CN106438605B - A kind of the jacking auxiliary device and jack-up construction method of vertical equipment - Google Patents

A kind of the jacking auxiliary device and jack-up construction method of vertical equipment Download PDF

Info

Publication number
CN106438605B
CN106438605B CN201610937297.3A CN201610937297A CN106438605B CN 106438605 B CN106438605 B CN 106438605B CN 201610937297 A CN201610937297 A CN 201610937297A CN 106438605 B CN106438605 B CN 106438605B
Authority
CN
China
Prior art keywords
jacking
clamp structure
equipment
support construction
clamp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610937297.3A
Other languages
Chinese (zh)
Other versions
CN106438605A (en
Inventor
黄正斌
朱金孝
郝长山
王刚
赵坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ji'nan Fenghui Technology Co Ltd
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
Ji'nan Fenghui Technology Co Ltd
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ji'nan Fenghui Technology Co Ltd, SEPCO1 Electric Power Construction Co Ltd filed Critical Ji'nan Fenghui Technology Co Ltd
Priority to CN201610937297.3A priority Critical patent/CN106438605B/en
Publication of CN106438605A publication Critical patent/CN106438605A/en
Application granted granted Critical
Publication of CN106438605B publication Critical patent/CN106438605B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B2/00Friction-grip releasable fastenings
    • F16B2/02Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening
    • F16B2/06Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening external, i.e. with contracting action
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F3/00Devices, e.g. jacks, adapted for uninterrupted lifting of loads

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of jacking auxiliary device of vertical equipment and jack-up construction methods, including the first clamp structure, the second clamp structure, locking mechanism and jacking support construction, wherein, the working face for jacking support construction is plane, provides the jacking face contacted with climbing structure;First clamp structure and the second clamp structure are mounted on the side of jacking support construction, and the working face of the first clamp structure and the second clamp structure is outer male structure, and the two is opposite to be installed, and constitute the space for accommodating equipment supporting leg;Locking mechanism is mounted between the first clamp structure and the second clamp structure, and the relative position of the first clamp structure and the second clamp structure is fixed.It is fixed on jacking support construction on equipment supporting leg.It is conveniently fixed on the supporting leg of equipment by the first clamp structure and the second clamp structure by support construction is jacked, jacking apparatus is installed in the lower end of jacking support construction, jacking apparatus exerts a force simultaneously, equipment can smoothly be jacked at the position of setting.

Description

A kind of the jacking auxiliary device and jack-up construction method of vertical equipment
Technical field
Present invention relates particularly to a kind of jacking auxiliary device of vertical equipment and jack-up construction methods.
Background technique
It is vertical that the precision processing of large nuclear-power and fired power generating unit and specialty chemical relevant device are usually that volume is big, weight is big Case jar structure, such as: mixed bed, poplar bed etc..The prior art is usually that suspension centre is arranged above equipment on-station position, and equipment arrives at just Behind the position of position, equipment is assisted in place using chain block etc..
When large equipment in place being installed using conventional method, often " top-heavy " due to such equipment feature, and one As belong to line with rubber, lining plastic or stainless steel equipment, such equipment do not allow weld support construction.And such equipment is installed at the scene When, often due to design is limited with regard to bit space, after causing such equipment to enter workshop or arrive at installation site, without suitable Suspension centre work in place to complete the installation of equipment.In this case it is necessary to using above on-station position welded steel beam, hang The arrangement work of the means such as disk or floor with opening completion suspension centre.In hoisting process, equipment is also easy to shake, due to setting It is standby that and volume is big from great, equipment shake can people to surrounding and object generate some potential safety problems.So using When these methods, risk factor increases, and safety coefficient reduces, meanwhile, larger, consuming is destroyed to completed civil engineering operation finished product It is artificial more.
Summary of the invention
For the technical problems in the prior art, it is an object of the present invention to provide a kind of jackings of vertical equipment Auxiliary device, the positioning apparatus may be implemented the integral jacking of large equipment, jack from bottom to top, avoid in a limited space Use Large-scale Hoisting equipment.
A second object of the present invention is to provide a kind of jack-up construction methods of vertical equipment.It assists filling using above-mentioned jacking It sets and constructs, it is interior in a limited space to ensure that the accuracy that equipment is installed in place.
In order to solve the above technical problems, the technical solution of the present invention is as follows:
A kind of jacking auxiliary device of vertical equipment, including the first clamp structure, the second clamp structure, locking mechanism and top Ascending branch support structure, wherein
The working face for jacking support construction is plane, provides the jacking face contacted with climbing structure;
First clamp structure and the second clamp structure are mounted on the side of jacking support construction, the first clamp structure and second The working face of clamp structure is outer male structure, and the two is opposite to be installed, and constitutes the space for accommodating equipment supporting leg;
Locking mechanism is mounted between the first clamp structure and the second clamp structure, and the first clamp structure and second are clamped The relative position of structure is fixed, and is fixed on jacking support construction on equipment supporting leg.
Multiple jacking support constructions are fixed on the different supporting legs of equipment, in the lower section of the working face of jacking support construction The climbing structures such as jack are placed, climbing structure work can jack up jacking support construction, and it is related to jack up equipment supporting leg, And then jack equipment to setting position, equipment is installed ready.
Since, there are larger space, the present invention makes full use of this segment space, between the legs cloth between the supporting leg of equipment If jack-up system jacks equipment, the use using Large-scale Hoisting equipment is avoided, completion equipment is installed same in place When, realize the accuracy of equipment jacking.In order to guarantee the balance of equipment jacking, positioning apparatus can be symmetrically mounted at The lower section of equipment makes each position of equipment while jacking, can be to avoid people and object of the unstable promotion to surrounding of equipment Generate security risk.
Preferably, first clamp structure and the second clamp structure are anchor ears, and the working face of the two is the arc of evagination Shape.
Since supporting leg is usually cylindrical structure, the contact area between supporting leg is can be improved in the arcuate structure of evagination, In the case that the coefficient of friction of chucking power and supporting leg surface that first clamp structure and the second clamp structure apply is certain, clamping knot The stiction formed between structure and supporting leg is larger, it is ensured that the safety jacking of equipment.
It is further preferred that the jacking support construction is plate structure, the first clamp structure and the second clamp structure hinge It connects in the side of jacking support construction.
First clamp structure and the second clamp structure are hinged on the side of jacking support construction, facilitate adjusting the first clamping knot Openings of sizes between structure and the second clamp structure facilitates and jacking support construction is fixed on the supporting leg of equipment.
Preferably, first clamp structure and the second clamp structure include interconnecting piece, work department and support portion, work The working face in portion is the arc of evagination, and interconnecting piece and support portion are located at the both ends of work department, the lock are arranged on interconnecting piece Locking structure is fixedly connected between support portion and the jacking support construction.
It is further preferred that the jacking support construction is plate structure, on the fixed support portion of the plate structure.
It is further preferred that the interconnecting piece is laminated structure, the locking mechanism is bolt.
The jacking installation method carried out using the positioning apparatus of above-mentioned vertical equipment, is included the following steps:
1) opening between the first clamp structure and the second clamp structure is tuned up, the supporting leg of vertical equipment is put into the first folder It holds in the space between structure and the second clamp structure, turns the opening between the first clamp structure and the second clamp structure down, make The supporting leg of equipment and the working face of the first clamp structure and the second clamp structure fit closely, and pass through locking mechanism locking first Opening between clamp structure and the second clamp structure, at this point, jacking support construction is located at the side of the supporting leg of equipment, jacking branch The lower surface of support structure and horizontal direction parallel are arranged;
2) and so on, the positioning apparatus is all installed on all supporting legs of equipment, locking mechanism is by adjusting first Opening between clamp structure and the second clamp structure adjusts the first clamp structure and the second clamp structure to the folder of equipment supporting leg Holding force, so that upward frictional force suffered by equipment supporting leg is greater than the gravity of equipment itself during equipment jacking;
3) jack, the lower surface of jack and jacking support construction are respectively mounted in the lower end of all jacking support constructions Contact starts jack, applies upward active force to jacking support construction, equipment is jacked up.
Advantageous effects of the invention are as follows:
Jacking support construction can be conveniently fixed in by the first clamp structure and the second clamp structure and be set by the present invention On standby supporting leg, jacking apparatus is installed in the lower end of jacking support construction, such as jack, jacking apparatus exert a force simultaneously, it can be with Equipment is smoothly jacked at the position of setting.
Since there are biggish spaces between the supporting leg of equipment, the volume for jacking support construction is not too large, greatlys save Space needed for Lifting Equipment.
The shape of the working face of the evagination of first clamp structure and the second clamp structure can be according to the shape of the supporting leg of equipment Shape is adjusted, and has extensive promotional value.
The positioning apparatus is respectively mounted at all supporting legs of vertical case tank equipment, all jacking support constructions constitute one A jacking plane, which is located at the leg location of vertical case tank equipment, and substantially completely covers vertical case tank and set The standby plane covered, i.e., the center of gravity of vertical case tank equipment do not deviate by the jacking plane that jacking support construction is constituted, ensure that The stability of jacking;The jacking plane that jacking support construction is constituted is located at the lower section of vertical case tank, from bottom to top Lifting Equipment, nothing Large-scale hanging device, the jacking assembly of the equipment suitable for small space need to be set in the top of equipment;It is supported in jacking The multiple positions for the jacking plane that structure is constituted jack simultaneously, can be ensure that same flat by the amount of feeding of control jack The error in face is no more than 3mm, compared to the lifting of Large-scale Hoisting equipment, substantially increases the precision of the jacking installation of vertical case tank Degree.
Detailed description of the invention
Fig. 1 is mounting structure schematic diagram of the invention;
Fig. 2 is structural schematic diagram of the invention;
Fig. 3 is main view schematic diagram of the invention.
Wherein, 1, clamping screw, 2, jacking support construction, the 3, first clamp structure, the 4, second clamp structure, 5, jacking it is auxiliary Help device.
Specific embodiment
The present invention is further explained in the light of specific embodiments.
Embodiment 1
As shown in Figures 2 and 3, the jacking auxiliary device of a kind of vertical equipment, including the clamping of the first clamp structure 3, second Structure 4, locking mechanism and jacking support construction 2, wherein
The working face for jacking support construction 2 is plane, provides the jacking face contacted with climbing structure;
First clamp structure 3 and the second clamp structure 4 are mounted on the side of jacking support construction 2,3 He of the first clamp structure The working face of second clamp structure 4 is outer male structure, and the two is opposite to be installed, and constitutes the space for accommodating equipment supporting leg;
Locking mechanism is mounted between the first clamp structure 3 and the second clamp structure 4, by the first clamp structure 3 and second The relative position of clamp structure 4 is fixed, and is fixed on jacking support construction 2 on equipment supporting leg.
As shown in Figure 1, multiple above-mentioned jacking auxiliary devices 5 are fixed on the different supporting legs of equipment, as much as possible, setting It is respectively mounted above-mentioned jacking auxiliary device 5 on standby all supporting legs, places jack in the lower section of the working face of jacking support construction 2 Equal climbing structures, climbing structure work can jack up jacking support construction 2, related to jack up equipment supporting leg, and then by equipment It jacks to setting position, equipment is installed ready.Jacking auxiliary device 5 is respectively mounted on all supporting legs, jack is same simultaneously Work is walked, jacking auxiliary device 5 can smoothly be jacked.
First clamp structure 3 and the second clamp structure 4 are anchor ears, and the working face of the two is the arc of evagination, the structure It is suitable for cylindrical equipment supporting leg.Jacking support construction 2 is plate structure, the first clamp structure 3 and the second clamp structure 4 It is hinged on the side of jacking support construction.First clamp structure 3 and the second clamp structure 4 can be in certain angular ranges It is rotated relative to jacking support construction 2, adjusts the opening angle between the first clamp structure 3 and the second clamp structure 4.Convenient for inciting somebody to action Equipment supporting leg is linked between the first clamp structure 3 and the second clamp structure 4.Locking mechanism is clamping screw 1, can be by first The opening of clamp structure 3 and the second clamp structure 4 is locked.
Embodiment 2
As another embodiment, the first clamp structure 3 and the second clamp structure 4 include interconnecting piece, work department and Support portion, the working face of work department are the arc (can also be adjusted according to the concrete shape of supporting leg) of evagination, interconnecting piece and Support portion is located at the both ends of work department, and the locking mechanism, support portion and the jacking support construction are arranged on interconnecting piece Between be fixedly connected.The jacking support construction 2 is plate structure, on the fixed support portion of the plate structure.
The interconnecting piece is laminated structure, and laminated structure is provided with hole, and the locking mechanism is clamping screw 1, Clamping screw 1 passes through hole, cooperates with nut, by adjusting the positional relationship of the two, adjusts the first clamp structure 3 and the second clamping Openings of sizes between structure 4.
Locking mechanism can also be other structures, such as: the open end of the first clamp structure 3 is hinged with engaging button, the The open end of two clamp structures 4 is provided with protrusion, can be by the first clamp structure 3 when which is fastened in protrusion It is fixed with the opening of the second clamp structure 4.
At this point, the opening angle between the first clamp structure 3 and the second clamp structure 4 is not easy to adjust, need to apply outer Opening angle between first clamp structure 3 and the second clamp structure 4 is tuned up, positioning apparatus 5 is fastened on to the branch of equipment by power On leg.
Jacking auxiliary device is arranged according to the quantity of equipment supporting leg, when equipment is transported to above Equipment Foundations by slideway Afterwards, the jack by adjusting 2 lower section of jacking support construction jacks up equipment, it is noted that jack operation will synchronize, and jack up Cheng Zhong places scale in very heavy top side face and controls jack stroke, guarantees jack synchronization of jacking up, and same plane error is no more than 3mm.Equipment extracts the delivery slideway below equipment out after jacking up.Synchronous landing jack, until equipment is in place in base position.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not to invention protection scope Limitation, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not required to It is still within the scope of the present invention to make the creative labor the various modifications or changes that can be made.

Claims (5)

1. a kind of big part vertical equipment jacking method, it is characterised in that: this method based on jacking auxiliary device include first folder Hold structure, the second clamp structure, locking mechanism and jacking support construction, jack support construction working face be plane, provide with The jacking face of climbing structure contact;First clamp structure and the second clamp structure be mounted on jacking support construction side, first The working face of clamp structure and the second clamp structure is outer male structure, and the two is opposite to be installed, and constitutes the sky for accommodating equipment supporting leg Between;Locking mechanism is mounted between the first clamp structure and the second clamp structure, by the first clamp structure and the second clamp structure Relative position fix, make jack support construction be fixed on equipment supporting leg;Multiple jacking support constructions are fixed on equipment On different supporting legs, climbing structure is placed in the lower section of the working face of jacking support construction, climbing structure work can be by jacking branch Support structure jacks up, related to jack up equipment supporting leg, and then equipment is jacked to setting position, equipment is installed ready;Described One clamp structure and the second clamp structure are anchor ears, and the working face of the two is the arc of evagination;The jacking support construction is Plate structure, the first clamp structure and the second clamp structure are hinged on the side of jacking support construction;First clamp structure and Two clamp structures, relative to jacking support construction rotation, adjust the first clamp structure and the second folder in certain angular range Hold the opening angle between structure;
This method comprises the following steps:
1) using the space between the supporting leg of big part vertical equipment, jacking is laid respectively on the different supporting legs of big part vertical equipment Auxiliary device tunes up the opening between the first clamp structure and the second clamp structure, and the supporting leg of equipment is put into the first clamping knot In space between structure and the second clamp structure, turns the opening between the first clamp structure and the second clamp structure down, make equipment The working face of supporting leg and the first clamp structure and the second clamp structure fit closely, and pass through the first clamping of locking mechanism locking Opening between structure and the second clamp structure, at this point, jacking support construction is located at the side of the supporting leg of equipment, jacking support knot The lower surface of structure and horizontal direction parallel are arranged;
2) and so on, all installation jacking auxiliary device, all jackings support knot on all supporting legs of big part vertical equipment Structure constitutes a jacking plane, which is located at the leg location of big part vertical equipment, and covers that big part is vertical to be set The standby plane covered, the center of gravity of big part vertical equipment do not deviate by the jacking plane that jacking support construction is constituted;Locking mechanism By adjusting the opening between the first clamp structure and the second clamp structure, the first clamp structure and the second clamp structure pair are adjusted The chucking power of equipment supporting leg, so that upward frictional force suffered by equipment supporting leg is greater than equipment itself during equipment jacking Gravity;
3) it is respectively mounted jack in the lower end of all jacking support constructions, jack and the lower surface of jacking support construction connect Touching starts jack, applies upward active force to jacking support construction, and jacking auxiliary device exerts a force simultaneously, keeps big part vertical Each position of equipment jacks simultaneously, and the whole smoothly jacking of big part vertical equipment is realized narrow sky at the position of setting Between in big part vertical equipment jacking assembly.
2. big part vertical equipment jacking method according to claim 1, it is characterised in that: first clamp structure and Two clamp structures include interconnecting piece, work department and support portion, and the working face of work department is the arc of evagination, interconnecting piece and support Portion is located at the both ends of work department, the locking mechanism is arranged on interconnecting piece, between support portion and the jacking support construction It is fixedly connected.
3. big part vertical equipment jacking method according to claim 2, it is characterised in that: the jacking support construction is plate Shape structure, on the fixed support portion of the plate structure.
4. big part vertical equipment jacking method according to claim 2, it is characterised in that: the interconnecting piece is sheet knot Structure, the locking mechanism are bolt, and connecting hole is provided on interconnecting piece, and bolt passes through connecting hole, is coupled with nut.
5. big part vertical equipment jacking method according to claim 2, it is characterised in that: the interconnecting piece is sheet knot Structure is provided with threaded hole on interconnecting piece, and locking mechanism is clamping screw, and clamping screw is coupled with threaded hole.
CN201610937297.3A 2016-11-01 2016-11-01 A kind of the jacking auxiliary device and jack-up construction method of vertical equipment Active CN106438605B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610937297.3A CN106438605B (en) 2016-11-01 2016-11-01 A kind of the jacking auxiliary device and jack-up construction method of vertical equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610937297.3A CN106438605B (en) 2016-11-01 2016-11-01 A kind of the jacking auxiliary device and jack-up construction method of vertical equipment

Publications (2)

Publication Number Publication Date
CN106438605A CN106438605A (en) 2017-02-22
CN106438605B true CN106438605B (en) 2019-03-12

Family

ID=58178176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610937297.3A Active CN106438605B (en) 2016-11-01 2016-11-01 A kind of the jacking auxiliary device and jack-up construction method of vertical equipment

Country Status (1)

Country Link
CN (1) CN106438605B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107044123B (en) * 2017-03-17 2019-02-01 岩土科技股份有限公司 A kind of construction static pressed pile device and the method using the device piling

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1331785A (en) * 1998-12-23 2002-01-16 奎·迪伊制造有限公司 Clamping device for mounting on profile member
CN2584986Y (en) * 2002-12-10 2003-11-05 胜利油田胜利石油化工建设有限责任公司 Device for fixing submarine pipeline
CN204281191U (en) * 2014-11-21 2015-04-22 何洁茹 One is applied to railcar and installs Air compressor lifting operation platform
CN204384733U (en) * 2015-01-14 2015-06-10 国家电网公司 Bus plug-in strip Lift-on/Lift-off System
CN105605318A (en) * 2015-10-28 2016-05-25 林佳一 Pipeline rigid support mechanism of centrifugal pump test bed and ascending and descending adjustment method of pipeline rigid support mechanism
CN206190655U (en) * 2016-11-01 2017-05-24 山东电力建设第一工程公司 Jacking auxiliary device of vertical equipment

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11165978A (en) * 1997-12-05 1999-06-22 Ishikawajima Harima Heavy Ind Co Ltd Hitching hook

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1331785A (en) * 1998-12-23 2002-01-16 奎·迪伊制造有限公司 Clamping device for mounting on profile member
CN2584986Y (en) * 2002-12-10 2003-11-05 胜利油田胜利石油化工建设有限责任公司 Device for fixing submarine pipeline
CN204281191U (en) * 2014-11-21 2015-04-22 何洁茹 One is applied to railcar and installs Air compressor lifting operation platform
CN204384733U (en) * 2015-01-14 2015-06-10 国家电网公司 Bus plug-in strip Lift-on/Lift-off System
CN105605318A (en) * 2015-10-28 2016-05-25 林佳一 Pipeline rigid support mechanism of centrifugal pump test bed and ascending and descending adjustment method of pipeline rigid support mechanism
CN206190655U (en) * 2016-11-01 2017-05-24 山东电力建设第一工程公司 Jacking auxiliary device of vertical equipment

Also Published As

Publication number Publication date
CN106438605A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106438605B (en) A kind of the jacking auxiliary device and jack-up construction method of vertical equipment
CN104499619A (en) PC outer hanging wall bottom adjusting component
CN210288117U (en) Angle-adjustable support jacking
CN210239222U (en) Template strutting arrangement for building engineering
CN203092049U (en) Weld holder for fillet welding in flat position of tower leg of electric transmission line iron tower
CN212984700U (en) Anti-falling device is used in construction steel structure engineering construction
CN206190655U (en) Jacking auxiliary device of vertical equipment
CN103821136B (en) Hang single-row of scaffold and construction method thereof
JP2000291262A (en) Erection piece for column erection and column erection method
CN106193591A (en) A kind of aluminum alloy mould plate form bracing fast assembly and disassembly mechanism
US3829053A (en) Tripod supporting a framing table for concrete works
CN211371499U (en) Metal pipeline support for steel structure engineering construction
CN110805149B (en) Support column self-locking splicing structure
CN204418440U (en) Adjusting part bottom the plug-in wall of a kind of PC
CN203891023U (en) Pile driving platform device
CN108385710B (en) Reusable tower foundation and installation method thereof
CN201319484Y (en) Portable cable workbench
CN207293959U (en) Special lifting platform is installed in the lifting of assembly concrete building element
JP2001065175A (en) Finely adjusting support base for structure
CN206000167U (en) Adjustable Alminum Project slab form support meanss
CN216006664U (en) Public road bridge roof beam construction bracket convenient to it is fixed
CN102758523B (en) Bracket for floor hoisting die construction and use method thereof
CN210339322U (en) Material transportation device for building construction
CN109534180A (en) Steel structure hoisting device in a kind of reusable adjustable room
CN202755642U (en) Bracket used for floor hanging mold construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant