CN106408158A - Project cost progress management system - Google Patents
Project cost progress management system Download PDFInfo
- Publication number
- CN106408158A CN106408158A CN201610731642.8A CN201610731642A CN106408158A CN 106408158 A CN106408158 A CN 106408158A CN 201610731642 A CN201610731642 A CN 201610731642A CN 106408158 A CN106408158 A CN 106408158A
- Authority
- CN
- China
- Prior art keywords
- controller
- progress
- unit
- time
- memory element
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Marketing (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a project cost progress management system. The system comprises a controller, an input unit, a storage unit, a time unit, a comparison unit, a display unit and a reading unit; the input unit is connected with the controller and inputs a completed cost process; the storage unit is connected with the controller, and stores data related to the project cost progress; the time unit is connected with the controller, and stores real time of the controller; the comparison unit is connected with the controller, and compares data of the storage unit with that of the time unit; the display unit is connected with the controller, displays the present progress and a comparison result of the comparison unit, and also displays name and completing time of a next process; and the reading unit is connected with the controller, and the signal input end of the reading unit is connected with the reading signal output end of the controller. The project cost progress management system can be used to count the project progresses in the real time, convenience is provided for real-time adjustment of the progress, and the progress is adjusted.
Description
Technical field
The present invention relates to construction costs technical field is and in particular to a kind of construction costs progress control system.
Background technology
At present, construction costs can be made to the engineering accepted before bid by the enterprise being responsible for bid, existing cost
The information that flow process provides according to owner for staff, and the information oneself obtaining to reconnaissance at criminal scene carries out to the engineering accepted
Cost evaluation work, due to cost work loaded down with trivial details, need the work of cost staff is exercised supervision, and can only lead at present
Cross related personnel cost work is exercised supervision, do not meet and modern automation is required, simultaneously need to extra work, cause people
The waste of power resource.
Based on this, study and develop a kind of construction costs progress control system of design.
Content of the invention
The technical problem to be solved is:Overcome prior art defect, a kind of construction costs progress control is provided
System, in solution prior art, construction costs efficiency is low, causes the technical problems such as waste of human resource.
The present invention is achieved through the following technical solutions:
It is connected with controller including controller, input block, input block, input block carries out defeated to completed cost process
Enter;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters
The title of degree and the time completing;
Reading unit, is connected with controller, and the signal input part of reading unit is connected with the read signal outfan of controller.
Preferably, also include alarm unit, be connected with controller, the signal input part of alarm unit and the alarm signal of controller
Number outfan connects.
Preferably, also include progress name storage unit, be connected with controller, be mainly used in storing entering of construction costs work
Degree title.
Preferably, also include deadline memory element, be connected with controller, be mainly used in storage single with the storage of progress title
The deadline of unit's each progress title corresponding.
Preferably, the signal output part of described controller is connected with progress name storage unit, deadline memory element respectively
Connect, the progress name information of controller difference Load Game name storage unit, the deadline letter of deadline memory element
Breath.
Preferably, the progress name information of described controller difference Load Game name storage unit, deadline storage is single
The finishing time information of unit, is to be completed by read module.
The controller that is related in the technical program, memory element, deadline memory element, the storage of progress title are single
Unit, display unit, input block, alarm unit, the structure of comparison unit and its principle are the common knowledge of art, no
Describe in detail again.
The present invention compared with prior art, has such advantages as and beneficial effect:
(1)Construction costs progress control system of the present invention, can achieve and in real time project progress is counted, and is easy to entering
Degree carries out real-time adjustment, and adjusts progress.
(2)Progress controller input currently being completed by outside input block, controller will control reading single
Unit's time that this progress in progress msg memory element should be completed, transfer in main control unit time quantum simultaneously at that time when
Between, then control comparison unit two times to be compared, if staff is not according to time schedule, controller
Alarm unit is controlled to be reported to the police.Therefore, the present invention completes other staff to exercise supervision work, effectively saves
Human resourcess, make cost work be timely completed simultaneously.
Brief description:
Wherein:Fig. 1 is the structural schematic block diagram of the present invention.
Specific embodiment
For making the object, technical solutions and advantages of the present invention become more apparent, with reference to embodiment and accompanying drawing, to this
Invention is described in further detail, and the exemplary embodiment of the present invention and its explanation are only used for explaining the present invention, do not make
For limitation of the invention.
Embodiment 1:
As shown in figure 1, a kind of construction costs progress control system, including controller, input block, input block and controller even
Connect, input block inputs to completed cost process;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters
The title of degree and the time completing;
Reading unit, is connected with controller, and the signal input part of reading unit is connected with the read signal outfan of controller.
Wherein, also include alarm unit, be connected with controller, the signal input part of alarm unit and the alarm signal of controller
Number outfan connects.
Wherein, described also include progress name storage unit, be connected with controller, be mainly used in store construction costs work
Progress title.
Wherein, described also include deadline memory element, be connected with controller, be mainly used in storage deposit with progress title
The deadline of storage unit each progress title corresponding.
Wherein, the signal output part of described controller is connected with progress name storage unit, deadline memory element respectively
Connect, the progress name information of controller difference Load Game name storage unit, the deadline letter of deadline memory element
Breath.
Wherein, the progress name information of described controller difference Load Game name storage unit, deadline storage is single
The finishing time information of unit, is to be completed by read module.
Specific work process is:
Staff passes through input block by the work completing input controller, and controller extracts the name of progress name storage unit
Title, the time of time memory cell, the current real-time time extraction to time quantum for the controller simultaneously, during two then transferring
Between send and compare to contrast module, if the time of time module is prior to the time of time memory cell, staff
Complete this progress, shown in display module simultaneously, show that this staff carries out the time of next progress, title simultaneously,
On the contrary, then this progress control personnel do not complete corresponding task in time, and alarm unit is pointed out.
Above-described specific embodiment, has been carried out to the purpose of the present invention, technical scheme and beneficial effect further
Describe in detail, be should be understood that the specific embodiment that the foregoing is only the present invention, be not intended to limit the present invention
Protection domain, all any modification, equivalent substitution and improvement within the spirit and principles in the present invention, done etc., all should comprise
Within protection scope of the present invention.
Claims (6)
1. a kind of construction costs progress control system it is characterised in that:Including controller, input block, input block and control
Device connects, and input block inputs to completed cost process;
Memory element, memory element is connected with controller, for storing the data related to construction costs progress;
Time quantum, is connected with controller, for the real-time time of storage control;
Comparison unit, is connected with controller, and the data of memory element, time quantum is compared;
Display unit, is connected with controller, for showing the comparing result of current schedules and comparison unit, and shows that next enters
The title of degree and the time completing;
Reading unit, is connected with controller, and the signal input part of reading unit is connected with the read signal outfan of controller.
2. a kind of construction costs progress control system according to claim 1 is it is characterised in that also include alarm unit,
It is connected with controller, the signal input part of alarm unit is connected with the alarm signal output ends of controller.
3. a kind of construction costs progress control system according to claim 1 it is characterised in that:Described also include progress name
Claim memory element, be connected with controller, be mainly used in storing the progress title of construction costs work.
4. a kind of construction costs progress control system according to claim 3 it is characterised in that:Described when also including completing
Between memory element, be connected with controller, be mainly used in store each progress title corresponding with progress name storage unit complete
The one-tenth time.
5. a kind of construction costs progress control system according to claim 4 it is characterised in that:The signal of described controller
Outfan is connected with progress name storage unit, deadline memory element respectively, controller Load Game title storage respectively
The progress name information of unit, the finishing time information of deadline memory element.
6. a kind of construction costs progress control system according to claim 4 it is characterised in that:Described controller is read respectively
Take the progress name information of progress name storage unit, the finishing time information of deadline memory element, be by reading mould
Block completes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610731642.8A CN106408158A (en) | 2016-08-26 | 2016-08-26 | Project cost progress management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610731642.8A CN106408158A (en) | 2016-08-26 | 2016-08-26 | Project cost progress management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106408158A true CN106408158A (en) | 2017-02-15 |
Family
ID=58004806
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610731642.8A Pending CN106408158A (en) | 2016-08-26 | 2016-08-26 | Project cost progress management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106408158A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111047098A (en) * | 2019-12-16 | 2020-04-21 | 四川众合广汇企业管理咨询有限公司 | Construction progress and cost management system, computer equipment and computer readable storage medium |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203118041U (en) * | 2013-02-20 | 2013-08-07 | 瑞和安惠项目管理集团有限公司 | Project cost progress management system |
CN104517168A (en) * | 2013-09-30 | 2015-04-15 | 宁夏先锋软件有限公司 | Engineering project construction cost schedule management system |
-
2016
- 2016-08-26 CN CN201610731642.8A patent/CN106408158A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203118041U (en) * | 2013-02-20 | 2013-08-07 | 瑞和安惠项目管理集团有限公司 | Project cost progress management system |
CN104517168A (en) * | 2013-09-30 | 2015-04-15 | 宁夏先锋软件有限公司 | Engineering project construction cost schedule management system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111047098A (en) * | 2019-12-16 | 2020-04-21 | 四川众合广汇企业管理咨询有限公司 | Construction progress and cost management system, computer equipment and computer readable storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109543992A (en) | Intelligent polling method, device, intelligent terminal and server | |
CN103197640B (en) | Production technology intelligence managing and control system and method | |
CN109299156A (en) | Electronic device, the electric power data predicting abnormality method based on XGBoost and storage medium | |
CN203118041U (en) | Project cost progress management system | |
CN104346839B (en) | A kind of employee's electronic attendance system based on LAN | |
CN104517168A (en) | Engineering project construction cost schedule management system | |
CN106407580B (en) | Rule detection romote controlled locking method based on script | |
CN109410068A (en) | Electronic device, the electric power data Missing Data Filling method based on XGBoost and storage medium | |
CN103247086A (en) | Security guard patrol management system and method | |
CN107392706A (en) | Bicycle intelligence lending system | |
CN104484908B (en) | A kind of control method of roll-call monitoring system | |
CN106408157A (en) | Building project progress and cost management system | |
CN106408158A (en) | Project cost progress management system | |
CN106296037A (en) | Cost method of data capture based on big data technique | |
CN106327086A (en) | Cost data collection system based on internet technology | |
CN209248321U (en) | Factory management system | |
CN107358673A (en) | A kind of automatic Student Attendance System | |
NICOLAS | France and China's Belt and Road Initiative | |
CN102750751A (en) | Handover control system and method for railway crossing duty room of industrial and mining enterprises | |
CN108710873A (en) | It is a kind of based on the student of image recognition in school attendance checking system | |
CN207249753U (en) | automatic student attendance system | |
CN203969733U (en) | A kind of wine cabinet type intelligence minute drinking vessel | |
CN204066228U (en) | System is signed in a kind of intelligent express delivery | |
CN202167059U (en) | Parking lot management system based on CAN bus | |
CN106875647A (en) | A kind of data service system based on Internet of Things |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170215 |