CN106480821A CN201611184518.0A CN201611184518A CN106480821A CN 106480821 A CN106480821 A CN 106480821A CN 201611184518 A CN201611184518 A CN 201611184518A CN 106480821 A CN106480821 A CN 106480821A
Authority
CN
China
Prior art keywords
attachment strap
arc
seamless
arc attachment
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611184518.0A
Other languages
Chinese (zh)
Other versions
CN106480821B (en
Inventor
薛俊青
唐玉风
布鲁诺.布里斯杰拉
陈宝春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201611184518.0A priority Critical patent/CN106480821B/en
Publication of CN106480821A publication Critical patent/CN106480821A/en
Application granted granted Critical
Publication of CN106480821B publication Critical patent/CN106480821B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • E01D19/067Flat continuous joints cast in situ

Abstract

The present invention provides seamless bridge neotectonics and its construction method of a kind of end using arc attachment strap, including seamless abutment and the embankment filled soil of connection adjacent with seamless abutment, horizontal attachment strap is provided with the embankment filled soil, one end-rack of horizontal attachment strap is on the bracket of seamless abutment, the other end is connected with arc attachment strap, and the arc attachment strap is extended downwardly from seamless abutment to embankment filled soil direction.The arc attachment strap present invention is stated by adding arc attachment strap in horizontal attachment strap rear end, and slided in oil immersion fiber cloth by arc attachment strap, the translation that panel type attachment strap or horizontal flush type attachment strap are passed over is converted into rotation, and the rotational deformation at connection reinforcing bar is absorbed by the bending of connection reinforcing bar, arc attachment strap provides a more preferable stiffness transition to road surface, is conducive to alleviating the generation of differential settlement.

Description

A kind of end is using seamless bridge neotectonics and its construction method of arc attachment strap
Technical field
The present invention relates to seamless bridge neotectonics and its construction method of a kind of end using arc attachment strap.
Background technology
Bridge expanssion joint is to receive bridge to indulge bridge to due under the cyclic deformation under temperature action and Vehicle Load A kind of device of length travel, but due to the not enough problem of its durability, jump car problem can be caused to vehicle and reduced driving and relax Adaptive, and rain penetration, debris filling make expansion joint lose performance and corrode substructure.Also, frequently keep in repair Maintain and can suspend traffic circuit and raise maintenance cost.As can be seen here, solving the series of problems that brings of bridge expanssion joint is Imperative.
At present for expansion joint solve problem, generally there are following two thinkings:One is improvement retractor device.Stretch dress at present Put type a lot, its service life is typically within 5 years, but improvement retractor device, thoroughly do not eliminate the dimension of retractor device Shield and replacing problem, so improvement retractor device is cured the symptoms, not the disease.Two is fundamentally solving the problems, such as retractor device, passes through Reduce or cancel bridge expanssion joint and retractor device, due to the retractor device of cancellation Abutment, its attachment strap is except sending out for seamless bridge Wave outside the effect of seamed bridge attachment strap, also a part of girder is indulged bridge to displacement transfer to adjacent road.Panel type attachment strap is flat Flush type attachment strap is put by the temperature movement passed over by girder or received by the loop control of attachment strap end seam, for following Ring control seam, the shift reciprocately brought due to temperature cycles change and material are directly contacted with soil, its durability existing problem.
Content of the invention
The present invention is improved to the problems referred to above, i.e., the technical problem to be solved in the present invention is existing seamless bridge construction The shift reciprocately that temperature cycles change brings and material are directly contacted with soil, its durability existing problem.
Specific embodiments of the present invention are:A kind of end adopts the seamless bridge neotectonics of arc attachment strap, including seamless bridge Platform and the embankment filled soil of connection adjacent with seamless abutment, are provided with horizontal attachment strap, the horizontal attachment strap one in the embankment filled soil On the bracket of seamless abutment, the other end is connected with arc attachment strap to end-rack, and the arc attachment strap is from seamless abutment to embankment filled soil Direction extends downwardly.State arc attachment strap
Further, through connecting bar connecting between the arc attachment strap and horizontal attachment strap.
Further, the arc attachment strap has buffering froth bed between the end of seamless abutment and embankment filled soil.
Further, the periphery of the arc attachment strap and buffering froth bed is provided with oil immersion fiber cloth.
Further, expansion joint (E.J.) is left between the arc attachment strap and horizontal attachment strap.
Further, supercrust is provided with the embankment filled soil.
Further, the horizontal attachment strap is panel type attachment strap or horizontal flush type attachment strap.
Further, the buffering foam layer material is polystyrene foam.
Further, the central angle of arc attachment strap is 45 °.
Present invention additionally comprises a kind of construction method of manufacture above-mentioned end using the seamless bridge neotectonics of arc attachment strap, which is special Levy and be, comprise the following steps:
(1)When embankment filled soil is constructed to certain altitude, by laying oil immersion fiber cloth and polystyrene foam after fill compaction, this When embankment filled soil upper surface have leave with arc attachment strap lower surface be adapted profile;
(2)Prefabricated arc attachment strap is placed on above oil immersion fiber cloth, the end position of arc attachment strap and polystyrene foam Contact;
(3)Arc attachment strap is prefabricated with connection reinforcing bar towards one end of seamless abutment, arc attachment strap towards seamless abutment side False form is built in setting, prepares the horizontal attachment strap of cast in situs, and false form is stayed towards the end face of seamless abutment with arc attachment strap There is gap;
(4)The horizontal attachment strap of cast in situs, form removal after the completion of pouring;
(5)Horizontal attachment strap is formed after meeting intensity requirement, fills expansion joint (E.J.), and up lay upper strata oil immersion fiber in gap location Cloth;
(6)After the completion of the laying of upper strata oil immersion fiber cloth, proceed to banket, until road surface.
Compared with prior art, the invention has the advantages that:The present invention is by burying in panel type attachment strap or horizontal Entering formula attachment strap rear end and one section of arc attachment strap being added, both are connected with one layer of connection reinforcing bar, a depthkeeping are filled in arc attachment strap end The foam of degree, wraps up one layer of oil immersion fiber cloth for being easy to its slip around arc attachment strap, and by arc attachment strap in oil immersion fiber Slide in cloth, the translation that panel type attachment strap or horizontal flush type attachment strap are passed over is converted into rotation, and at connection reinforcing bar Rotational deformation by connecting the bending of reinforcing bar absorbing.And, arc attachment strap has provided one preferably just to road surface of leading the way Spend and cross, be conducive to alleviating the generation of differential settlement.
Description of the drawings
Fig. 1 is using the structural representation of the seamless bridge neotectonics of the board-like attachment strap of arcwall face;
Fig. 2 is using the structural representation of the seamless bridge neotectonics of arc horizontal flush type attachment strap;
Fig. 3 is using the arc attachment strap structural representation of panel type attachment strap structure;
Fig. 4 is using the arc attachment strap structural representation of horizontal flush type attachment strap structure;
One schematic diagram of Fig. 5 construction procedure;
Two schematic diagram of Fig. 6 construction procedure;
Three schematic diagram of Fig. 7 construction procedure;
Four schematic diagram of Fig. 8 construction procedure;
Five schematic diagram of Fig. 9 construction procedure;
Six schematic diagram of Figure 10 construction procedure;
In figure 1- arc attachment strap, 2- supercrust, 3- horizontal flush type attachment strap, 4- panel type attachment strap, 5- is seamless abutment, 6- embankment Banket, 7- polystyrene foam, 8- connect reinforcing bar, 9- expansion joint (E.J.), 10- oil immersion fiber cloth, 11- false form.
Specific embodiment
The present invention will be further described in detail with reference to the accompanying drawings and detailed description.
As shown in Fig. 1~10, embodiment one;A kind of end adopts the seamless bridge neotectonics of arc attachment strap, including seamless bridge Platform 5 and the embankment filled soil 6 of connection adjacent with seamless abutment, are provided with panel type attachment strap 4, the panel in the embankment filled soil 6 On the bracket of seamless abutment 5, the other end is connected with arc attachment strap 1 to 4 one end-rack of formula attachment strap, and the arc attachment strap 1 is by seamless bridge Platform is extended downwardly to embankment filled soil direction, and in the present embodiment, the central angle of arc attachment strap 1 is 45 °, is provided with embankment filled soil 6 Supercrust 2.
In the present embodiment, between the arc attachment strap 1 and panel type attachment strap 4 through be connected reinforcing bar 8 connect and arc attachment strap 1 with Expansion joint (E.J.) 9 is left between panel type attachment strap 4.
In the present embodiment, the arc attachment strap 1 has buffering foam between the end of seamless abutment 5 and embankment filled soil Layer, in the present embodiment, buffering foam layer material is polystyrene foam 7, the arc attachment strap 1, buffering froth bed and panel type Attachment strap 4 is provided with oil immersion fiber cloth 10 with the periphery at 1 place of continuing of arc attachment strap.The design of oil immersion fiber cloth 10 can be beneficial to arc and take Plate slides, and arc attachment strap is slided in oil immersion fiber cloth, and the translation that panel type attachment strap is passed over is converted into rotation.
Embodiment two, in the present embodiment, horizontal attachment strap is horizontal flush type attachment strap 3, and remaining structure is identical with embodiment one, Difference of banketing above only horizontal attachment strap and arc attachment strap.
Comprise the following steps during construction:
(1)When embankment filled soil 6 is constructed to certain altitude, laying oil immersion fiber cloth 10 and polyphenyl second after embankment filled soil 6 is compacted Alkene foam 7, now 6 upper surface of embankment filled soil have leave with 1 lower surface of arc attachment strap be adapted profile, as shown in Figure 5;
(2)Prefabricated arc attachment strap 1 is placed on 10 top of oil immersion fiber cloth, the end position of arc attachment strap 1 and polystyrene Foam 7 is contacted, as shown in Figure 6;
(3)Arc attachment strap 1 is prefabricated with connection reinforcing bar 8 towards one end of seamless abutment 5, in arc attachment strap 1 towards seamless abutment 5 Side is arranged builds false form 11, prepares the horizontal attachment strap of cast in situs, and false form 11 is with arc attachment strap 1 towards seamless abutment 5 end face leaves gap, as shown in Figure 7;
(4)The horizontal attachment strap of cast in situs, form removal after the completion of pouring, as shown in Figure 8;
(5)Horizontal attachment strap is formed after meeting intensity requirement, fills expansion joint (E.J.), and up lay upper strata oil immersion fiber in gap location Cloth 10, as shown in Figure 9;
(6)After the completion of upper strata oil immersion fiber cloth 10 is laid, proceed to banket, until supercrust 2, as shown in Figure 10.
In above-described embodiment, arc attachment strap is integrally slided in oil immersion fiber cloth 10, not easy to crack, the ductility ratio coagulation of reinforcing bar Native attachment strap is good, receives the rotational deformation of arc attachment strap with connection reinforcing bar, make use of material property well.Polystyrene foam 7 are placed in arc attachment strap below 1, and in the parcel of oil immersion fiber cloth, are located at horizontal flush type attachment strap with tradition or panel type is taken The expansion joint (E.J.) of plate rear end is compared, and more preferably, arc attachment strap 1 is in panel type attachment strap or horizontal flush type attachment strap end road pavement for its durability There is provided good transition, be conducive to alleviating the generation of differential settlement.
The term for representing position relationship or shape applied in arbitrary technical scheme disclosed in the invention described above is removed Otherwise indicated its implication outer includes approximate with which, similar or close state or shape.Finally it should be noted that:Above enforcement Example is only in order to illustrate technical scheme rather than a limitation;Although having carried out in detail to the present invention with reference to preferred embodiment Explanation, those of ordinary skill in the art should be understood:Still the specific embodiment of the present invention can be modified Or equivalent is carried out to some technical characteristics;Without deviating from the spirit of technical solution of the present invention, which all should be covered at this In the middle of the bright technical scheme scope being claimed.

Claims (9)

1. a kind of end using arc attachment strap seamless bridge neotectonics, it is characterised in that including seamless abutment and with seamless abutment The embankment filled soil of adjacent connection, is provided with horizontal attachment strap in the embankment filled soil, one end-rack of horizontal attachment strap is in seamless abutment Bracket on, the other end is connected with arc attachment strap, and the arc attachment strap is extended downwardly from seamless abutment to embankment filled soil direction.
2. a kind of end according to claim 1 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that the arc Through connecting bar connecting between shape attachment strap and horizontal attachment strap, between the arc attachment strap and horizontal attachment strap, expansion joint (E.J.) is left.
3. a kind of end according to claim 2 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that the arc Shape attachment strap has buffering froth bed between the end of seamless abutment and embankment filled soil.
4. a kind of end according to claim 3 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that the arc The periphery of shape attachment strap and buffering froth bed is provided with oil immersion fiber cloth.
5. a kind of end according to claim 1 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that the road Dike is provided with supercrust on banketing.
6. a kind of end according to Claims 1 to 5 any claim adopts the seamless bridge neotectonics of arc attachment strap, its It is characterised by, the horizontal attachment strap is panel type attachment strap or horizontal flush type attachment strap.
7. a kind of end according to claim 3 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that described slow Foam layer material is rushed for polystyrene foam.
8. a kind of end according to claim 3 is using the seamless bridge neotectonics of arc attachment strap, it is characterised in that arc is taken The central angle of plate is 45 °.
9. a kind of manufacture end as claimed in claim 4 is using the construction method of the seamless bridge neotectonics of arc attachment strap, its feature It is, comprises the following steps:
(1)When embankment filled soil is constructed to certain altitude, by laying oil immersion fiber cloth and polystyrene foam after fill compaction, this When embankment filled soil upper surface have leave with arc attachment strap lower surface be adapted profile;
(2)Prefabricated arc attachment strap is placed on above oil immersion fiber cloth, the end position of arc attachment strap and polystyrene foam Contact;
(3)Arc attachment strap is prefabricated with connection reinforcing bar towards one end of seamless abutment, arc attachment strap towards seamless abutment side False form is built in setting, prepares the horizontal attachment strap of cast in situs, and false form is stayed towards the end face of seamless abutment with arc attachment strap There is gap;
(4)The horizontal attachment strap of cast in situs, form removal after the completion of pouring;
(5)Horizontal attachment strap is formed after meeting intensity requirement, fills expansion joint (E.J.), and up lay upper strata oil immersion fiber in gap location Cloth;
(6)After the completion of the laying of upper strata oil immersion fiber cloth, proceed to banket, until road surface.
CN201611184518.0A 2016-12-20 2016-12-20 A kind of end is constructed using the seamless bridge of arc attachment strap and its construction method Active CN106480821B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611184518.0A CN106480821B (en) 2016-12-20 2016-12-20 A kind of end is constructed using the seamless bridge of arc attachment strap and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611184518.0A CN106480821B (en) 2016-12-20 2016-12-20 A kind of end is constructed using the seamless bridge of arc attachment strap and its construction method

Publications (2)

Publication Number Publication Date
CN106480821A true CN106480821A (en) 2017-03-08
CN106480821B CN106480821B (en) 2018-03-16

Family

ID=58284817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611184518.0A Active CN106480821B (en) 2016-12-20 2016-12-20 A kind of end is constructed using the seamless bridge of arc attachment strap and its construction method

Country Status (1)

Country Link
CN (1) CN106480821B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587420A (en) * 2017-08-01 2018-01-16 温州华隆建设有限公司 A kind of abutment approach pavement structure and its construction method
CN110093850A (en) * 2019-06-20 2019-08-06 福州大学 A kind of seamless bridge corbel back slab construction and its construction method with X-shaped steel muscle
CN111074762A (en) * 2019-12-11 2020-04-28 南通大学 Seamless expansion joint of compound concrete bridge face of carbon cloth

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2533153Y (en) * 2002-03-20 2003-01-29 宁波市城市建设设计院 Bridge approach capable of preventing car from skipping
US20050241084A1 (en) * 2004-04-21 2005-11-03 State Of California, Department Of Transportation Seismic joint seal
CN2853885Y (en) * 2005-12-30 2007-01-03 衡水宝力工程橡胶有限公司 Arc type bridge expansion device
CN103122605A (en) * 2013-03-24 2013-05-29 宁波市镇海怡福莱文化创意有限公司 Bridge end transition slab
CN103614961A (en) * 2013-12-12 2014-03-05 西藏大学农牧学院 Stepped reinforced concrete slab capable of preventing abutment vehicle skips and construction method
CN205012214U (en) * 2015-09-09 2016-02-03 盐城工学院 Chain formula attachment strap structure based on seamless bridge
CN206486803U (en) * 2016-12-20 2017-09-12 福州大学 A kind of end uses the seamless bridge neotectonics of arc attachment strap

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2533153Y (en) * 2002-03-20 2003-01-29 宁波市城市建设设计院 Bridge approach capable of preventing car from skipping
US20050241084A1 (en) * 2004-04-21 2005-11-03 State Of California, Department Of Transportation Seismic joint seal
CN2853885Y (en) * 2005-12-30 2007-01-03 衡水宝力工程橡胶有限公司 Arc type bridge expansion device
CN103122605A (en) * 2013-03-24 2013-05-29 宁波市镇海怡福莱文化创意有限公司 Bridge end transition slab
CN103614961A (en) * 2013-12-12 2014-03-05 西藏大学农牧学院 Stepped reinforced concrete slab capable of preventing abutment vehicle skips and construction method
CN205012214U (en) * 2015-09-09 2016-02-03 盐城工学院 Chain formula attachment strap structure based on seamless bridge
CN206486803U (en) * 2016-12-20 2017-09-12 福州大学 A kind of end uses the seamless bridge neotectonics of arc attachment strap

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587420A (en) * 2017-08-01 2018-01-16 温州华隆建设有限公司 A kind of abutment approach pavement structure and its construction method
CN110093850A (en) * 2019-06-20 2019-08-06 福州大学 A kind of seamless bridge corbel back slab construction and its construction method with X-shaped steel muscle
CN111074762A (en) * 2019-12-11 2020-04-28 南通大学 Seamless expansion joint of compound concrete bridge face of carbon cloth
CN111074762B (en) * 2019-12-11 2021-08-31 南通大学 Seamless expansion joint of compound concrete bridge face of carbon cloth

Also Published As

Publication number Publication date
CN106480821B (en) 2018-03-16

Similar Documents

Publication Publication Date Title
WO2017185906A1 (en) Transitional structure for turnout and non-turnout zones in low-set, mid-to-low speed magnetic levitation lines
CN204551241U (en) A kind of crack resistance type seamless bridge bridge abutment structure with X muscle
CN105887586A (en) Low implantation line double-wire section terminal spine type bearing rail beam limiting structure in medium and low speed magnetic levitation transportation engineering
CN106480821A (en) A kind of end is using seamless bridge neotectonics and its construction method of arc attachment strap
CN205276086U (en) Expansion joint device is handled to combined type road surface tip
CN206941325U (en) The newly-built peg board formula roadbed of girder construction system in length and breadth
CN105821725A (en) Intra-segment limit structure for bearing-trail beams at double-line section of middle-low speed magnetic levitation traffic engineering low-laying line
CN105926380A (en) Limiting structure between terminal spine type rail bearing beam joints of single-line segment for medium-low-speed magnetic levitation traffic engineering low-arranged line
CN105951535B (en) Middle low speed magnetic suspension traffic engineering is low to put circuit single line location support rail beam internode position limiting structure
CN207017093U (en) New-old concrete bond widens seam-line removal structure
CN105178171B (en) Chain type butt strap structure based on seamless bridge
CN206486803U (en) A kind of end uses the seamless bridge neotectonics of arc attachment strap
CN104499425A (en) Structure and construction process for reducing power impact response at back of seamless bridge abutment
CN104213500B (en) Based on the jointless bridge and the construction method thereof that arrange domes after platform
CN206298820U (en) It is used to receive the U-shaped seal sleeve structure of seamless bridge attachment strap end displacement
CN204475161U (en) Arch reinforcing bar between beam-ends and abutment is put more energy into type seamless process stretching device
CN206298822U (en) The seamless pavement structure that optimization CRCP is connected with floorings
CN110230255A (en) The novel whole bridge corbel back slab of one kind and its construction method
CN205603974U (en) Low circuit single line location support rail girder segment limit structure within a definite time that puts of well low -speed maglev traffic engineering
CN105113384A (en) Z-shaped bridge end transition slab structure and construction method thereof
CN206298821U (en) Simply supported girder bridge composite connection board is constructed
CN205474609U (en) A joggle formula support rail girder construction that is arranged in low circuit of putting of low -speed maglev traffic engineering
CN209384097U (en) A kind of Simple telescopic crack structure
CN204185754U (en) A kind of jointless bridge based on arranging domes after platform
CN203256597U (en) Novel seamless bridge structure comprising swing beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant