CN106481004B - Air-flow guiding and system is utilized in a kind of double-layer curtain wall - Google Patents
Air-flow guiding and system is utilized in a kind of double-layer curtain wall Download PDFInfo
- Publication number
- CN106481004B CN106481004B CN201611156765.XA CN201611156765A CN106481004B CN 106481004 B CN106481004 B CN 106481004B CN 201611156765 A CN201611156765 A CN 201611156765A CN 106481004 B CN106481004 B CN 106481004B
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- layer curtain
- cavity
- air
- transverse slat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/90—Curtain walls comprising panels directly attached to the structure
- E04B2/92—Sandwich-type panels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
- E04F17/04—Air-ducts or air channels
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Load-Bearing And Curtain Walls (AREA)
- Building Environments (AREA)
Abstract
The present invention relates to air-flow guiding in a kind of double-layer curtain wall and utilize system, it includes internal layer curtain wall, outer layer curtain wall and central cantilever, the center cantilever includes internal connecting pin and external connection terminal, the inside connecting pin and the external connection terminal are located at the both ends of the center cantilever, the internal layer curtain wall is connected with the inside connecting pin, the outer layer curtain wall is connected with the external connection terminal, the internal layer curtain wall and the outer layer curtain wall are hung on the steel construction of building simultaneously by the center cantilever, and a cavity is formed between the internal layer curtain wall and the outer layer curtain wall, the center cantilever is located in the cavity, the cavity is connected with air duct, the air duct is connected between the cavity and building elevator, generated air-flow directly passes through the air duct and is directed into the building elevator in the cavity, wind-force is provided in the air duct Generator, the airflow function in the air duct enable the wind-driven generator to generate electricity on the wind-driven generator.
Description
Technical field
The present invention relates to a kind of guiding of air-flow and system is utilized, a kind of air-flow applied in double-layer curtain wall is particularly related to and leads
Draw and utilize system.
Background technique
It is well known that double-layer curtain wall is also known as passage of heat curtain wall, type of respiration curtain wall, ventilation type curtain wall, energy-saving curtain wall etc..Its
By inside and outside two layers of facade contexture, the air cushion between an indoor and outdoor is formed.Outer layer can be by bright frame, hidden frame or point branch
Formula curtain wall is constituted.Internal layer can be made of bright frame, frame concealed curtain wall or door and window with opening door-leaf and access path.It can also be one
Glass surface layer is arranged in the two sides of a separate support structure, forms the lesser double-skin facade construction of space length.Its inside and outside curtain wall it
Between formed a relative closure space.There is air inlet in its underpart, and exhaust outlet is arranged at top, and controllable air flows shape therebetween
State.Equipped with controllable air inlet, exhaust outlet, sunshading board and blinds etc..The main function of double-layer curtain wall is, makes construction outer layer
Natural Changes in weather is effectively adapted to, the thermal and insulating performance of curtain wall is improved.The sound insulation property of curtain wall is improved, indoor item is improved
Part.In addition its noise control significant effect that insulates against sound.
Double-layer curtain wall has inside and outside two layers of curtain wall layer, and will necessarily have a cavity between two layers of curtain wall layer, due to curtain
Wall various pieces by its different cavity of intensity of solar irradiation will necessarily there is air-flows, if when specific implementation not
Air-flow is exported to pole to hold the case where security risk occurs, in addition also will appear curtain wall hot-spot from cavity, and traditional technology
In be all to be exported air-flow by the way of additionally opening up air outlet, but just need to open up number when curtain wall area is very big
Purpose derived from air-flow can be realized by measuring numerous air outlets, meanwhile, only simply air-flow is led in traditional technology
Out, absolutely not it is utilized, in turn results in the waste of wind energy, and this is the major defect for traditional technology.
Summary of the invention
The present invention provides in a kind of double-layer curtain wall air-flow guiding and using system, can to the air-flow in double-layer curtain wall into
Row is guided and is used, and this is for the main object of the present invention.
The technical scheme adopted by the invention is as follows: air-flow guiding and system is utilized in a kind of double-layer curtain wall comprising internal layer
Curtain wall, outer layer curtain wall and central cantilever, which includes internal connecting pin and external connection terminal, the inside connecting pin
And the external connection terminal is located at the both ends of the center cantilever, which is connected with the inside connecting pin, should
Outer layer curtain wall is connected with the external connection terminal, hangs the internal layer curtain wall and the outer layer curtain wall simultaneously by the center cantilever
A cavity is formed on the steel construction of building, and between the internal layer curtain wall and the outer layer curtain wall, which is located at should
In cavity.
The cavity is connected with air duct, which is connected between the cavity and building elevator, is produced in the cavity
Raw air-flow directly passes through the air duct and is directed into the building elevator, is provided with wind-driven generator in the air duct, the wind
Airflow function in road enables the wind-driven generator to generate electricity on the wind-driven generator.
The building elevator passes through several air ducts simultaneously and is connected with the cavity from top to bottom, sets in the air duct
It is equipped with narrow passage, which is arranged in the narrow passage.
The outer layer curtain wall includes shingle nail and partition panel, wherein several pieces of shingle nails are stitched together to be formed each other
The outer layer curtain wall, the partition panel are connected to the inside of the shingle nail, meanwhile, the partition panel be arranged in the cavity, by this every
Disconnected plate is isolated in the cavity forms several airslides, the air-flow in the cavity can be made smoothly to be directed to by the airslide
In the air duct, which includes inner wall panel, and several pieces of inner wall panels are stitched together to form the internal layer curtain wall each other.
The partition panel is vertical with the shingle nail, also, the seaming position of the shingle nail is arranged in the partition panel.
The center cantilever includes outer pawl head, interior pawl head and connecting rod, wherein the outer pawl head and the interior pawl head are set respectively
It sets at the both ends of the connecting rod, the outer pawl capitiform is at the external connection terminal, and the interior pawl capitiform is at the inside connecting pin.
The outer pawl head includes external splint and inner splint, which is folded on the lateral surface of the shingle nail, the inner clip
Plate is folded on the medial surface of the shingle nail, and fixed screw is successively threaded through in the external splint, the shingle nail and the inner splint,
To which three to be fixed together, between two pieces of the arbitrary neighborhood shingle nails, and fills out and be equipped in the outer pawl head
Sealed gluing block.
The interior pawl head includes connection framework and fixed frame, wherein the fixed frame is fixed by screws in the steel of building
In structure, which includes two blocks of side plates, the first transverse slat and the second transverse slat, and two blocks of side plates are arranged in parallel, this first
Transverse slat and second transverse slat are arranged in parallel between two blocks of side plates, are surrounded and are formed with first transverse slat by two blocks of side plates
One connecting cavity, by two blocks of side plates and first transverse slat, second transverse slat around forming a cavity, the cavity be located at this first
Between transverse slat and second transverse slat, which is located in the connecting cavity, which is fixedly connected at by screw
On first transverse slat, it is provided with boss on second transverse slat, which is fixedly connected in the boss, respectively should at two pieces
The upper and lower ends portion of side plate is provided with card slot, is inserted with sealing strip in the card slot.
The connecting rod includes outside linking arm and inside linking arm, and the outside linking arm and the inside linking arm are by turning
Axis is articulated, and facilitates construction and installation by the design of such structure, which is arranged in the end of linking arm on the outside of this, and
The end of linking arm on the inside of this is arranged in the interior pawl head.
The partition panel is fastened in the outside linking arm, which includes cursor and snap-arms, the rotation
Arm is fixedly connected with the snap-arms, wherein the snap-arms include two arm bodies, and two arm bodies are arranged in parallel, and should at two
A holding chamber is formed between arm body, which is folded in the holding chamber, is screwed respectively on two arm bodies
There is arm plate, can be folded in the partition panel is stable in the holding chamber by the arm plate.
The inside linking arm includes pivot end and inserted terminal, and wherein the pivot end is articulated with the cursor, should
Inserted terminal is plugged in the boss of the interior pawl head, is also arranged with cutting ferrule on the inserted terminal, which is embedded in the inner wall panel
In to fix relative position.
The invention has the benefit that because the curtain wall area outside buildings in general is all bigger, double-layer curtain wall
The cavity size of middle formation is also bigger, thus there are should when the temperature difference inside and outside double-layer curtain wall or between various pieces
Will occur air motion in cavity, and then generate wind energy, when concrete application, if wind energy cannot be guided and from this
Outflow certainly will will appear security risk and other many problems in cavity, and all be to use additionally to open up out in traditional technology
The mode in air port exports air-flow, can but just need to open up large number of air outlet when curtain wall area is very big
Realize purpose derived from air-flow, meanwhile, only simply air-flow is exported in traditional technology, and absolutely not it is carried out
It utilizes, in turn results in the waste of wind energy, in technology of the invention, can be filled by the wind-driven generator being arranged in the air duct
Divide and generated electricity using wind energy caused by the cavity in double-layer curtain wall, achievees the purpose that adaptation to local conditions generates green electric power supply, value
, it is emphasized that be equipped with multiple elevator and elevator in current building, and the size of elevator all compares
Greatly, while using the air duct by the cavity be connected its exhaust effect ideal with multiple elevators.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is overlooking structure diagram of the invention.
Fig. 3 is the structural schematic diagram of present invention connection framework.
Fig. 4 is side structure schematic view of the invention.
Specific embodiment
As shown in Figures 1 to 4, air-flow guides and utilizes system in a kind of double-layer curtain wall comprising internal layer curtain wall 10, outer layer curtain
Wall 20 and central cantilever 30.
The center cantilever 30 include internal connecting pin 31 and external connection terminal 32, the inside connecting pin 31 and this outside
Connecting pin 32 is located at the both ends of the center cantilever 30.
The internal layer curtain wall 10 is connected with the inside connecting pin 31, which is connected with the external connection terminal 32
It connects.
The internal layer curtain wall 10 and the outer layer curtain wall 20 are hung on to the steel knot of building simultaneously by the center cantilever 30
On structure 40, and a cavity 50 is formed between the internal layer curtain wall 10 and the outer layer curtain wall 20, which is located at the cavity
In 50.
When specific implementation, because the curtain wall area outside buildings in general is all bigger, in double-layer curtain wall
50 size of cavity formed is also bigger, thus there are should when the temperature difference inside and outside double-layer curtain wall or between various pieces
Will occur air motion in cavity 50, and then generate wind energy, when concrete application, if wind energy cannot be guided and from
Outflow certainly will will appear security risk and other many problems in the cavity 50, and all be to use additionally to open in traditional technology
The mode for setting out air port exports air-flow, but just needs to open up large number of outlet air eloquence when curtain wall area is very big
It can be realized purpose derived from air-flow, meanwhile, only simply air-flow is exported in traditional technology, and absolutely not to it
It is utilized, in turn results in the waste of wind energy.
The cavity 50 is connected with air duct 60, which is connected between the cavity 50 and building elevator 70.
Generated air-flow directly passes through the air duct 60 and is directed into the building elevator 70 in the cavity 50.
Due to can all configure elevator in present high-rise, and elevator is all arranged in elevator, the present invention
Directly the cavity 50 is connected to the building elevator 70 using air duct, the case where additionally not increasing air inlet and outlet
It is lower directly to carry out air draft using elevator, architectural construction can be greatly simplified, curtain wall cost is reduced.
Be provided with wind-driven generator 61 in the air duct 60, the airflow function in the air duct 60 on the wind-driven generator 61,
The wind-driven generator 61 is set to generate electricity, power transmission caused by the wind-driven generator 61 is for people to use into building.
In technology of the invention, the double-deck curtain can make full use of by the wind-driven generator 61 being arranged in the air duct 60
Wind energy caused by the cavity 50 generates electricity in wall, achievees the purpose that adaptation to local conditions generates green electric power supply, it is emphasized that
Multiple elevator and elevator are equipped in current building, and the size of elevator is all bigger, utilizes simultaneously
The air duct 60 cavity 50 is connected with multiple elevators its exhaust effect ideal.
When specific implementation, the building elevator 70 passes through several air ducts 60 and the sky simultaneously from top to bottom
Chamber 50 is connected.
It is provided with narrow passage 62 in the air duct 60, which is arranged in the narrow passage 62 to reach convergence
The purpose that air-flow sufficiently generates electricity.
When specific implementation, which includes shingle nail 21 and partition panel 22, wherein several pieces of walls
Panel 21 is stitched together to form the outer layer curtain wall 20 each other, which is connected to the inside of the shingle nail 21, meanwhile, it should
Partition panel 22 is arranged in the cavity 50.
It is isolated in the cavity 50 by the partition panel 22 and forms several airslides 221, can be made by the airslide 221
Air-flow in the cavity 50 is smoothly directed in the air duct 60, to promote the speed and flow efficiency of air-flow flowing.
When specific implementation, the partition panel 22 is vertical with the shingle nail 21, also, the partition panel 22 is arranged in the wall
The seaming position of panel 21.
The internal layer curtain wall 10 includes inner wall panel 11, and several pieces of inner wall panels 11 are stitched together to form the internal layer each other
Curtain wall 10.
When specific implementation, the shingle nail 21, the partition panel 22 and the inner wall panel 11 are all by can be by tempering
Doubling glass is made, to promote the overall beautiful effect of curtain wall.
When specific implementation, which includes outer pawl head 33, interior pawl head 34 and connecting rod 35, wherein
The outer pawl head 33 and the interior pawl head 34 are separately positioned on the both ends of the connecting rod 35, which forms the external connection terminal
32, which forms the inside connecting pin 31.
The outer pawl head 33 includes external splint 331 and inner splint 332, which is folded in the outer of the shingle nail 21
On side, which is folded on the medial surface of the shingle nail 21.
Fixed screw is successively threaded through in the external splint 331, the shingle nail 21 and the inner splint 332, thus by three
It is fixed together.
The outer pawl head 33 can by four pieces, the shingle nail 21 be fixed together simultaneously.
It fills out between two pieces of the arbitrary neighborhood shingle nails 21, and in the outer pawl head 33 equipped with sealed gluing block 333.
The interior pawl head 34 includes connection framework 341 and fixed frame 342, wherein the fixed frame 342 is fixed by screws in
On the steel construction 40 of building.
The connection framework 341 includes two blocks of side plates 343, the first transverse slat 344 and the second transverse slat 345.
Two blocks of side plates 343 are arranged in parallel, and first transverse slat 344 and second transverse slat 345 are arranged in parallel in two pieces and are somebody's turn to do
Between side plate 343.
By two blocks of side plates 343 and first transverse slat 344 around one connecting cavity 346 of formation.
By two blocks of side plates 343 and first transverse slat 344, second transverse slat 345 around one cavity 347 of formation, the sky
Chamber 347 is located between first transverse slat 344 and second transverse slat 345.
The fixed frame 342 is located in the connecting cavity 346, the fixed frame 342 by screw be fixedly connected at this
On one transverse slat 344, it is provided with boss 348 on second transverse slat 345, which is fixedly connected in the boss 348.
The upper and lower ends portion of two blocks of side plates 343 is provided with card slot 349 respectively, is inserted with sealing strip in the card slot 349,
To have the function that waterproof.
The connecting rod 35 includes outside linking arm 36 and inside linking arm 37, which connect with the inside
Arm 37 is articulated by shaft 38, facilitates construction and installation by the design of such structure, which is arranged on the outside of this
The end of linking arm 36, and the end of linking arm 37 on the inside of this is arranged in the interior pawl head 34.
The partition panel 22 is fastened in the outside linking arm 36, which includes cursor 361 and clamping
Arm 362.
The cursor 361 is fixedly connected with the snap-arms 362, wherein the snap-arms 362 include two arm bodies 363, two
The arm body 363 is arranged in parallel, and forms a holding chamber between two arm bodies 363, which is folded in the clamping
In chamber.
It has been screwed arm plate 364 respectively on two arm bodies 363, it can be by the partition panel by the arm plate 364
22 stable are folded in the holding chamber.
The inside linking arm 37 includes pivot end and inserted terminal 371, and wherein the pivot end is articulated in the cursor 361
Together, which is plugged in the boss 348 of the interior pawl head 34.
It is also arranged with cutting ferrule 372 on the inserted terminal 371, which is embedded in the inner wall panel 11 with stationary phase pair
Position.
Claims (6)
1. air-flow guides and utilizes system in a kind of double-layer curtain wall comprising internal layer curtain wall, outer layer curtain wall and central cantilever, it should
Central cantilever includes internal connecting pin and external connection terminal, and the inside connecting pin and the external connection terminal are located in this
The both ends of cantilever are entreated, which is connected with the inside connecting pin, which is connected with the external connection terminal,
The internal layer curtain wall and the outer layer curtain wall are hung on the steel construction of building simultaneously by the center cantilever, and in the internal layer
A cavity is formed between curtain wall and the outer layer curtain wall, which is located in the cavity, it is characterised in that:
The cavity is connected with air duct, which is connected between the cavity and building elevator, generated in the cavity
Air-flow directly passes through the air duct and is directed into the building elevator, wind-driven generator is provided in the air duct, in the air duct
Airflow function on the wind-driven generator, so that the wind-driven generator is generated electricity.
2. air-flow guides and utilizes system in a kind of double-layer curtain wall as described in claim 1, it is characterised in that: from top to bottom should
Building elevator passes through several described air ducts simultaneously and is connected with the cavity, is provided with narrow passage in the air duct, should
Wind-driven generator is arranged in the narrow passage.
3. air-flow guides and utilizes system in a kind of double-layer curtain wall as described in claim 1, it is characterised in that: the outer layer curtain wall
Including shingle nail and partition panel, wherein several pieces of shingle nails are stitched together to form the outer layer curtain wall, the partition each other
Plate is connected to the inside of the shingle nail, meanwhile, the partition panel be arranged in the cavity, by the partition panel in the cavity every
From several airslides are formed, the air-flow in the cavity can be made smoothly to be directed in the air duct by the airslide, the internal layer
Curtain wall includes inner wall panel, and several pieces of inner wall panels are stitched together to form the internal layer curtain wall each other.
4. air-flow guiding and utilizing system in a kind of double-layer curtain wall as claimed in claim 3, it is characterised in that: the partition panel with
The shingle nail is vertical, also, the seaming position of the shingle nail is arranged in the partition panel.
5. air-flow guides and utilizes system in a kind of double-layer curtain wall as claimed in claim 3, it is characterised in that: the center cantilever
Including outer pawl head, interior pawl head and connecting rod, wherein the outer pawl head and the interior pawl head are separately positioned on the two of the connecting rod
End, the outer pawl capitiform at the external connection terminal, the interior pawl capitiform at the inside connecting pin,
The outer pawl head includes external splint and inner splint, which is folded on the lateral surface of the shingle nail, inner splint folder
It being located on the medial surface of the shingle nail, fixed screw is successively threaded through in the external splint, the shingle nail and the inner splint, thus
Three is fixed together, between two pieces of the arbitrary neighborhood shingle nails, and is filled out in the outer pawl head and is equipped with sealing
Blob of viscose,
The interior pawl head includes connection framework and fixed frame, wherein the fixed frame is fixed by screws in the steel construction of building
On, which includes two blocks of side plates, the first transverse slat and the second transverse slat, and two blocks of side plates are arranged in parallel, first transverse slat
And second transverse slat is arranged in parallel between two blocks of side plates, is surrounded by two blocks of side plates and first transverse slat and is formed a company
Chamber is connect, by two blocks of side plates and first transverse slat, second transverse slat around a cavity is formed, which is located at first transverse slat
Between second transverse slat, which is located in the connecting cavity, the fixed frame by screw be fixedly connected at this
On one transverse slat, it is provided with boss on second transverse slat, which is fixedly connected in the boss, respectively in two blocks of side plates
Upper and lower ends portion be provided with card slot, be inserted with sealing strip in the card slot.
6. air-flow guides and utilizes system in a kind of double-layer curtain wall as claimed in claim 5, it is characterised in that: the connecting rod packet
It includes outside linking arm and inside linking arm, the outside linking arm is articulated by shaft with the inside linking arm, is passed through
Such structure design facilitates construction and installation, which is arranged in the end of linking arm on the outside of this, and the interior pawl head is arranged at this
The end of inside linking arm,
The partition panel is fastened in the outside linking arm, which includes cursor and snap-arms, the cursor with
The snap-arms are fixedly connected, wherein the snap-arms include two arm bodies, and two arm bodies are arranged in parallel, and in two arm bodies
Between form a holding chamber, which is folded in the holding chamber, has been screwed arm respectively on two arm bodies
Plate can be folded in the partition panel is stable in the holding chamber by the arm plate,
The inside linking arm includes pivot end and inserted terminal, and wherein the pivot end is articulated with the cursor, the grafting
End be plugged in the boss of the interior pawl head, be also arranged with cutting ferrule on the inserted terminal, the cutting ferrule be embedded in the inner wall panel with
Fixed relative position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611156765.XA CN106481004B (en) | 2016-12-15 | 2016-12-15 | Air-flow guiding and system is utilized in a kind of double-layer curtain wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611156765.XA CN106481004B (en) | 2016-12-15 | 2016-12-15 | Air-flow guiding and system is utilized in a kind of double-layer curtain wall |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106481004A CN106481004A (en) | 2017-03-08 |
CN106481004B true CN106481004B (en) | 2019-04-05 |
Family
ID=58284941
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611156765.XA Active CN106481004B (en) | 2016-12-15 | 2016-12-15 | Air-flow guiding and system is utilized in a kind of double-layer curtain wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106481004B (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3801826A1 (en) * | 1988-01-22 | 1989-08-03 | Fraenkische Thermoglas Gmbh & | All-glass facade |
EP0519416A1 (en) * | 1991-06-21 | 1992-12-23 | GL LOCATELLI S.p.A. | Method and device for fixing prefabricated walls or the like to the load-bearing structures of buildings |
JPH1072887A (en) * | 1996-08-30 | 1998-03-17 | Natl House Ind Co Ltd | Ventilating wall structure |
KR0172033B1 (en) * | 1995-10-26 | 1999-02-18 | 최훈 | Construction for curtain walls |
CN102213018A (en) * | 2010-04-08 | 2011-10-12 | 叶芸 | Novel adjustable double-layer glass curtain wall |
JP2012007374A (en) * | 2010-06-24 | 2012-01-12 | Kajima Corp | Curtain wall |
CN203808302U (en) * | 2014-01-03 | 2014-09-03 | 中建三局装饰有限公司 | Point supporting double-layer glass curtain wall connecting element and curtain wall connecting system of point supporting double-layer glass curtain wall connecting element |
CN206319457U (en) * | 2016-12-15 | 2017-07-11 | 深圳市博大建设集团有限公司 | Air-flow guides and utilized system in a kind of double-layer curtain wall |
-
2016
- 2016-12-15 CN CN201611156765.XA patent/CN106481004B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3801826A1 (en) * | 1988-01-22 | 1989-08-03 | Fraenkische Thermoglas Gmbh & | All-glass facade |
EP0519416A1 (en) * | 1991-06-21 | 1992-12-23 | GL LOCATELLI S.p.A. | Method and device for fixing prefabricated walls or the like to the load-bearing structures of buildings |
KR0172033B1 (en) * | 1995-10-26 | 1999-02-18 | 최훈 | Construction for curtain walls |
JPH1072887A (en) * | 1996-08-30 | 1998-03-17 | Natl House Ind Co Ltd | Ventilating wall structure |
CN102213018A (en) * | 2010-04-08 | 2011-10-12 | 叶芸 | Novel adjustable double-layer glass curtain wall |
JP2012007374A (en) * | 2010-06-24 | 2012-01-12 | Kajima Corp | Curtain wall |
CN203808302U (en) * | 2014-01-03 | 2014-09-03 | 中建三局装饰有限公司 | Point supporting double-layer glass curtain wall connecting element and curtain wall connecting system of point supporting double-layer glass curtain wall connecting element |
CN206319457U (en) * | 2016-12-15 | 2017-07-11 | 深圳市博大建设集团有限公司 | Air-flow guides and utilized system in a kind of double-layer curtain wall |
Also Published As
Publication number | Publication date |
---|---|
CN106481004A (en) | 2017-03-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201817940U (en) | Internal recycling double-layer curtain wall | |
CN206554336U (en) | A kind of Internet of Things building curtain wall | |
CN202380616U (en) | Double-layer curtain wall system | |
CN209891487U (en) | Double-deck unit curtain wall construction in wind channel that leads to more | |
CN201897282U (en) | Power ventilator for doors, windows and curtain walls | |
KR20090053471A (en) | Window system for balcony | |
CN206319457U (en) | Air-flow guides and utilized system in a kind of double-layer curtain wall | |
CN106481004B (en) | Air-flow guiding and system is utilized in a kind of double-layer curtain wall | |
CN206346364U (en) | A kind of environmentally friendly hollow glass curtain wall of energy-saving double-layer | |
CN205776938U (en) | Circulation dual layer elements curtain wall in energy-conserving intelligent | |
CN205259897U (en) | Exterior window structure of area door | |
CN206722157U (en) | A kind of full-automatic photovoltaic shutter breathing glass curtain wall | |
CN205329841U (en) | Seal balcony | |
CN204753916U (en) | Energy -conserving curtain of double -deck type of respiration of inner loop | |
CN2755487Y (en) | Convective solar air conditioner | |
CN201526233U (en) | Automatic environment friendly closing window | |
CN106246081A (en) | A kind of ventilation type aluminum window | |
CN202913549U (en) | Gallery type circulating curtain wall | |
CN104963435A (en) | Internal-circulation double-layer respiration type energy-saving curtain wall | |
CN202706279U (en) | Double-layer internal-circulation photovoltaic curtain wall unit | |
CN207485294U (en) | A kind of auxiliary window of solar energy type ventilation | |
KR101239547B1 (en) | A double window system for energy saving | |
CN204804640U (en) | Energy -saving insulation's flat outer wall tripe device | |
CN203821658U (en) | Internal-circulation double-layered ventilation type energy-saving curtain wall | |
CN205259859U (en) | Solar energy light and heat window with sunshade heat preservation function |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |