CN106401015B - Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section - Google Patents

Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section Download PDF

Info

Publication number
CN106401015B
CN106401015B CN201610866864.0A CN201610866864A CN106401015B CN 106401015 B CN106401015 B CN 106401015B CN 201610866864 A CN201610866864 A CN 201610866864A CN 106401015 B CN106401015 B CN 106401015B
Authority
CN
China
Prior art keywords
wall
embedded joint
steel beam
wall unit
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610866864.0A
Other languages
Chinese (zh)
Other versions
CN106401015A (en
Inventor
卢海陆
肖绪文
孙鹏程
张津荣
关军
张起维
吴文伶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN201610866864.0A priority Critical patent/CN106401015B/en
Publication of CN106401015A publication Critical patent/CN106401015A/en
Application granted granted Critical
Publication of CN106401015B publication Critical patent/CN106401015B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/562Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with fillings between the load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • E04B2/60Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal characterised by special cross-section of the elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

一种带有预埋接缝钢梁段的装配式混合连肢墙体系及施工方法,该体系包括分别于水平方向、竖直方向连接的墙单元,其中竖直方向上连接的墙单元之间设有楼板,墙单元包括墙单元混凝土墙体和位于墙单元混凝土墙体内部的墙单元钢筋骨架,墙单元钢筋骨架的上下两侧的中部对应预埋有墙单元预埋接缝柱,墙单元钢筋骨架的左右两侧的上部对称连接有预埋接缝钢梁段,墙单元预埋接缝柱和预埋接缝钢梁段的外端部均超出墙单元混凝土墙体的侧边缘。本发明建立有限元模型对装配式混合连肢墙体系进行力学分析,验证其结构可靠性,具有抗震性能好、强震震后便于修复的优势;建造质量易保障,绿色环保性能好;设计灵活、制作高效、运输方便、安装便捷、经济效益好。

A prefabricated hybrid connected-limb wall system and construction method with pre-embedded joint steel beam sections, the system includes wall units connected in the horizontal direction and vertical direction respectively, wherein the wall units connected in the vertical direction There are floor slabs, and the wall unit includes the concrete wall of the wall unit and the reinforced skeleton of the wall unit located inside the concrete wall of the wall unit. The upper parts of the left and right sides of the reinforcement frame are symmetrically connected with pre-embedded joint steel beam sections, and the outer ends of the wall unit pre-embedded joint columns and the pre-embedded joint steel beam sections exceed the side edges of the wall unit concrete wall. The present invention establishes a finite element model to perform mechanical analysis on the prefabricated mixed limb wall system to verify its structural reliability, and has the advantages of good seismic performance and easy repair after strong earthquakes; the construction quality is easy to guarantee, and the environmental protection performance is good; the design is flexible , Efficient production, convenient transportation, convenient installation, and good economic benefits.

Description

带有预埋接缝钢梁段的装配式混合连肢墙体系及施工方法Prefabricated hybrid connected limb wall system and construction method with pre-embedded joint steel beam sections

技术领域technical field

本发明涉及建筑施工领域,特别是一种装配式墙肢结构及其施工方法。The invention relates to the field of building construction, in particular to an assembled wall pier structure and a construction method thereof.

背景技术Background technique

高层建筑结构是我国城市化过程中解决城镇人口不断增长与城市用地逐渐短缺矛盾的必然选择,而连肢墙结构体系是高层建筑结构中不可缺少的元素。根据以往实测资料,连肢墙体系既继承了单纯剪力墙工程造价低廉、抗侧刚度大等优点,又体现出了在强震作用下连梁屈服耗能、避免或减少了大量裂缝集中于墙体底部的情况,以降低震后修复成本的优点。The high-rise building structure is an inevitable choice to solve the contradiction between the growing urban population and the gradual shortage of urban land in the process of urbanization in my country, and the connected wall structure system is an indispensable element in the high-rise building structure. According to the measured data in the past, the attached wall system not only inherits the advantages of simple shear wall engineering such as low cost and high lateral stiffness, but also reflects the yield energy consumption of the connecting beam under the action of strong earthquakes, avoiding or reducing a large number of cracks concentrated in the The situation at the bottom of the wall has the advantage of reducing the cost of post-earthquake repairs.

但在实际应用过程中,限于建筑使用功能要求,传统混凝土连梁往往难以满足截面抗剪需求,给设计人员造成了一定的困难。与传统连肢墙相比,混合连肢墙特点在于使用钢连梁替代混凝土连梁,并应用现行相关规范、规程中的偏心支撑耗能梁理论,使得后者比前者具备更好的耗能能力和抗连续倒塌能力,且利于满足建筑使用要求和简化装配工序。对于新型装配式结构体系,解决其墙体装配单元间的连接形式成为了亟待解决的问题。However, in the actual application process, limited to the functional requirements of the building, traditional concrete coupling beams are often difficult to meet the shear resistance requirements of the section, which has caused certain difficulties for designers. Compared with the traditional connected limb wall, the characteristic of the hybrid connected limb wall is that the steel connecting beam is used to replace the concrete connecting beam, and the theory of eccentrically supported energy-dissipating beams in the current relevant codes and regulations is applied, so that the latter has better energy dissipation than the former. ability and resistance to continuous collapse, and is conducive to meeting the requirements of building use and simplifying the assembly process. For the new prefabricated structural system, solving the connection form between the wall assembly units has become an urgent problem to be solved.

发明内容Contents of the invention

本发明的目的是提供一种带有预埋接缝钢梁段的装配式混合连肢墙体系及其施工方法,要解决传统结构受力复杂、结构不稳定、连接关系不可靠、施工不便的技术问题。The purpose of the present invention is to provide a prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections and its construction method, to solve the problems of complex stress, unstable structure, unreliable connection relationship and inconvenient construction of traditional structures technical problem.

为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:

一种带有预埋接缝钢梁段的装配式混合连肢墙体系,包括分别于水平方向、竖直方向连接的墙单元,其中竖直方向上连接的墙单元之间设有楼板,所述墙单元包括墙单元混凝土墙体和位于墙单元混凝土墙体内部的墙单元钢筋骨架,墙单元钢筋骨架的上下两侧的中部对应预埋有墙单元预埋接缝柱,墙单元钢筋骨架的左右两侧的上部对称连接有预埋接缝钢梁段,所述墙单元预埋接缝柱和预埋接缝钢梁段的外端部均超出墙单元混凝土墙体的侧边缘。A prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections, including wall units connected in the horizontal direction and vertical direction respectively, wherein floor slabs are arranged between the wall units connected in the vertical direction, so The wall unit includes the concrete wall of the wall unit and the reinforced skeleton of the wall unit located inside the concrete wall of the wall unit. The upper parts of the left and right sides are symmetrically connected with pre-embedded joint steel beam sections, and the outer ends of the pre-embedded joint columns of the wall unit and the pre-embedded joint steel beam sections both exceed the side edges of the concrete wall of the wall unit.

水平方向上的左、右墙单元之间通过预埋接缝钢梁段对应连接,所述左右墙单元之间的接缝处填充有填充物;如有窗洞或者门洞时,左、右墙单元的预埋接缝钢梁段之间另外连接一根钢连梁。The left and right wall units in the horizontal direction are correspondingly connected by pre-embedded joint steel beam sections, and the joints between the left and right wall units are filled with fillers; if there is a window or door opening, the left and right wall units An additional steel connecting beam is connected between the pre-buried joint steel beam sections.

竖直方向上的上、下墙单元之间通过墙单元预埋接缝柱和墙单元钢筋骨架对应连接,所述上下墙单元之间的墙单元预埋接缝柱对接并浇筑在楼板内部。The upper and lower wall units in the vertical direction are correspondingly connected through the pre-embedded joint columns of the wall units and the steel bar skeleton of the wall units, and the pre-embedded joint columns of the wall units between the upper and lower wall units are butted and poured inside the floor slab.

所述墙单元混凝土墙体的上下两侧对称连接有两个墙单元预埋接缝柱,同侧的两个墙单元预埋接缝柱均匀间隔分布,所述墙单元预埋接缝柱长度约为40cm,其外端部超出第一墙单元混凝土墙体的侧边缘的长度约为楼板厚度的一半。The upper and lower sides of the concrete wall of the wall unit are symmetrically connected with two wall unit pre-embedded joint columns, and the two wall unit pre-embedded joint columns on the same side are evenly spaced, and the length of the wall unit pre-embedded joint columns is It is about 40cm, and the length of its outer end beyond the side edge of the concrete wall of the first wall unit is about half of the thickness of the floor slab.

所述预埋接缝钢梁段沿墙单元混凝土墙体长度方向布置、在预埋接缝钢梁段上、下翼缘上分别焊接预埋件抗剪栓钉和辅助钢筋连接器,所述辅助钢筋连接器上连接有预埋接缝梁端辅助钢筋。The pre-embedded joint steel beam section is arranged along the length direction of the concrete wall of the wall unit, and the pre-embedded part shear studs and auxiliary steel bar connectors are respectively welded on the upper and lower flanges of the pre-embedded joint steel beam section, and the auxiliary steel bar The connector is connected with auxiliary steel bars at the end of the pre-embedded joint beam.

所述上预埋接缝钢梁段的外端部超出墙单元混凝土墙体的侧边缘的长度范围是5厘米~10厘米,内端部不超过墙单元混凝土墙体的长度的三分之一。The length of the outer end of the upper pre-embedded joint steel beam section beyond the side edge of the concrete wall of the wall unit is 5 cm to 10 cm, and the inner end does not exceed one-third of the length of the concrete wall of the wall unit .

所述预埋接缝钢梁段的上表面与墙单元混凝土墙体边缘平齐、连接在预埋接缝梁的上表面的预埋件抗剪栓钉的端部超出墙单元混凝土墙体边缘。The upper surface of the pre-embedded joint steel beam section is flush with the edge of the wall unit concrete wall, and the end of the embedded part shear stud connected to the upper surface of the pre-embedded joint beam exceeds the edge of the wall unit concrete wall .

所述埋接缝钢梁段之间通过螺栓连接、焊接连接或者是螺栓与焊接混合方式连接。The buried joint steel beam sections are connected by bolts, welds or a combination of bolts and welds.

所述墙单元混凝土墙体上下左右四面中的一面或者多面为粗糙面或者在水平方向开有墙单元键槽。One or more of the top, bottom, left, and right sides of the wall unit concrete wall is a rough surface or has a wall unit keyway in the horizontal direction.

所述墙单元钢筋骨架包括由水平钢筋、竖直钢筋和拉结在两者之间的拉结筋构成的钢筋网架以及设置在墙单元预埋接缝柱四周的墙单元接缝柱构造筋,所述上下墙单元的墙单元钢筋骨架的竖直钢筋之间通过浆锚套筒对接。The reinforced skeleton of the wall unit includes a reinforced grid frame composed of horizontal steel bars, vertical steel bars and tie bars between the two, and wall unit seam column construction bars arranged around the pre-embedded joint columns of the wall unit , the vertical steel bars of the wall unit reinforcement frame of the upper and lower wall units are butted through the grout anchor sleeve.

所述楼板为现场浇筑的混凝土结构或者是装配式预制混凝土结构。The floor slab is an on-site poured concrete structure or an assembled prefabricated concrete structure.

所述墙单元预埋接缝柱和预埋接缝钢梁段为H型钢或者组合工字钢。The pre-embedded joint column of the wall unit and the pre-embedded joint steel beam section are H-shaped steel or combined I-beam.

所述预埋接缝钢梁段的两翼缘之间垂直焊接有预埋接缝钢梁段加劲板,所述预埋接缝钢梁段加劲板不超过墙单元混凝土墙体边缘,可以与墙单元混凝土墙体边缘齐平。The pre-embedded joint steel beam section stiffener is vertically welded between the two flanges of the pre-embedded joint steel beam section, and the pre-embedded joint steel beam section stiffener does not exceed the edge of the concrete wall of the wall unit and can be connected with the wall The unit concrete walls have flush edges.

一种如所述的带有预埋接缝钢梁段的装配式混合连肢墙体系的施工方法,其特征在于,包括墙单元的预制工序和现场装配工序,具体步骤如下:A construction method for a prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections as described, characterized in that it includes a prefabrication process and an on-site assembly process for wall units, and the specific steps are as follows:

墙单元的预制工序:Prefabrication process for wall units:

步骤一,在墙单元预埋接缝柱上焊接预埋件抗剪栓钉。Step 1: Weld the embedded part shear studs on the pre-embedded joint column of the wall unit.

步骤二,制作预埋接缝钢梁段:在型钢梁或焊接工字钢梁上、下翼缘上分别焊接预埋件抗剪栓钉、辅助钢筋连接器,然后再将预埋接缝梁端辅助钢筋与辅助钢筋连接器相连。Step 2, making steel beam sections with embedded joints: Weld the shear studs of embedded parts and auxiliary steel bar connectors on the upper and lower flanges of shaped steel beams or welded I-beams respectively, and then install the embedded joints Beam end auxiliary bars are connected with auxiliary bar connectors.

步骤三,将墙单元预埋接缝柱和预埋接缝钢梁段对应连接在设计位置上。Step 3, correspondingly connecting the pre-embedded joint column of the wall unit and the pre-embedded joint steel beam section at the design position.

步骤四,根据设计要求进行绑扎墙单元钢筋骨架。Step 4, according to the design requirements, bind the steel skeleton of the wall unit.

步骤五,并在墙单元预埋接缝柱周围固定墙单元接缝柱构造筋。Step 5, and fix the structural reinforcement of the wall unit joint column around the pre-embedded joint column of the wall unit.

步骤六,支设墙单元的浇筑模板,并根据需要、在上下左右四个面中的一面或者多面进行水平键槽或者粗糙面处理。Step 6, supporting the pouring formwork of the wall unit, and performing horizontal keyway or rough surface treatment on one or more of the four sides of the upper, lower, left, and right sides as required.

步骤七,浇筑墙单元的混凝土。Step seven, pouring concrete for the wall unit.

步骤八,待浇筑成型和养护后,通过吊环吊起并脱模,完成墙单元的预制工序。Step 8: After pouring, forming and maintenance, lift and demould through lifting rings, and complete the prefabrication process of the wall unit.

混合连肢墙的现场装配工序:On-site assembly process of mixed limb wall:

步骤一,将预制好的墙单元运至施工现场,开始现场施工工序。Step 1, transport the prefabricated wall units to the construction site, and start the site construction process.

步骤二,进行竖直方向上墙单元的连接,将上、下墙单元的墙单元预埋接缝柱与墙单元钢筋骨架分别对应连接。The second step is to connect the wall units in the vertical direction, and respectively connect the pre-embedded joint columns of the wall units of the upper and lower wall units with the reinforcement skeleton of the wall units.

步骤三,进行水平方向上墙单元的连接,将左、右墙单元的预埋接缝钢梁段对应连接,并在竖向接缝处填充填充物;如有窗洞或者门洞时,左、右墙单元的之间增设钢连梁。Step 3, connect the wall units in the horizontal direction, connect the pre-embedded joint steel beam sections of the left and right wall units correspondingly, and fill the vertical joints with filler; if there is a window or door opening, the left and right Steel connecting beams are added between the wall units.

步骤四,绑扎楼板的钢筋并支设楼板的模板。Step 4, binding the reinforcing bars of the floor slab and supporting the formwork of the floor slab.

步骤五,浇筑楼板的混凝土。Step five, pouring the concrete for the floor slab.

步骤六,待浇筑成型,并进行养护。Step 6, to be poured into shape and maintained.

步骤七,重复本工序中步骤一至步骤六,完成整个装配式混合连肢墙体系的施工工序。In step seven, repeat steps one to six in this process to complete the construction process of the entire prefabricated mixed limb wall system.

与现有技术相比本发明具有以下特点和有益效果:Compared with the prior art, the present invention has the following characteristics and beneficial effects:

本发明基于有限元理论,建立有限元模型对装配式混合连肢墙体系进行力学分析,验证其结构的可靠性,该体系与混凝土剪力墙结构体系相比,具有抗震性能好、强震震后便于修复的优势;与采用传统现浇方式相比,建造质量易保障,绿色环保性能好;与现有装配式剪力墙相比,具有设计灵活、制作高效、运输方便、安装便捷、经济效益好等优点,具体表现在以下几个方面:Based on the finite element theory, the present invention establishes a finite element model to perform mechanical analysis on the prefabricated hybrid connected wall system to verify the reliability of its structure. Compared with the concrete shear wall structure system, the system has good seismic performance, strong earthquake resistance Compared with the traditional cast-in-place method, the construction quality is easy to guarantee, and the environmental protection performance is good; compared with the existing prefabricated shear wall, it has the advantages of flexible design, efficient production, convenient transportation, convenient installation and economical Good benefits and other advantages are embodied in the following aspects:

1、抗震性能好:本发明依靠预埋接缝钢梁段将各个墙单元连接成混合连肢墙体系,在地震反复作用下,该结构体系可以使得预埋接缝梁外露部分较好地形成剪切型屈服,其耗能方式与偏心支撑消能梁段耗能相似,具有耗能能力大、变形小的特点,预埋接缝钢梁段可以沿结构全高布置,犹如在结构中设置了数量可观的“保险丝”,由此形成较好的耗能机制;与混凝土连梁相比,前者的剪切屈服耗能性能优于混凝土连梁梁端塑性铰耗能,且前者剪切屈服耗能变形小,强震作用下,抗连续倒塌能力强。1. Good seismic performance: the present invention relies on pre-embedded joint steel beam sections to connect each wall unit into a mixed limb wall system. Under the repeated action of earthquakes, this structural system can make the exposed part of the pre-embedded joint beam better formed Shear-type yielding, its energy dissipation mode is similar to that of eccentrically supported energy-dissipating beam sections, and has the characteristics of large energy dissipation capacity and small deformation. Embedded joint steel beam sections can be arranged along the entire height of the structure, just like setting A considerable amount of "fuse", thus forming a better energy dissipation mechanism; compared with concrete coupling beams, the shear yield energy dissipation performance of the former is better than the plastic hinge energy dissipation at the beam end of concrete coupling beams, and the shear yield dissipation of the former The deformation is small, and the ability to resist continuous collapse is strong under the action of strong earthquakes.

2、强震震后便于修复:强震下传递给结构的能量主要是被预埋接缝梁和连梁以塑性变形的形式所吸收,在强震作用下,延缓裂缝的发展,较好地避免了或减少了剪力墙底部的裂缝扩展。因此,强震后的修复只需进行外露预埋接缝钢梁段或连梁的更换以及少量开裂墙体做的加固工作即可。2. It is easy to repair after strong earthquakes: the energy transmitted to the structure under strong earthquakes is mainly absorbed by the pre-embedded joint beams and connecting beams in the form of plastic deformation. Under the action of strong earthquakes, the development of cracks is delayed and better avoided Or reduced crack propagation at the bottom of the shear wall. Therefore, the repair after a strong earthquake only needs to replace the exposed pre-embedded steel beam sections or connecting beams and a small amount of cracked wall reinforcement.

3、施工工艺优化,建造质量便于保证:墙体的制作大部分是在工厂内完成,因此可以把有效的现场监督集中于墙体单元间的连接之上,工程施工质量易于保证;与现浇混凝土剪力墙相比,工厂制作与现场安装同时进行,解决现浇混凝土剪力墙现场湿作业量大的问题;与现有一般装配式剪力墙相比,预埋接缝柱可以解决上层墙体施工过程稳定性的问题,为实现同层连肢墙单元现场拼接与楼板的浇筑立体交叉施工,提供了技术上的可能性;钢连梁替代混凝土连梁,解决现浇混凝土连梁现场湿作业量大的问题。3. The construction process is optimized, and the construction quality is easy to guarantee: most of the wall production is completed in the factory, so the effective on-site supervision can be concentrated on the connection between the wall units, and the construction quality is easy to guarantee; compared with cast-in-place Compared with concrete shear walls, factory production and on-site installation are carried out at the same time, which solves the problem of large amount of wet work on site for cast-in-place concrete shear walls; compared with existing general prefabricated shear walls, pre-embedded joint columns can solve the problem of The problem of the stability of the wall construction process provides a technical possibility for the on-site splicing of the same floor wall units and the three-dimensional cross construction of the floor slab pouring; steel coupling beams replace concrete coupling beams to solve the problem The problem of heavy wet work.

4、绿色环保性能好:由于墙体的制作大部分是在工厂完成的,模板可以有效重复利用,预埋接缝钢梁段、连梁又无需使用模板和临时支撑,故建造过程减少了建筑垃圾的产生。4. Good environmental protection performance: Since most of the wall is made in the factory, the formwork can be effectively reused, and the pre-embedded joint steel beam sections and connecting beams do not need to use formwork and temporary supports, so the construction process reduces construction costs. Garbage generation.

5、设计灵活、制作高效、运输方便、安装便捷:现有预制装配式剪力墙设计中,往往是把连梁、与连梁两端相连的墙体划分成一个装配单元,造成单元体积过大,给运输、安装带来诸多不便;另外,此种单元体设计方式,不但给设计人员造成不便,而且墙体装配单元不宜形成标准件,导致模具利用效率低下。本专利提出采用预埋接缝钢梁段间、预埋接缝钢梁段与连梁间连接的方式来实现墙肢间的有效连接,为结构设计人员灵活的设计预制单元提供了便利,同时也利于墙体装配单元形成标准件;预埋接缝钢梁段与连梁在现场连接,就不必考虑把连梁与其两端的墙体浇筑成一个单元体,从而方便运输与安装;本专利还为上下墙单元的连接设置了预埋接缝柱,省去其现场临时支撑的工序,真正实现“搭积木”式的建造方式,方便安装。总之,与现有装配式剪力墙相比,具有设计灵活、制作高效、运输方便、安装便捷等优点。5. Flexible design, efficient production, convenient transportation, and convenient installation: In the existing prefabricated shear wall design, the coupling beam and the wall connected to the two ends of the coupling beam are often divided into an assembly unit, resulting in excessive unit volume. Large, which brings a lot of inconvenience to transportation and installation; in addition, this kind of unit body design method not only causes inconvenience to designers, but also the wall assembly unit is not suitable for forming standard parts, resulting in low mold utilization efficiency. This patent proposes to realize the effective connection between wall piers by adopting the connection between pre-buried joint steel beam sections and between pre-buried joint steel beam sections and connecting beams, which provides convenience for structural designers to design prefabricated units flexibly, and at the same time It is also conducive to the formation of standard parts for the wall assembly unit; the pre-embedded joint steel beam section and the connecting beam are connected on site, so there is no need to consider pouring the connecting beam and the walls at both ends into a unit body, so as to facilitate transportation and installation; The pre-embedded joint column is set for the connection of the upper and lower wall units, which saves the process of temporary support on site, and truly realizes the "building block" construction method, which is convenient for installation. In short, compared with the existing prefabricated shear walls, it has the advantages of flexible design, efficient production, convenient transportation, and convenient installation.

6、经济效益好:现阶段,装配式剪力墙造价居高不下,究其原因,主要就是因为连梁与其两端的墙体浇筑成一个大单元体,从而为运输和安装造成不便;另外就是不规则墙体装配单元,不易形成标准件,模具利用率低,采用预埋接缝钢梁段间、预埋接缝钢梁段与连梁间连接方式实现墙肢间的有效连接,上述问题就可迎刃而解,可以明显降低造价,凸显装配式结构的经济优势。6. Good economic benefits: At this stage, the cost of prefabricated shear walls remains high. The main reason is that the connecting beams and the walls at both ends are poured into a large unit, which causes inconvenience for transportation and installation; the other is Irregular wall assembly units are not easy to form standard parts, and the mold utilization rate is low. The effective connection between the wall limbs is realized by the connection between the pre-embedded joint steel beam sections, the pre-embedded joint steel beam section and the connecting beam. The above problems It can be easily solved, can significantly reduce the cost, and highlights the economic advantages of the assembled structure.

附图说明Description of drawings

下面结合附图对本发明做进一步详细的说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.

图1是本发明的墙单元结构示意图。Fig. 1 is a structural schematic diagram of a wall unit of the present invention.

图2是图1的A-A剖面示意图。FIG. 2 is a schematic cross-sectional view of A-A in FIG. 1 .

图3是本发明的结构示意图。Fig. 3 is a structural schematic diagram of the present invention.

图4是图3的B-B剖面示意图。FIG. 4 is a schematic cross-sectional view along B-B of FIG. 3 .

附图标记:1-墙单元、2-墙单元混凝土墙体、3-墙单元预埋接缝柱、4-墙单元接缝柱构造筋、5-墙单元键槽、6-墙单元钢筋骨架、7-预埋件抗剪栓钉、8-预埋接缝钢梁段、9-预埋接缝钢梁段辅助钢筋、10-辅助钢筋连接器、11-预埋接缝钢梁段加劲板、、12-填充物、13-楼板、14-钢连梁、15-浆锚套筒。Reference signs: 1 - wall unit, 2 - concrete wall of wall unit, 3 - pre-embedded joint column of wall unit, 4 - structural reinforcement of joint column of wall unit, 5 - keyway of wall unit, 6 - reinforced skeleton of wall unit, 7- Shear studs of embedded parts, 8- Embedded joint steel beam section, 9- Auxiliary reinforcement of embedded joint steel beam section, 10- Auxiliary reinforcement connector, 11- Embedded joint steel beam section stiffener ,, 12-filler, 13-floor, 14-steel connecting beam, 15-slurry anchor sleeve.

具体实施方式Detailed ways

实施例参见图3、 图4所示,这种带有预埋接缝钢梁段的装配式混合连肢墙体系,包括分别于水平方向、竖直方向连接的墙单元1,所述墙单元1为预制构件,混凝土强度等级不小于C30,不高于C60,墙体高度约为层高减去楼板厚度,其中竖直方向上连接的墙单元之间设有楼板13,水平方向上的左、右墙单元1之间通过预埋接缝钢梁段8对应连接,所述左右墙单元之间的接缝处填充有填充物12,所述填充物可以选择低强度的填充物,例如空心小砌块、多孔砖等,如有窗洞或者门洞时,左、右墙单元1的预埋接缝钢梁段8之间增设钢连梁14;竖直方向上的上、下墙单元1之间通过墙单元预埋接缝柱3经高强螺栓或栓焊混合连接、墙单元钢筋骨架6的竖向钢筋经浆锚套筒15对应连接,所述上下墙单元之间的墙单元预埋接缝柱3对接并浇筑在楼板13内部。Referring to the embodiment shown in Fig. 3 and Fig. 4, this prefabricated hybrid connected limb wall system with pre-embedded joint steel beam sections includes wall units 1 connected in the horizontal and vertical directions respectively, and the wall units 1 is a prefabricated component, the concrete strength grade is not less than C30 and not higher than C60, the height of the wall is about the floor height minus the thickness of the floor slab, wherein a floor 13 is arranged between the wall units connected in the vertical direction, and the left side in the horizontal direction 1. The right wall units 1 are correspondingly connected by pre-embedded joint steel beam sections 8, and the joints between the left and right wall units are filled with fillers 12, and the fillers can be low-strength fillers, such as hollow Small blocks, perforated bricks, etc., if there are window openings or door openings, add steel connecting beams 14 between the pre-embedded joint steel beam sections 8 of the left and right wall units 1; The pre-embedded joint columns 3 through the wall units are connected through high-strength bolts or bolt welding, and the vertical steel bars of the wall unit reinforcement skeleton 6 are correspondingly connected through the grout anchor sleeves 15. The wall units between the upper and lower wall units are pre-embedded. The seam column 3 is butted and poured inside the floor slab 13 .

参见图1、图2所示,所述墙单元1包括墙单元混凝土墙体2和位于墙单元混凝土墙体内部的墙单元钢筋骨架6,墙单元钢筋骨架的上下两侧的中部对应预埋有墙单元预埋接缝柱3,墙单元钢筋骨架的左右两侧的上部对称连接有预埋接缝钢梁段8,所述墙单元预埋接缝柱3和预埋接缝钢梁段8的外端部均超出墙单元混凝土墙体2的侧边缘。Referring to Figures 1 and 2, the wall unit 1 includes a wall unit concrete wall 2 and a wall unit steel skeleton 6 located inside the wall unit concrete wall, and the middle parts of the upper and lower sides of the wall unit steel skeleton are correspondingly pre-embedded. The pre-embedded joint column 3 of the wall unit, the upper part of the left and right sides of the steel skeleton of the wall unit are symmetrically connected with the pre-embedded joint steel beam section 8, and the pre-embedded joint column 3 and the pre-embedded joint steel beam section 8 of the wall unit The outer ends of all exceed the side edges of the concrete wall body 2 of the wall unit.

所述第一墙单元混凝土墙体的上下两侧对称连接有两个第一墙单元预埋接缝柱,同侧的两个第一墙单元预埋接缝柱均匀间隔分布,所述第一墙单元预埋接缝柱长度约为40cm,其外端部超出第一墙单元混凝土墙体的侧边缘的长度范围是5厘米~10厘米,约为楼板厚度的一半。The upper and lower sides of the concrete wall of the first wall unit are symmetrically connected with two first wall unit pre-embedded joint columns, and the two first wall unit pre-embedded joint columns on the same side are evenly spaced. The length of the pre-embedded joint column of the wall unit is about 40cm, and the length of the outer end beyond the side edge of the concrete wall of the first wall unit is 5 cm to 10 cm, which is about half of the thickness of the floor slab.

所述预埋接缝钢梁段8沿墙单元混凝土墙体2长度方向布置,其上焊接预埋件抗剪栓钉7、并通过辅助钢筋连接器10与预埋接缝钢梁段辅助钢筋9连接。所述上预埋接缝钢梁段8的外端部超出墙单元混凝土墙体2的侧边缘的长度范围是5厘米~10厘米,内端部不超过墙单元混凝土墙体的长度的三分之一。The pre-embedded joint steel beam section 8 is arranged along the length direction of the wall unit concrete wall 2, on which the embedded part shear stud 7 is welded, and the auxiliary steel bar of the pre-embedded joint steel beam section is connected through the auxiliary steel bar connector 10 9 connections. The outer end of the upper pre-embedded joint steel beam section 8 exceeds the side edge of the wall unit concrete wall 2 in a length range of 5 cm to 10 cm, and the inner end does not exceed one-third of the length of the wall unit concrete wall. one.

所述预埋接缝梁的上表面与墙单元混凝土墙体边缘平齐、连接在预埋接缝梁的上表面的预埋件抗剪栓钉的端部超出墙单元混凝土墙体边缘。The upper surface of the pre-embedded joint beam is flush with the edge of the concrete wall of the wall unit, and the ends of the shear studs of the pre-embedded parts connected to the upper surface of the pre-embedded joint beam exceed the edge of the concrete wall of the wall unit.

所述预埋接缝钢梁段8之间通过螺栓连接、焊接连接或者是螺栓与焊接混合方式连接。The pre-embedded joint steel beam sections 8 are connected by bolts, welds or a combination of bolts and welds.

所述墙单元混凝土墙体2上下左右四面中的一面或者多面为粗糙面或者在水平方向开有墙单元键槽5。One or more of the four sides of the wall unit concrete wall 2 is rough or has a wall unit keyway 5 in the horizontal direction.

所述墙单元钢筋骨架6包括由水平钢筋、竖直钢筋和拉结在两者之间的拉结筋构成的钢筋网架以及设置在墙单元预埋接缝柱3四周的墙单元接缝柱构造筋4。The wall unit reinforced skeleton 6 includes a reinforced grid frame composed of horizontal steel bars, vertical steel bars and tie bars between the two, and wall unit joint columns arranged around the wall unit pre-embedded joint columns 3 Structural Rib4.

所述墙单元预埋接缝柱3和预埋接缝钢梁段8为H型钢或者组合工字钢,强度等级不低于Q235,不高于Q420。The pre-embedded joint column 3 of the wall unit and the pre-embedded joint steel beam section 8 are H-shaped steel or combined I-beam, and the strength grade is not lower than Q235 and not higher than Q420.

所述预埋接缝梁9的两翼缘之间垂直焊接有预埋接缝钢梁段加劲板12,所述预埋接缝钢梁段加劲板11与墙单元混凝土墙体2齐平。A pre-embedded joint steel beam section stiffener 12 is vertically welded between the two flanges of the pre-embedded joint beam 9 , and the pre-embedded joint steel beam section stiffener 11 is flush with the concrete wall 2 of the wall unit.

一种如所述的带有预埋接缝钢梁段的装配式混合连肢墙体系的施工方法,包括墙单元的预制工序和现场装配工序,其特征在于,具体步骤如下:A construction method for a prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections as described, including prefabrication and on-site assembly of wall units, characterized in that the specific steps are as follows:

墙单元的预制工序:Prefabrication process for wall units:

步骤一,在墙单元预埋接缝柱3上焊接固定墙单元抗剪栓钉4。Step 1, welding and fixing the wall unit shear stud 4 on the pre-embedded joint column 3 of the wall unit.

步骤二,制作预埋接缝钢梁段8:在型钢梁或焊接工字钢梁上、下翼缘上分别焊接预埋件抗剪栓钉、辅助钢筋连接器,然后再将预埋接缝梁端辅助钢筋与辅助钢筋连接器相连。Step 2, making pre-embedded joint steel beam section 8: Weld the pre-embedded shear studs and auxiliary steel bar connectors on the upper and lower flanges of the shaped steel girder or welded I-beam respectively, and then connect the pre-embedded joints The auxiliary reinforcement at the end of the slotted beam is connected with the auxiliary reinforcement connector.

步骤三,将墙单元预埋接缝柱3和预埋接缝钢梁段8对应连接在设计位置上。Step 3, correspondingly connecting the pre-embedded joint column 3 of the wall unit and the pre-embedded joint steel beam section 8 at the design position.

步骤四,根据设计要求进行绑扎墙单元钢筋骨架6。Step 4, according to the design requirements, bind the steel frame 6 of the wall unit.

步骤五,并在墙单元预埋接缝柱3周围固定墙单元接缝柱构造筋4。Step five, and fix the wall unit joint column structural reinforcement 4 around the wall unit pre-embedded joint column 3 .

步骤六,支设墙单元1的浇筑模板,并根据需要、在上下左右四个面中的一面或者多面进行水平键槽或者粗糙面处理。Step 6, supporting the pouring formwork of the wall unit 1, and performing horizontal keyway or rough surface treatment on one or more of the four surfaces of the upper, lower, left, and right sides as required.

步骤七,浇筑墙单元1的混凝土。Step seven, pouring the concrete of the wall unit 1.

步骤八,待浇筑成型和养护后,通过吊环吊起并脱模,完成墙单元的预制工序。Step 8: After pouring, forming and maintenance, lift and demould through lifting rings, and complete the prefabrication process of the wall unit.

混合连肢墙的现场装配工序:On-site assembly process of mixed limb wall:

步骤一,将预制好的墙单元运至施工现场,开始现场施工工序。Step 1, transport the prefabricated wall units to the construction site, and start the site construction process.

步骤二,进行竖直方向上墙单元的连接,将上、下墙单元的墙单元预埋接缝柱3与墙单元钢筋骨架6分别对应连接,其中墙单元预埋接缝柱3之间通过高强螺栓或栓焊混合连接、墙单元钢筋骨架6的竖直钢筋之间通过浆锚套筒15连接。Step 2, connect the wall units in the vertical direction, connect the wall unit pre-embedded joint columns 3 of the upper and lower wall units with the wall unit reinforcement skeleton 6 respectively, wherein the wall unit pre-embedded joint columns 3 pass through The high-strength bolts or bolt-welding hybrid connection, and the vertical steel bars of the steel bar skeleton 6 of the wall unit are connected through the grout anchor sleeve 15 .

步骤三,进行水平方向上墙单元的连接,将左、右墙单元的预埋接缝钢梁段对应通过高强螺栓或栓焊混合连接,并在竖向接缝处填充填充物12;如有窗洞或者门洞时,左、右墙单元的预埋接缝钢梁段之间增设钢连梁。Step 3, connect the wall units in the horizontal direction, connect the pre-embedded joint steel beam sections of the left and right wall units through high-strength bolts or bolt welding, and fill the vertical joints with filler 12; if any For window openings or door openings, add steel connecting beams between the pre-embedded joint steel beam sections of the left and right wall units.

步骤四,绑扎楼板13的钢筋并支设楼板13的模板。Step 4, binding the steel bars of the floor 13 and supporting the formwork of the floor 13 .

步骤五,浇筑楼板13的混凝土。Step five, pouring the concrete of the floor slab 13 .

步骤六,待浇筑成型,并进行养护。Step 6, to be poured into shape and maintained.

步骤七,重复本工序中步骤一至步骤六,完成整个装配式混合连肢墙体系的施工工序。In step seven, repeat steps one to six in this process to complete the construction process of the entire prefabricated mixed limb wall system.

Claims (10)

1.一种带有预埋接缝钢梁段的装配式混合连肢墙体系,包括分别于水平方向、竖直方向连接的墙单元(1),其中竖直方向上连接的墙单元之间设有楼板(13),其特征在于:所述墙单元(1)包括墙单元混凝土墙体(2)和位于墙单元混凝土墙体内部的墙单元钢筋骨架(6),墙单元钢筋骨架的上下两侧的中部对应预埋有墙单元预埋接缝柱(3),墙单元钢筋骨架的左右两侧的上部对称连接有预埋接缝钢梁段(8),所述墙单元预埋接缝柱(3)和预埋接缝钢梁段(8)的外端部均超出墙单元混凝土墙体(2)的侧边缘;1. A prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections, including wall units (1) connected in the horizontal direction and vertical direction respectively, wherein the wall units connected in the vertical direction A floor (13) is provided, characterized in that: the wall unit (1) includes a wall unit concrete wall (2) and a wall unit steel skeleton (6) located inside the wall unit concrete wall, the upper and lower parts of the wall unit steel skeleton The middle parts of both sides correspond to the pre-embedded joint columns (3) of the wall units, and the upper parts of the left and right sides of the steel skeleton of the wall units are symmetrically connected with the pre-embedded joint steel beam sections (8), and the pre-embedded joints of the wall units The outer ends of the joint column (3) and the pre-embedded joint steel beam section (8) both exceed the side edge of the concrete wall (2) of the wall unit; 水平方向上的左、右墙单元(1)之间通过预埋接缝钢梁段(8)对应连接,所述左右墙单元之间的接缝处填充有填充物(12);The left and right wall units (1) in the horizontal direction are correspondingly connected by pre-embedded joint steel beam sections (8), and the joints between the left and right wall units are filled with fillers (12); 竖直方向上的上、下墙单元(1)之间通过墙单元预埋接缝柱(3)和墙单元钢筋骨架(6)对应连接,所述上下墙单元之间的墙单元预埋接缝柱(3)对接并浇筑在楼板(13)内部。The upper and lower wall units (1) in the vertical direction are correspondingly connected through the wall unit pre-embedded joint column (3) and the wall unit steel skeleton (6), and the wall units between the upper and lower wall units are pre-embedded The joint column (3) is butted and poured inside the floor slab (13). 2.根据权利要求1所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述预埋接缝钢梁段(8)沿墙单元混凝土墙体(2)长度方向布置,其上焊接预埋件抗剪栓钉(7)、并通过辅助钢筋连接器(10)与预埋接缝钢梁段辅助钢筋连接(9)。2. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 1, characterized in that: said pre-embedded joint steel beam sections (8) along the wall unit concrete wall ( 2) Arranged in the length direction, on which the shear studs (7) of the embedded parts are welded, and connected with the auxiliary reinforcement of the embedded joint steel beam section (9) through the auxiliary reinforcement connector (10). 3.根据权利要求2所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述预埋接缝钢梁段(8)的外端部超出墙单元混凝土墙体(2)的侧边缘的长度范围是5厘米~10厘米,内端部不超过墙单元混凝土墙体的长度的三分之一。3. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 2, characterized in that: the outer end of the pre-embedded joint steel beam section (8) exceeds the wall unit The length of the side edge of the concrete wall (2) ranges from 5 cm to 10 cm, and the inner end does not exceed one-third of the length of the concrete wall of the wall unit. 4.根据权利要求3所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述预埋接缝钢梁段(8)的上表面与墙单元混凝土墙体边缘平齐、连接在预埋接缝钢梁段的上表面的预埋件抗剪栓钉(7)的端部超出墙单元混凝土墙体边缘。4. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 3, characterized in that: the upper surface of the pre-embedded joint steel beam sections (8) and the wall unit concrete The edge of the wall body is flush, and the end of the embedded part shear stud (7) connected to the upper surface of the pre-embedded joint steel beam section exceeds the edge of the concrete wall body of the wall unit. 5.根据权利要求4所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述预埋接缝钢梁段(8)之间通过焊接连接或者是螺栓与焊接混合方式连接。5. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 4, characterized in that: the pre-embedded joint steel beam sections (8) are connected by welding or Bolted and welded joints. 6.根据权利要求1所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述墙单元混凝土墙体(2)上下左右四面中的一面或者多面为粗糙面或者在水平方向开有墙单元键槽(5)。6. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 1, characterized in that: one or more of the four sides of the wall unit concrete wall (2) are The rough surface or the wall unit keyway (5) is opened in the horizontal direction. 7.根据权利要求1所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述墙单元钢筋骨架(6)包括由水平钢筋、竖直钢筋和拉结在两者之间的拉结筋构成的钢筋网架以及设置在墙单元预埋接缝柱(3)四周的墙单元接缝柱构造筋(4)。7. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 1, characterized in that: the wall unit reinforcement skeleton (6) consists of horizontal reinforcement, vertical reinforcement and tension A reinforced grid frame composed of tie bars tied between the two and wall unit joint column construction bars (4) arranged around the wall unit pre-embedded joint column (3). 8.根据权利要求1所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述墙单元预埋接缝柱(3)和预埋接缝钢梁段(8)为H型钢或者组合工字钢。8. The prefabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 1, characterized in that: said wall unit pre-embedded joint columns (3) and pre-embedded joint steel beams Section (8) is H-shaped steel or combined I-beam. 9.根据权利要求8所述的带有预埋接缝钢梁段的装配式混合连肢墙体系,其特征在于:所述预埋接缝钢梁段(8)的两翼缘之间垂直焊接有预埋接缝钢梁段加劲板(11),所述预埋接缝钢梁段加劲板(11)不超过墙单元混凝土墙体边缘。9. The fabricated hybrid connected-limb wall system with pre-embedded joint steel beam sections according to claim 8, characterized in that: the two flanges of the pre-embedded joint steel beam sections (8) are welded vertically There are pre-embedded joint steel beam section stiffeners (11), and the pre-embedded joint steel beam section stiffeners (11) do not exceed the edge of the concrete wall of the wall unit. 10.一种如权利要求1至9任意一项所述的带有预埋接缝钢梁段的装配式混合连肢墙体系的施工方法,其特征在于,包括墙单元的预制工序和现场装配工序,其特征在于,具体步骤如下:10. A construction method for a prefabricated hybrid connected wall system with pre-embedded joint steel beam sections as claimed in any one of claims 1 to 9, characterized in that it includes the prefabrication process and on-site assembly of wall units The operation is characterized in that the specific steps are as follows: 墙单元的预制工序:Prefabrication process for wall units: 步骤一,在墙单元预埋接缝柱(3)上焊接预埋件抗剪栓钉(7);Step 1, welding the embedded part shear studs (7) on the pre-embedded joint column (3) of the wall unit; 步骤二,制作预埋接缝钢梁段(8);Step 2, making the pre-embedded joint steel beam section (8); 步骤三,将墙单元预埋接缝柱(3)和预埋接缝钢梁段(8)对应连接在设计位置上;Step 3, correspondingly connect the pre-embedded joint column (3) of the wall unit and the pre-embedded joint steel beam section (8) at the design position; 步骤四,根据设计要求进行绑扎墙单元钢筋骨架(6);Step 4, according to the design requirements, bind the steel skeleton of the wall unit (6); 步骤五,并在墙单元预埋接缝柱(3)周围固定墙单元接缝柱构造筋(4);Step five, and fix the wall unit joint column structural reinforcement (4) around the wall unit pre-embedded joint column (3); 步骤六,支设墙单元(1)的浇筑模板,并根据需要、在上下左右四个面中的一面或者多面进行水平键槽或者粗糙面处理;Step 6, support the pouring formwork of the wall unit (1), and perform horizontal keyway or rough surface treatment on one or more of the four sides of the upper, lower, left, and right sides as required; 步骤七,浇筑墙单元(1)的混凝土;Step seven, pouring the concrete of the wall unit (1); 步骤八,待浇筑成型和养护后,通过吊环吊起并脱模,完成墙单元的预制工序;Step 8: After pouring and curing, lift and demould through lifting rings to complete the prefabrication process of the wall unit; 混合连肢墙的现场装配工序:On-site assembly process of mixed limb wall: 步骤一,将预制好的墙单元运至施工现场,开始现场施工工序;Step 1, transport the prefabricated wall units to the construction site, and start the on-site construction process; 步骤二,进行竖直方向上墙单元的连接,将上、下墙单元的墙单元预埋接缝柱(3)与墙单元钢筋骨架(6)分别对应连接;Step 2, connect the wall units in the vertical direction, and connect the pre-embedded joint columns (3) of the wall units of the upper and lower wall units with the reinforcement skeleton (6) of the wall units respectively; 步骤三,进行水平方向上墙单元的连接,将左、右墙单元的预埋接缝钢梁段(8)对应连接,并在竖向接缝处填充填充物(12);Step 3, connecting the wall units in the horizontal direction, correspondingly connecting the pre-embedded joint steel beam sections (8) of the left and right wall units, and filling the vertical joints with fillers (12); 步骤四,绑扎楼板(13)的钢筋并支其模板;Step 4, binding the steel bars of the floor slab (13) and supporting its formwork; 步骤五,浇筑楼板(13)的混凝土;Step 5, pouring the concrete of the floor slab (13); 步骤六,待浇筑成型,并进行养护;Step 6, to be poured into shape and maintained; 步骤七,重复本工序中步骤一至步骤六,完成整个装配式混合连肢墙体系的施工工序。In step seven, repeat steps one to six in this process to complete the construction process of the entire prefabricated mixed limb wall system.
CN201610866864.0A 2016-09-30 2016-09-30 Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section Expired - Fee Related CN106401015B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610866864.0A CN106401015B (en) 2016-09-30 2016-09-30 Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610866864.0A CN106401015B (en) 2016-09-30 2016-09-30 Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section

Publications (2)

Publication Number Publication Date
CN106401015A CN106401015A (en) 2017-02-15
CN106401015B true CN106401015B (en) 2018-10-26

Family

ID=59229350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610866864.0A Expired - Fee Related CN106401015B (en) 2016-09-30 2016-09-30 Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section

Country Status (1)

Country Link
CN (1) CN106401015B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116084595A (en) * 2023-03-20 2023-05-09 中国建筑第七工程局有限公司 Side-free support system for assembled hybrid limb wall construction and mounting method thereof
CN119663990B (en) * 2025-02-20 2025-05-27 上海结奕建筑科技有限公司 Modularized combined reinforced concrete building unit and production method and installation method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291181A (en) * 1999-04-13 2000-10-17 Taisei Corp Construction method of precast shear wall
CN201991110U (en) * 2011-01-19 2011-09-28 潍坊绿城低碳建筑科技有限公司 Assembly-type building enveloping and filling energy-saving wallboard system
CN104032861A (en) * 2014-05-15 2014-09-10 中国建筑股份有限公司 Joint structure and construction method of hybrid connected-wall steel column and non-energy-dissipating beam
CN104895220A (en) * 2015-06-17 2015-09-09 长春工程学院 Connecting joint of assembled profile steel confined concrete shear wall structure
CN206189653U (en) * 2016-09-30 2017-05-24 中国建筑股份有限公司 Assembled mixes even limb wall body system with pre -buried seam girder steel section

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291181A (en) * 1999-04-13 2000-10-17 Taisei Corp Construction method of precast shear wall
CN201991110U (en) * 2011-01-19 2011-09-28 潍坊绿城低碳建筑科技有限公司 Assembly-type building enveloping and filling energy-saving wallboard system
CN104032861A (en) * 2014-05-15 2014-09-10 中国建筑股份有限公司 Joint structure and construction method of hybrid connected-wall steel column and non-energy-dissipating beam
CN104895220A (en) * 2015-06-17 2015-09-09 长春工程学院 Connecting joint of assembled profile steel confined concrete shear wall structure
CN206189653U (en) * 2016-09-30 2017-05-24 中国建筑股份有限公司 Assembled mixes even limb wall body system with pre -buried seam girder steel section

Also Published As

Publication number Publication date
CN106401015A (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN108049498B (en) Prefabricated column and prefabricated beam connection structure and method of prefabricated building frame structure
CN104032854B (en) Assembled T-shaped mixing coupled wall and construction method thereof
CN111424850A (en) Prefabricated reinforced concrete shear wall and construction method
CN104929034A (en) Small modularized steel-concrete rapid-construction box girder bridge and construction method thereof
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN113653235A (en) Laminated slab, connecting structure of laminated slab and combination beam and construction method
CN106193292A (en) A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN113356405A (en) Prefabricated composite wall structure based on embedded profile steel and construction method thereof
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN203834738U (en) T-shaped prefabricated mixed coupled wall
CN207794299U (en) A kind of complete assembled steel reinforced concrete frame structure system
CN111749364B (en) A C-steel-based assembled composite wall and construction method thereof
CN203905214U (en) Assembled type blend coupled wall system
CN104032855B (en) Assembled cross mixing coupled wall and construction method thereof
CN107905368A (en) A kind of assembled beam and assembled column connection structure and construction method
CN104032861B (en) Connecting joint structure of mixed coupled wall section steel column and non-energy dissipation beam and construction method thereof
CN106401015B (en) Assembled mixing coupled wall system and construction method with pre-buried seam girder steel section
CN104032859B (en) Assembled L-shaped mixing coupled wall and construction method thereof
CN104032862B (en) Assembled girder steel seam line L shape mixing coupled wall and construction method thereof
CN203834692U (en) Connection joint structure of hybrid connected-wall steel columns and non-energy-dissipating steel short beams
CN206189653U (en) Assembled mixes even limb wall body system with pre -buried seam girder steel section
CN104032863B (en) Assembled in-line mixing coupled wall and construction method thereof
CN203834741U (en) Prefabricated steel beam joint L-shaped mixed coupled wall
CN104047380B (en) Assembled girder steel seam T-shaped mixing coupled wall and construction method thereof
CN106401017B (en) L-shaped flexible joint coupled wall with pre-buried seam beam section and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181026

Termination date: 20200930