CN106368216B - The construction method that a kind of steel sheet pile precisely closes - Google Patents

The construction method that a kind of steel sheet pile precisely closes Download PDF

Info

Publication number
CN106368216B
CN106368216B CN201510423732.6A CN201510423732A CN106368216B CN 106368216 B CN106368216 B CN 106368216B CN 201510423732 A CN201510423732 A CN 201510423732A CN 106368216 B CN106368216 B CN 106368216B
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
sample
precisely
adjacent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active - Reinstated
Application number
CN201510423732.6A
Other languages
Chinese (zh)
Other versions
CN106368216A (en
Inventor
李红业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Think Of Jade-Like Stone Moistens Dynamo-Electric Co Ltd
Original Assignee
Shanghai Think Of Jade-Like Stone Moistens Dynamo-Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Think Of Jade-Like Stone Moistens Dynamo-Electric Co Ltd filed Critical Shanghai Think Of Jade-Like Stone Moistens Dynamo-Electric Co Ltd
Priority to CN201510423732.6A priority Critical patent/CN106368216B/en
Publication of CN106368216A publication Critical patent/CN106368216A/en
Application granted granted Critical
Publication of CN106368216B publication Critical patent/CN106368216B/en
Active - Reinstated legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses the construction method that a kind of steel sheet pile precisely closes, its step are as follows:1)The shape surrounded and relative dimensions for having measured steel sheet pile dig out steel sheet pile pit in the measured position of survey, and ready short steel sheet pile sample is positioned over and surveys measured position;2)Prepare level meter in pit and ground and adjust level simultaneously with theodolite with perpendicularity;3)When beating first steel sheet pile, one short steel sheet pile sample is extracted out from the position of placement.The lock of two adjacent steel sheet pile samples is directed at, first steel sheet pile is pressed into, can either accurately find the position of steel sheet pile, and can ensures the perpendicularity of steel sheet pile.4)Likewise, second steel sheet pile, the steel sheet pile sample adjacent with first steel sheet pile is extracted out, second steel sheet pile catching groove is directed at first steel sheet pile lock and latched with adjacent steel sheet pile, completely second sheet pile of insertion, steel sheet pile is equally with such a method afterwards, and to the last a steel sheet pile precisely closes.

Description

The construction method that a kind of steel sheet pile precisely closes
Technical field
The invention belongs to construction technology in geotechnical engineering field, the construction party precisely closed more particularly to a kind of steel sheet pile Method.
Background technology
Steel sheet pile have high intensity, in light weight, stable performance, construction transport and it is easy to maintenance, speed of application is fast, quality hold It is easy to control, short time limit, and scene is clean and tidy.In addition, steel sheet pile may be reused, reduce investment outlay, thus in Geotechnical Engineering Extensive utilization is arrived.But steel sheet pile can also run into some problems in work progress, as in re-closed shaped steel plate pile work progress Steel sheet pile is not easy precisely closure, it is necessary to carry out last closure by modes such as artificial welding;During steel sheet pile is pressed into, steel The more difficult correction of perpendicularity of sheet pile, steel sheet pile head is easily subjected to displacement.
In the prior art, the problem of being not easy precisely to close for steel sheet pile, the mode of generally use be screen squeeze into method, Special-shaped pile construction method carries out enclosed type steel sheet pile construction.
Screen-type squeezes into method, is in a row to insert 10-20 roots steel sheet pile in saddle, in screen shape, then injection in batches again. First the steel sheet pile at screen panel both ends is beaten to designed elevation or certain depth during injection, turns into positioning sheet pile, is then pressed in centre Order divides the advantages of 1/3,1/2 sheet pile is highly stepped to be squeezed into, and screen-type squeezes into method to be:Heeling error accumulation can be reduced, Excessive inclination is placed, and is easily achieved closing and closes up, can guarantee that the construction quality of sheet pile wall.Its shortcoming is:Pitching pile from Vertical highly larger, stability is bad during pitching pile, and working security is not high.
Special-shaped pile construction method, it is the problem of being not easy precisely to close for steel sheet pile, and with techniques such as cutting, polishing, welding, The profile for making off-gauge steel sheet pile closes whole steel sheet pile.Deformed steel flats pile construction method, though make flexibly, pin To being processed to steel sheet pile for property, but the crudy of special-shaped sheet pile is relatively difficult to ensure card, and squeezes into and extract also more difficult, spy Be not for closing the special-shaped sheet pile that closes up, being usually processed as needed before closing is closed up, often influence to construct into Degree.
The problem of being difficult to correction for steel plate pile verticality, the solution method of generally use is that instrument is used in work progress The perpendicularity of steel sheet pile is checked, corrected at any time, and progressively correction is beaten with steel wire rope pulling pile body Bian Labian for run-off the straight.Such a correction Method is calibrated and detected using instrument and manually to the perpendicularity of steel sheet pile.Such a construction method process is complicated, easily production Raw deviation, has deviation to need to readjust afterwards, wastes time and energy.
The content of the invention
The purpose of the present invention is in view of the above-mentioned problems existing in the prior art, it is proposed that what a kind of steel sheet pile precisely closed applies Work method.
The construction method that a kind of steel sheet pile precisely closes, is mainly included the following steps that:1)Surrounding for steel sheet pile is measured Shape and relative dimensions dig out steel sheet pile pit in the measured position of survey, and it is measured that ready short steel sheet pile sample is positioned over into survey Position;2)Prepare level meter in pit and ground and adjust level simultaneously with theodolite with perpendicularity;3)When beating first steel sheet pile, One short steel sheet pile sample is extracted out from the position of placement, the lock of two adjacent steel sheet pile samples is directed at, first steel sheet pile is pressed into, The position of steel sheet pile can either be accurately found, and can grasps the perpendicularity for ensureing steel sheet pile.4)Likewise, second steel plate Stake, the steel sheet pile sample adjacent with first steel sheet pile are extracted out, second steel sheet pile catching groove be aligned first steel sheet pile lock with it is adjacent Steel sheet pile sample lock, completely insert second steel sheet pile, steel sheet pile equally uses the method afterwards, a to the last steel sheet pile Precisely closure.
The beneficial effects of the invention are as follows:The engineering method solves the last steel sheet pile often occurred during steel sheet pile construction Closing close up problem and when being pressed into steel sheet pile the perpendicularity of steel sheet pile be difficult to control the problem of, completely can quickly close Each steel sheet pile, the steel sheet pile of such a construction method press-in have very strong water resistance and anti-stress energy, can extensive use In the construction field of steel sheet pile.
Brief description of the drawings
Fig. 1 is the schematic side view after first steel sheet pile press-in.
In figure:1st, short steel sheet pile sample;2nd, pit;3rd, first steel sheet pile.
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows:
1)The shape surrounded and relative dimensions of steel sheet pile have been measured, steel sheet pile pit 2 is dug out surveying measured position, will Ready short steel sheet pile sample 1, which is positioned over, surveys measured position, surrounds a ground enclosed construction;
2)Prepare level meter in pit 2 and ground and adjust level simultaneously with theodolite with perpendicularity;
3)When beating first steel sheet pile 3, a steel sheet pile sample is extracted from the position of placement, is directed at two adjacent steel sheet pile samples Lock, first steel sheet pile 3 is pressed into, can either accurately find the position of steel sheet pile, and can ensures the perpendicularity of steel sheet pile;
4)Likewise, second steel sheet pile, the steel sheet pile sample adjacent with first steel sheet pile 3 is extracted out, second steel sheet pile button Groove is directed at first steel sheet pile lock and latched with adjacent steel sheet pile sample, completely inserts second steel sheet pile, steel sheet pile is same afterwards With such a method, to the last a steel sheet pile precisely closes.

Claims (1)

  1. A kind of 1. construction method that steel sheet pile precisely closes, it is characterised in that:
    The steel sheet pile precisely closes construction and comprised the following steps:
    1)The shape surrounded and relative dimensions of steel sheet pile have been measured, steel sheet pile pit has been dug out surveying measured position, will prepare Good short steel sheet pile sample, which is positioned over, surveys measured position, surrounds ground closing means;
    2)Prepare level meter in pit and ground and adjust level simultaneously with theodolite with perpendicularity;
    3)When beating first steel sheet pile, one short steel sheet pile sample is extracted out from the position of placement, is directed at the lock of two adjacent steel sheet pile samples Button, first steel sheet pile is pressed into, can either precisely find the position of steel sheet pile, and can grasps the perpendicularity for ensureing steel sheet pile;
    4)Likewise, second steel sheet pile, steel sheet pile sample adjacent with first steel sheet pile is extracted out, and second steel sheet pile catching groove alignment is first Root steel sheet pile latches the lock with adjacent steel sheet pile sample, completely inserts second steel sheet pile, steel sheet pile is equally with such a afterwards Method, to the last a steel sheet pile precisely close.
CN201510423732.6A 2015-07-20 2015-07-20 The construction method that a kind of steel sheet pile precisely closes Active - Reinstated CN106368216B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510423732.6A CN106368216B (en) 2015-07-20 2015-07-20 The construction method that a kind of steel sheet pile precisely closes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510423732.6A CN106368216B (en) 2015-07-20 2015-07-20 The construction method that a kind of steel sheet pile precisely closes

Publications (2)

Publication Number Publication Date
CN106368216A CN106368216A (en) 2017-02-01
CN106368216B true CN106368216B (en) 2018-04-03

Family

ID=57879795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510423732.6A Active - Reinstated CN106368216B (en) 2015-07-20 2015-07-20 The construction method that a kind of steel sheet pile precisely closes

Country Status (1)

Country Link
CN (1) CN106368216B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118294995B (en) * 2024-02-22 2024-10-01 中建三局集团华南有限公司 Intelligent pile machine positioning system based on satellite positioning technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837512A (en) * 2006-04-07 2006-09-27 上海市政工程设计研究总院 Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN201704691U (en) * 2010-07-02 2011-01-12 中国海洋石油总公司 Position-limiting pile follower of steel sheet pile
CN102619215A (en) * 2012-05-05 2012-08-01 中铁十六局集团第五工程有限公司 Lock catch type steel pipe pile structure and construction method thereof
CN104652434A (en) * 2014-12-23 2015-05-27 广州机施建设集团有限公司 Pile planting construction method for steel sheet piles

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012207371A (en) * 2011-03-29 2012-10-25 Penta Ocean Construction Co Ltd Method for installing steel sheet pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837512A (en) * 2006-04-07 2006-09-27 上海市政工程设计研究总院 Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN201704691U (en) * 2010-07-02 2011-01-12 中国海洋石油总公司 Position-limiting pile follower of steel sheet pile
CN102619215A (en) * 2012-05-05 2012-08-01 中铁十六局集团第五工程有限公司 Lock catch type steel pipe pile structure and construction method thereof
CN104652434A (en) * 2014-12-23 2015-05-27 广州机施建设集团有限公司 Pile planting construction method for steel sheet piles

Also Published As

Publication number Publication date
CN106368216A (en) 2017-02-01

Similar Documents

Publication Publication Date Title
Montagnat et al. Fabric along the NEEM ice core, Greenland, and its comparison with GRIP and NGRIP ice cores
CN110163533A (en) A kind of comprehensive compressibility Slope map of pixels of shale air cleft net
WO2010129780A3 (en) Directional resistivity imaging using harmonic representations
CN105544538B (en) Self-locking tubular ground pile and embedding method
CN106132190A (en) Including the device for automatically adjusting harvesting unit and for gathering in the machine of root such as Radix Betae
CN106368216B (en) The construction method that a kind of steel sheet pile precisely closes
CN108442421A (en) Large-diameter tubular pile centrifugal test modelling equipment and its working method
CN107513993A (en) Overlength Straight Combination steel sheet pile construction method
CN103541339A (en) Pull rod type testing device and method for unsaturated undisturbed loess slope soil pressure
CN110321576A (en) Partially-penetrated well precipitation makes the outer earth's surface settlement calculation method of foundation pit in diving stratum foundation pit
CN106703000A (en) Field earth pressure cell burying device and method thereof
CN108978635A (en) Synchronous grouting steel sheet pile and using method
CN105096718A (en) Test method and model for simulating impervious curtain of reservoir dam
CN104060624A (en) Method for arranging pile foundations in complex soft soil foundation
CN104929133A (en) Deep foundation pit Larsen steel sheet pile bottom sloping support construction method
CN205576880U (en) Luoyang shovel with anti - tooth shovel head
CN202208933U (en) Sampler for bored pile
CN104153341B (en) A kind of flatly moving type soil pressure surveys model test device
CN204024560U (en) A kind of sliding inclinometer gauge head fishing device
CN205530236U (en) Building pile
CN105279381B (en) A method of assessment earthquake Slope Stability safety effects
KR102066253B1 (en) Semi-permanent soil sampler using inner tube made of steel pipe
CN202730734U (en) Unsaturation original state loess side slope soil pressure pull rod type testing device
CN205653802U (en) Prop up interim block structure in fender pile clearance
CN105155604B (en) A kind of spade and the method using spade laying straw checkerboard barrier

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180403

Termination date: 20210720

RR01 Reinstatement of patent right
RR01 Reinstatement of patent right

Former decision: Termination of patent rights for unpaid annual fees

Former decision publication date: 20220708