CN106408113A - Production order scheduling management method and system - Google Patents

Production order scheduling management method and system Download PDF

Info

Publication number
CN106408113A
CN106408113A CN201610787236.3A CN201610787236A CN106408113A CN 106408113 A CN106408113 A CN 106408113A CN 201610787236 A CN201610787236 A CN 201610787236A CN 106408113 A CN106408113 A CN 106408113A
Authority
CN
China
Prior art keywords
scheduling
production
management
order
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610787236.3A
Other languages
Chinese (zh)
Inventor
梁铁军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Aumix Billion Software Ltd By Share Ltd
Original Assignee
Guangzhou Aumix Billion Software Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Aumix Billion Software Ltd By Share Ltd filed Critical Guangzhou Aumix Billion Software Ltd By Share Ltd
Priority to CN201610787236.3A priority Critical patent/CN106408113A/en
Publication of CN106408113A publication Critical patent/CN106408113A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/0601Electronic shopping [e-shopping]
    • G06Q30/0633Lists, e.g. purchase orders, compilation or processing
    • G06Q30/0635Processing of requisition or of purchase orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Accounting & Taxation (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Finance (AREA)
  • General Factory Administration (AREA)
  • Manufacturing & Machinery (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Educational Administration (AREA)

Abstract

An embodiment of the invention discloses a production order scheduling management method and system. The method comprises the following steps: a visualization Gantt chart production scheduling device is used for managing and scheduling production orders, and a GA algorithm is used for intelligently optimize production scheduling operation. Based on the production order scheduling management method and system disclosed in the embodiment of the invention, optimized configuration of the production orders and a production line can be realized via production order scheduling management and optimization, scientific management of garment production can be realized, and management efficiency and production efficiency are improved; compared with technologies of the prior art, the production order scheduling management method and system are advantageous in that an estimated 90% of production scheduling time can be saved, rapid and accurate replies of order delivery time can be made, visualized and intelligent production scheduling operation can be realized, stock can be reduced, production cost can be lowered, production delivery time can be optimized, and factory planning and scheduling operation and production management can be visualized.

Description

Produce scheduling management method and the system of order
Technical field
The present invention relates to garment production technology, the scheduling manager of the production order in especially a kind of Apparel Manufacturing Method and system.
Background technology
Apparel industry, as the traditional manufacture of China, occupies critical role in the light industry development of China, in recent years, With the development of intelligent automation, the manufacturing field of apparel industry has been realized in automatization, mechanical metaplasia Produce, greatly improve production efficiency, but in existing Apparel Manufacturing, intelligent production management also exists much to be asked Topic.
The inventors discovered that, at least there is problems with prior art:
Order planning management relies primarily on EXCEL scheduling, is completely dependent on the experience of scheduling personnel it is impossible to meet and modernizes large-scale clothes The order planning regulatory requirement of dress enterprise, therefore, prior art needs to improve.
Content of the invention
An embodiment of the present invention technical problem to be solved is:A kind of production order in Apparel Manufacturing is provided Scheduling management method and system, to improve production optimization operating capability and production efficiency in Apparel Manufacturing.
One side according to embodiments of the present invention, a kind of scheduling management method producing order providing, including:
Manage scheduling order using visual Gantt chart scheduling device, described visualization Gantt chart is made up of two dimensions, one For plant produced line dimension, another is time dimension, and what two kinds of dimensions crossed interval represents plant produced line in not same date Under space, what here gunter bar spatially represented is each production schedule, and the different color of gunter bar represents different Projected state;
Using GA algorithm intelligent optimization scheduling, described use GA algorithm intelligent optimization scheduling is to being discharged to using GA algorithm Unlocked the working out a scheme of line carries out multiple target global optimization, using mathematical modeling and operational research Methods, arranges multiple constraintss, right The production schedule carries out multiple target global optimization, generates the production scheduling scheme optimizing..
Based in another embodiment of said method, described manage scheduling order using visual Gantt chart scheduling device Including manual scheduling, regular scheduling, Optimal Scheduling.
Based in another embodiment of said method, described multiple target global optimization that the production schedule is carried out includes reducing Produce and postpone the raw fixture date of optimization, reduce and reduce production cost when shifting to an earlier date Optimizing manufacture stock, reducing production chief engineer.
Other side according to embodiments of the present invention, a kind of scheduling management system producing order providing, including:
Server, system management module, production scheduling module, analytical statement module, interface module;
Described server provides data to calculate and management of process for scheduling management system, and described system management module is with server even Connect, for the management of scheduling order and production line, described production scheduling module is connected with server, for the life to order process Occurrence condition is managed, and described analytical statement module is connected with server, for completing production task, just in production task and The inventory of task to be produced carries out statistical report form, and described interface module is responsible for scheduling management system and is connected with external equipment.
Based in another embodiment of said system, described system management module includes visual Gantt chart scheduling Device, described visualization Gantt chart is made up of two dimensions, and one is plant produced line dimension, and another is time dimension, two kinds The interval expression space under not same date for the plant produced line that dimension crosses, what here gunter bar spatially represented is each The individual production schedule, the different color of gunter bar represents different projected state, way to manage include manual scheduling, regular scheduling, Optimal Scheduling.
Based in another embodiment of said system, described production scheduling module realizes intelligent optimization row using GA algorithm Produce, described use GA algorithm realize intelligent optimization scheduling be using GA algorithm to be discharged to online unlocked work out a scheme carry out many Target global optimization, using mathematical modeling and operational research Methods, arranges multiple constraintss, carries out multiple target to the production schedule whole Body optimizes, and generates the production scheduling scheme optimizing.
A kind of scheduling management method producing order being provided based on the above embodiment of the present invention and system, are ordered by producing Single scheduling management and optimizing it is achieved that producing the optimization collocation of order and production line it is achieved that science in garment production Change management, improve the efficiency of management and production efficiency, the present invention is compared with prior art it is contemplated that the scheduling time saves nine than front Become it is achieved that quick, accurately reply order form delivery time, meet visualization, intelligent scheduling, reduce stock, reduce production cost, excellent Metaplasia produces the friendship phase, realizes the visualization of factory planning scheduling and production management.
Below by drawings and Examples, technical scheme is described in further detail.
Brief description
Constitute the Description of Drawings of a part the embodiments of the invention of description, and be used for explaining together with description The principle of the present invention.
Referring to the drawings, according to detailed description below, the present invention can be more clearly understood from, wherein:
Fig. 1 is the flow chart of one embodiment of scheduling management method of production order of the present invention.
Fig. 2 is the structural representation of an embodiment of production optimization device of the present invention.
Specific embodiment
To describe the various exemplary embodiments of the present invention now with reference to accompanying drawing in detail.It should be noted that:Unless other have Body illustrates, the positioned opposite, numerical expression of the part otherwise illustrating in these embodiments and step and numerical value do not limit this The scope of invention.
Simultaneously it should be appreciated that for the ease of description, the size of the various pieces shown in accompanying drawing is not according to reality Proportionate relationship draw.
Description only actually at least one exemplary embodiment is illustrative below, never as to the present invention And its application or any restriction using.
May be not discussed in detail for technology, method and apparatus known to person of ordinary skill in the relevant, but suitable When in the case of, described technology, method and apparatus should be considered a part for description.
It should be noted that:Similar label and letter represent similar terms in following accompanying drawing, therefore, once a certain Xiang Yi It is defined in individual accompanying drawing, then do not need it is further discussed in subsequent accompanying drawing.
The flow chart that Fig. 1 produces one embodiment of scheduling management method of order for the present invention.As shown in figure 1, this enforcement The scheduling management method of the production order of example includes:
10, manage scheduling order using visual Gantt chart scheduling device, described visualization Gantt chart is made up of two dimensions, one Individual another is time dimension for plant produced line dimension, and what two kinds of dimensions crossed interval represents plant produced line not on the same day Space under phase, what here gunter bar spatially represented is each production schedule, and the different color of gunter bar represents different Projected state;
20, using GA algorithm intelligent optimization scheduling, described use GA algorithm intelligent optimization scheduling is to having arranged using GA algorithm Carry out multiple target global optimization to online unlocked working out a scheme, using mathematical modeling and operational research Methods, multiple constraint bars are set Part, carries out multiple target global optimization to the production schedule, generates the production scheduling scheme optimizing..
Described include manual scheduling, regular scheduling, optimize row using visual Gantt chart scheduling device management scheduling order Produce.
Described the production schedule carried out with multiple target global optimization include reducing producing postponing to optimize raw fixture date, reducing and shift to an earlier date Optimizing manufacture stock, minimizing produce and reduce production cost during chief engineer.
Based on another aspect of the present invention, the present invention provides a kind of scheduling management system producing order, as Fig. 2 institute Show, the described scheduling management system producing order includes:
Server 1, system management module 2, production scheduling module 3, analytical statement module 4, interface module 5;
Described server 1 provides data to calculate and management of process, described system management module 2 and server for scheduling management system 1 connection, for the management of scheduling order and production line, described production scheduling module 3 is connected with server 1, for entering to order The production status of journey are managed, and described analytical statement module 4 is connected with server 1, for completing production task, giving birth to The inventory of product task and task to be produced carries out statistical report form, and described interface module 5 is responsible for scheduling management system and external equipment Connect.
Described system management module 2 includes visual Gantt chart scheduling device, and described visualization Gantt chart is by two dimensions Composition, one is plant produced line dimension, and another is time dimension, and what two kinds of dimensions crossed interval represents that plant produced line exists The not space under same date, what here gunter bar spatially represented is each production schedule, the different color table of gunter bar Show different projected state, way to manage includes manual scheduling, regular scheduling, Optimal Scheduling.
Described production scheduling module 3 realizes intelligent optimization scheduling using GA algorithm, and it is excellent that described use GA algorithm realizes intelligence Changing scheduling is to carry out multiple target global optimization using GA algorithm to being discharged to online unlocked working out a scheme, using mathematical modeling and Operational research Methods, arrange multiple constraintss, and the production schedule is carried out with multiple target global optimization, generate the production scheduling side optimizing Case.
In this specification, each embodiment is all described by the way of going forward one by one, and what each embodiment stressed is and it The difference of its embodiment, same or analogous part cross-reference between each embodiment.For system embodiment For, because it is substantially corresponding with embodiment of the method, so description is fairly simple, referring to the portion of embodiment of the method in place of correlation Defend oneself bright.
The method of the present invention and system may be achieved in many ways.For example, can by software, hardware, firmware or Software, hardware, any combinations of firmware are realizing the method for the present invention and system.Said sequence for the step of methods described Merely to illustrating, the step of the method for the present invention is not limited to order described in detail above, special unless otherwise Do not mentionlet alone bright.Additionally, in certain embodiments, also the present invention can be embodied as recording program in the recording medium, these programs Including the machine readable instructions for realizing the method according to the invention.Thus, the present invention also covers storage and is used for executing basis The recording medium of the program of the method for the present invention.
Description of the invention is given for the sake of example and description, and is not exhaustively or by the present invention It is limited to disclosed form.Many modifications and variations are obvious for the ordinary skill in the art.Select and retouch Stating embodiment is in order to the principle of the present invention and practical application are more preferably described, and so that those of ordinary skill in the art is managed The solution present invention is thus design is suitable to the various embodiments with various modifications of special-purpose.

Claims (6)

1. a kind of scheduling management method producing order is it is characterised in that comprise the following steps:
Manage scheduling order using visual Gantt chart scheduling device, described visualization Gantt chart is made up of two dimensions, one For plant produced line dimension, another is time dimension, and what two kinds of dimensions crossed interval represents plant produced line in not same date Under space, what here gunter bar spatially represented is each production schedule, and the different color of gunter bar represents different Projected state;
Using GA algorithm intelligent optimization scheduling, described use GA algorithm intelligent optimization scheduling is to being discharged to using GA algorithm Unlocked the working out a scheme of line carries out multiple target global optimization, using mathematical modeling and operational research Methods, arranges multiple constraintss, right The production schedule carries out multiple target global optimization, generates the production scheduling scheme optimizing.
2. method according to claim 1 is it is characterised in that described manage scheduling using visual Gantt chart scheduling device Order includes manual scheduling, regular scheduling, Optimal Scheduling.
3. method according to claim 1 is it is characterised in that described carry out multiple target global optimization to the production schedule and include Reduce to produce and postpone the raw fixture date of optimization, reduce and reduce production cost when shifting to an earlier date Optimizing manufacture stock, reducing production chief engineer.
4. a kind of scheduling management system producing order is it is characterised in that include:
Server, system management module, production scheduling module, analytical statement module, interface module;
Described server provides data to calculate and management of process for scheduling management system, and described system management module is with server even Connect, for the management of scheduling order and production line, described production scheduling module is connected with server, for the life to order process Occurrence condition is managed, and described analytical statement module is connected with server, for completing production task, just in production task and The inventory of task to be produced carries out statistical report form, and described interface module is responsible for scheduling management system and is connected with external equipment.
5. system according to claim 4 is it is characterised in that described system management module includes visual Gantt chart row Produce device, described visualization Gantt chart is made up of two dimensions, one is plant produced line dimension, and another is time dimension, two Plant the interval expression space under not same date for the plant produced line that dimension crosses, what here gunter bar spatially represented is every One production schedule, the different color of gunter bar represents different projected state, and way to manage includes manual scheduling, rule row Product, Optimal Scheduling.
6. system according to claim 4 is it is characterised in that described production scheduling module uses GA algorithm realization intelligence excellent Change scheduling, described use GA algorithm realize intelligent optimization scheduling be using GA algorithm to be discharged to online unlocked work out a scheme into Row multiple target global optimization, using mathematical modeling and operational research Methods, arranges multiple constraintss, carries out many mesh to the production schedule Mark global optimization, generates the production scheduling scheme optimizing.
CN201610787236.3A 2016-08-31 2016-08-31 Production order scheduling management method and system Pending CN106408113A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610787236.3A CN106408113A (en) 2016-08-31 2016-08-31 Production order scheduling management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610787236.3A CN106408113A (en) 2016-08-31 2016-08-31 Production order scheduling management method and system

Publications (1)

Publication Number Publication Date
CN106408113A true CN106408113A (en) 2017-02-15

Family

ID=58000947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610787236.3A Pending CN106408113A (en) 2016-08-31 2016-08-31 Production order scheduling management method and system

Country Status (1)

Country Link
CN (1) CN106408113A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105741036A (en) * 2016-01-29 2016-07-06 苏州浙远自动化工程技术有限公司 Scheduling system and method for intelligent traditional Chinese medicine factory
CN107168263A (en) * 2017-06-16 2017-09-15 江南大学 A kind of knitting MES Production-Plan and scheduling methods excavated based on big data
CN108985711A (en) * 2018-06-29 2018-12-11 北京仿真中心 A kind of intelligent plant dynamic planning scheduling system
CN109902906A (en) * 2017-12-09 2019-06-18 英业达科技有限公司 The manufacturing process management system and method for production
CN110009202A (en) * 2019-03-15 2019-07-12 安徽省司尔特肥业股份有限公司 A kind of intelligent scheduled production program system and method for fertilizer factory
CN110501978A (en) * 2018-05-18 2019-11-26 中国科学院沈阳自动化研究所 A kind of robot product workshop scheduled production dispatching method
CN110516936A (en) * 2019-08-13 2019-11-29 武汉攀升鼎承科技有限公司 A kind of intelligence production line mixing system
CN112712290A (en) * 2021-01-18 2021-04-27 上海交通大学 Self-organizing method, system, and medium for intelligent production system for emergency products
CN112734222A (en) * 2021-01-06 2021-04-30 成都星云智联科技有限公司 Factory order production scheduling self-adaptive method, equipment and storage medium
WO2023082549A1 (en) * 2021-11-12 2023-05-19 珠海格力电器股份有限公司 Manufacturing task allocation method and apparatus oriented toward intermodal freight transport under multi-factor constraints
CN116629552A (en) * 2023-05-26 2023-08-22 讯猫软件集团有限公司 Intelligent industrial management regulation and control system
CN117311296A (en) * 2023-11-29 2023-12-29 青岛创新奇智科技集团股份有限公司 Industrial model-based high-strength production line collaborative optimization and energy efficiency management method
CN117952567A (en) * 2024-03-25 2024-04-30 四川多联实业有限公司 Production management method and system based on MES intelligent manufacturing

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040117048A1 (en) * 2002-12-13 2004-06-17 Hung-Shan Wei Master production scheduling management system and method
CN105160439A (en) * 2015-10-08 2015-12-16 桥弘软件开发(上海)有限公司 Production scheduling method and automatic scheduling system
CN105741036A (en) * 2016-01-29 2016-07-06 苏州浙远自动化工程技术有限公司 Scheduling system and method for intelligent traditional Chinese medicine factory

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040117048A1 (en) * 2002-12-13 2004-06-17 Hung-Shan Wei Master production scheduling management system and method
CN105160439A (en) * 2015-10-08 2015-12-16 桥弘软件开发(上海)有限公司 Production scheduling method and automatic scheduling system
CN105741036A (en) * 2016-01-29 2016-07-06 苏州浙远自动化工程技术有限公司 Scheduling system and method for intelligent traditional Chinese medicine factory

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
金剑 等: "卷烟生产计划排产模型建立与优化", 《计算机工程与应用》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105741036A (en) * 2016-01-29 2016-07-06 苏州浙远自动化工程技术有限公司 Scheduling system and method for intelligent traditional Chinese medicine factory
CN107168263A (en) * 2017-06-16 2017-09-15 江南大学 A kind of knitting MES Production-Plan and scheduling methods excavated based on big data
CN109902906A (en) * 2017-12-09 2019-06-18 英业达科技有限公司 The manufacturing process management system and method for production
CN110501978A (en) * 2018-05-18 2019-11-26 中国科学院沈阳自动化研究所 A kind of robot product workshop scheduled production dispatching method
CN108985711A (en) * 2018-06-29 2018-12-11 北京仿真中心 A kind of intelligent plant dynamic planning scheduling system
CN110009202A (en) * 2019-03-15 2019-07-12 安徽省司尔特肥业股份有限公司 A kind of intelligent scheduled production program system and method for fertilizer factory
CN110516936A (en) * 2019-08-13 2019-11-29 武汉攀升鼎承科技有限公司 A kind of intelligence production line mixing system
CN110516936B (en) * 2019-08-13 2022-04-08 武汉攀升鼎承科技有限公司 Intelligent production line allocation system
CN112734222A (en) * 2021-01-06 2021-04-30 成都星云智联科技有限公司 Factory order production scheduling self-adaptive method, equipment and storage medium
CN112712290A (en) * 2021-01-18 2021-04-27 上海交通大学 Self-organizing method, system, and medium for intelligent production system for emergency products
WO2023082549A1 (en) * 2021-11-12 2023-05-19 珠海格力电器股份有限公司 Manufacturing task allocation method and apparatus oriented toward intermodal freight transport under multi-factor constraints
CN116629552A (en) * 2023-05-26 2023-08-22 讯猫软件集团有限公司 Intelligent industrial management regulation and control system
CN117311296A (en) * 2023-11-29 2023-12-29 青岛创新奇智科技集团股份有限公司 Industrial model-based high-strength production line collaborative optimization and energy efficiency management method
CN117311296B (en) * 2023-11-29 2024-02-13 青岛创新奇智科技集团股份有限公司 Industrial model-based high-strength production line collaborative optimization and energy efficiency management method
CN117952567A (en) * 2024-03-25 2024-04-30 四川多联实业有限公司 Production management method and system based on MES intelligent manufacturing

Similar Documents

Publication Publication Date Title
CN106408113A (en) Production order scheduling management method and system
Grabowska Smart factories in the age of Industry 4.0
Guo et al. Synchronization of shop-floor logistics and manufacturing under IIoT and digital twin-enabled graduation intelligent manufacturing system
Morris et al. Industrialization trajectories in Madagascar’s export apparel industry: Ownership, embeddedness, markets, and upgrading
CN106408112A (en) Production order production scheduling management method and production scheduling optimizer system
Dombrowski et al. Industrie 4.0 in production ramp-up management
CN106897809A (en) Workflow creation method, workflow designer and workflow system
CN106897806A (en) Workflow creation method and system, operation system
CN109784656A (en) A kind of discrete manufacture collaborative production planning scheduling method
CN104020676A (en) Garment production line arrangement method based on analogue simulation technology
CN110232526A (en) A kind of factory technics management system and method
CN104850068B (en) A kind of intelligent modeling method of complicated production manufacture process
CN105809302A (en) Production line scheduling method and system based on CEP inference engine
Pirola et al. Applying simulation for sustainable production scheduling: a case study in the textile industry
Wu et al. Smart factory reference architecture based on CPS fractal
CN109085804A (en) It is a kind of for electronic product multiplexing factory manufacture process Optimization Scheduling
CN104517186A (en) Business process design method based on data drive
CN101447065A (en) Method for uniformly collecting engineering progress data
US10845782B2 (en) Method for monitoring and controlling the energy cost for the production of a product lot
CN204331731U (en) A kind of product automatic assembly design system based on Pro/E
CN102651100B (en) A kind of generation system of clothes BOM and method
CN104036371A (en) Method for mapping assembly technology tree into assembly technological processes
CN103455853B (en) The procreative collaboration operational method of the multistage part of a kind of multistage supplier
CN103632222A (en) Manufacturing resource service state monitoring system
CN112650508A (en) Intelligent MES platform software operation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170215