CN106121030A - Selective model integral system - Google Patents

Selective model integral system Download PDF

Info

Publication number
CN106121030A
CN106121030A CN201610296940.9A CN201610296940A CN106121030A CN 106121030 A CN106121030 A CN 106121030A CN 201610296940 A CN201610296940 A CN 201610296940A CN 106121030 A CN106121030 A CN 106121030A
Authority
CN
China
Prior art keywords
cavity
steel
plate member
floor
wall plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610296940.9A
Other languages
Chinese (zh)
Inventor
王本淼
尚仁杰
扶长生
韩爱兴
王海崴
贾英杰
程志军
王晓锋
马锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan BDF Energy Saving Technology Co Ltd
Original Assignee
Hunan BDF Energy Saving Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan BDF Energy Saving Technology Co Ltd filed Critical Hunan BDF Energy Saving Technology Co Ltd
Priority to CN201610296940.9A priority Critical patent/CN106121030A/en
Publication of CN106121030A publication Critical patent/CN106121030A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/26Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated with filling members between the beams
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2103/00Material constitution of slabs, sheets or the like
    • E04B2103/02Material constitution of slabs, sheets or the like of ceramics, concrete or other stone-like material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention provides selective model integral system, comprises building structure main body, the floor of horizontal direction, the wallboard of vertical direction and door and window mouth;Described building structure main body is reinforced concrete structure or steel-concrete combined structure;The floor of described horizontal direction is assembled cavity floor or cast-in-situ steel reinforced concrete cavity floor;Described assembled cavity floor precast frame component makes in factory, top flange plate cast on-site;The wallboard of described vertical direction is assembled by prefabricated wall plate member;Described prefabricated wall plate member is decomposed the physical dimension determined and the production of specifications and models tissue by factory by design drawing;Described prefabricated wall plate member has self-heat conserving function;Described door and window mouth is formed when prefabricated wall plate member assembly.The prefabricated wall plate member that above-mentioned flow process produces, globality is strong, rational in infrastructure, and quality standard is high, and operation is controlled, and self-heat conserving sound insulation value is good.

Description

Selective model integral system
Technical field
The present invention relates to a kind of housing industrialization systems technology, be specifically related to selective model integral system skill Art.
Background technology
The eighties in 20th century, China's concrete prefabricated element produced the great development stage that is in, and country is in dwelling construction process In, floor have employed hollowcore precast plate structure, large panel structure, cast-in-place concrete structure, cast-in-place concrete hollow floor slab structure, shows Water frame-shear-wall structure etc., along with Process of Housing Industrialization, a few days ago, steel-concrete combined structure and steel reinforced concrete combination cavity building roof Structural system is got back and is developed rapidly.
The ZL98231113.3 structural member for concrete thin-wall cylinder declared such as inventor, is fabricated to the tubular obturator sealed, Provide tubular, hollow obturator for realizing cast-in-situ hollow building roof, solve the non-technique difficulty taking out heart pore-forming of cast-in-place cavity building roof Topic;But there is single load bearing and the low problem of evacuation rate;In order to solve this defect, as inventor declares ZL200410082381.9 " a kind of hollow floor slab with small dense ribs ", hollow filling body is embedded in floor slab with small dense ribs formation " T font " and is subject to Power cross-section hollow layer, solves the problem that " T font " stress cross section little ribbed cavity superstructure top board is smooth.But produce hollow filling out It is long to fill the body setting and hardening time, and mould utilization factor is low, hollow filling body density big matter weight, and production and transport inconvenience and obturator are overall The defects such as property difference cracky.
In order to advance China's housing industrialization development, ZL200820126232.1 " a kind of cast-in-place shaped steel of inventor's application Concrete cavity building roof " and ZL200910143977.8 " a kind of cast-in-place open web superstructure building heating utilizing solar energy " and ZL201110332999.6 " a kind of hollow floor system using foam composition obturator to make " assembled formed steel construction with cast-in-place Armored concrete cavity building roof organically combines, and solves the fire prevention of assembled formed steel construction, gets rusty, quality, shearing resistance, ties up throughout the year Protect, the problem of the aspect such as cost and inexhaustible solar energy is converted into hot blast can warm oneself and utilize foam plastic Material, had both solved the technical barrier of non-core-drawing pore-creating, played again the effect of sound-insulating and heat-insulating insulation;Inventor also applies for ZL200810192973.4 " a kind of expanding material for cast-in-place cavity floor " foam cement;Although these patent applications are for I State's Process of Housing Industrialization has tamped basis, but entirely cast-in-site, poor controllability, implement technical by force, be difficult to shape Become industrialized production.
For realizing industrialized production, inventor applies for that ZL201320467350.X " use by a kind of cast-in-situ hollow building roof pore-forming again The netted box component of combination type " and ZL201420814197.8 " the self-heat conserving wall that a kind of mechanism steel mesh is compound with light-weight inorganic thing Plate ", existing hollow building cover technology of watering is carried out General Promotion, it is achieved that transition and upgrade, update and significantly reduce cavity The deadweight of superstructure, adds self-heat preservation heat insulation performance, and safety of structure is strong, it is achieved that superstructure large span, large space, big load; Though the problem solving into pole industrialized production, still there is site operation poor controllability, need substantial amounts of building template And bracing members, cause molding time length and affect construction speed and the defect of potential safety hazard that steel support structure part rapid wear causes.
Country carries out steel construction strategy and carries out assembled architecture at present, lays foundation for housing industrialization, no matter from building The connotation and extension how to extend and to update, all relevant with architectural structure system;Use multi-functional, economy, scientific and technological content, joint Can environmental protection and the market demand is big, safety coefficient is high, meet again the building structure of national industrial policies and industrial development direction System.Therefore, prior art, on the basis of existing background technology of controlling oneself, is carried out perfect, upgrading by inventor, and integrated application is to living In residence industrialization, formed in novel prefabricated assembled frame-shear-wall structure system;Cast-in-place cavity building roof Technology Difficulties is asked Topic is dissolved certainly at factory industry, shapes, lattice of establishing rules, surely assembles position, quantitatively produces prefabricated member, and structure entirety is forced through existing The mode of field cast concrete processes, organic with cast-in-site armored concrete for prefabricated assembled for industrialized production Cavity structural member Combine.Research and development selective model integral system, is to realize the prefabricated assembled new skill of frame-shear-wall structure system The great breakthrough of art, has become as the urgent need of housing industrialization technical field innovation.
Summary of the invention
It is an object of the invention to advance Process of Housing Industrialization, utilize selective model integral system, perfect Available frame shear wall structure system;Make full use of the advantage of factory industry, the prefabricated wall plate member of Prefabrication, solve The problems such as the construction of existing system of determining existence, environmental protection, matter weight, cost, work efficiency;Building structure entirety is forced through cast-in-site steel The mode of reinforced concrete solves, and prefabricated assembled for industrialized production wallboard and assembled cavity floor are mixed with cast-in-site reinforcing bar Solidifying soil combines, and reaches to optimize available frame shear wall structure system technology, ties existing assembling frame shear wall Structure system system carries out transition and upgrade, updates;Solve existing system exist overall cast-in-site poor controllability, implement technical By force, site operation causes environmental pollution, matter weight, construction cost is high, engineering progress is slow, exempt substantial amounts of building template and steel props up Support, causes molding time length to affect construction speed;Use the potential safety hazard that causes of its structural member rapid wear of bracing members and be difficult to shape Become the problems such as industrialized production.
Technical scheme is as follows, selective model integral system, comprises building structure main body, level side To floor, the wallboard of vertical direction and door and window mouth;Described building structure main body is reinforced concrete structure or steel reinforced concrete combination knot Structure;The floor of described horizontal direction is assembled cavity floor or cast-in-situ steel reinforced concrete cavity floor;Described assembled cavity Floor precast frame component makes in factory, top flange plate cast on-site;The wallboard of described vertical direction is by prefabricated Wall plate member is assembled;Described prefabricated wall plate member is decomposed the physical dimension and rule determined by factory by design drawing Lattice number tissue produces;Described prefabricated wall plate member has self-heat conserving function;Described door and window mouth is at prefabricated wall Formed during board member assembly.
The assembled cavity floor precast frame component thickness of the floor of described horizontal direction equal with depth of beam or height Unequal, time the most unequal, deck-molding is in framework.
The girt strip reinforcing bar that described assembled cavity floor precast frame component two ends are exposed extend in beam steel, prick or The girt strip reinforcing bar that welding extend in beam.
In the precast frame of described assembled cavity floor precast frame component, it is preset with obturator;Described obturator is Steel mesh with ribbing is engraved or polyphenyl block or plastics cavity or cement cavity or sheet material cavity.
The precast frame of described assembled cavity floor precast frame component, is formed N number of band bottom wing by N number of open mold body The precast frame cavity of listrium,;Described open mold is steel mould or bamboo wooden model or plastics mould;Described leukorrhagia flange plate is prefabricated Framework cavity is covered with permanent thin cover plate, and permanent thin cover plate physical dimension is more than the physical dimension of open mold bore.
At the reinforced concrete girt strip natural axis of described assembled cavity floor precast frame component, it is prefabricated with connection gluten concrete rib The hole of beam adjacent both sides cavity.
Described self-heat conserving function be armored concrete rib be cavity rib, cavity rib is formed by steel mesh cylinder with ribbing, band rib steel Net cylinder waters and is inoculated with the self-thermal insulation material that cement mortar foaming is formed;Described steel mesh with ribbing waters in engraving and is inoculated with what cement mortar foaming was formed Self-thermal insulation material.
Described cast-in-situ reinforced concrete column, the outdoor face of cast-in-situ steel reinforced concrete beam are mounted with heat-barrier material.
Described prefabricated Cavity structural member is preset with forceful electric power or the sleeve pipe of light current circuit or pipeline.
In described reinforced concrete bottom wing listrium, it is preset with fire-fighting smoke controlling mouth.
The outdoor table of described prefabricated wall plate member is provided with solar energy equipment.
The selective model integral system of the present invention, is carried out on the basis of by architectural design drawing, first Decomposing architectural design drawing, for function and the physical dimension of cavity building roof, assembling form quantifies, and is meeting principal mode specification On the premise of, resolve into the drawing of the specifications and models of N number of prefabricated wall plate member, factory is raw by the paper organization being decomposed Produce;Produce prefabricated wall plate member process as follows: one. preparation, get the raw materials ready, mainly include reinforcing bar, cement, sandstone, mould Tool, steel mesh with ribbing are engraved, cement foamed device and material, plant equipment etc.;Two. make important document, 1. by the drawing making being decomposed Colligation rib reinforcement, to meet energy-saving and thermal insulating requirement, needs to arrange steel mesh cylinder with ribbing, binding strap in the middle of colligation rib reinforcement Rib steel net cylinder becomes cavity reinforcing rib;2. assembled belt rib steel net is engraved, and will utilize the special machines such as feeding machine, bicker system, cutter Tool equipment making steel plate dictyosome or reinforcing bar dictyosome;Net compacting bending trace will be engraved, engrave and hold the two-port up and down of net vertical direction to pack Steel plate molding edge, supporting network pack respectively after by engrave net, supporting network, engrave end net usage ratio transport composing room;Beat Open and engrave net, bending at the bending trace of compacting, put in the V-arrangement rib engraving network edge, at equivalent steel plate by engraving end net molding edge " Jiong shape " supporting network placed by net thread, will engrave to net two ends split and carry out welding and make steel mesh with ribbing and engrave;A point die-cut expansion engraved by steel mesh Opening formula and be die-cut into cellular type, both main identical points are to have rib and die-cut and other common ground, and difference is material width Different;3. intercostal through tube (needing to use solar heating or fire-fighting fire-proof smokejack) enables;4. longitudinal rib beam steel is set Expose outside mouth die end;The most prefabricated wall plate member opening basis mould;The most prefabricated wall plate member Liu Kou or inclined-plane exist Vertical formwork adds module formed;Three. the making of prefabricated wall plate member, by prefabricated wall plate member band cincture The bed die system of track forwards die-filling workshop and rib reinforcement and obturator workshop to, equipped shuttering on bed die, forms required specification The opening basis of model is framed, opening basis framed in lay girt strip reinforcing bar, steel mesh with ribbing is engraved, between willow mouth die, girt strip through Pipeline etc.;Band is forwarded to pouring hall again around the bed die system of track. computer is delivered to after automatically joining in cement, sand, stone ratio Mixing plant adds water and stirs into concrete, and its slump controls within 200mm;Vibration on Start-up platform, pours into a mould prefabricated wallboard The concrete of component, with flat board shake device prefabricated wall plate member surface is shaken touch flat receive smooth treatment after rest;Again will band Bed die system around track forwards steam curing system to;Forwarding band to finished product station around the bed die system of track again, form removal obtains Prefabricated wall plate member needed for;It is formulated to warehouse for finished product respectively support eventually or stock;Band turns around the bed die system of track To initial position, enter next flow state;The band bed die system around track is set, allows for intersection dislocation operation, Improving efficiency, connected by each workshop endless track manner, band is speeded around track one week, explanation around the bed die system of track One prefabricated wall plate member has produced;Keep in balance drop around track, be to reduce the resistance that track runs, unloaded Climbing up slope, prefabricated wall plate member is poured into load row descending from concrete;The prefabricated wall that above-mentioned flow process produces Board member, globality is strong, rational in infrastructure, and quality standard is high, and operation is controlled, and self-heat conserving sound insulation value is good.Pour main body frame, shape Post reinforcing bar is pricked in the main body frame mouth or the field fabrication that become to install wallboard, with engineering mould, the post reinforcing bar pricked is prepared vertical bag Wrap up in, set reserved opening, the thickness of reserved opening width >=prefabricated wall plate member in the post engineering mould both sides installing wallboard face; Prefabricated wall plate member side is placed in the surface of post binding site or prefabricated wall plate member is lifted In the reserved opening that the engineering mould both sides pricking post reinforcing bar set, the another both sides of post engineering mould are fixed, prefabricated wallboard The girt strip reinforcing bar that component two ends are exposed extend in post reinforcing bar, then cast-in-situ reinforced concrete column, will extend into post reinforcing bar partial Prefabricated wall plate member and the girt strip steel exposed now are cast in cast-in-situ reinforced concrete column;Steel column is formed installs wallboard Main body frame mouth, the post reinforcing bar will pricked with engineering mould prepares vertical parcel, in the quiet type concrete-type installing wallboard face Steel column engineering mould both sides set reserved opening, the thickness of reserved opening width >=prefabricated wall plate member;By prefabricated wall Board member side is placed in the surface of steel column binding site or prefabricated wall plate member is lifted on steel column In the reserved opening that engineering mould both sides set, being fixed the another both sides of post engineering mould, prefabricated wall plate member two ends are exposed Girt strip reinforcing bar extend in steel column, then cast-in-situ steel reinforced concrete, will extend into post reinforcing bar partial prefabricated wallboard structure Part and the girt strip steel exposed now are cast in steel column;If pure steel column, prefabricated wall plate member exposed steel bar is stretched Enter and weld in steel column.The installation of prefabricated wall plate member, is to carry out in building cavity building roof girder, if Pure section steel beam, extend into prefabricated floor member exposed steel bar in section steel beam and welds;Joint connection in site installs its dress Join formula prefabricated panel component, be with engineering mould, fine strain of millet reinforcing bar to be pricked on beam bottom board, reinforcement mould support, support to meet and execute The requirement of work load;Being lifted on beam bottom board by prefabricated wall plate member, prefabricated wall plate member two ends are exposed Girt strip reinforcing bar extend in girder reinforcing bar, adjusts adjacent members interface flatness, in prefabricated wall plate member middle part Increase the girt strip reinforcing bar that coaxial support, colligation or welding are exposed, girder reinforcing bar middle rib beam steel will be extend into and be now cast in cast-in-place In reinforced concrete girder;Again by laying top flange plate reinforcing bar above prefabricated wall plate member and girder reinforcing bar, spread If top flange plate reinforcing bar partially pass through or colligation is in reserved U-loop or by U-loop, increase laid top flange plate reinforcing bar With the bond strength of prefabricated wall plate member, cast-in-situ steel reinforced concrete forms superstructure top flange plate;Cast concrete is entered Row maintenance, form removal, thus obtain the cavity building roof of required selective model integral system cast-in-site simultaneously.
Accompanying drawing explanation
Fig. 1 is selective model integral system plane graph of the present invention.
Fig. 2 is that structure chart engraved by present invention steel mesh with ribbing.
Fig. 3 is that the two of structure chart engraved by present invention steel mesh with ribbing.
Fig. 4 is the ribbed belt willow mouth embodiment of the prefabricated wall plate member of the present invention.
Fig. 5 is that the present invention prefabricated wall plate member rib reinforcement exposes embodiment.
Fig. 6 is the cross rib through hole embodiment of the prefabricated wall plate member of the present invention.
Fig. 7 is to be reserved with U-loop embodiment on the present invention prefabricated wall plate member girt strip.
Detailed description of the invention
The present invention is further described below in conjunction with the accompanying drawings.
Fig. 1 is selective model integral system plane graph of the present invention, when the present invention implements, is by factory's flowing water The prefabricated assembled prefabricated panel component 2 that line produces;Its production process is by prefabricated wall plate member band cincture track Bed die system forwards die-filling workshop and rib reinforcement and obturator workshop to;Equipped shuttering on bed die, forms required specifications and models Opening basis framed, opening basis framed in lay girt strip reinforcing bar, steel mesh with ribbing is engraved, straight through tube between willow mouth die, girt strip Deng;Band is forwarded to pouring hall again around the bed die system of track. computer delivers to stirring after automatically joining in cement, sand, stone ratio Station adds water and stirs into concrete, and its slump controls within 200mm;Vibration on Start-up platform, pours into a mould prefabricated wall plate member Concrete, with flat board shake device prefabricated wall plate member jolt ramming surface is touched flat receive smooth treatment after rest;Again by band Bed die system around track forwards steam curing system to;Forwarding band to finished product station around the bed die system of track, form removal obtains institute The prefabricated wall plate member needed;It is formulated to warehouse for finished product respectively support eventually or stock;Band is at the beginning of the bed die system of track forwards to Beginning position, enters next flow state;The band bed die system around track is set, allows for intersection dislocation operation, improve Efficiency, connects each workshop endless track manner, and band speeds, around track one week, to illustrate one around the bed die system of track Prefabricated wall plate member has produced;Handling is on main fine strain of millet mould 42, by the part structure of prefabricated assembled prefabricated panel component 2 Part 2 and the rib reinforcement 58 exposed are embedded in post mold, carry out cast-in-site.When post and beam are formed steel construction, rib will be exposed Reinforcing bar is directly welded on steel column and section steel beam;Prefabricated assembled prefabricated panel component 2 may be designed to optimum state one-way slabs, The joint portion that two module components 2 are adjacent is arranged to willow mouth 592;Combination is to carry out in building cavity building roof girder, uses engineering mould Fine strain of millet reinforcing bar is pricked on beam bottom board, reinforcement mould support, support the requirement meeting construction loads;By prefabricated wallboard Lifting component is on beam bottom board, and the girt strip reinforcing bar that prefabricated wall plate member two ends are exposed extend in girder reinforcing bar, adjusts Adjacent members interface flatness, increases what coaxial support, colligation or welding were exposed in prefabricated wall plate member middle part Rib girt strip reinforcing bar, will extend into girder reinforcing bar middle rib joist steel and now be cast in cast-in-situ steel reinforced concrete girder;The most again will assembling Laying reinforcing bar above formula prefabricated panel component and girder reinforcing bar, laid reinforcing bar partially passes through or colligation is at reserved U-loop 521 In, increase the bond strength of laid reinforcing bar and prefabricated wall plate member;In order to realize effective 4/000 springing height, In the middle of prefabricated wall plate member, take coaxial support, both facilitated arch camber, supported again prefabricated wall plate member;Existing Water armored concrete and form superstructure top flange plate, cast concrete is carried out maintenance, form removal, thus the quilt needed for simultaneously obtaining The cavity building roof of dynamic formula building energy conservation integral system cast-in-site.Steel column forms the main body frame mouth installing wallboard, recruitment The post reinforcing bar pricked is prepared vertical parcel by journey mould, sets in the quiet type concrete-type steel column engineering mould both sides installing wallboard face Reserved opening, the thickness of reserved opening width >=prefabricated wall plate member;Prefabricated wall plate member side is placed in The surface of steel column binding site or prefabricated wall plate member is lifted on that the engineering mould both sides of steel column set pre- Staying in mouth, fixed the another both sides of post engineering mould, the girt strip reinforcing bar that prefabricated wall plate member two ends are exposed extend into shaped steel In post, then cast-in-situ steel reinforced concrete, by existing for the girt strip steel extending into the post prefabricated wall plate member of reinforcing bar partial and expose It is cast in steel column;If pure steel column, prefabricated wall plate member exposed steel bar is extend in steel column welding i.e. Can;If pure section steel beam, prefabricated floor member exposed steel bar is extend in section steel beam and welds.
Fig. 2 is that structure chart engraved by present invention steel mesh with ribbing, as in figure 2 it is shown, feeding machine, bicker system, cutter will be utilized 6 are engraved Deng special mechanical equipment making expanded metal lath, at the construction field (site) by bending tool, with ribbing by bending form one by one at bending trace What 6 peripheries engraved by steel mesh engraves net 61 main body;Factory engraves end net 62 expanded metal lath body length according to the height that steel mesh with ribbing is engraved needed for cutting, Engraving end net 62 for every and cut out sheet metal two panels, the width of 6 engraved by two panels sheet metal leaf length≤steel mesh with ribbing, with special equipment by thin steel Plate is pressed into V-shape, and V-shape sheet metal sheet is wrapped in after engraving the two ends of end net 62 by parcel by stamping machine to be engraved end and net two ends Mouth flattens, and both end net two-port was engraved in shaping protection, and inhibitory action is played in the distortion engraved steel mesh with ribbing again, and steel mesh with ribbing engraves 6 Inside is supported by supporting network.
Fig. 4 is the ribbed belt willow mouth embodiment of the present invention prefabricated assembled prefabricated panel component, and the present embodiment is two pieces of cavitys The joint portion that plate 2 is adjacent is arranged to willow mouth 592, and the amount of lap adjusting willow mouth 592 carrys out the flatness of tuning plate, first meets combination dress Join formula prefabricated panel component bottom surface Pingdu and reinforce by lower floor coaxial support prefabricated wall plate member middle-end, can also be used with This support adjusts the size of superstructure arch camber, and superstructure springing height is about the 4/1000 of superstructure width.
Fig. 5 is that the present invention prefabricated wall plate member rib reinforcement exposes embodiment, as post reinforcing bar is pricked in figure field fabrication 3, hold up the beam steel and prefabricated wall plate member pricked and construction loads with aluminium alloy fixed shape mould, in order to assemble structure The firmest, cast-in-place at existing girder steel with the rib reinforcement 58 exposed by extending into the prefabricated wall plate member of beam steel partial In reinforced concrete.
Fig. 6 is the cross rib through hole embodiment of the prefabricated wall plate member of the present invention.
Prefabricated wall plate member through hole embodiment, the present embodiment will use solar heating function or fire-fighting smoke controlling merit During energy, before girder is poured into a mould by the connected mode of serial or parallel connection by prefabricated wall plate member through hole 531 with equipment even Logical.
Fig. 7 is to be reserved with U-loop embodiment on the present invention prefabricated wall plate member girt strip.
It is reserved with U-loop 10 on prefabricated wall plate member girt strip, when prefabricated assembled prefabricated panel component rib reinforcement, rib N number of U-loop 10 has been reserved as lifting and prefabricated assembled prefabricated panel component and cast-in-place concrete cavity building roof in the middle of reinforcing bar The combination of top flange plate reinforcing bar is used;By laying top flange plate reinforcing bar above prefabricated wall plate member and girder reinforcing bar, laid Top flange plate reinforcing bar partially pass through or colligation is in reserved U-loop 10 or by U-loop, increase laid top flange plate reinforcing bar 11 form superstructure top flange plate with the bond strength of prefabricated wall plate member, cast-in-situ steel reinforced concrete, solve with cast-in-place Structural integrity.
Finally should be noted that: above example is only in order to illustrate that technical scheme is not intended to limit, to the greatest extent The present invention has been described in detail by pipe with reference to above-described embodiment, it should be understood by a person of ordinary skill in the art that still The detailed description of the invention of the present invention can be modified or equivalent, and any without departing from spirit and scope of the invention Amendment or equivalent, it all should be contained in the middle of scope of the presently claimed invention.

Claims (10)

1. selective model integral system, comprises building structure main body, the floor of horizontal direction, the wallboard of vertical direction With door and window mouth;Described building structure main body is reinforced concrete structure or steel-concrete combined structure;The floor of described horizontal direction is Assembled cavity floor or cast-in-situ steel reinforced concrete cavity floor;Described assembled cavity floor precast frame component is in factory's system Make, top flange plate cast on-site;The wallboard of described vertical direction is assembled by prefabricated wall plate member;Described assembling Formula prefabricated panel component is decomposed the physical dimension determined and the production of specifications and models tissue by factory by design drawing;Described assembled Prefabricated panel component has self-heat conserving function;Described door and window mouth is formed when prefabricated wall plate member assembly.
2. selective model integral system as claimed in claim 1, it is characterised in that the floor of described horizontal direction Assembled cavity floor precast frame component thickness equal with depth of beam or the most unequal, time the most unequal, deck-molding is in frame Frame.
3. selective model integral system as claimed in claim 1, it is characterised in that described assembled cavity floor The girt strip reinforcing bar that precast frame component two ends are exposed extend in beam steel, pricks or weld the girt strip reinforcing bar extending in beam.
4. selective model integral system as claimed in claim 1, it is characterised in that described assembled cavity floor In the precast frame of precast frame component, it is preset with obturator;Described obturator is that steel mesh with ribbing is engraved or polyphenyl block or plastics are empty Chamber or cement cavity or sheet material cavity.
5. selective model integral system as claimed in claim 1, it is characterised in that described assembled cavity floor The precast frame of precast frame component, is formed the precast frame cavity of N number of leukorrhagia flange plate by N number of open mold body,;Described open Mouth die tool is steel mould or bamboo wooden model or plastics mould;Described leukorrhagia flange plate precast frame cavity is covered with permanent thin cover plate, Permanent thin cover plate physical dimension is more than the physical dimension of open mold bore.
6. selective model integral system as claimed in claim 1, it is characterised in that described assembled cavity floor At the reinforced concrete girt strip natural axis of precast frame component, it is prefabricated with the hole of connection reinforced concrete girt strip adjacent both sides cavity.
7. selective model integral system as claimed in claim 1, it is characterised in that described self-heat conserving function is Armored concrete rib is cavity rib, and cavity rib is formed by steel mesh cylinder with ribbing, waters and be inoculated with cement mortar foaming formation in steel mesh cylinder with ribbing Self-thermal insulation material;Described steel mesh with ribbing waters in engraving and is inoculated with the self-thermal insulation material that cement mortar foaming is formed.
8. selective model integral system as claimed in claim 1, it is characterised in that described cast-in-situ steel reinforced concrete Post, the outdoor face of cast-in-situ steel reinforced concrete beam are mounted with heat-barrier material.
9. selective model integral system as claimed in claim 1, it is characterised in that described prefabricated cavity Component is preset with forceful electric power or the sleeve pipe of light current circuit or pipeline.
10. selective model integral system as claimed in claim 1, it is characterised in that described reinforced concrete bottom wing listrium In, it is preset with fire discharge smoke mouth.
CN201610296940.9A 2016-05-06 2016-05-06 Selective model integral system Pending CN106121030A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610296940.9A CN106121030A (en) 2016-05-06 2016-05-06 Selective model integral system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610296940.9A CN106121030A (en) 2016-05-06 2016-05-06 Selective model integral system

Publications (1)

Publication Number Publication Date
CN106121030A true CN106121030A (en) 2016-11-16

Family

ID=57270567

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610296940.9A Pending CN106121030A (en) 2016-05-06 2016-05-06 Selective model integral system

Country Status (1)

Country Link
CN (1) CN106121030A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107524231A (en) * 2017-10-09 2017-12-29 徐州工业职业技术学院 A kind of assembled architecture training equipment system
CN107700659A (en) * 2017-09-22 2018-02-16 万尔特(唐山)钢结构有限公司 A kind of assembling type steel structure building of welding

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1804263A (en) * 2006-01-13 2006-07-19 姚谦峰 Multi-rib structure system and its connection construction method
JP2009007759A (en) * 2007-06-26 2009-01-15 Takenaka Komuten Co Ltd Concrete earthquake-resisting wall and floor type structure
CN105421637A (en) * 2015-12-23 2016-03-23 王海崴 Cavity floor with hollow ribbed steel mesh
CN105421663A (en) * 2015-12-23 2016-03-23 王本淼 Ribbed steel engraved mesh for cast-in-place cavity floor
CN205839952U (en) * 2016-05-06 2016-12-28 湖南标迪夫节能科技有限公司 Selective model integral system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1804263A (en) * 2006-01-13 2006-07-19 姚谦峰 Multi-rib structure system and its connection construction method
JP2009007759A (en) * 2007-06-26 2009-01-15 Takenaka Komuten Co Ltd Concrete earthquake-resisting wall and floor type structure
CN105421637A (en) * 2015-12-23 2016-03-23 王海崴 Cavity floor with hollow ribbed steel mesh
CN105421663A (en) * 2015-12-23 2016-03-23 王本淼 Ribbed steel engraved mesh for cast-in-place cavity floor
CN205839952U (en) * 2016-05-06 2016-12-28 湖南标迪夫节能科技有限公司 Selective model integral system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700659A (en) * 2017-09-22 2018-02-16 万尔特(唐山)钢结构有限公司 A kind of assembling type steel structure building of welding
CN107524231A (en) * 2017-10-09 2017-12-29 徐州工业职业技术学院 A kind of assembled architecture training equipment system

Similar Documents

Publication Publication Date Title
CN106381952B (en) A kind of assembled overlapping cavity building roof
CN106013567A (en) Fabricated stressed island reinforced concrete cavity floor system
CN105804272B (en) It is a kind of to engrave prefabricated assembled wallboard component with steel mesh with ribbing
CN105863140A (en) Precast hollow floor's component for stress island based hollow floor system
CN205839952U (en) Selective model integral system
CN105839822A (en) Assembly type prefabricated part for cavity floor system
CN105780993B (en) One kind exempting from the prefabricated assembled cavity plate of formwork
CN105780990A (en) Prefabricated assembly type cavity floor slab for cavity floor system
CN105971174A (en) Building method for assembly type cast-in-place cavity building cover
CN205840083U (en) One exempts from the prefabricated assembled cavity plate of formwork
CN106121030A (en) Selective model integral system
CN205857446U (en) A kind of engrave prefabricated assembled wallboard component with steel mesh with ribbing
CN105839812A (en) Self-thermal insulation wall assembled by prefabricated wallboard components
CN206110473U (en) Atress island cavity is assembled cavity board for superstructure
CN206110324U (en) Wall body with prefabricated assembled wall panel component combination
CN205857490U (en) A kind of assembled cavity precoated plate exempting from a module and cast-in-situ cavity building roof
CN206245558U (en) A kind of prefabricated component for cavity building roof
CN206220324U (en) A kind of open cavity prefabricated board in cast-in-place cavity building roof
CN105804302A (en) Assembly type cavity prefabricated slab of formwork-erecting-free cast-in-situ cavity floor system
CN206070837U (en) A kind of prefabricated assembled cavity floor for cavity building roof
CN206110427U (en) Assembled coincide cavity superstructure
CN205935349U (en) Atress island cavity superstructure is with prefabricated cavity component
CN205822504U (en) A kind of body of wall of prefabricated hollow rib assembled wallboard Component composition
CN205822505U (en) A kind of self-heat conserving external wall body of assembled wallboard Component composition
CN106381951A (en) Assembling type building cavity floor slab

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161116

WD01 Invention patent application deemed withdrawn after publication