CN106480899A - 一种全地形自平衡塔基连接结构 - Google Patents

一种全地形自平衡塔基连接结构 Download PDF

Info

Publication number
CN106480899A
CN106480899A CN201610817610.XA CN201610817610A CN106480899A CN 106480899 A CN106480899 A CN 106480899A CN 201610817610 A CN201610817610 A CN 201610817610A CN 106480899 A CN106480899 A CN 106480899A
Authority
CN
China
Prior art keywords
column foot
plate
attachment structure
basis
full landform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610817610.XA
Other languages
English (en)
Inventor
汤晓刚
刘琨
李昆梅
张莉
陈伟
张雯
曾海兵
谈超
刘震
刘俊悦
汪珂
谢聪
王陈杰
徐硕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huadian Engineering Consulting and Design Co Ltd
Original Assignee
Anhui Huadian Engineering Consulting and Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huadian Engineering Consulting and Design Co Ltd filed Critical Anhui Huadian Engineering Consulting and Design Co Ltd
Priority to CN201610817610.XA priority Critical patent/CN106480899A/zh
Publication of CN106480899A publication Critical patent/CN106480899A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

一种全地形自平衡塔基连接结构,包括四只塔腿和连接基础,所述四只塔腿分别通过连接塔脚板与连接基础相连接;四只塔腿之间通过工字钢梁相连接,呈十字交叉梁;所述连接基础至少设有一层;所述连接塔脚板包括塔脚底板和塔脚侧板,塔脚通过塔脚底板与连接基础的一端相接触,并通过地脚螺栓相固定。本发明的有益效果:该连接基础的连接结构实现全地形塔基自平衡、全方位连接。一方面可以有效减少基础工程量、降低塔基开方量,另一方面可以提高上部结构整体刚度,有效抵抗上部结构的水平荷载。

Description

一种全地形自平衡塔基连接结构
技术领域
本发明涉及输电线路杆塔领域,具体是一种全地形自平衡塔基连接结构。
背景技术
随着我国经济社会和电网建设的发展,在山区需根据地形地质自然环境等条件架设输电线路,由于山区线路走廊条件复杂,塔基一般位于不等高的基面上,目前比较常用处理方式共计3种:其中第一种采用降方使每基塔的四个塔腿位于同一基面标高;第二种采用基础立柱抬升至同一基面;第三种采用“长短腿+高低立柱”的方案。第一种方案需根据中心桩高程,对4个塔腿的山体进行开挖降方,降方的工程量一般很大大,同时该方式对于山体和植被破坏较为严重,对塔基稳定性产生不利影响,同时不符合环境保护的要求;第二种方案通过基础抬升的方式使基面保持一致,由于露头较高故基础的有效埋深需增加,从而最终的基础的工程量较大。第三种方案仅适用于配备高低腿的角钢塔,对110kV及以下电压等级的平腿角钢塔而言不适用。因此设计一种全地形自平衡塔基连接结构是非常有必要的。
发明内容
为了克服现有技术的不足,本发明提供一种全地形自平衡塔基连接结构,A、B、C、D四只塔腿之间以工字钢梁相连接形成十字交叉梁。A、B、C、D四只塔腿下部分别采用钢结构的连接结构,该结构的数量根据塔腿位置断面的高程相对应设置。连接结构的顶部与上部角钢塔采用塔脚板连接,连接结构的底部与混凝土基础采用锚栓连接。
本发明解决上述技术问题所采用的技术方案是;
一种全地形自平衡塔基连接结构,包括四只塔腿和连接基础,所述四只塔腿分别通过连接塔脚板与连接基础相连接;四只塔腿之间通过工字钢梁相连接,呈十字交叉梁;所述连接基础至少设有一层。
所述连接塔脚板包括塔脚底板和塔脚侧板,塔脚通过塔脚底板与连接基础的一端相接触,并通过地脚螺栓相固定。
还包括混凝土层,所述连接基础包括上底板和下底板,所述上底板上设有方钢板、加劲肋和垫板,连接基础通过上底板与连接塔脚板相连接,所述下底板通过连接螺栓与混凝土层相连接。
所述工字钢梁包括方钢板,所述方钢板与连接塔脚板相连接,且方钢板与连接塔脚板的连接位置的上下两端设有加劲板,两侧边安装有侧连板。
所述工字钢梁的交叉连接位置设有连接板,并通螺栓固定在工字钢梁的方钢板上。
所述连接基础的下底板与混凝土层相连接的连接螺栓为锚栓。
本发明的有益效果:该连接基础的连接结构实现全地形塔基自平衡、全方位连接。一方面可以有效减少基础工程量、降低塔基开方量,另一方面可以提高上部结构整体刚度,有效抵抗上部结构的水平荷载。
附图说明
下面结合附图和实施例进一步说明。
图1为本发明结构示意图;
图2为图1连接塔脚板的结构示意图;
图3为图1连接基础的结构示意图;
图4为图3的仰视图结构示意图;
图5为图1结构局部示意图;
图6为图1结构局部示意图;
图7为图1结构局部示意图。
具体实施方式
如图1-图7所示的一种全地形自平衡塔基连接结构,包括四只塔腿5和连接基础2,所述四只塔腿5分别通过连接塔脚板1与连接基础2相连接;四只塔腿5之间通过工字钢梁3相连接,呈十字交叉梁;所述连接基础2至少设有一层;连接基础2可以根据塔腿5位置断面的高程相对应设置,从而增加和减少连接基础2的数量,使塔基保持稳定。
所述连接塔脚板1包括塔脚底板51和塔脚侧板52,塔脚5通过塔脚底板51与连接基础2的一端相接触,并通过地脚螺栓6相固定。
还包括混凝土层10,所述连接基础2包括上底板21和下底板24,所述上底板21上设有方钢板7、加劲肋22和垫板23,连接基础2通过上底板21与连接塔脚板1相连接,所述下底板24通过连接螺栓与混凝土层10相连接。
所述工字钢梁3包括方钢板7,所述方钢板7与连接塔脚板1相连接,且方钢板7与连接塔脚板1的连接位置的上下两端设有加劲板4,两侧边安装有侧连板13。
所述工字钢梁3的交叉连接位置设有连接板12,并通螺11栓固定在工字钢梁3的方钢板7上。
所述连接基础2的下底板24与混凝土层10相连接的连接螺栓9为锚栓。
本发明已经通过上述实施例进行了说明,但应当理解的是,上述实施例只是用于举例和说明的目的,而非意在将本发明限制于所描述的实施例范围内。此外本领域技术人员可以理解的是,本发明并不局限于上述实施例,根据本发明的教导还可以做出更多种的变型和修改,这些变型和修改均落在本发明所要求保护的范围以内。

Claims (6)

1.一种全地形自平衡塔基连接结构,包括四只塔腿和连接基础,其特征在于,所述四只塔腿分别通过连接塔脚板与连接基础相连接;四只塔腿之间通过工字钢梁相连接,呈十字交叉梁;所述连接基础至少设有一层。
2.根据权利要求1所述的一种全地形自平衡塔基连接结构,其特征在于,所述连接塔脚板包括塔脚底板和塔脚侧板,塔脚通过塔脚底板与连接基础的一端相接触,并通过地脚螺栓相固定。
3.根据权利要求1所述的一种全地形自平衡塔基连接结构,其特征在于,还包括混凝土层,所述连接基础包括上底板和下底板,所述上底板上设有方钢板、加劲肋和垫板,连接基础通过上底板与连接塔脚板相连接,所述下底板通过连接螺栓与混凝土层相连接。
4.根据权利要求1所述的一种全地形自平衡塔基连接结构,其特征在于,所述工字钢梁包括方钢板,所述方钢板与连接塔脚板相连接,且方钢板与连接塔脚板的连接位置的上下两端设有加劲板,两侧边安装有侧连板。
5.根据权利要求1或4所述的一种全地形自平衡塔基连接结构,其特征在于,所述工字钢梁的交叉连接位置设有连接板,并通螺栓固定在工字钢梁的方钢板上。
6.根据权利要求3所述的一种全地形自平衡塔基连接结构,其特征在于,所述连接基础的下底板与混凝土层相连接的连接螺栓为锚栓。
CN201610817610.XA 2016-09-12 2016-09-12 一种全地形自平衡塔基连接结构 Pending CN106480899A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610817610.XA CN106480899A (zh) 2016-09-12 2016-09-12 一种全地形自平衡塔基连接结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610817610.XA CN106480899A (zh) 2016-09-12 2016-09-12 一种全地形自平衡塔基连接结构

Publications (1)

Publication Number Publication Date
CN106480899A true CN106480899A (zh) 2017-03-08

Family

ID=58273701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610817610.XA Pending CN106480899A (zh) 2016-09-12 2016-09-12 一种全地形自平衡塔基连接结构

Country Status (1)

Country Link
CN (1) CN106480899A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110016965A (zh) * 2019-04-30 2019-07-16 北京建筑大学 钢柱柱脚连接结构
CN113195835A (zh) * 2018-12-03 2021-07-30 Hws混凝土塔有限公司 一种用于风力涡轮机塔架的地基件
CN114525806A (zh) * 2022-03-31 2022-05-24 四川电力设计咨询有限责任公司 铁塔单桩联合基础及其施工方法

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338034A (ja) * 1995-06-14 1996-12-24 Hitachi Ltd クレーンの固定構造、その固定方法及びその固定構造の撤去方法
CN201254731Y (zh) * 2008-09-19 2009-06-10 浙江省东阳第三建筑工程有限公司 一种钢十字梁式可拆卸塔基
CN101660315A (zh) * 2009-09-05 2010-03-03 浙江省东阳第三建筑工程有限公司 一种钢十字梁式可拆卸塔基构筑方法及结构
CN201722970U (zh) * 2010-07-03 2011-01-26 烟台电力设计院有限责任公司 一种输电线路铁塔岩石基础固定装置
CN202090362U (zh) * 2011-04-21 2011-12-28 中国电力工程顾问集团西北电力设计院 一种特高压直流线路钢结构高抬基础型式
CN202416341U (zh) * 2011-12-16 2012-09-05 山东中凯海洋工程有限公司 一种钢桁架自立式海上测风塔
CN202416339U (zh) * 2011-10-13 2012-09-05 南通市常青建筑安装工程有限公司 一种塔式起重机固定基础
CN203905586U (zh) * 2014-06-25 2014-10-29 中国电力工程顾问集团西南电力设计院 一种用于输电铁塔的延长腿
CN104775447A (zh) * 2015-04-13 2015-07-15 中国电力工程顾问集团中南电力设计院有限公司 用于陡峭山区输电塔的子母基础框架及其施工工艺
CN204492310U (zh) * 2015-01-13 2015-07-22 中国电力工程顾问集团西北电力设计院有限公司 一种±500kV直流输电线路避雷器安装支柱式结构
CN105484285A (zh) * 2015-11-27 2016-04-13 中国一冶集团有限公司 一种拼装钢管混凝土柱式高承台塔吊基础结构及施工方法
CN206052764U (zh) * 2016-09-12 2017-03-29 安徽华电工程咨询设计有限公司 一种全地形自平衡塔基连接结构

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338034A (ja) * 1995-06-14 1996-12-24 Hitachi Ltd クレーンの固定構造、その固定方法及びその固定構造の撤去方法
CN201254731Y (zh) * 2008-09-19 2009-06-10 浙江省东阳第三建筑工程有限公司 一种钢十字梁式可拆卸塔基
CN101660315A (zh) * 2009-09-05 2010-03-03 浙江省东阳第三建筑工程有限公司 一种钢十字梁式可拆卸塔基构筑方法及结构
CN201722970U (zh) * 2010-07-03 2011-01-26 烟台电力设计院有限责任公司 一种输电线路铁塔岩石基础固定装置
CN202090362U (zh) * 2011-04-21 2011-12-28 中国电力工程顾问集团西北电力设计院 一种特高压直流线路钢结构高抬基础型式
CN202416339U (zh) * 2011-10-13 2012-09-05 南通市常青建筑安装工程有限公司 一种塔式起重机固定基础
CN202416341U (zh) * 2011-12-16 2012-09-05 山东中凯海洋工程有限公司 一种钢桁架自立式海上测风塔
CN203905586U (zh) * 2014-06-25 2014-10-29 中国电力工程顾问集团西南电力设计院 一种用于输电铁塔的延长腿
CN204492310U (zh) * 2015-01-13 2015-07-22 中国电力工程顾问集团西北电力设计院有限公司 一种±500kV直流输电线路避雷器安装支柱式结构
CN104775447A (zh) * 2015-04-13 2015-07-15 中国电力工程顾问集团中南电力设计院有限公司 用于陡峭山区输电塔的子母基础框架及其施工工艺
CN105484285A (zh) * 2015-11-27 2016-04-13 中国一冶集团有限公司 一种拼装钢管混凝土柱式高承台塔吊基础结构及施工方法
CN206052764U (zh) * 2016-09-12 2017-03-29 安徽华电工程咨询设计有限公司 一种全地形自平衡塔基连接结构

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113195835A (zh) * 2018-12-03 2021-07-30 Hws混凝土塔有限公司 一种用于风力涡轮机塔架的地基件
CN113195835B (zh) * 2018-12-03 2023-12-22 Hws混凝土塔有限公司 一种用于风力涡轮机塔架的地基件
CN110016965A (zh) * 2019-04-30 2019-07-16 北京建筑大学 钢柱柱脚连接结构
CN114525806A (zh) * 2022-03-31 2022-05-24 四川电力设计咨询有限责任公司 铁塔单桩联合基础及其施工方法

Similar Documents

Publication Publication Date Title
CN201850498U (zh) 水中钢栈桥
CN203296038U (zh) 一种高路堤椅式桩板墙结构
CN202492865U (zh) 输电塔架的纠偏装置
CN106480899A (zh) 一种全地形自平衡塔基连接结构
CN102936897B (zh) 一种兼作支撑加固结构的钢桥
CN206052764U (zh) 一种全地形自平衡塔基连接结构
CN101187268B (zh) 可均匀沉降和高度可调的输电铁塔
CN211949863U (zh) 基于空间桁架的老旧角钢塔塔腿加固装置
CN212534196U (zh) 一种填土边坡的支挡结构
CN206971084U (zh) 桥梁盖梁模板的支撑结构
CN202298638U (zh) 斜柱式铁塔基础
CN203462797U (zh) 一种具有悬翘结构的架空式电缆终端场
CN208415290U (zh) 室外变电站钢构架基础施工结构
CN202672176U (zh) 输电线路角钢塔独柱高平台支承式基础
CN103726505B (zh) 海上风电场风机基础
CN213897208U (zh) 输电窄基塔基础
CN208604470U (zh) 一种中承式拱桥
CN208934293U (zh) 竖井楼梯
CN203462804U (zh) 一种输电线路悬翘式塔座
CN201128915Y (zh) 斜柱式铁塔基础
CN208685646U (zh) 一种建筑地基基础结构
CN103216134B (zh) 一种输电线路悬翘式塔座
CN215714566U (zh) 一种用于防止软土地区桥头道路沉降的结构
CN205369298U (zh) 一种预制n型桩板式挡土墙
CN204875841U (zh) 输电联合板式基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170308