CN106381953B - A kind of assembled bidirectional stress floor - Google Patents

A kind of assembled bidirectional stress floor Download PDF

Info

Publication number
CN106381953B
CN106381953B CN201610921100.7A CN201610921100A CN106381953B CN 106381953 B CN106381953 B CN 106381953B CN 201610921100 A CN201610921100 A CN 201610921100A CN 106381953 B CN106381953 B CN 106381953B
Authority
CN
China
Prior art keywords
assembled
board member
bidirectional stress
cavity
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610921100.7A
Other languages
Chinese (zh)
Other versions
CN106381953A (en
Inventor
王本淼
王海崴
李国强
贾英杰
杨建军
马锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan BDF Energy Saving Technology Co Ltd
Original Assignee
Hunan BDF Energy Saving Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan BDF Energy Saving Technology Co Ltd filed Critical Hunan BDF Energy Saving Technology Co Ltd
Priority to CN201610921100.7A priority Critical patent/CN106381953B/en
Publication of CN106381953A publication Critical patent/CN106381953A/en
Application granted granted Critical
Publication of CN106381953B publication Critical patent/CN106381953B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/28Cross-ribbed floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/326Floor structures wholly cast in situ with or without form units or reinforcements with hollow filling elements

Abstract

The present invention provides a kind of assembled bidirectional stress floor, includes column, girder, regeneration beam, cavity board member, floor top flange plate and joint close;It is characterized in that same period cast-in-place concrete is combined into a kind of assembled bidirectional stress floor on girder reinforcing bar space, cavity board member transverse direction frame rib beam steel formation regeneration beam connecting portion, cavity plate component surface steel mesh;The regeneration beam is the frame rib beam steel of site welding adjacent cavities board member;The girt strip of the reinforced concrete frame girt strip composition assembled bidirectional stress floor of the regeneration beam and longitudinal direction;The cavity board member is constituted by reinforced concrete frame girt strip and surface exposed reinforcing bar and at pole and bottom wing listrium;For the joint close in the lower surface of assembled bidirectional stress floor, joint close is intermittent;Joint close does not extend through the top flange plate of assembled bidirectional stress floor.

Description

A kind of assembled bidirectional stress floor
Technical field
The present invention relates to a kind of assembled architecture systems technologies, and in particular to a kind of assembled bidirectional stress floor.
Background technique
Concrete prefabricated board member production department, China's the 1980s is in the great development stage, due to concrete prefabricated board structure The bad reason of the entirety of part, is prohibited from using;Floor is carried out using large panel structure, cast-in-place during dwelling construction by country Concrete structure, cast-in-place concrete hollow floor slab structure, cast-in-place concrete frame structure, cast-in-place concrete frame-shear-wall structure Deng;With Process of Housing Industrialization, a few days ago, steel-mix the mixed combination cavity building roof structural system of composite structure and steel-get back it is fast That is speed development, China's precast assemble floor ground zero, it is big to overlap assembled in the upper surface of beam using longitudinal superimposed sheet again Plate.
The ZL200410082381.9 " a kind of hollow floor slab with small dense ribs " declared such as inventor, hollow filling body is embedded in small close " T font " stress cross-section hollow layer is formed in rib superstructure, and it is smooth to solve the small ribbed cavity superstructure top plate in " T font " stress section The problem of with large span, large space, big load.But the generation hollow filling body setting and hardening time is long, mould utilization factor is low, empty The defects of heart filling big matter weight of volume density, production and transport inconvenience and obturator globality poor cracky.
In order to promote China's housing industrialization to develop, a kind of ZL200820126232.1 " cast-in-place fashioned iron of inventor's application Concrete cavity building roof " and ZL200910143977.8 " a kind of cast-in-place open web superstructure building heating using solar energy " and ZL201110332999.6 " it is a kind of using foam composition obturator make hollow floor system " assembled formed steel construction with it is cast-in-place Armored concrete cavity building roof organically combines, and solves the fire prevention of assembled formed steel construction, gets rusty, quality, shearing resistance, throughout the year dimension The problem of shield, cost etc. and inexhaustible solar energy is converted into hot wind it can warm oneself and utilize foam plastic Material, had both solved the technical problem of non-core-drawing pore-creating, and played sound-insulating and heat-insulating heat preservation;Inventor also applies A kind of ZL200810192973.4 " expanding material for cast-in-place cavity floor " foamed cement;These inventions, although being China Process of Housing Industrialization has tamped basis, but entirely cast-in-site, poor controllability, implements technical strong, is not easy to be formed Industrialized production.
To realize industrialized production, inventor applies for a kind of ZL201320467350.X " cast-in-situ hollow building roof pore-forming use again The netted box component of combined type " and ZL201520186565.2 " a kind of that cast-in-place cavity building roof is engraved with steel mesh with ribbing ", to existing It pours hollow floor technology and carries out General Promotion, realize transition and upgrade, update and significantly reduce the self weight of cavity building roof, Self-heat preservation heat insulation performance is added, safety of structure is strong, realizes superstructure large span, large space, big load;Though solving pore-forming The problem of component industrialized production, needs big building template and steel pipe column to support, and causes the molding time long and influences construction speed Defect;But the continuous promotion of the above cast-in-situ hollow building roof background technique, it is assembled architecture large span, the water without bright beam Flat structure has established the basis of hard stone.
Country pushes away assembled architecture by force at present, promotes building science and technology progress;No matter from the connotation and extension of building How to extend and updates, it is all related with architectural structure system;Using multi-functional, economy, scientific and technological content, energy conservation and environmental protection and market Demand is big, safety coefficient is high, and meets the architectural structure system of national industrial policies and industrial development direction.Therefore, inventor On the basis of existing background technique self, by cast-in-situ hollow building roof technical application into assembled architecture, formed novel pre- Assembling frame structural system processed;By cast-in-place cavity building roof Technology Difficulties problem factory industry neutralizing determine, be formed, lattice of establishing rules, Fixed assembly position quantitatively produces prefabricated member, and the mode that structure is integrally forced through cast-in-place concrete is handled, industrialization Prefabricated assembled Cavity structural member is produced to combine with cast-in-site rc-frame-beam column.Research and develop a kind of assembled Bidirectional stress floor solves the problems, such as existing one-way slabs bidirectional stress, while solving existing longitudinal superimposed sheet, is superimposed on the upper surface of beam It is formed with the assembled architecture of bright beam, longitudinal superimposed relationship of beam and assembled superimposed sheet, is changed into assembled superimposed sheet It is superimposed on beam horizontal direction, is the great breakthrough for realizing assembling frame structural system new technology, has become assembled and build Build the urgent need of technical field innovation.
Summary of the invention
It is an object of the invention to play the advantage of the prior art, overcome the prior art;Specifically " concrete is pre- Problem between component processed " and " building cast-in-situ technology ", the former is globality poor, and the latter is controllable not strong;Industrialized production is pre- Assembled cavity board member processed combines with cast-in-site reinforced concrete beam column, efficiently solves " concrete prefabricated The globality of component technology ", the controllability of " building cast-in-situ technology ", fundamentally improves the overall security of building, promotes to build Build scientific and technological progress;Using frame-type armored concrete girt strip and the assembled cavity constituted at pole and book bottom wing listrium Board member greatly alleviates assembled cavity plate construction weight, has established base to realize that large span has no bright beam building Plinth;In order to solve bidirectional stress, structure order forms regeneration beam, constitutes a kind of assembled bidirectional stress floor, save to rib of slab muscle The benefit that layer high spatial shared by bright beam generates reaches optimization available frame structure technology system;Make full use of the prefabricated life of industrialization The advantage of assembled cavity board member is produced, then longitudinal superimposed relationship of beam and assembled superimposed sheet the prior art optimizes, and turns Become for assembled superimposed sheet being superimposed on beam horizontal direction, realizes assembled concealed-beam floor, both improved the general safety of building Property, and solve existing longitudinal superimposed sheet, it is superimposed on the upper surface of beam and is formed with bright beam building structure, cause bright beam to occupy interlayer high Degree, implement controllability is difficult, site operation cause environmental pollution, matter weight, construction cost is high, engineering progress is slow, with largely building Building mould and bracing members such as lead to the molding time long and influence construction speed at a series of defects.
Technical scheme is as follows, a kind of assembled bidirectional stress floor, includes column, girder, regeneration beam, cavity plate Component, floor top flange plate and joint close;It is characterized in that in girder reinforcing bar space, cavity board member transverse direction frame rib beam steel On formation regeneration beam connecting portion, cavity plate component surface steel mesh, it is double that same period cast-in-place concrete is combined into a kind of assembled To stress floor;The regeneration beam is the frame rib beam steel of site welding adjacent cavities board member;The regeneration beam and vertical side To reinforced concrete frame girt strip composition assembled bidirectional stress floor girt strip;The adjacent cavities board member frame girt strip The contact site of reinforcing bar is provided with built in frame rib beam steel or exposed device;The cavity board member is by reinforced concrete frame It girt strip and surface exposed reinforcing bar and is constituted at pole and bottom wing listrium;The joint close is under assembled bidirectional stress floor Surface, joint close are intermittent;Joint close does not extend through the top flange plate of assembled bidirectional stress floor.
Another preferred embodiment, adjacent two pieces of cavitys board member transverse direction frame rib beam steel end preset to " L shape ".
Another preferred embodiment, the transverse direction bar dowel use truss frame girt strip;Under the truss frame girt strip End bar is prefabricated into built in " L shape " or directly to exposed;End bar is directly exposed on the truss frame girt strip, truss-like frame The protruded length > 40mm of end bar on frame girt strip.
Another preferred embodiment, it is described at pole be steel mesh with ribbing engrave or polyphenyl block or plastics cavity or cement cavity or Plate cavity;Cracking resistance steel mesh is compounded in the lower flange, lower flange plate thickness is less than 30mm.
Another preferred embodiment, the base angle chamfered edge of adjacent two pieces of cavitys board member longitudinal direction at inclined-plane or arc or Ornamental strip is set on engagement sealing.
Another preferred embodiment, the girder is locally exposed, pads head beam height in the beam steel two sides of beam bottom engineering template Rectangle cushion block mould, assembled cavity board member is placed on the rectangle cushion block mould.
Another preferred embodiment, the interior dew device of the transverse direction frame rib beam steel use delicate light material or small band Rib cavity.
The cavity board member bottom surface of another preferred embodiment, the interior dew part of the transverse direction frame rib beam steel is locally pre- If steel net plate with ribbing.
Another preferred embodiment, the assembled cavity board member both ends slope inwardly downward.
Another preferred embodiment is provided in the assembled cavity board member using solar powered ventilation system and fire-fighting row The default air supply duct of cigarette system;
A kind of assembled bidirectional stress floor of the invention, the mainly prefabricated assembled cavity board member skill of industrialized production Art and assembled in situ and integrally formed bidirectional stress floor technology.
Assembled cavity plate element precast technology is decomposition architectural design drawing on the basis of by architectural design drawing, For the function and geometric dimension of cavity building roof, assembling form is quantified, under the premise of meeting principal mode specification, drawing point Solution is produced at N number of assembled cavity board member, factory by the paper organization being decomposed;Produce assembled cavity plate building course such as Under: stock, mainly include reinforcing bar, cement, sandstone, mold, steel mesh with ribbing engrave, cement foamed device and material, mechanical equipment Deng;Two, make important document, and 1. by the drawing making binding rib reinforcement or machinery production girder truss being decomposed;2. assembling steel mesh with ribbing It engraves, special mechanical equipment is made into ribbed steel dictyosome and reinforcing bar dictyosome;Engraving ribbed steel dictyosome network pressure bending trace, engrave The upper and lower ends mouth of end net vertical direction packs steel plate molding edge, after supporting network is packed respectively by engraving net, supporting network, engrave end net Usage ratio transport composing room;Opening engraves net, from bending from the bending trace of compacting, will engrave end net molding edge and is put into and engrave net In the V-arrangement rib at edge, " Jiong shape " supporting network is placed in equivalent expanded metal lath thread, will be engraved net both ends split and is carried out welding and is made Steel mesh with ribbing is engraved;Steel mesh engraves point punching expanding and is punched into cellular type, and the main identical point of the two is that have rib and punching and other Common ground, difference are that material width and mesh are different;3. intercostal through tube (needs anti-using solar heating or fire-fighting When fire row flue) it enables;4. the exposed outlet mold end of longitudinal rib beam steel is arranged;5. assembled cavity plate member openings basis mould;6. Assembled cavity board member Liu Kou or the inclined-plane adding module in vertical formwork are formed;The production of three, assembled cavity board members, The bed die system of assembled cavity plate frame rail is gone into die-filling workshop and rib reinforcement and obturator workshop, is equipped on bed die vertical The opening basis of template, specifications and models needed for being formed is framed, on opening basis framed interior placement girt strip reinforcing bar, steel mesh with ribbing engrave, Straight through tube etc. between willow mouth mold, girt strip;Bed die system track will be carried again goes to pouring hall's computer automatically by cement, sand, stone ratio Example is sent to mixing plant and adds water and stirs into concrete after matching, the slump controls within 200mm;Start shake table, casting assembly The concrete of formula cavity board member is rested after touching flat receipts smooth treatment to the vibration of assembled cavity plate component surface with plate vibration device; The bed die system of track is gone into steam curing system again;The bed die system of track is gone into finished product station again, needed for demoulding obtains Assembled cavity board member;It is formulated to warehouse for finished product feeding or inventory eventually respectively;The bed die system of track goes to initial position, enters Next flow state;The bed die system of track is set, allows for intersection dislocation operation, improves efficiency, each workshop is used Endless track manner connection, the bed die system loop orbit of track one week illustrate that an assembled cavity board member production is completed;Ring It keeps in balance drop around track, is the resistance for reducing track operation, slope is climbed up in zero load, and assembled cavity board member is poured from concrete Note extremely unloading row descending;The assembled cavity board member of above-mentioned process production, globality is strong, and structurally reasonable, quality standard is high, work Sequence is controlled, and self-heat conserving sound insulation value is good.
Assembled in situ and integrally formed bidirectional stress floor technology;The assembly of assembled cavity board member is empty in building It is carried out in chamber superstructure girder horizontal direction, the girder engineering mold of Zhi Li 1000mm wide, reinforcement mould support, support, which meets, to be applied The requirement of work load;Peng pricks beam steel on beam bottom board, by assembled cavity plate lifting component on beam bottom board, by assembled sky Cavity plate component both ends tilt angle is downward, has both increased the stress section of beam, and increases the effective of assembled cavity board member and beam Engagement section;The exposed girt strip reinforcing bar in assembled cavity board member both ends is extend into girder reinforcing bar, extend into girder reinforcing bar Girt strip reinforcing bar, overlaps as far as possible;Adjacent members interface flatness is adjusted, increases coaxial branch in assembled cavity board member middle part position Support, the arch camber for adjustment assembly formula cavity board member;Assembled cavity board member transverse direction bar dowel uses truss frame rib Beam;End bar is prefabricated into built in " L shape " under truss frame girt strip, mainly spells touching weldering in adjacent two " L shape " girt strip reinforcing bars When connecing, increase engagement welding surface;Truss frame girt strip reinforcing bar can also directly exposed, truss frame girt strip protruded length > 40mm mainly increases welding distance and is conducive to dislocation welding;When according to solar powered ventilation system and fire-fighting smoke exhaust system, The adjacent preset pipeline of assembled cavity board member of logical girder is connected with short tube;Assembled cavity board member upper berth is set again Flange plate reinforcing bar penetrating main beam reinforcing bar, the top flange plate reinforcing bar being laid with partially passes through or bind in reserved U ring or U By ring or on girder truss exposed steel bar, increase the bond strength of be laid with top flange plate reinforcing bar and assembled cavity board member;If The bright beam of dew point is wanted, in the rectangle cushion block mould of the beam steel two sides of beam bottom engineering template pad head beam height, which is both assembly The cushion block of formula cavity board member, and be the mold of head beam height, assembled cavity board member both ends are placed on rectangle cushion block On mould;Cast-in-situ steel reinforced concrete forms the concealed beam assembled cavity building roof top flange plate integrated poured with girder, regeneration beam, Casting concrete is conserved, demoulding, thus a kind of assembled bidirectional stress floor needed for obtaining.
Detailed description of the invention
Fig. 1 is a kind of assembled bidirectional stress of the invention floor level figure.
Fig. 2 is that present invention steel mesh with ribbing engraves structure chart.
Fig. 3 is the girder truss embodiment of assembled cavity board member of the present invention.
Fig. 4 is the joint close chamfered edge or arc schematic diagram of assembled cavity board member of the present invention.
Fig. 5 is the joint close ornamental strip schematic diagram of assembled cavity board member of the present invention.
Fig. 6 is that a kind of assembled bidirectional stress floor regeneration of present invention beam bottom portion sets steel mesh schematic diagram.
Specific embodiment
The present invention is further described with reference to the accompanying drawing.
Fig. 1 is a kind of assembled bidirectional stress of the invention floor level figure, when the present invention is implemented, assembled bidirectional stress building Plate 1;The column net of the composition floor 1 of column 2;Girder 3 and column 2 constitute the frame for haveing suffered building, and girder 3 and column 2 are armored concrete knots Formed steel construction can also be used in structure;Regeneration beam 6 is that 7 transverse direction frame girt strip of cavity board member, 5 reinforcement welding is generated to regeneration beam 6; Cavity board member 7 is prefabricated in the factory, comprising reinforced concrete frame girt strip 5 and surface exposed reinforcing bar 122 and at 12 He of pole Bottom wing listrium is constituted;Its geometric dimension is depending on the decomposition of architectural design drawing Secondary Design, according to decomposing standard component or different The production of type number of packages amount tissue;Assembled cavity board member upper berth is set top flange plate reinforcing bar penetrating main beam by 1 top flange plate 21 of floor Reinforcing bar 31, the top flange plate reinforcing bar being laid with partially passes through or bind in reserved U ring 18 or by U ring or girder truss 11 On exposed steel bar, increase the bond strength of be laid with top flange plate reinforcing bar and assembled cavity board member 7, cast-in-situ steel reinforced concrete Form the concealed beam assembled cavity building roof top flange plate 21 integrated poured with main 3 beams, regeneration beam 6;Joint close 9 is two-way in assembled The lower surface of stress floor, joint close depth > 120m, joint close 9 do not extend through the top flange plate of assembled bidirectional stress floor 21, for the holistic resistant behavior of assembled bidirectional stress floor, joint close is intermittent, bidirectional stress floor only some Joint close 9, another part are the plates of whole stress, and that is, the position not stressed is joint close 9, and the position of stress is close Real top flange plate 21 and regeneration beam;The key problem in technology is the formation for regenerating beam, and regeneration beam 6 is that scene is welded by welding machine special The frame rib beam steel 51 of adjacent cavities board member 7, frame rib beam steel are prefabricated into " L shape " and mainly increase two pieces of adjacent cavities The face of the contact site of board member frame rib beam steel 51 and effectively welding, with the steel reinforced concrete frame of regeneration beam 6 and longitudinal direction The girt strip 5 of the composition assembled bidirectional stress floor of frame girt strip 51;The contact of the adjacent cavities board member frame rib beam steel 51 Position is provided with built in frame rib beam steel or exposed device 10;Device 10 is temporarily arranged, and main function is to guarantee coagulation 5 transverse steel of girt strip is exposed when soil casting cavity board member 7, is implemented with delicate light material or areola, cavity board member 7 Device 10 is abolished after moulding by casting;It is to increase structural strength and be conducive to industrialized life using truss frame girt strip 11 It produces, when using solar powered ventilation system and fire-fighting smoke exhaust system, connects the adjacent assembled cavity board member of logical girder with short tube Preset pipeline;The base angle chamfered edge of adjacent two pieces of cavitys board member longitudinal direction is at inclined-plane or arc, on the engagement sealing of longitudinal direction Setting ornamental strip is to realize structure problem with decorating and solve.
Fig. 2 is that present invention steel mesh with ribbing engraves structure chart, as shown in Fig. 2, feeding machine, bicker system, cutter will be utilized Equal special mechanical equipments make steel mesh with ribbing and engrave 12;The mesh that steel mesh with ribbing is engraved, can use expanding or punched holes type, and the two is only used Expect that width and pass are different;At the construction field (site) by bending tool, by bending form steel mesh with ribbing engraves 12 one by one at bending trace Engrave 125 main body of net in periphery;Factory engraves according to needed for the height cutting that steel mesh with ribbing is engraved and holds 121 expanded metal lath body length of net, and every It engraves end net 121 and cuts out sheet metal two panels bound edge, two panels sheet metal leaf length≤steel mesh with ribbing engraves 12 width, will be thin with special equipment Sheet steel is pressed into V-shape, wraps up being wrapped in V-shape sheet metal piece by press machine after engraving the both ends for holding net 121 and engraves end net Two-port flattens, and both end net two-port was engraved in shaping and protection, and inhibiting effect, steel mesh with ribbing are played in the distortion engraved to steel mesh with ribbing It engraves inside 12 by supporting network support 124.
Fig. 3 is the girder truss embodiment of assembled cavity board member of the present invention, and the present embodiment uses truss frame girt strip 11 be in order to increase and structural strength and be conducive to industrialized production, it is main consider the built-in of transverse truss formula frame girt strip 11 or It is exposed, it is intended that be conducive to adjacent transverse truss frame girt strip 11 connects into regeneration beam 6.
Fig. 4 is the chamfered edge or arc schematic diagram of assembled cavity board member of the present invention, assembled cavity board member joint close 9 It is structure problem, because 11 stress area of truss girt strip of the joint close 9 has connected regeneration beam 6 and the casting of 10 position of built-in is mixed Solidifying soil solves, and by taking the measure of chamfered edge or arc, gap 901 is decorated in artificial formation, by doing for structure flaw decoration Method solves.
Fig. 5 is the joint close ornamental strip schematic diagram of assembled cavity board member of the present invention, the engagement of assembled cavity board member Seam 9 is structure problem, because 11 stress area of truss girt strip of the joint close 9 has connected regeneration beam 6 and 10 position of built-in is poured It infuses concrete to solve, by applying 9 ornamental strip 902 of joint close, artificial decorates joint close by ornamental strip.
Fig. 6 is that a kind of assembled bidirectional stress floor regeneration of present invention beam bottom portion sets steel mesh schematic diagram, to form regeneration beam, Ensure reinforcing steel bars exposed by setting built-in 10, although exposed reinforcing bar after removing device, leaves cavity, be poured coagulation Leakage must be descended when native, regeneration beam bottom portion sets steel mesh 19 and stops monolithic concrete not lower leakage when being poured.
Finally it should be noted that: the above embodiments are merely illustrative of the technical scheme of the present invention and are not intended to be limiting thereof, to the greatest extent Invention is explained in detail referring to above-described embodiment for pipe, it should be understood by a person of ordinary skill in the art that still Can be with modifications or equivalent substitutions are made to specific embodiments of the invention, and end is detached from any of spirit and scope of the invention Modification or equivalent replacement, are intended to be within the scope of the claims of the invention.

Claims (6)

1. a kind of assembled bidirectional stress floor includes column, girder, regeneration beam, cavity board member, floor top flange plate and engagement Seam;It is characterized in that forming regeneration beam connecting portion, cavity in girder reinforcing bar space, cavity board member transverse direction frame rib beam steel On the steel mesh of board member surface, same period cast-in-place concrete is combined into a kind of assembled bidirectional stress floor;The regeneration beam is The frame rib beam steel of site welding adjacent cavities board member;The reinforced concrete frame girt strip group of the regeneration beam and longitudinal direction At the girt strip of assembled bidirectional stress floor;The contact site of the adjacent cavities board member frame rib beam steel is provided with frame Girt strip reinforcing bar is built-in or exposed device;The cavity board member is by reinforced concrete frame girt strip and surface exposed reinforcing bar and pore-forming Component and bottom wing listrium are constituted;For the joint close in the lower surface of assembled bidirectional stress floor, joint close is intermittent;Engagement Seam does not extend through the top flange plate of assembled bidirectional stress floor.
2. a kind of assembled bidirectional stress floor as described in claim 1, it is characterised in that adjacent two pieces of cavity plate structures Part transverse direction frame rib beam steel end presets to " L shape ".
3. a kind of assembled bidirectional stress floor as described in claim 1, it is characterised in that adjacent two pieces of cavity plates The base angle chamfered edge of component longitudinal direction at inclined-plane or arc or engagement sealing on ornamental strip is set.
4. a kind of assembled bidirectional stress floor as described in claim 1, it is characterised in that the girder is locally exposed, in beam The rectangle cushion block mould of head beam height is padded in the beam steel two sides of bottom engineering template, and it is empty to place assembled on the rectangle cushion block mould Cavity plate component.
5. a kind of assembled bidirectional stress floor as described in claim 1, it is characterised in that the assembled cavity board member Both ends slope inwardly downward.
6. a kind of assembled bidirectional stress floor as described in claim 1, it is characterised in that the assembled cavity board member In be provided with default air supply duct using solar powered ventilation system and fire-fighting smoke exhaust system.
CN201610921100.7A 2016-10-21 2016-10-21 A kind of assembled bidirectional stress floor Active CN106381953B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610921100.7A CN106381953B (en) 2016-10-21 2016-10-21 A kind of assembled bidirectional stress floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610921100.7A CN106381953B (en) 2016-10-21 2016-10-21 A kind of assembled bidirectional stress floor

Publications (2)

Publication Number Publication Date
CN106381953A CN106381953A (en) 2017-02-08
CN106381953B true CN106381953B (en) 2019-03-26

Family

ID=57958123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610921100.7A Active CN106381953B (en) 2016-10-21 2016-10-21 A kind of assembled bidirectional stress floor

Country Status (1)

Country Link
CN (1) CN106381953B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989247B (en) * 2017-12-19 2023-09-22 广东省建筑设计研究院 Assembled superposed hollow floor system and construction method thereof
CN110284650A (en) * 2019-06-28 2019-09-27 王本淼 A kind of production method of assembled cavity floor

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4196242B2 (en) * 1999-12-13 2008-12-17 清水建設株式会社 Large span slab frame and slab and frame construction method for frame
GB0619580D0 (en) * 2006-10-04 2006-11-15 Expament Building Products Ltd Formwork system
CN105839812A (en) * 2016-05-06 2016-08-10 湖南标迪夫节能科技有限公司 Self-thermal insulation wall assembled by prefabricated wallboard components
CN105804272B (en) * 2016-05-06 2018-11-02 湖南标迪夫节能科技有限公司 It is a kind of to engrave prefabricated assembled wallboard component with steel mesh with ribbing
CN105888127A (en) * 2016-05-06 2016-08-24 湖南标迪夫节能科技有限公司 Prefabricated assembly type self-insulation wallboard component
CN105971174A (en) * 2016-05-06 2016-09-28 湖南标迪夫节能科技有限公司 Building method for assembly type cast-in-place cavity building cover
CN105839822A (en) * 2016-05-06 2016-08-10 湖南标迪夫节能科技有限公司 Assembly type prefabricated part for cavity floor system
CN106013567A (en) * 2016-06-08 2016-10-12 湖南标迪夫节能科技有限公司 Fabricated stressed island reinforced concrete cavity floor system
CN105863140A (en) * 2016-06-08 2016-08-17 湖南标迪夫节能科技有限公司 Precast hollow floor's component for stress island based hollow floor system
CN206581467U (en) * 2016-10-21 2017-10-24 王本淼 A kind of assembled bidirectional stress floor

Also Published As

Publication number Publication date
CN106381953A (en) 2017-02-08

Similar Documents

Publication Publication Date Title
CN106381952B (en) A kind of assembled overlapping cavity building roof
CN106351375A (en) Stress island assembled type hollow floor
CN105804272B (en) It is a kind of to engrave prefabricated assembled wallboard component with steel mesh with ribbing
CN106013567A (en) Fabricated stressed island reinforced concrete cavity floor system
CN105863140A (en) Precast hollow floor's component for stress island based hollow floor system
CN105780993B (en) One kind exempting from the prefabricated assembled cavity plate of formwork
CN105839822A (en) Assembly type prefabricated part for cavity floor system
CN205839952U (en) Selective model integral system
CN106381953B (en) A kind of assembled bidirectional stress floor
CN106381951B (en) A kind of assembled architecture cavity floor
CN206110473U (en) Atress island cavity is assembled cavity board for superstructure
CN105780990A (en) Prefabricated assembly type cavity floor slab for cavity floor system
CN105971174A (en) Building method for assembly type cast-in-place cavity building cover
CN206581467U (en) A kind of assembled bidirectional stress floor
CN206233435U (en) A kind of assembled architecture cavity floor
CN206110398U (en) Outer wall body of antidetonation flexonics assembly self preservation temperature
CN205840083U (en) One exempts from the prefabricated assembled cavity plate of formwork
CN206110428U (en) Form assembled cavity board of two -way atress superstructure
CN206581465U (en) A kind of stress island assembled cavity floor
CN205857446U (en) A kind of engrave prefabricated assembled wallboard component with steel mesh with ribbing
CN206110324U (en) Wall body with prefabricated assembled wall panel component combination
CN206110426U (en) Dark roof beam superstructure of assembled
CN206110427U (en) Assembled coincide cavity superstructure
CN106121030A (en) Selective model integral system
CN206220324U (en) A kind of open cavity prefabricated board in cast-in-place cavity building roof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant