一种煤与瓦斯协调开采方法 Download PDFInfo
- Publication number
- CN106468177A CN106468177A CN201510512099.8A CN201510512099A CN106468177A CN 106468177 A CN106468177 A CN 106468177A CN 201510512099 A CN201510512099 A CN 201510512099A CN 106468177 A CN106468177 A CN 106468177A
- Authority
- CN
- China
- Prior art keywords
- gas
- extraction
- coal
- work surface
- haulage way
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000605 extraction Methods 0.000 title claims abstract description 40
- 239000003245 coal Substances 0.000 title claims abstract description 27
- 238000004519 manufacturing process Methods 0.000 claims abstract description 13
- 238000005086 pumping Methods 0.000 claims abstract description 13
- 238000007789 sealing Methods 0.000 claims description 12
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 claims description 6
- 241001101720 Murgantia histrionica Species 0.000 claims description 3
- 238000000034 method Methods 0.000 claims description 3
- 230000005641 tunneling Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 6
- 238000005553 drilling Methods 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 208000019901 Anxiety disease Diseases 0.000 description 1
- 230000036506 anxiety Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F7/00—Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
一种煤与瓦斯协调开采方法,涉及煤矿采掘与瓦斯抽采领域。在运输平巷中向本区段和下邻近区段沿煤层走向布置多条平行顺层钻孔,并与抽采管路联通对上、下区段的区域煤层进行瓦斯抽采;抽采结束后,掘进本区段的回风平巷,同时掘进下区段的运输平巷;掘进完成后进行本工作面回采;重复上述步骤直至完成所有区段煤层的开采;其有益效果为:节省了瓦斯总的抽采时间,加快了煤巷掘进速度,实现采、掘、抽平衡,提高了生产效率。
Description
技术领域
本发明涉及煤矿采掘与瓦斯抽采领域。尤其是适用于无保护层开采的一种煤与瓦斯协调开采方法。
背景技术
近年来随着开采深度的增加,煤层瓦斯压力逐渐增高,瓦斯含量逐渐变大,地应力也同时增大,煤与瓦斯突出的危险性日趋严重。煤矿瓦斯治理必须本着区域防突措施先行的原则,即开采保护层和预抽煤层瓦斯。然而,对于无保护层的煤层而言,只能采取预抽煤层瓦斯的措施。
对于低透气性又无保护层的突出煤层,地面井抽采和穿层钻孔抽采是应当优先选择的方式之一,但是工程量大,成本高,施工时间长,有时地面井抽采范围小,穿层钻孔岩石层位不易选,穿层抽采后有时还必须采取顺层钻孔进行补充抽采等等问题;在突出煤层巷道掘进中,顺层条带预抽煤层瓦斯的方式,虽然也是行之有效的方式,但严重影响着巷道的掘进速度。
发明内容
技术问题:本发明的目的是克服已有技术中的不足之处,提出工程量小,成本低,加快瓦斯总抽采时间,同时不影响抽采效果、又能够保证掘进速度的一种煤与瓦斯协调开采方法。
技术方案:本发明的一种煤与瓦斯协调开采方法,包括以下步骤:
a.提前掘出运输平巷,在运输平巷中向工作面和沿煤层走向布置多条平行顺层钻孔,顺层钻孔要超出回风平巷和运输平巷巷道轮廓线以外15-30m的距离,用封孔管对顺层钻孔进行封孔,并连接瓦斯抽采管路,进行瓦斯抽采;
b.当工作面和中煤层的残余瓦斯压力降到0.65MPa以下或残余瓦斯含量降至7m3/t以下时,从运输平巷掘出切眼,再由切眼掘进回风平巷,同时掘进下区段运输平巷。掘进期间可用封孔管对顺层钻孔再次封孔,运输平巷仍继续抽采上、下工作面和瓦斯,从而增加工作面区域瓦斯抽采时间,实现掘进与抽采平行作业,直至掘进完成。
c.当工作面形成即可进行回采,同时由于工作面已经消除煤与瓦斯突出危险性,运输平巷仅需沿煤层走向布置多条平行顺层钻孔抽放下区段瓦斯,且抽采与工作面的回采可平行作业。
d.重复上述步骤掘出新工作面并进行回采,同时进行新的区段瓦斯抽采,直至完成煤层的开采。所述顺层钻孔(2)的封孔长度8m-10m,顺层钻孔(2)间排距为1m~3m,顺层钻孔(2)的直径为75mm~110mm。
有益技术效果:1、本发明可以省去瓦斯抽放岩石巷道,减少岩巷掘进工程量,降低了生产成本;2、对上、下区段煤层瓦斯同时实施抽采,瓦斯总抽采时间降低一半;3、上区段的回风平巷和下区段的运输平巷同时掘进,掘进速度加快了1倍,且掘进期间,仍可继续抽采上下区段工作面的瓦斯,掘进与抽采平行作业,延长了工作面抽采时间;4、在上区段回采的同时,通过下区段运输平巷抽采临近区段煤层瓦斯,采煤与抽采平行作业,为下区段平巷掘进赢得时间,实现采、掘、抽平衡,缓解了区段接续紧张,提高了生产效率。。
附图说明
图1是本发明一种煤与瓦斯协调开采方法示意图。
图1中:1-上区段运输平巷,2-顺层钻孔,3-上区段工作面开切眼,4-上区段回风平巷,5-下区段运输平巷,6-上区段工作面,7-采空区,8-煤柱,9-下区段工作面切眼,10-下区段回风平巷。
具体实施方式
如图1所示,本发明的一种煤与瓦斯协调开采方法,包括如下步骤:提前掘出运输平巷(1),在运输平巷(1)中向工作面(6)和(12)沿煤层走向布置多条平行顺层钻孔(2),顺层钻孔(2)要超出回风平巷(4)和运输平巷(5)巷道轮廓线以外15-30m的距离,用封孔管对顺层钻孔(2)进行封孔,并连接瓦斯抽采管路,进行瓦斯抽采;
b.当工作面(6)和(12)中煤层的残余瓦斯压力降到0.65MPa以下或残余瓦斯含量降至7m3/t以下时,从运输平巷(1)掘出切眼(3),再由切眼(3)掘进回风平巷(4),同时掘进下区段运输平巷(5)。掘进期间可用封孔管对顺层钻孔(2)再次封孔,运输平巷(1)仍继续抽采上、下工作面(6)和(12)瓦斯,从而增加工作面区域瓦斯抽采时间,实现掘进与抽采平行作业,直至掘进完成。
c.当工作面(6)形成即可进行回采,同时由于工作面(12)已经消除煤与瓦斯突出危险性,运输平巷(5)仅需沿煤层走向布置多条平行顺层钻孔(2)抽放下区段瓦斯,且抽采与工作面(6)的回采可平行作业。
d.重复上述步骤掘出新工作面并进行回采,同时进行新的区段瓦斯抽采,直至完成煤层的开采。
所述顺层钻孔(2)的封孔长度8m-10m,顺层钻孔(2)间排距为1m~3m,顺层钻孔(2)的直径为75mm~110mm。
Claims (2)
1.一种煤与瓦斯协调开采方法,其特征在于:所述巷道掘进与瓦斯抽采方法包括以下步骤:
a提前掘出运输平巷(1),在运输平巷(1)中向工作面(6)和(12)沿煤层走向布置多条平行顺层钻孔(2),顺层钻孔(2)超出回风平巷(4)和运输平巷(5)巷道轮廓线外15-30m的距离,用封孔管对顺层钻孔(2)进行封孔,并连接瓦斯抽采管路,进行瓦斯抽采;
b.当工作面(6)和(12)中煤层的残余瓦斯压力降到0.65MPa以下或残余瓦斯含量降至7m3/t以下时,从运输平巷(1)掘出切眼(3),再由切眼(3)掘进回风平巷(4),同时掘进下区段运输平巷(5);掘进期间可用封孔管对顺层钻孔(2)再次封孔,运输平巷(1)仍继续抽采上、下工作面(6)和(12)瓦斯,从而增加工作面区域瓦斯抽采时间,实现掘进与抽采平行作业,直至掘进完成。
c.当工作面(6)形成即可进行回采,同时由于工作面(12)已经消除煤与瓦斯突出危险性,运输平巷(5)仅需沿煤层走向布置多条平行顺层钻孔(2)抽放下区段瓦斯,且抽采与工作面(6)的回采可平行作业。
d.重复上述步骤掘出新工作面并进行回采,同时进行新的区段瓦斯抽采,直至完成煤层的开采;
2.根据权利要求1所述的一种煤与瓦斯协调开采方法,其特征在于:所述顺层钻孔(2)的封孔长度为8m-10m,顺层钻孔(2)间排距为1m~3m,顺层钻孔(2)的直径为75mm~110mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510512099.8A CN106468177A (zh) | 2015-08-14 | 2015-08-14 | 一种煤与瓦斯协调开采方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510512099.8A CN106468177A (zh) | 2015-08-14 | 2015-08-14 | 一种煤与瓦斯协调开采方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106468177A true CN106468177A (zh) | 2017-03-01 |
Family
ID=58213801
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510512099.8A Pending CN106468177A (zh) | 2015-08-14 | 2015-08-14 | 一种煤与瓦斯协调开采方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106468177A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109736876A (zh) * | 2018-12-19 | 2019-05-10 | 中煤科工集团重庆研究院有限公司 | 采动体涌出瓦斯顶板大直径定向长钻孔抽采方法 |
CN110836114A (zh) * | 2019-11-21 | 2020-02-25 | 中煤科工集团重庆研究院有限公司 | 一种煤矿冲击地压与瓦斯复合灾害的治理方法 |
CN110905505A (zh) * | 2019-11-28 | 2020-03-24 | 辽宁工程技术大学 | 一种基于二氧化碳爆破的煤炭开采方法 |
CN111456794A (zh) * | 2020-04-20 | 2020-07-28 | 北京中矿创新联盟能源环境科学研究院 | 用于采煤区的通风方法 |
CN112253240A (zh) * | 2020-10-10 | 2021-01-22 | 安徽理工大学 | 一种高瓦斯工作面采空区密闭封存方法 |
CN114263493A (zh) * | 2021-12-28 | 2022-04-01 | 贵州盘江精煤股份有限公司 | 一种采煤工作面下区段瓦斯治理方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102352769A (zh) * | 2011-10-21 | 2012-02-15 | 河南煤业化工集团研究院有限责任公司 | 高突矿井煤与瓦斯共采一体化开采方法 |
CN102587960A (zh) * | 2012-03-22 | 2012-07-18 | 中国矿业大学 | 一种高瓦斯煤层回采工作面巷道的布置方法 |
RU2011128115A (ru) * | 2011-07-07 | 2013-01-20 | Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН | Способ дегазации угольного пласта |
CN103670496A (zh) * | 2013-12-12 | 2014-03-26 | 中国矿业大学 | 单一低透气性突出煤层沿空留巷与预抽区段煤层瓦斯方法 |
CN104018874A (zh) * | 2014-06-13 | 2014-09-03 | 中煤科工集团重庆研究院有限公司 | 一种顺层钻孔预抽工作面瓦斯的方法 |
-
2015
- 2015-08-14 CN CN201510512099.8A patent/CN106468177A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2011128115A (ru) * | 2011-07-07 | 2013-01-20 | Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН | Способ дегазации угольного пласта |
CN102352769A (zh) * | 2011-10-21 | 2012-02-15 | 河南煤业化工集团研究院有限责任公司 | 高突矿井煤与瓦斯共采一体化开采方法 |
CN102587960A (zh) * | 2012-03-22 | 2012-07-18 | 中国矿业大学 | 一种高瓦斯煤层回采工作面巷道的布置方法 |
CN103670496A (zh) * | 2013-12-12 | 2014-03-26 | 中国矿业大学 | 单一低透气性突出煤层沿空留巷与预抽区段煤层瓦斯方法 |
CN104018874A (zh) * | 2014-06-13 | 2014-09-03 | 中煤科工集团重庆研究院有限公司 | 一种顺层钻孔预抽工作面瓦斯的方法 |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109736876A (zh) * | 2018-12-19 | 2019-05-10 | 中煤科工集团重庆研究院有限公司 | 采动体涌出瓦斯顶板大直径定向长钻孔抽采方法 |
CN110836114A (zh) * | 2019-11-21 | 2020-02-25 | 中煤科工集团重庆研究院有限公司 | 一种煤矿冲击地压与瓦斯复合灾害的治理方法 |
CN110905505A (zh) * | 2019-11-28 | 2020-03-24 | 辽宁工程技术大学 | 一种基于二氧化碳爆破的煤炭开采方法 |
CN111456794A (zh) * | 2020-04-20 | 2020-07-28 | 北京中矿创新联盟能源环境科学研究院 | 用于采煤区的通风方法 |
CN111456794B (zh) * | 2020-04-20 | 2020-12-18 | 北京中矿创新联盟能源环境科学研究院 | 用于采煤区的通风方法 |
CN112253240A (zh) * | 2020-10-10 | 2021-01-22 | 安徽理工大学 | 一种高瓦斯工作面采空区密闭封存方法 |
CN114263493A (zh) * | 2021-12-28 | 2022-04-01 | 贵州盘江精煤股份有限公司 | 一种采煤工作面下区段瓦斯治理方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103670496B (zh) | 单一低透气性突出煤层沿空留巷与预抽区段煤层瓦斯方法 | |
CN106468177A (zh) | 一种煤与瓦斯协调开采方法 | |
CN101915083B (zh) | 煤矿井上下联合抽采煤层气的方法 | |
CN104533416B (zh) | 极厚大矿体大规模机械化无底柱分段崩落采矿方法 | |
CN104481539B (zh) | 自拉槽挤压爆破崩落采矿法 | |
US8820847B2 (en) | Block caving method | |
CN108397227A (zh) | 一种倾向递进消突巷道布置方法 | |
CN104481578B (zh) | 一种高瓦斯煤层大采高工作面瓦斯治理方法 | |
CN107975373B (zh) | 一种液气相变诱导下机械化连续采掘硬岩矿方法 | |
CN101737047A (zh) | 一种急倾斜薄煤层的采煤方法 | |
CN104775819A (zh) | 一种深部倾斜煤层回采巷道矿压控制开采方法 | |
CN109882175B (zh) | 实现一巷三用的工作面回采与停采设备回撤的协同作业方法 | |
CN102777180A (zh) | 一种煤矿主动式区域性防治冲击地压的方法 | |
CN104832176A (zh) | 一种低透气性煤层群卸压瓦斯抽采高抽巷的一巷多用布置方法 | |
CN102587960A (zh) | 一种高瓦斯煤层回采工作面巷道的布置方法 | |
CN114215530B (zh) | 一种坚硬顶板定向水压致裂沿空巷道快速掘巷方法 | |
CN102678166B (zh) | 单一厚煤层区域增透提高瓦斯抽采率的方法 | |
CN108505999A (zh) | 一种高突煤层工作面多巷布置方法 | |
CN108506000A (zh) | 一种突出煤层平巷快速掘进方法 | |
CN110030013A (zh) | 一种过渡支架区三缝周期切顶自成巷帮的沿空留巷方法 | |
CN105649633A (zh) | 一种定向钻孔劈岩成硐法 | |
CN110966005A (zh) | 一种新型中深孔落矿阶段矿房法 | |
CN101042051B (zh) | 无底柱分段崩落法首采分段回采进路的布置方法 | |
CN108952725A (zh) | 一种适用于缓倾斜薄矿体的低贫化采矿方法 | |
CN101737051A (zh) | 一种盲矿体覆盖层形成方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170301 |
|
WD01 | Invention patent application deemed withdrawn after publication |