CN106493144B - A kind of refuse disposal installation and installation method for gaolu wetland - Google Patents

A kind of refuse disposal installation and installation method for gaolu wetland Download PDF

Info

Publication number
CN106493144B
CN106493144B CN201610846487.4A CN201610846487A CN106493144B CN 106493144 B CN106493144 B CN 106493144B CN 201610846487 A CN201610846487 A CN 201610846487A CN 106493144 B CN106493144 B CN 106493144B
Authority
CN
China
Prior art keywords
plate
rubbish
collection box
garbage collection
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610846487.4A
Other languages
Chinese (zh)
Other versions
CN106493144A (en
Inventor
刘学应
黄正福
刘东哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Water Resources and Electric Power
Original Assignee
Zhejiang University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Water Resources and Electric Power filed Critical Zhejiang University of Water Resources and Electric Power
Priority to CN201610846487.4A priority Critical patent/CN106493144B/en
Publication of CN106493144A publication Critical patent/CN106493144A/en
Application granted granted Critical
Publication of CN106493144B publication Critical patent/CN106493144B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B1/00Dumping solid waste
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B5/00Operations not covered by a single other subclass or by a single other group in this subclass
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B15/00Cleaning or keeping clear the surface of open water; Apparatus therefor
    • E02B15/04Devices for cleaning or keeping clear the surface of open water from oil or like floating materials by separating or removing these materials
    • E02B15/10Devices for removing the material from the surface

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses a kind of refuse disposal installation and installation method for gaolu wetland, which includes rubbish bleeder, separator frame, the first garbage collection box, garbage separator, the second garbage collection box, body and water circle device.Installation method includes: rubbish bleeder installation in the lake (a);(b) loke shore side concreting;(c) body is installed;(d) water circle device is installed;(e) the first garbage collection box and separator frame installation;(f) positioning plate and deflector installation;(g) the second garbage collection box and garbage separator installation;(h) outlet pipe is laid with;(i) soil backfills.Rubbish on lake surface can be collected by the present invention, play the effect of cleaning rubbish, the biggish rubbish of volume is collected in the first garbage collection box simultaneously, the rubbish of small volume is collected in the second garbage collection box, accomplish to handle garbage classification, and part lake water can be recycled after treatment, improve water quality.

Description

A kind of refuse disposal installation and installation method for gaolu wetland
Technical field
The invention belongs to gaolu wetland construction technique fields, and in particular to a kind of refuse disposal installation for gaolu wetland And installation method.
Background technique
Currently, being directed to the improvement of " black smelly " water body, many gaolu wetland variation technologies are had already appeared, artificial gaolu is wet Ground is that one kind naturally purifies the combination process combined with artificial-strengthening, can take suitable scale according to the size of sewage quantity It adapts to therewith, improves the water quality of water body using the catharsis of gaolu wetland, and then eliminate black smelly.Artificial gaolu wetland and tradition Secondary biochemical treatment compare, have and build and operating cost is low, maintenance is simple, effluent quality is good and to load variations adaptation energy The advantages that power is strong, being relatively more suitable for technology management level not is very high, the lesser cities and towns of scale or rural sewage treatment.Promoting Under the premise of the benign cycle of Pollutants in Wastewater matter, the productive potentialities of resource can be given full play to, the recontamination of environment is prevented, from And the optimum efficiency of sewage treatment and recycling is obtained, obtain more and more extensive research and application.
The rubbish at loke shore is cleared up at present, achievees the effect that the water quality for improving water body, it is main to be salvaged using artificial Rubbish is purged, although removing rubbish, increases labour cost, there is also salvage difficulty.
Summary of the invention
Above-mentioned technical problem present in present invention aims to solve the prior art provides a kind of for gaolu wetland Rubbish on lake surface can be collected by refuse disposal installation and installation method, the refuse disposal installation, play cleaning rubbish Effect, while categorised collection is carried out to rubbish, the biggish rubbish of volume is collected in the first garbage collection box, small volume Rubbish is collected in the second garbage collection box, accomplishes to handle garbage classification, and follow after capable of being handled part lake water Ring utilizes, and improves water quality;It is first whole according to the porousness and lake water of soil height in the refuse disposal installation installation process Body installs rubbish bleeder in lake, installs body further according to the setting height of rubbish bleeder, thus can will be at rubbish The position of reason is determined, and convenient for installing one by one, and the position of associated components is carried out alignment up and down, is accelerated installation speed, mention High installation accuracy.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of refuse disposal installation for gaolu wetland, it is characterised in that: including rubbish bleeder, separator frame, One garbage collection box, garbage separator, the second garbage collection box, body and water circle device;Rubbish bleeder includes being discharged into Plate, the first mounting plate and rubbish flow direction controller, be discharged into plate two sides be equipped with the first mounting bracket, be discharged into plate be equipped be discharged into Mouthful, there are two rubbish flow direction controller, the direction of rotation of two rubbish flow direction controllers is opposite for installation on the first mounting plate;Separation Frame includes the first guide plate, separating plate and the second guide plate, and the two sides of the first guide plate are equipped with the second mounting plate, the second mounting plate It is fixed on and is discharged between plate and body, the inclination of the first guide plate is set to row inlet;First garbage collection box is fixed in body, The end of second guide plate is passed into the first garbage collection box, and the side of the first garbage collection box is equipped with rubbish outlet;Rubbish Rubbish separator includes suction bucket, driver and water-supply-pipe, and the second garbage collection box is set to the lower section of separating plate, the second garbage collection The second mounting bracket, the fixed suction bucket of the second mounting bracket are equipped in case;Positioning plate is equipped in body, one end of positioning plate is equipped with Discharge port is positioned, positioning discharge port is set between separating plate and the second garbage collection box, and positioning plate is fixedly connected with driver;Water Circulator includes spray equipment and water treatment facilities, and water-supply-pipe connects spray equipment, and one end of positioning plate is equipped with deflector, leads Flowing plate is set to the lower section of spray equipment, and the end of deflector is passed into water treatment facilities, and the bottom of water treatment facilities is equipped with Water pipe.
Further, rubbish flow direction controller includes motor and rotating disc, and motor drives rotation disc spins, and rotating disc is equipped with Rotatable lamella, motor drive turn disc, so that rotatable lamella is movable in lake water, accelerate lake water mobility, convenient for arranging rubbish Enter.
Further, the first mounting bracket includes installation mobile jib and connection cross bar, and installation mobile jib is fixedly connected with plate is discharged into, even The bottom for connecing cross bar is equipped at least three insertion rods, and three insertion rods are arranged vertically upward, and connection cross bar can be in installation mobile jib Upper appropriate adjustment position, in this way when insertion rod is inserted into soil, staff can continue to exert a force on connection cross bar, be inserted into Bar can be inserted downwardly into soil again, increase the fastness of installation.
Further, the inclination angle of the first guide plate is 5 °~15 °, and the plate face of the second guide plate is arc surface, the first guiding Plate and the second guide plate play the role of guiding, and the first guide plate setting inclination angle is generally 10 ° or so, should not be too large, in this way Separating plate is enabled to play the role of separating rubbish.
Further, the top of the first garbage collection box is equipped with baffle, and baffle can carry out barrier effect to rubbish, by rubbish quilt It is collected into the first garbage collection box.
Further, the bottom of the second garbage collection box be equipped with leveling bracket, leveling bracket can by the second garbage collection box into Row leveling effect, and then guarantee that garbage separator setting plane is horizontal plane, play the effect of garbage separator normal operation.
Further, outlet pipe includes branch pipe and supervisor, and branch pipe and supervisor connect, and branch pipe is set to the bottom of water treatment facilities, Convenient for the control to flow.
A kind of installation method of the refuse disposal installation for gaolu wetland, it is characterised in that include the following steps:
(a) rubbish bleeder is installed in lake: two the first mounting brackets are first kept into same setting height on the ground, A connecting rod is welded between two the first mounting brackets again, then bolt fixation is discharged between two the first mounting brackets Plate, then the first mounting plate and rubbish flow direction controller are installed at the top for being discharged into plate, then according to the soil at loke shore side Porousness and lake water height, control reference line is pulled out in lake, then the first mounting bracket is inserted into soil, and is controlled Rubbish flow direction controller is in lake water, and control is discharged into mouth at lake surface, then accesses floating plate in the bottom for being discharged into plate, so Spud pile is added in the surrounding of the first mounting bracket afterwards, and is connected spud pile and the first mounting bracket with iron wire;
(b) loke shore side concreting;
(c) body is installed: according to the installation site of rubbish bleeder, drawing the installation of body with pencil on concrete Position builds supporting plank in installed position, is then caught in body between supporting plank further according to setting-out position, and The height of the bottom casting concrete protective layer of body, concrete shield is controlled in 10~20mm;
(d) water circle device is installed;
(e) the first garbage collection box and separator frame installation: first according to being put into the first garbage collection at the rubbish taking-up of body Case, and the contact portion of the first garbage collection box and body is welded, then separator frame is put into the first garbage collection box In, then the end of the first guide plate is kept flushing with the end face for being discharged into mouth, and welded, then at the end of the second mounting plate Portion, which is passed into, to be discharged into mouth, then moves laterally into the other end of the second mounting plate, by the second mounting plate and body, separator frame It contacts with each other, then welds the second mounting plate respectively with plate, body, separator frame is discharged into;
(f) positioning plate and deflector installation: according to the setting position of separator frame, the welding location-plate in body is being welded In the process, it is held in position discharge port and is aligned up and down with separating plate, then one end of deflector is passed into water treatment facilities, simultaneously The end of the other end of deflector and separating plate is welded, then water conservancy diversion crab bolt is fixed on body;
(g) the second garbage collection box the second garbage collection box and garbage separator installation: is mounted on positioning discharge port Lower section adjusts the vertical height of the second garbage collection box further according to the position of suction bucket, and the second garbage collection box is leveled, Second mounting bracket is installed in the second garbage collection box again, is then welded the second mounting bracket and suction bucket, simultaneously Driver is integrally provided in positioning plate, and is welded, is then connected to water-supply-pipe with spray equipment, then is twined in junction Upper adhesive plaster;
(h) outlet pipe is laid with;
(i) soil backfills: soil is inserted in the surrounding of body, soil is covered into outlet pipe, then soil is compacted, The cover height of soil and the height of concrete shield are consistent.
The present invention is by adopting the above-described technical solution, have the advantages that
1, for the present invention when to lake surface garbage disposal, two rubbish flow direction controllers accelerate lake to a mouthful phase reverse rotation is discharged into Water to being discharged into mouth flowing, take advantage of a situation and be discharged into from being discharged into mouth by the rubbish at loke shore, reduces the rubbish on lake surface, in this way can will be on lake surface Rubbish is collected, and plays the effect of cleaning rubbish.The biggish rubbish of volume can not be separated by separating plate simultaneously, be led along first It is collected in the first garbage collection box to the guiding role of plate and the second guide plate, the rubbish of small volume is by separating plate point From being collected in the second garbage collection box under the guiding role of positioning discharge port, while lake water also drops onto the second rubbish Collecting box, staff are periodically handled the first garbage collection box and the second garbage collection box, accomplish to receive garbage classification Collection processing.
And the present invention, under driver effect, suction bucket carries out suction, lake to the bottom of the second garbage collection box Water is inhaled into suction bucket, and the second garbage collection box is fallen by the strainer isolation of suction bucket, and lake water is passed by water-supply-pipe In spray equipment, the spray head on spray equipment sprays lake water onto deflector, what deflector shunted lake water and cleaned Effect, then lake water enters water treatment facilities and carries out physics and chemical treatment, purifies water, increases the dissolved oxygen of lake water, only Lake water after change is drained into lake again by outlet pipe, is recycled after treatment in this way to part lake water, and water quality is improved Quality reinforces improvement of the ecological environment.
2, first whole according to the porousness of soil and lake water height in the refuse disposal installation installation process in the present invention Rubbish bleeder in lake is installed, convenient for controlling the setting height for being discharged into plate, and plate is discharged into and keeps horizontal, and be discharged into Floating plate is accessed in the bottom of plate, then adds spud pile in the surrounding of the first mounting bracket, and pacified spud pile and first with iron wire Bracket connection is filled, the stability of rubbish bleeder installation is improved.Further according to the setting height fitting machine of rubbish bleeder Body needs in installation process to build supporting plank, improves the accuracy of body installation, and protect in the bottom casting concrete of body Layer, increases the stability of body.Then according to the command range being discharged between plate and body, to the first garbage collection box and separation Frame is installed, according to the setting position of separator frame, the welding location-plate in body, positioning discharge port with it is right above and below separating plate Standard installs the second garbage collection box further according to the position of positioning discharge port, further according to the position of suction bucket, adjusts the second rubbish The vertical height of collecting box, and the second garbage collection box is leveled, it will be on separating plate, positioning discharge port and the second garbage collection box The position of garbage disposal, can thus be determined by lower alignment installation, convenient for installing one by one, and by the position of associated components into Row alignment up and down, accelerates installation speed, improves installation accuracy.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is a kind of structural schematic diagram of the refuse disposal installation for gaolu wetland in the present invention;
Fig. 2 be Fig. 1 in A to structural schematic diagram;
Fig. 3 be Fig. 1 in B to structural schematic diagram;
Fig. 4 is the structural schematic diagram of rubbish flow direction controller in the present invention;
Fig. 5 is the structural schematic diagram of rubbish bleeder in the present invention;
Fig. 6 is the structural schematic diagram being arranged between separator frame and the first garbage collection box in the present invention;
Fig. 7 is the structural representation being arranged between garbage separator, the second garbage collection box and water circle device in the present invention Figure;
Fig. 8 is the structural schematic diagram of spray equipment in the present invention;
Fig. 9 is the structural schematic diagram of garbage separator in the present invention;
Figure 10 is the structural schematic diagram of body in the present invention;
Figure 11 is the structural schematic diagram after the refuse disposal installation installation for gaolu wetland a kind of in the present invention.
Specific embodiment
As shown in Figure 1 to 11, it is discharged into for a kind of refuse disposal installation for gaolu wetland in the present invention, including rubbish Device 1, separator frame 2, the first garbage collection box 3, garbage separator 4, the second garbage collection box 5, body 6 and water circle device 7.
Rubbish bleeder 1 includes being discharged into plate 8, the first mounting plate 9 and rubbish flow direction controller 10.It is discharged into the two sides of plate 8 Equipped with the first mounting bracket 11, it is discharged into plate 8 equipped with mouth 12 is discharged into, it can be according to the size and lake surface SEA LEVEL VARIATION situation tune of rubbish The size of entire row entrance 12.There are two rubbish flow direction controller 10, two rubbish flow direction controllers 10 for installation on first mounting plate 9 Direction of rotation on the contrary, mainly to be discharged into mouth 12 rotate.Rubbish flow direction controller 10 includes motor 28 and rotating disc 29, motor 28 Rotating disc 29 is driven to rotate.Rotating disc 29 is equipped with rotatable lamella 30, and motor 28 drives rotating disc 29 to rotate, so that rotatable lamella 30 exists It is movable in lake water, accelerate lake water mobility, convenient for rubbish to be discharged into.First mounting bracket 11 includes that installation mobile jib 31 and connection are horizontal Bar 32, connection cross bar 32 can be fixedly connected in 31 activity of installation mobile jib, installation mobile jib 31 with plate 8 is discharged into.Connect the bottom of cross bar 32 Portion is equipped at least three insertion rods 33, and three insertion rods 33 are arranged vertically upward, and connection cross bar 32 can be on installation mobile jib 31 Appropriate adjustment position, in this way when insertion rod 33 is inserted into soil, staff can continue to exert a force on connection cross bar 32, insert Entering bar 33 can be inserted downwardly into soil again, increase the fastness of installation.
Separator frame 2 includes the first guide plate 13, separating plate 14 and the second guide plate 15, and the two sides of the first guide plate 13 are equipped with Second mounting plate 16, the second mounting plate 16, which is fixed on, to be discharged between plate 8 and body 6, and the inclination of the first guide plate 13, which is set to, is discharged into mouth At 12.The inclination angle of first guide plate 13 is 5 °~15 °, and the plate face of the second guide plate 15 is arc surface, 13 He of the first guide plate Second guide plate 15 plays the role of guiding, and the first guide plate 13 setting inclination angle is generally 10 ° or so, should not be too large, in this way Separating plate 14 is enabled to play the role of separating rubbish.
First garbage collection box 3 is fixed in body 6, and the end of the second guide plate 15 is passed into the first garbage collection box 3 In, the side of the first garbage collection box 3 is equipped with rubbish outlet 17, and staff opens rubbish outlet 17, can handle the Rubbish in one garbage collection box 3.The top of first garbage collection box 3 is equipped with baffle 34, and baffle 34 can stop rubbish Effect, rubbish is collected into the first garbage collection box 3.
Garbage separator 4 includes suction bucket 18, driver 19 and water-supply-pipe 20, and the second garbage collection box 5 is set to separating plate 14 lower section.It is equipped with the second mounting bracket 21 in second garbage collection box 5, the fixed suction bucket 18 of the second mounting bracket 21, second Mounting bracket 21 is A-frame.The bottom of second garbage collection box 5 is equipped with leveling bracket 35, and leveling bracket 35 can be by the second rubbish Rubbish collecting box 5 carries out leveling effect, and then guaranteeing that plane is arranged in garbage separator 4 is horizontal plane, and it is normal to play garbage separator 4 The effect of running.
Equipped with positioning plate 22 in body 6, one end of positioning plate 22 is equipped with positioning discharge port 23, and positioning discharge port 23, which is set to, to be divided From between plate 14 and the second garbage collection box 5, positioning plate 22 is fixedly connected with driver 19, and positioning discharge port 23 plays installation position Set positioning and the effect to rubbish guiding.
Water circle device 7 includes spray equipment 24 and water treatment facilities 25, and water-supply-pipe 20 connects spray equipment 24.Positioning plate 22 one end is equipped with deflector 26, and deflector 26 is set to the lower section of spray equipment 24, and the end of deflector 26 is passed into water process In device 25.Equipped with outlet pipe 27, outlet pipe 27 includes branch pipe 36 and supervisor 37, branch pipe 36 and master for the bottom of water treatment facilities 25 Pipe 37 connects, and branch pipe 36 is set to the bottom of water treatment facilities 25, convenient for the control to flow.
The present invention when to lake surface garbage disposal, accelerate to 12 phase reverse rotation of mouth is discharged by two rubbish flow direction controllers 10 Lake water is flowed to mouth 12 is discharged into, and the rubbish at loke shore is taken advantage of a situation and is discharged into from being discharged into mouth 12, and the rubbish on lake surface is reduced, in this way can be by lake Rubbish on face is collected, and plays the effect of cleaning rubbish.The biggish rubbish of volume can not be separated by separating plate 14 simultaneously, suitable The guiding role of the first guide plate 13 and the second guide plate 15 be collected in the first garbage collection box 3, the rubbish of small volume Rubbish is separated by separating plate 14, is collected in the second garbage collection box 5 under the guiding role of positioning discharge port 23, while lake water Also drop onto the second garbage collection box 5, staff periodically to the first garbage collection box 3 and the second garbage collection box 5 at Reason accomplishes to handle separate waste collection.
And the present invention, under the effect of driver 19, the bottom of 18 pair of second garbage collection box 5 of suction bucket carries out suction work With lake water is inhaled into suction bucket 18, and the second garbage collection box 5 is fallen by the strainer isolation of suction bucket 18, and lake water passes through defeated Water pipe 20 is passed into spray equipment 24, and the spray head on spray equipment 24 sprays lake water onto deflector 26, and deflector 26 is right The effect that lake water is shunted and cleaned, then lake water enters water treatment facilities 25 and carries out physics and chemical treatment, purified water Matter increases the dissolved oxygen of lake water, and purified lake water is drained into lake again by outlet pipe 27, carries out in this way to part lake water It is recycled after processing, improves water quality, reinforce improvement of the ecological environment.
A kind of installation method of the refuse disposal installation for gaolu wetland, includes the following steps:
(a) rubbish bleeder 1 is installed in lake: first keeping same setting high two the first mounting brackets 11 on the ground It spends, then welds a connecting rod between two the first mounting brackets 11, then the bolt between two the first mounting brackets 11 It is fixed to be discharged into plate 8, then first mounting plate 9 and rubbish flow direction controller 10 are installed at the top for being discharged into plate 8, then according to close to lake The porousness and lake water height of soil at bank pull out control reference line in lake, then the first mounting bracket 11 are inserted into It into soil, and controls rubbish flow direction controller 10 and is in lake water, control is discharged into mouth 12 at lake surface, is then being discharged into plate Floating plate is accessed in 8 bottom, then adds spud pile in the surrounding of the first mounting bracket 11, and with iron wire by spud pile and first Mounting bracket 11 connects.Since lake surface water level changes constantly, when rubbish bleeder 1 is arranged, lake surface is generally calculated The range of SEA LEVEL VARIATION, then select it is biggish be discharged into mouth 12 be discharged into plate 8, avoid lake surface SEA LEVEL VARIATION to the shadow of garbage disposal It rings.
(b) loke shore side concreting: first sundries is purged, base is flattened, then uses microlith at base Sand filling, and compacting is flattened, stone then is inserted in microlith sand, then carries out concreting, 10~15d is conserved after pouring.
(c) body 6 is installed: according to the installation site of rubbish bleeder 1, drawing body 6 with pencil on concrete Installation site builds supporting plank in installed position, body 6 is then caught between supporting plank further according to setting-out position, And in the bottom casting concrete protective layer of body 6, the height of concrete shield is controlled in 10~20mm.
(d) water circle device 7 is installed.
(e) the first garbage collection box 3 and separator frame 2 are installed: elder generation receives according to the first rubbish is put at the rubbish taking-up of body 6 Header 3, and the contact portion of the first garbage collection box 3 and body 6 is welded, then separator frame 2 is put into the first rubbish In collecting box 3, then the end of the first guide plate 13 is kept flushing with the end face for being discharged into mouth 12, and be welded, then the The end of two mounting plates 16, which is passed into, to be discharged into mouth 12, is then moved laterally into the other end of the second mounting plate 16, by second Mounting plate 16 contacts with each other with body 6, separator frame 2, then distinguishes the second mounting plate 16 with plate 8, body 6, separator frame 2 is discharged into It is welded.
(f) positioning plate 22 and deflector 26 are installed: according to the setting position of separator frame 2, the welding location-plate in body 6 22, in the welding process, it is held in position discharge port 23 and is aligned with about 14 separating plate, then one end of deflector 26 is passed into water In processing unit 25, while the end of the other end of deflector 26 and separating plate 14 being welded, then consolidates 26 bolt of deflector Determine onto body 6.
(g) the second garbage collection box 5 and garbage separator 4 are installed: the second garbage collection box 5 is mounted on positioning discharge port 23 lower section adjusts the vertical height of the second garbage collection box 5 further according to the position of suction bucket 18, and by the second garbage collection Case 5 levels, then the second mounting bracket 21 is installed in the second garbage collection box 5, then by the second mounting bracket 21 and suction bucket 18 are welded, while driver 19 being integrally provided in positioning plate 22, and is welded, then by water-supply-pipe 20 and spray Device 24 is connected to, then is wrapped with adhesive plaster in junction.
(h) outlet pipe 27 is laid with.
(i) soil backfills: inserting soil in the surrounding of body 6, soil is covered outlet pipe 27, is then pressed soil Real, the cover height of soil and the height of concrete shield are consistent.
In refuse disposal installation installation process in the present invention, first integrally pacified according to the porousness and lake water height of soil Rubbish bleeder 1 in lake is filled, convenient for controlling the setting height for being discharged into plate 8, and plate 8 is discharged into and keeps horizontal, and arranging Enter the bottom access floating plate of plate 8, then add spud pile in the surrounding of the first mounting bracket 11, and with iron wire by spud pile and the The connection of one mounting bracket 11, improves the stability of the installation of rubbish bleeder 1.Setting further according to rubbish bleeder 1 is high Degree installs body 6, needs to build supporting plank in installation process, improves the accuracy that body 6 is installed, and pour in the bottom of body 6 Concrete shield is built, the stability of body 6 is increased.Then according to the command range being discharged between plate 8 and body 6, to first Garbage collection box 3 and separator frame 2 are installed, according to the setting position of separator frame 2, the welding location-plate 22 in body 6, and positioning Discharge port 23 is aligned with about 14 separating plate, further according to the position of positioning discharge port 23, installs the second garbage collection box 5, then root According to the position of suction bucket 18, the vertical height of the second garbage collection box 5 is adjusted, and the second garbage collection box 5 is leveled, will be separated Plate 14, positioning discharge port 23 are directed at installation with the second about 5 garbage collection box, can thus carry out the position of garbage disposal true It is fixed, convenient for installing one by one, and the position of associated components is subjected to alignment up and down, accelerates installation speed, improve installation accuracy.
The above is only specific embodiments of the present invention, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to solve essentially identical technical problem, essentially identical technical effect is realized, made simple change, etc. With replacement or modification etc., all it is covered by among protection scope of the present invention.

Claims (8)

1. a kind of refuse disposal installation for gaolu wetland, it is characterised in that: including rubbish bleeder, separator frame, first Garbage collection box, garbage separator, the second garbage collection box, body and water circle device;The rubbish bleeder includes row Enter plate, the first mounting plate and rubbish flow direction controller, the two sides for being discharged into plate are equipped with the first mounting bracket, described to be discharged into plate Equipped with mouth is discharged into, there are two the rubbish flow direction controller, two rubbish traffic organisings for installation on first mounting plate The direction of rotation of device is opposite;The separator frame includes the first guide plate, separating plate and the second guide plate, first guide plate Two sides are equipped with the second mounting plate, second mounting plate be fixed on it is described be discharged between plate and the body, first guiding Plate inclination is set to the row inlet;First garbage collection box is fixed in the body, the end of second guide plate Portion is passed into first garbage collection box, and the side of first garbage collection box is equipped with rubbish outlet;The rubbish Separator includes suction bucket, driver and water-supply-pipe, and second garbage collection box is set to the lower section of the separating plate, and described the The second mounting bracket, the fixed suction bucket of second mounting bracket are equipped in two garbage collection box;It is equipped in the body Positioning plate, one end of the positioning plate are equipped with positioning discharge port, and the positioning discharge port is set to the separating plate and described second Between garbage collection box, the positioning plate is fixedly connected with the driver;The water circle device includes spray equipment and water Processing unit, the water-supply-pipe connect the spray equipment, and one end of the positioning plate is equipped with deflector, and the deflector is set to The lower section of the spray equipment, the end of the deflector are passed into the water treatment facilities, the bottom of the water treatment facilities Portion is equipped with outlet pipe.
2. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: the waste flow It include motor and rotating disc to controller, the motor drives the rotation disc spins, and the rotating disc is equipped with rotatable lamella.
3. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: first peace Filling bracket includes installation mobile jib and connection cross bar, and the installation mobile jib is fixedly connected with the plate that is discharged into, the connection cross bar Bottom is equipped at least three insertion rods, and three insertion rods are arranged vertically upward.
4. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: described first leads It is 5 °~15 ° to the inclination angle of plate, the plate face of second guide plate is arc surface.
5. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: first rubbish The top of rubbish collecting box is equipped with baffle.
6. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: second rubbish The bottom of rubbish collecting box is equipped with leveling bracket.
7. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that: the outlet pipe Including branch pipe and supervisor, the branch pipe and the supervisor are connected, and the branch pipe is set to the bottom of the water treatment facilities.
8. a kind of installation method based on the refuse disposal installation described in claim 1 for gaolu wetland, it is characterised in that Include the following steps:
(a) rubbish bleeder is installed in lake: two the first mounting brackets are first kept into same setting highly on the ground, then A connecting rod is welded between two the first mounting brackets, then bolt fixation is discharged into plate between two the first mounting brackets, The first mounting plate and rubbish flow direction controller are installed at the top for being discharged into plate again, then dredging according to the soil at loke shore side Loose degree and lake water height pull out control reference line in lake, then the first mounting bracket are inserted into soil, and control rubbish Flow direction controller is in lake water, and control is discharged into mouth at lake surface, is then accessed floating plate in the bottom for being discharged into plate, is then existed The surrounding of first mounting bracket adds spud pile, and is connected spud pile and the first mounting bracket with iron wire;
(b) loke shore side concreting;
(c) body is installed: according to the installation site of rubbish bleeder, drawing the installation position of body with pencil on concrete It sets, further according to setting-out position, builds supporting plank in installed position, body is then caught between supporting plank, and in machine The height of the bottom casting concrete protective layer of body, concrete shield is controlled in 10~20mm;
(d) water circle device is installed;
(e) the first garbage collection box and separator frame installation: first according to being put into the first garbage collection box at the rubbish taking-up of body, and The contact portion of first garbage collection box and body is welded, then separator frame is put into the first garbage collection box, so Afterwards the end of the first guide plate is kept flushing with the end face for being discharged into mouth, and welded, then is logical in the end of the second mounting plate Enter to being discharged into mouth, then moves laterally into the other end of the second mounting plate, the second mounting plate and body, separator frame is mutual Contact, then welds the second mounting plate with plate, body, separator frame is discharged into respectively;
(f) positioning plate and deflector installation: according to the setting position of separator frame, the welding location-plate in body, in welding process In, it is held in position discharge port and is aligned up and down with separating plate, then one end of deflector is passed into water treatment facilities, while will lead The other end of flowing plate and the end of separating plate are welded, and then water conservancy diversion crab bolt is fixed on body;
(g) the second garbage collection box: being mounted on the lower section of positioning discharge port by the second garbage collection box and garbage separator installation, Further according to the position of suction bucket, the vertical height of the second garbage collection box is adjusted, and the second garbage collection box is leveled, then the Second mounting bracket is installed in two garbage collection box, then welds the second mounting bracket and suction bucket, while will driving Device is integrally provided in positioning plate, and is welded, and is then connected to water-supply-pipe with spray equipment, then is wrapped with glue in junction Cloth;
(h) outlet pipe is laid with;
(i) soil backfills: inserting soil in the surrounding of body, soil is covered outlet pipe, is then compacted to soil, soil Cover height and the height of concrete shield be consistent.
CN201610846487.4A 2016-09-23 2016-09-23 A kind of refuse disposal installation and installation method for gaolu wetland Active CN106493144B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610846487.4A CN106493144B (en) 2016-09-23 2016-09-23 A kind of refuse disposal installation and installation method for gaolu wetland

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610846487.4A CN106493144B (en) 2016-09-23 2016-09-23 A kind of refuse disposal installation and installation method for gaolu wetland

Publications (2)

Publication Number Publication Date
CN106493144A CN106493144A (en) 2017-03-15
CN106493144B true CN106493144B (en) 2019-04-26

Family

ID=58290813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610846487.4A Active CN106493144B (en) 2016-09-23 2016-09-23 A kind of refuse disposal installation and installation method for gaolu wetland

Country Status (1)

Country Link
CN (1) CN106493144B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110667794B (en) * 2019-11-16 2020-08-07 华北水利水电大学 Water surface floating sundry cleaning boat
CN110904931B (en) * 2019-11-19 2021-04-27 江苏科技大学 Water surface garbage fishing device
CN112813943B (en) * 2021-01-04 2022-11-11 陕西智丽环保科技有限公司 Environment-friendly treatment equipment for cleaning river pollutants

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2707738Y (en) * 2004-04-15 2005-07-06 刘晓虹 Device for sucking and removing sewage on the water
US7465843B2 (en) * 2002-02-18 2008-12-16 E.E.R. Environmental Energy Resources (Israe) Ltd. Recycling system for a waste processing plant
CN202644506U (en) * 2012-05-29 2013-01-02 范福军 Water surface sewage collecting device
CN203546690U (en) * 2013-11-13 2014-04-16 张楠 River surface garbage fishing tool
CN203715335U (en) * 2013-11-01 2014-07-16 北京北科欧远科技有限公司山西分公司 Device for removing light-weight suspended solids out of sewage
CN204486451U (en) * 2015-02-14 2015-07-22 宁德师范学院 A kind of refuse disposal installation of deodorization
CN204551405U (en) * 2015-03-31 2015-08-12 徐卫东 A kind of river surface rubbish fishing device efficiently
CN105544639A (en) * 2016-01-25 2016-05-04 天津汇康田科技研发有限公司 Underwater waste collection system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7465843B2 (en) * 2002-02-18 2008-12-16 E.E.R. Environmental Energy Resources (Israe) Ltd. Recycling system for a waste processing plant
CN2707738Y (en) * 2004-04-15 2005-07-06 刘晓虹 Device for sucking and removing sewage on the water
CN202644506U (en) * 2012-05-29 2013-01-02 范福军 Water surface sewage collecting device
CN203715335U (en) * 2013-11-01 2014-07-16 北京北科欧远科技有限公司山西分公司 Device for removing light-weight suspended solids out of sewage
CN203546690U (en) * 2013-11-13 2014-04-16 张楠 River surface garbage fishing tool
CN204486451U (en) * 2015-02-14 2015-07-22 宁德师范学院 A kind of refuse disposal installation of deodorization
CN204551405U (en) * 2015-03-31 2015-08-12 徐卫东 A kind of river surface rubbish fishing device efficiently
CN105544639A (en) * 2016-01-25 2016-05-04 天津汇康田科技研发有限公司 Underwater waste collection system

Also Published As

Publication number Publication date
CN106493144A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN106493144B (en) A kind of refuse disposal installation and installation method for gaolu wetland
CN108438155A (en) A kind of water body cleaning device
CN103205991A (en) Channel cleanout device and method thereof
CN203174656U (en) Channel cleanout device
CN1259249C (en) Sorption algae apparatus of collecting blue algae water bloom
CN205307897U (en) A central transmission inhales mud scraper for two heavy ponds
CN106436668A (en) River channel rubbish automatic cleaning method
CN103071320A (en) Hydraulic particles separator used for rainwater pretreatment
CN202909499U (en) Hydraulic power particle separator for rainwater pretreatment
CN109056879A (en) A kind of riverway sludge cleaning plant and construction method
CN107989004A (en) A kind of new hydraulic engineering gate
CN208340198U (en) A kind of novel peripheral drive scraping and sucking machine
CN206591571U (en) A kind of gardens rain collector
CN110217908A (en) A kind of industrial tail water environment protection treating system
CN214460930U (en) Environment-friendly sponge city's rainwater circulation system
CN104371911A (en) Biogas fermentation tank deposit cleaning apparatus system and cleaning construction process
CN210439449U (en) City closed conduit intelligence is desilting device under water
CN210238633U (en) Rainwater recycling system
CN207950778U (en) A kind of truss-like pumping suction dredge
CN208949951U (en) A kind of riverway sludge cleaning plant
CN207749613U (en) Device for dragging dregs and shunting well equipped with device for dragging dregs
CN207121973U (en) A kind of automatic sewage collection system of urban flood control and drainage
CN106759766B (en) A kind of urban road rainwater retention purification system and construction method
CN2675641Y (en) Algae absorbing device for collecting blue algae water bloom
CN104727366B (en) What a kind of belt edge table rushed function rushes suction dredge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant