CN103821136B - Hang single-row of scaffold and construction method thereof - Google Patents

Hang single-row of scaffold and construction method thereof Download PDF

Info

Publication number
CN103821136B
CN103821136B CN201410090690.4A CN201410090690A CN103821136B CN 103821136 B CN103821136 B CN 103821136B CN 201410090690 A CN201410090690 A CN 201410090690A CN 103821136 B CN103821136 B CN 103821136B
Authority
CN
China
Prior art keywords
scaffold
cross bar
wall
row
montant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410090690.4A
Other languages
Chinese (zh)
Other versions
CN103821136A (en
Inventor
陈华
郭志鑫
陈新喜
李未
沈健
孙晓阳
王欣
何建军
王刚
支宵翔
许浒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201410090690.4A priority Critical patent/CN103821136B/en
Publication of CN103821136A publication Critical patent/CN103821136A/en
Application granted granted Critical
Publication of CN103821136B publication Critical patent/CN103821136B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to a kind of suspension single-row of scaffold for SMW engineering method wall and construction method thereof.This suspension single-row of scaffold, include the single support body of the first cross bar and the montant with crisscross connection for SMW engineering method wall and vertical connect described first cross bar and the connecting rod of described montant, described connecting rod include being located at described in enclose on purlin and sandwiched connects the head rod of described H profile steel and connects the second connecting rod of described body of wall.Scaffold cradle of the present invention have saving operating space, make full use of existing resource, set up simple and quick, save the advantage such as construction cost.

Description

Hang single-row of scaffold and construction method thereof
Technical field
The present invention relates to building field, a kind of suspension single-row of scaffold for SMW engineering method wall and Its construction method.
Background technology
SMW engineering method wall (Soil Mixing Wall, cement it is increasingly employed in foundation pit enclosure Soil churned pile wall), it is inserted into H profile steel at soil cement, bearing load is combined with antiseepage dash, Make the enclosure wall that there is stress simultaneously with the supporting construction of impervious two kinds of functions.This SMW engineering method H profile steel in wall can be with recycling, so H profile steel exposed end above body of wall, for H profile steel is extracted recycling by the later stage.
During construction foundation pit internal structure, needing pylon scaffold, convenient construction is carried out.Build single pin Hand cradle, can meet foundation ditch built-in function space, does not affect operating personnel's construction.But at the bottom of foundation ditch Portion's out-of-flatness, single-row of scaffold supports built on the sand, easily topples.In view of single-row of scaffold built on the sand, Using double-pole scaffold in existing foundation ditch, double-pole scaffold is because of out-of-flatness bottom foundation ditch so that pin hand Frame is built relatively difficult.It addition, the internal space of foundation ditch own is less, and what double-pole scaffold took Space is the biggest, so using double-pole scaffold can cause foundation ditch built-in function insufficient space, to construction Produce impact.
Summary of the invention
It is an object of the invention to overcome the defect of prior art, it is provided that a kind of hang single-row of scaffold and Its construction method, can solve existing single-row of scaffold built on the sand, double-pole scaffold operating space is not enough, And bottom foundation ditch out-of-flatness bring build difficulty etc. problem.
The technical scheme realizing above-mentioned purpose is:
One of the present invention hangs single-row of scaffold, is applied to SMW engineering method wall, described SMW engineering method wall bag Include body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing;Described suspension single-row of scaffold bag Include: there is the first cross bar of crisscross connection and the single support body of montant and vertical connection is described First cross bar and the connecting rod of described montant, described connecting rod include being located at described in enclose connection institute on purlin State the head rod of H profile steel and connect the second connecting rod of described body of wall.
Suspension single-row of scaffold is used to be connected with the H profile steel exposed of SMW engineering method wall, by single pin hand Frame hangs on SMW engineering method wall, and can effectively solve that out-of-flatness bottom foundation ditch causes builds scaffold The problem of difficulty.There is provided support by the SMW engineering method wall of foundation pit enclosure for single-row of scaffold, can solve Certainly single-row of scaffold easily topples unsteady problem.Protecting it addition, the present invention hangs single-row of scaffold While card structural strength, also solve double-pole scaffold and cause asking of foundation ditch built-in function insufficient space Topic.Scaffold cradle of the present invention have saving operating space, make full use of existing resource, set up simple Quickly, the advantages such as construction cost are saved.
The present invention hangs further improvement is that of single-row of scaffold, wing plate place in described H profile steel Both sides are provided with vertical the second cross bar connecting described head rod.
The present invention hangs further improvement is that of single-row of scaffold, the bottom of described montant and described wall The ground contact at place bottom body.
The present invention hangs further improvement is that of single-row of scaffold, described second cross bar and described first Connecting rod support is connected by fastener.
The present invention hangs further improvement is that of single-row of scaffold, and described second connecting rod is in described perpendicular It is provided with springboard between bar and described body of wall.
The present invention hangs further improvement is that of single-row of scaffold, described first cross bar, described montant, And connected by fastener between described connecting rod.
A kind of construction method hanging single-row of scaffold of the present invention, for SMW engineering method wall, described SMW Engineering method wall includes body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing, and described suspension is single The construction method of scaffold includes:
In enclosing the head rod that on purlin, laying is connected with described H profile steel described in SMW engineering method wall;
Connecting single support body in the end that described head rod is placed in foundation ditch, described single support body has There are the first cross bar and the montant of crisscross connection, described first cross bar vertical with described montant described One connecting rod;
One end of the second connecting rod is connected, by described in described first cross bar and described montant intersection The other end of two connecting rods and the wall connecting of SMW engineering method wall.
The present invention hangs further improvement is that of the construction method of single-row of scaffold, in described enclose purlin it On be also equipped with the second cross bar being connected with described H profile steel, described second cross bar is perpendicular to described first Connecting rod, and be connected with described head rod by fastener.
A kind of construction method hanging single-row of scaffold of the present invention, for SMW engineering method wall, described SMW Engineering method wall includes body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing, and described suspension is single The construction method of scaffold includes:
Connect in foundation ditch and form the single support body with the first crisscross cross bar and montant;
Vertical the first company connecting described first cross bar and described montant is laid on purlin then at described enclosing Extension bar, is connected described head rod with described H profile steel;
One end of the second connecting rod is connected, by described in described first cross bar and described montant intersection The other end of two connecting rods and described wall connecting.
The present invention hangs further improvement is that of the construction method of single-row of scaffold, in described enclose purlin it On be also equipped with the second cross bar being connected with described H profile steel, described second cross bar is perpendicular to described first Connecting rod, and be connected with described head rod by fastener.
Accompanying drawing explanation
Fig. 1 is the sectional view that the present invention hangs single-row of scaffold;
Fig. 2 is the top view that the present invention hangs single-row of scaffold;
Fig. 3 is the flow chart that the present invention hangs a better embodiment of single-row of scaffold construction method;
Fig. 4 is the flow process that the present invention hangs another better embodiment of single-row of scaffold construction method Figure.
Detailed description of the invention
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, it is shown that the present invention hangs the sectional view of single-row of scaffold.The present invention hangs single Scaffold is to be hung on by single-row of scaffold in the building enclosure of SMW engineering method wall, and SMW engineering method wall includes There is body of wall, enclose purlin and expose the H profile steel enclosed above purlin, single-row of scaffold is hanged by connecting rod It is hung on H profile steel exposed portion, on the connecting rod between scaffold and body of wall, springboard is set, this springboard Trample, for operating platform for workmen.By single-row of scaffold being hung on H profile steel exposed portion, Solve single-row of scaffold itself easily to topple unsteady problem, also solve ground out-of-flatness and cause pin hand The problem that difficulty built by frame.Single-row of scaffold is compared Two bors d's oeuveres scaffold and is taken up room little, can solve double The problem that row's scaffold causes foundation ditch built-in function insufficient space.Scaffold cradle of the present invention also has joint About operating space, make full use of existing resource, set up simple and quick, save the advantage such as construction cost. Below in conjunction with the accompanying drawings scaffold cradle of the present invention and construction method thereof are illustrated.
Refering to Fig. 1, hang the sectional view of single-row of scaffold for the present invention, below in conjunction with Fig. 1, to this Invention is hung single-row of scaffold and is illustrated.
Arrange as it is shown in figure 1, single-row of scaffold of the present invention depends on SMW engineering method wall, SMW engineering method wall It is the one of foundation pit enclosure structure, on the body of wall 101 being located at around foundation ditch, body of wall 101 Enclosing purlin 102 and expose the H profile steel 103 enclosed above purlin 102, this H profile steel 103 is located at body of wall 101 is internal, and H profile steel 103 is extracted by the exposed portion of this H profile steel 103 for the later stage, carries out again Utilize.The present invention hangs single-row of scaffold and includes having the first cross bar 201 of crisscross connection and erect The single support body of bar 202, the first cross bar 201 and montant 202 intersection are linked together by fastener, First cross bar 201 and montant 202 are single row configuration, and the first cross bar 201 is arranged at certain intervals, perpendicular Bar 202 is arranged the most at certain intervals.The present invention hangs single-row of scaffold and also includes vertically connecting first Cross bar 201 and the connecting rod of montant 202, connecting rod includes head rod 203 and the second connecting rod 203 ', head rod 203 is located at the exposed division enclosed on purlin 102 with adjacent H profile steel 103 Divide and connect, can use and be welded to connect.Second connecting rod 203 ' one end and the first cross bar 201 and montant The junction of 202 connects, and the other end is connected with body of wall 101.Head rod 203, second connects Bar 203 ' is connected by fastener with the first cross bar 201 and montant 202.The bottom of montant 202 and foundation ditch Ground contact, the top of montant 202 hangs on H profile steel 103 by head rod 203, though So out-of-flatness at the ground of foundation ditch, but do not interfere with the firm of montant 202.Wing plate in H profile steel 103 The both sides at place are provided with the second cross bar 201 ', and the second vertical head rod 203 of cross bar 201 ' also sets On head rod 203, the second cross bar 201 ' is connected fixing with H profile steel 103, can use It is welded to connect.By the second cross bar 201 ' and head rod 203, scaffold is hung on H profile steel On 103, it is ensured that the steadiness of single-row of scaffold.It is provided with springboard on second connecting rod 203 ' 301, springboard 301 is splat, is located on multiple second connecting rod 203 ', at body of wall 101 With the springboard 301 laid between single support body is for trampling for workmen, provide operation flat for construction Platform.
Refering to Fig. 2, hang the top view of single-row of scaffold for the present invention, below in conjunction with Fig. 2, to this Invention is hung single-row of scaffold and is illustrated.
As in figure 2 it is shown, the present invention hangs the head rod 203 of single-row of scaffold at certain intervals Being located at and enclose on purlin 102, the both sides at H profile steel 103 wing plate place are provided with the second cross bar 201 ', and second Cross bar 201 ' is connected fixing by fastener with head rod 203.Head rod 203 and second is horizontal Bar 201 ' is connected fixing with H profile steel 103.Montant 202 is vertical at the first cross bar at certain intervals On 201, and it is connected fixing by fastener with the first cross bar 201, montant 202 and the first cross bar 201 Intersection, be equipped with the second connecting rod 203, and connected by fastener and the second connecting rod 203.
The present invention hangs having the beneficial effect that of single-row of scaffold
Single-row of scaffold is hung on H profile steel exposed portion by head rod and the second cross bar, increases Add the steadiness of single-row of scaffold, solve single-row of scaffold itself and easily topple unsteady problem, also Solve the problem that ground out-of-flatness causes scaffold to build difficulty.
Use single-row of scaffold to compare Two bors d's oeuveres scaffold and take up room little, double-pole scaffold can be solved and lead The problem causing foundation ditch built-in function insufficient space.
Arranging springboard on connecting rod between scaffold and body of wall, this springboard is trampled for workmen, Operating platform is provided for workmen.
The present invention hangs single-row of scaffold also to be had saving operating space, makes full use of existing resource, takes If the advantages such as simple and quick, saving construction cost.
Refering to Fig. 3, hang a better embodiment of the construction method of single-row of scaffold for the present invention Flow chart, below in conjunction with Fig. 3, the construction method that the present invention hangs single-row of scaffold illustrates.
As it is shown on figure 3, perform step S11, vertically lay head rod on purlin in enclosing.In conjunction with Shown in Fig. 2, enclosing vertical laying head rod 203 on purlin 102, by head rod 203 It is connected fixing with H profile steel 103 exposed portion.Can use and be welded and fixed.Then step S12 is performed.
Perform step S12, lay the second of vertical head rod in the both sides at H profile steel wing plate place Cross bar.Shown in Fig. 2, lay the second cross bar 201 ' in the both sides at H profile steel 103 wing plate place, Second cross bar 201 ' is located on head rod 203, and uses fastener between head rod 203 Connect, the part that the second cross bar 201 ' also exposes with H profile steel 103 is connected fixing.Can use It is welded and fixed.Then step S13 is performed.
Perform step S13, connect the first crisscross cross bar in the end of head rod and erect Bar.Shown in Fig. 1, head rod 203 is placed in the end within foundation ditch and connects the first cross bar 201 and montant 202, the first cross bar 201 and montant 202 are vertically connected, and are single row configuration.The One cross bar 201 is arranged at certain intervals, and montant 202 also certain intervals is arranged, the first cross bar 201 Connected fixing by fastener with montant 202.First cross bar 201, montant 202 and head rod 203 Connect fixing also by fastener.Then step S14 is performed.
Performing step S14, the first cross bar and montant intersection arrange the second connecting rod.In conjunction with Fig. 1 institute Showing, the first cross bar 201 and montant 202 intersection connect fixes the second connecting rod 203 ', and second connects Bar 203 ' other end connecting wall 101, lays springboard 301, springboard 301 on the second connecting rod 203 ' For splat, being layed on multiple second connecting rod 203 ', springboard 301 is for for workmen Trample, provide operating platform for construction.Material is thus formed the single pin of suspension for SMW engineering method wall Hand cradle.
Refering to Fig. 4, hang another better embodiment of single-row of scaffold construction method for the present invention Flow chart.As shown in Figure 4, comprise the following steps that in the present embodiment
Step S21, arranges the first crisscross cross bar and montant in foundation ditch;
Step S22, vertically lays head rod in enclosing on purlin;
Step S23, lays the second cross bar of vertical head rod in the both sides at H profile steel wing plate place;
Step S24, arranges the second connecting rod in the first cross bar and montant intersection.
Present embodiment is with the difference of above-mentioned embodiment, first passes through fastener and by the first cross bar and erects Bar crisscross connection forms single support body, is then laying head rod, by single support body and H Shaped steel connects.Remaining is all identical with above-mentioned embodiment.
The present invention hangs the beneficial effect of the construction method of single-row of scaffold:
Single-row of scaffold is hung on H profile steel exposed portion by head rod and the second cross bar, increases Add the steadiness of single-row of scaffold, solve single-row of scaffold itself and easily topple unsteady problem, also Solve the problem that ground out-of-flatness causes scaffold to build difficulty.
Use single-row of scaffold to compare Two bors d's oeuveres scaffold and take up room little, double-pole scaffold can be solved and lead The problem causing foundation ditch built-in function insufficient space.
Arranging springboard on connecting rod between scaffold and body of wall, this springboard is trampled for workmen, Operating platform is provided for workmen.
The present invention hangs single-row of scaffold also to be had saving operating space, makes full use of existing resource, takes If the advantages such as simple and quick, saving construction cost.
Above in association with accompanying drawing embodiment, the present invention is described in detail, ordinary skill people in this area The present invention can be made many variations example by member according to the above description.Thus, some details in embodiment Should not constitute limitation of the invention, the present invention by the scope that defines using appended claims as this The protection domain of invention.

Claims (6)

1. hanging a single-row of scaffold, be applied to SMW engineering method wall, described SMW engineering method wall includes Body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing;It is characterized in that, described suspension is single Row's scaffold includes: has the first cross bar of crisscross connection and the single support body of montant and hangs down Direct-connected connect described first cross bar and the connecting rod of described montant, described connecting rod include being located at described in enclose purlin On connect described H profile steel head rod and connect described body of wall the second connecting rod;Described H In shaped steel, the both sides at wing plate place are provided with vertical the second cross bar connecting described head rod;Described Connected by fastener between one cross bar, described montant and described connecting rod.
Hang single-row of scaffold the most as claimed in claim 1, it is characterised in that described montant Bottom contacts with the ground at place bottom described body of wall.
Hang single-row of scaffold the most as claimed in claim 1, it is characterised in that described second is horizontal Bar is connected by fastener with described head rod support.
Hang single-row of scaffold the most as claimed in claim 1, it is characterised in that described second even Extension bar is provided with springboard between described montant and described body of wall.
5. hang a construction method for single-row of scaffold, for SMW engineering method wall, described SMW work Method wall includes body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing, it is characterised in that institute The construction method stating suspension single-row of scaffold includes:
In enclosing the head rod that on purlin, laying is connected with described H profile steel described in SMW engineering method wall;
Connecting single support body in the end that described head rod is placed in foundation ditch, described single support body has There are the first cross bar and the montant of crisscross connection, described first cross bar vertical with described montant described One connecting rod;
One end of the second connecting rod is connected, by described in described first cross bar and described montant intersection The other end of two connecting rods and the wall connecting of SMW engineering method wall;In described enclose also be equipped with on purlin with The second cross bar that described H profile steel connects, described second cross bar is perpendicular to described head rod, and leads to Cross fastener to be connected with described head rod.
6. hang a construction method for single-row of scaffold, for SMW engineering method wall, described SMW work Method wall includes body of wall, enclose purlin and enclose the H profile steel above purlin described in exposing, it is characterised in that institute The construction method stating suspension single-row of scaffold includes:
Connect in foundation ditch and form the single support body with the first crisscross cross bar and montant;
Vertical the first company connecting described first cross bar and described montant is laid on purlin then at described enclosing Extension bar, is connected described head rod with described H profile steel;
One end of the second connecting rod is connected, by described in described first cross bar and described montant intersection The other end of two connecting rods and described wall connecting;Also it is equipped with on purlin and described H in described enclosing The second cross bar that shaped steel connects, described second cross bar is perpendicular to described head rod, and passes through fastener It is connected with described head rod.
CN201410090690.4A 2014-03-12 2014-03-12 Hang single-row of scaffold and construction method thereof Active CN103821136B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410090690.4A CN103821136B (en) 2014-03-12 2014-03-12 Hang single-row of scaffold and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410090690.4A CN103821136B (en) 2014-03-12 2014-03-12 Hang single-row of scaffold and construction method thereof

Publications (2)

Publication Number Publication Date
CN103821136A CN103821136A (en) 2014-05-28
CN103821136B true CN103821136B (en) 2016-09-07

Family

ID=50756404

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410090690.4A Active CN103821136B (en) 2014-03-12 2014-03-12 Hang single-row of scaffold and construction method thereof

Country Status (1)

Country Link
CN (1) CN103821136B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113509A (en) * 2015-04-24 2015-12-02 北京卓良模板有限公司 Tool type foundation pit suspended step ladder
CN105239763A (en) * 2015-09-22 2016-01-13 上海十三冶建设有限公司 Scaffold for modularized construction of air separation cold box
CN109306754A (en) * 2017-07-27 2019-02-05 五冶集团上海有限公司 A kind of installing and fixing method of shear force wall reinforcing steel bar
CN113404268A (en) * 2021-06-25 2021-09-17 北京住总第一开发建设有限公司 Basement exterior wall scaffold system and construction method thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07259323A (en) * 1994-03-22 1995-10-09 Ishikawajima Harima Heavy Ind Co Ltd Exterior wall construction method using a gondola with trolley
JPH09310484A (en) * 1996-05-21 1997-12-02 Takenaka Komuten Co Ltd Large space applicable suspended scaffold constructing system
CN2494860Y (en) * 2001-09-07 2002-06-12 成军 Outrigger supporting type lifting scaffold
CN201221079Y (en) * 2008-05-16 2009-04-15 中冶天工建设有限公司 Supporting structure for deep foundation pit structure wall
CN201962932U (en) * 2010-12-20 2011-09-07 江苏南通三建集团第十六建设发展有限公司 Sectional cantilevered external scaffolding for building construction
CN103147582A (en) * 2013-03-19 2013-06-12 成军 Overhead cantilever formwork construction method
CN203878563U (en) * 2014-03-12 2014-10-15 中国建筑第八工程局有限公司 Suspended single-row scaffold

Also Published As

Publication number Publication date
CN103821136A (en) 2014-05-28

Similar Documents

Publication Publication Date Title
CN103821136B (en) Hang single-row of scaffold and construction method thereof
CN102926554B (en) Steel hanging seat formwork support and construction method thereof
CN204826589U (en) Folding suspension type operation platform
CN203963252U (en) A kind of petroleum pipeline bracket
CN205029274U (en) Fixed bolster that faces cable
CN104372923A (en) Scaffold
CN213115585U (en) Stable form bearing structure that building engineering used
CN203878563U (en) Suspended single-row scaffold
CN204543330U (en) A kind of substation equipment maintenance and repair safety belt suspension device
CN208650505U (en) Integrated formwork connection device for jacking platform
CN203514368U (en) Side slope detection work platform
CN203559570U (en) Operating platform for steel pipe support frame overhung on surrounding columns
CN206053276U (en) Steel construction high altitude operation platform
CN107381376B (en) Device and method for hoisting by utilizing curtain wall embedded part
CN104594617B (en) A span wire scaffold frame for construction of high-rise roof structure
CN205088680U (en) Manual hole digging pile support that is unearthed
CN105113776B (en) The support meanss and building method of pole inner top platform on a kind of spherical tank
CN204266194U (en) Fender post construction reinforcing cage installation structure below a kind of high-voltage line
CN207686266U (en) A kind of means for fastening scaffolding of fast demountable
CN106672743A (en) Temporary supporting device for large-space structure construction elevator wall attaching frame
CN205955205U (en) Formwork supporting device
CN207174408U (en) A kind of steel pipe storage device
CN206544855U (en) Supporting apparatus for large spatial structure construction elevator wall-attached frame
CN206888106U (en) Basin mounting structure under a kind of platform
CN205531402U (en) Steel construction temporary remove lattice column butting positioning device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant