |
CN102277900A (en) | Sectional-stacking jacking mounting method of vase-shaped space steel structure | |
CN103866700A (en) | Double-hanging-rod hanging widening structure for transforming platform coming into use |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170315 |
|
RJ01 | Rejection of invention patent application after publication |