CN106408157A - Building project progress and cost management system - Google Patents

Building project progress and cost management system Download PDF

Info

Publication number
CN106408157A
CN106408157A CN201610731638.1A CN201610731638A CN106408157A CN 106408157 A CN106408157 A CN 106408157A CN 201610731638 A CN201610731638 A CN 201610731638A CN 106408157 A CN106408157 A CN 106408157A
Authority
CN
China
Prior art keywords
controller
unit
progress
time
management system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610731638.1A
Other languages
Chinese (zh)
Inventor
郑毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Morning Cost Consulting Co Ltd
Original Assignee
Chengdu Morning Cost Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Morning Cost Consulting Co Ltd filed Critical Chengdu Morning Cost Consulting Co Ltd
Priority to CN201610731638.1A priority Critical patent/CN106408157A/en
Publication of CN106408157A publication Critical patent/CN106408157A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a building project progress and cost management system. The system comprises a controller, an input unit, a storage unit, a time unit, a comparison unit, a display unit and a reading unit; the input unit is connected with the controller and inputs a completed cost process; the storage unit is connected with the controller, and stores data related to the project cost progress; the time unit is connected with the controller, and stores real time of the controller; the comparison unit is connected with the controller, and compares data of the storage unit with that of the time unit; the display unit is connected with the controller, displays the present progress and a comparison result of the comparison unit, and also displays name and completing time of a next process; and the reading unit is connected with the controller, and the signal input end of the reading unit is connected with the reading signal output end of the controller. The system of the invention can be used to count the project progresses in the real time, convenience is provided for real-time adjustment of the progress, and the progress is adjusted.

Description

A kind of architectural engineering progress and cost management system
Technical field
The present invention relates to construction costs technical field is and in particular to a kind of architectural engineering progress and cost management system.
Background technology
At present, construction costs can be made to the engineering accepted before bid by the enterprise being responsible for bid, existing cost The information that flow process provides according to owner for staff, and the information oneself obtaining to reconnaissance at criminal scene carries out to the engineering accepted Cost evaluation work, due to cost work loaded down with trivial details, need the work of cost staff is exercised supervision, and can only lead at present Cross related personnel cost work is exercised supervision, do not meet and modern automation is required, simultaneously need to extra work, cause people The waste of power resource.
Based on this, study and develop a kind of architectural engineering progress of design and cost management system.
Content of the invention
The technical problem to be solved is:Overcome prior art defect, a kind of architectural engineering progress is provided and makes Valency management system, in solution prior art, construction costs efficiency is low, causes the technical problems such as waste of human resource.
The present invention is achieved through the following technical solutions:
A kind of architectural engineering progress and cost management system, are connected with controller including controller, input block, input block, Input block inputs to completed cost process;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters The title of degree and the time completing.
Preferably, also include alarm unit, be connected with controller, the signal input part of alarm unit and the alarm signal of controller Number outfan connects.
Preferably, also include progress name storage unit, be connected with controller, be mainly used in storing entering of construction costs work Degree title.
Preferably, also include deadline memory element, be connected with controller, be mainly used in storage single with the storage of progress title The deadline of unit's each progress title corresponding.
The controller that is related in the technical program, memory element, deadline memory element, the storage of progress title are single Unit, display unit, input block, alarm unit, the structure of comparison unit and its principle are the common knowledge of art, no Describe in detail again.Controller can be 80C51 single-chip microcomputer.
The present invention compared with prior art, has such advantages as and beneficial effect:
Construction costs progress control system of the present invention, can achieve and in real time project progress is counted, be easy to progress Carry out real-time adjustment, and adjust progress.
Brief description:
Wherein:Fig. 1 is the structural schematic block diagram of the present invention.
Specific embodiment
For making the object, technical solutions and advantages of the present invention become more apparent, with reference to embodiment and accompanying drawing, to this Invention is described in further detail, and the exemplary embodiment of the present invention and its explanation are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment 1:
As shown in figure 1, a kind of architectural engineering progress and cost management system, including controller, input block, input block with Controller connects, and input block inputs to completed cost process;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters The title of degree and the time completing.
Wherein, also include alarm unit, be connected with controller, the signal input part of alarm unit and the alarm signal of controller Number outfan connects.
Wherein, described also include progress name storage unit, be connected with controller, be mainly used in store construction costs work Progress title.
Wherein, described also include deadline memory element, be connected with controller, be mainly used in storage deposit with progress title The deadline of storage unit each progress title corresponding.
Specific work process is:
Staff passes through input block by the work completing input controller, and controller extracts the name of progress name storage unit Title, the time of time memory cell, the current real-time time extraction to time quantum for the controller simultaneously, during two then transferring Between send and compare to contrast module, if the time of time module is prior to the time of time memory cell, staff Complete this progress, shown in display module simultaneously, show that this staff carries out the time of next progress, title simultaneously, On the contrary, then this progress control personnel do not complete corresponding task in time, and alarm unit is pointed out.
Above-described specific embodiment, has been carried out to the purpose of the present invention, technical scheme and beneficial effect further Describe in detail, be should be understood that the specific embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, all any modification, equivalent substitution and improvement within the spirit and principles in the present invention, done etc., all should comprise Within protection scope of the present invention.

Claims (4)

1. a kind of architectural engineering progress and cost management system it is characterised in that:Including controller, input block, input block It is connected with controller, input block inputs to completed cost process;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters The title of degree and the time completing.
2. a kind of architectural engineering progress according to claim 1 and cost management system are it is characterised in that also include reporting to the police Unit, is connected with controller, and the signal input part of alarm unit is connected with the alarm signal output ends of controller.
3. a kind of architectural engineering progress according to claim 2 and cost management system it is characterised in that:Also include progress Name storage unit, is connected with controller, is mainly used in storing the progress title of construction costs work.
4. a kind of architectural engineering progress according to claim 3 and cost management system it is characterised in that:Also include completing Time memory cell, is connected with controller, is mainly used in storing each progress title corresponding with progress name storage unit Deadline.
CN201610731638.1A 2016-08-26 2016-08-26 Building project progress and cost management system Pending CN106408157A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610731638.1A CN106408157A (en) 2016-08-26 2016-08-26 Building project progress and cost management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610731638.1A CN106408157A (en) 2016-08-26 2016-08-26 Building project progress and cost management system

Publications (1)

Publication Number Publication Date
CN106408157A true CN106408157A (en) 2017-02-15

Family

ID=58005241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610731638.1A Pending CN106408157A (en) 2016-08-26 2016-08-26 Building project progress and cost management system

Country Status (1)

Country Link
CN (1) CN106408157A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107590875A (en) * 2017-07-24 2018-01-16 成都东易盛泰科技有限公司 A kind of hand-held process cycle index instrument

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203118041U (en) * 2013-02-20 2013-08-07 瑞和安惠项目管理集团有限公司 Project cost progress management system
CN104517168A (en) * 2013-09-30 2015-04-15 宁夏先锋软件有限公司 Engineering project construction cost schedule management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203118041U (en) * 2013-02-20 2013-08-07 瑞和安惠项目管理集团有限公司 Project cost progress management system
CN104517168A (en) * 2013-09-30 2015-04-15 宁夏先锋软件有限公司 Engineering project construction cost schedule management system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107590875A (en) * 2017-07-24 2018-01-16 成都东易盛泰科技有限公司 A kind of hand-held process cycle index instrument

Similar Documents

Publication Publication Date Title
CN108009758B (en) BIM-based intelligent management method for field construction materials
CN109543992A (en) Intelligent polling method, device, intelligent terminal and server
CN103366311B (en) A kind of Data Fusion method based on transformer station's multisystem
CN109299156A (en) Electronic device, the electric power data predicting abnormality method based on XGBoost and storage medium
CN104268291B (en) A kind of data consistency processing method and system
CN103197640B (en) Production technology intelligence managing and control system and method
CN106251061A (en) A kind of intellectual capital management system
CN104346839B (en) A kind of employee's electronic attendance system based on LAN
CN104408654A (en) Financial monitoring management system
CN112150100A (en) Bridge construction progress management system based on BIM information technology
CN203118041U (en) Project cost progress management system
CN111083662A (en) Water quality monitoring Internet of things system based on cloud computing
CN104517168A (en) Engineering project construction cost schedule management system
CN107221129A (en) Early warning system on a kind of line for geological disaster and weather warning
CN105956125A (en) Patent monitoring system and method
CN106408157A (en) Building project progress and cost management system
CN104851222B (en) A kind of NVSG relates to the management method of vouching position comprehensive security management system
CN110097328A (en) Engineering construction field management method and system based on BIM
CN106786533B (en) The acquisition methods and device of electric dispatching plan data
CN106408158A (en) Project cost progress management system
CN209248321U (en) Factory management system
CN106157137A (en) The control method of a kind of bank account amount of money and device
CN106296037A (en) Cost method of data capture based on big data technique
CN106779113A (en) A kind of Laboratory Instruments preengages platform
CN106327086A (en) Cost data collection system based on internet technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215

RJ01 Rejection of invention patent application after publication