CN106354945A - Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight - Google Patents

Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight Download PDF

Info

Publication number
CN106354945A
CN106354945A CN201610780683.6A CN201610780683A CN106354945A CN 106354945 A CN106354945 A CN 106354945A CN 201610780683 A CN201610780683 A CN 201610780683A CN 106354945 A CN106354945 A CN 106354945A
Authority
CN
China
Prior art keywords
model
dimensional
module
bim
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610780683.6A
Other languages
Chinese (zh)
Inventor
徐海林
胡欣彦
黄克凡
孙素娟
王超军
崔留强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianhe Dacheng Construction Cloud Technology (tianjin) Co Ltd
Original Assignee
Tianhe Dacheng Construction Cloud Technology (tianjin) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianhe Dacheng Construction Cloud Technology (tianjin) Co Ltd filed Critical Tianhe Dacheng Construction Cloud Technology (tianjin) Co Ltd
Priority to CN201610780683.6A priority Critical patent/CN106354945A/en
Publication of CN106354945A publication Critical patent/CN106354945A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Abstract

The invention belongs to the technical field of construction systems, and particularly relates to a device and a method for dynamic association of two-dimensional and three-dimensional engineering data based on BIM (building information modeling) lightweight. The device comprises a drawing association module, a synchronous model module and a data dynamic association module, wherein the drawing association module is used for a first step, the synchronous model module is used for a second step, and the data dynamic association module is used for a third step. The device and the method solve the problems that BIM based design document informatization management is absent, consequently, corresponding design documents and engineering data cannot be called by positioning corresponding positions in BIM, and two-dimensional and three-dimensional linkage cannot be realized in the prior art. The device and the method have the advantages of high informationization degree, convenience in dynamic maintenance, customized development, business customization, high safety and good dynamic performance.

Description

The device being dynamically associated based on BIM lightweight two, three-dimensional engineering data And method
Technical field
The invention belongs to building work systems technology field, more particularly, to a kind of lightweight Ji Yu BIM (bim) 2nd, the apparatus and method that three-dimensional engineering data dynamically associates.
Background technology
It is numerous due to building participant by project based on BIM (bim), including owner, design and its all kinds of Advisory group, general contractor and each specialized contractors, operation management team and end user etc..Smoothly enter for guarantee project OK, mutual between each participant cooperation work just seems particularly important.How in the project implementation process, effectively manage The generation of project each participant and the data needing, ensure that the data interaction of each participant is efficient, timely, orderly and safety, and make These data eventually become the data assets after project is smoothly built up, be project management will faced by a significant challenge, with When, this project introduces bim in Design coordination and construction management, and bim dissolves as a kind of up-to-date numeral of engineering construction industry Certainly scheme.
Model lightweight feature is:
Model lightweight, provides revit plug-in unit, can derive revit model by a key;
Model cutting function;Can define and manage multiple Section Views;
Viewport storage and recovery, viewport management function;
The synchronization supporting revit linking relationship imports, and that is, revit exists to link after link imports and yet suffers from;
Automatically bringing into of revit model attributes, can bring various structure attributes into, including quantities data etc.;
Model simple editing and display control;
Special bim defect management module, supports online bim issue management it is possible to monitor issue handling process;Defect management Associate with viewport, viewport can be positioned in defect management;
The measurement function of support model, multiple metering systems.Area, length, vertical, level, angle etc. are it is possible to again in figure Mark;
Support that a key is derived and generate bim audit report process document it is possible to derive issue handling process simultaneously;
Design problem function of statistic analysis;
Model division, point specialized management;
Model roams, outside, internal roaming;
Entity shows, wire frame shows, renders pinup picture, 2d, 3d function;
Multi-direction 3d browses;
In addition to can importing revit, support directly opening of the forms such as dgn/skp/dwg/dxf simultaneously;
Powerful Custom Workflow engine is with list in that context it may be convenient to (owner, design, bim, construction, seek advice from by multi-party Deng) include workflow management simultaneously;
Strict personnel, role, control of authority, can require customized development according to proprietor, support in multi-party and participant Different role, priority assignation;
Bim model version management function, can support that the increment of multi version bim model stores it is ensured that being not take up excessively storing sky Between;
The storage of polymorphic type document, management, version etc..
Software support distributed deployment and multi-level buffer accelerate and push function, and this function is when the project operation of strange land Very meaningful it can be ensured that the calling all by local cache so that user experience has very big improvement of Most models (major part can call local operation, system bottom automatic governing automatically);
If necessary to progress and quality management function can be provided.
Industry-leading technology is:
Model lightweight, supports revit plug-in unit, can produce light weighed model by a key, and guarantees that model information is protected with revit Hold synchronization;
Model volume is very little, generally less than dwf form, but incidental information amount;
Model surfing is fast, and with sketchup, navisworks maintains an equal level, and browses software far faster than universal model on the market;
Can combine closely with management platform, powerful workflow table single-unit supported by this platform simultaneously.Can be very easily Realize customized development and the extension of management function;
Support model file and light-weighted increment storage are it can be ensured that in the case of storage multi version file, temporary is too many Memory space, increases substantially remote download efficiency.
Prior art is due to lacking the design documentation information system management based on bim model it is impossible to pass through in bim model The positioning of correspondence position can recall corresponding design documentation and engineering data, thus asking of two, three-dimensional linkage cannot be realized Topic.
Content of the invention
The present invention provides a kind of device dynamically associating based on BIM lightweight two, three-dimensional engineering data and side Method, to solve prior art in above-mentioned background technology due to lacking design documentation information system management based on bim model it is impossible to logical Cross the positioning for correspondence position in bim model and can recall corresponding design documentation and engineering data, thus cannot realize two, The problem of three-dimensional linkage.The present invention has that the level of informatization is high, Dynamic Maintenance is convenient, customized development, realize business on demand Customization, the technique effect that safe, dynamic property is good.
A kind of device bag being dynamically associated based on BIM lightweight two, three-dimensional engineering data that the present invention provides Include: drawing relating module, synchronistic model module, data relating module;
Described drawing relating module is used for drawing associated steps: the three-dimensional bim model of two-dimensional engineering drawing association;
Described synchronistic model module is used for synchronistic model step: by two-dimensional engineering drawing basic point, two-dimensional engineering drawing synchronous three Dimension bim model;
Described data relating module is used for data associated steps: the related work of two-dimensional engineering drawing described in three-dimensional bim model interaction Journey data simultaneously forms lightweight bim model.
Further, described two, the device that three-dimensional engineering data dynamically associates also includes model management module, described model pipe Reason module is used for by two, the three-dimensional engineering data device bim model management generating dynamically associating and the data associating correlation Storehouse.
Further, described model management module is additionally operable to the 3d model of bim model and shows;
Further, the display of described bim model include amplifying, reduce, translate, roaming, rendering, hiding, cutting.
Further, described two, the device that three-dimensional engineering data dynamically associates also includes quality management module, described quality pipe Reason module includes defect management submodule and on-line monitoring submodule.
Further, the device that described defect management submodule is used for by two, three-dimensional engineering data dynamically associates generates Bim model, the 3d model of the bim model of the problem being existed by sectional drawing or viewport display.
Further, described on-line monitoring submodule is used for monitoring issue handling process: the bim model of the problem including existing 3d model interaction sectional drawing or positioning viewport.
Further, described two, the device that three-dimensional engineering data dynamically associates also includes information inquiry module, and described information is looked into Ask needed for the incidence relation inquiry that module is used for the engineering data related by two-dimensional engineering drawing described in three-dimensional bim model interaction Engineering data.
Further, described two, the device that three-dimensional engineering data dynamically associates also includes model measurement module, and described model is surveyed Amount module is used for measuring and marking the graphic attribute of bim model, and described graphic attribute includes the area of figure, length, vertical, water Flat, angle.
Further, described two, the device that three-dimensional engineering data dynamically associates also includes a key export module, and a described key is led Go out module for revit model is derived by revit plug-in unit one key.
Briefly, one kind that the present invention provides is based on BIM lightweight two, three-dimensional engineering data dynamically associates The step that includes of method:
1) pass through drawing relating module and two-dimensional engineering drawing is associated three-dimensional bim model, realize the first step of drawing association;
2) synchronistic model module passes through two-dimensional engineering drawing basic point, by two-dimensional engineering drawing synchronous three-dimensional bim model;Realize synchronous The second step of model;
3) data dynamically associates module and by the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction and is formed gently Quantify the third step of bim model realization data association;
4) generate bim model management through model management module and associate the data base of correlation, and show the 3d model of bim model Including: amplify, reduce, translating, roaming, rendering, hiding, cutting;
5) the defect management submodule of quality management module manages the 3d mould of the bim model of problem of sectional drawing or viewport display presence Type;The 3d model interaction sectional drawing of the bim model of problem or positioning that the on-line monitoring submodule monitoring of quality management module exists Viewport;
6) pass through the association of the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction via information inquiry module Engineering data needed for relational query;
7) model measurement module measures and marks the graphic attribute of bim model, and described graphic attribute includes the area of figure, length Degree, vertical, level, angle;
8) revit model is derived by revit plug-in unit one key by a key export module.
The invention has the benefit that
First, the present invention adopts and includes drawing relating module, synchronistic model module, data relating module, described drawing relating module For first step: drawing associated steps: the three-dimensional bim model of two-dimensional engineering drawing association, described synchronistic model module is used for the Two steps: synchronistic model step: by two-dimensional engineering drawing basic point, two-dimensional engineering drawing synchronous three-dimensional bim model, described data Relating module is used for third step: data associated steps: the related engineering money of two-dimensional engineering drawing described in three-dimensional bim model interaction Expect and formed lightweight bim model, in the application, by initially setting up the pass between three-dimensional bim model and two-dimensional engineering drawing Connection relation, then realizes the synchronization of X-Y scheme paper and three-dimensional bim model by drawing basic point to it, sets up three-dimensional bim after blocking Incidence relation between model and each engineering data, can easily be inquired about to engineering data by bim model, be improve 2nd, the three-dimensional engineering data composite system level of informatization.
2nd, the present invention also includes model management module, institute using by described two, three-dimensional engineering data composite system State model management module to be used for by two, the bim model management of three-dimensional engineering data composite system generation and associate correlation Data base.System built-in files and documents management module, it is possible to achieve the effective control of photo information, including but not limited to authority Control, Version Control, editing mode control etc., bim model then can be dynamically associated with design document, construction information etc., thus Realize the dynamic management to design document, construction information, and realize the Dynamic Maintenance of incidence relation.
3rd, the present invention using described two, three-dimensional engineering data composite system also include a key export module, described one Key export module is used for deriving revit model by revit plug-in unit one key, and the present invention provides efficiently light from master cast in the industry Quantify platform, lightweight data can be derived by one key from revit design document, can take out of several in the light weighed model of derivation All attribute datas, and the customized development of lightweight platform can be realized according to service needed.
4th, the present invention, using by bim model management and collaborative design management subsystem tight association, can make full use of The powerful performance of collaboration platform, realizes the on-demand customization of business.
5th, bim model lightweight platform provided by the present invention is directly to derive from revit, does not lose any pass bond number According to, the effect of derivation substantially completely consistent with revit model (color, display effect etc.), general data participant can be made thorough The worry installing revit design software is broken away from bottom, improves the two, safety of three-dimensional engineering data composite system.
6th, from the point of view of the present invention is directed to the velocity test of bim model lightweight platform by certain owner's unit, platform is in display Significant advantage is had on speed, system can easily carry out treatment inquiry, and query time is usually no more than 1 second. Model was usually no more than 0.5 second with the linkage time of document, improve the dynamic of two, three-dimensional engineering data composite system Performance.
Brief description
Fig. 1 is that a kind of lightweight two Ji Yu BIM (bim) of the present invention, three-dimensional engineering data dynamically associate The flow process connection diagram of device.
Fig. 2 is that a kind of lightweight two Ji Yu BIM (bim) of the present invention, three-dimensional engineering data dynamically associate The modular structure schematic diagram of device.
Fig. 3 is that a kind of lightweight two Ji Yu BIM (bim) of the present invention, three-dimensional engineering data dynamically associate The display renderings of the model management module of device.
Fig. 4 is that a kind of lightweight two Ji Yu BIM (bim) of the present invention, three-dimensional engineering data dynamically associate The display renderings of the information inquiry module of device.
Fig. 5 is that a kind of lightweight two Ji Yu BIM (bim) of the present invention, three-dimensional engineering data dynamically associate The systems function diagram of device.
Specific embodiment
Below in conjunction with accompanying drawing, the present invention is described further.The experimental technique of unreceipted actual conditions in embodiment, leads to Often according to the condition described in normal condition and handbook, or according to the condition proposed by manufacturer;Part used, such as no Specified otherwise, all commercially obtains.
In figure: 1- first step, 2- second step, 3- third step, 4- drawing relating module, 5- synchronistic model module, 6- data relating module, 7-bim model, 8- information inquiry module, 9- mono- key export module, 10- model management module, 11- matter Amount management module, 12- on-line monitoring submodule, 13- defect management submodule, 14- model measurement module.
The dress that the lightweight two based on BIM (bim) of present invention offer, three-dimensional engineering data dynamically associate Put and be divided into three-level, the first order is that drawing relating module, synchronistic model module, data dynamically associate module three zones module, phase Interaction forms second level model data and dynamically associates, and last rank is to be dynamically associated according to model, implementation model quality pipe Reason, model information inquiry, moulded dimension measurement and can a key reduced model.
Embodiment:
The present embodiment includes: as shown in Figure 1, 2, a kind of lightweight two Ji Yu BIM (bim), three-dimensional engineering data The device dynamically associating, including drawing relating module 4, synchronistic model module 5, data relating module 6;
Described drawing relating module 4 is used for first step 1: drawing associated steps: the three-dimensional bim model of two-dimensional engineering drawing association;
Described synchronistic model module 5 is used for second step 2: synchronistic model step: by two-dimensional engineering drawing basic point, Two-dimensional Engineering Drawing synchronous three-dimensional bim model;
Described data relating module 6 is used for third step 3: data associated steps: two-dimensional engineering graphic described in three-dimensional bim model interaction The related engineering data of paper simultaneously forms lightweight bim model 7.
Set up the incidence relation between three-dimensional bim model and two-dimensional engineering drawing, two dimension is realized to it by drawing basic point Drawing and the synchronization of three-dimensional bim model;Set up the incidence relation between three-dimensional bim model and each engineering data, by bim model Engineering data easily can be inquired about.
Because using including drawing relating module, synchronistic model module, data relating module, described drawing relating module is used In first step: drawing associated steps: the three-dimensional bim model of two-dimensional engineering drawing association, described synchronistic model module is used for second Step: synchronistic model step: by two-dimensional engineering drawing basic point, two-dimensional engineering drawing synchronous three-dimensional bim model, described data is closed Gang mould block is used for third step: data associated steps: the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction And form lightweight bim model, in the application, by initially setting up associating between three-dimensional bim model and two-dimensional engineering drawing Relation, then realizes the synchronization of X-Y scheme paper and three-dimensional bim model by drawing basic point to it, sets up three-dimensional bim mould after blocking Incidence relation between type and each engineering data, can easily be inquired about to engineering data by bim model, be improve 2nd, the device information degree that three-dimensional engineering data dynamically associates.
As shown in figure 5, system should support that bim model passes through Lightweight Technology and design documentation, effective pass of engineering data Hang together and connect, and the bim model after lightweight should not lose color, material, the relevant information such as attribute.Support to be based on bim model Design documentation management, by the positioning for correspondence position in bim model can recall corresponding design documentation and engineering money Material, thus realize two, three-dimensional linkage.Including model lightweight, roaming, 2d/3d association, paper space collision detection management, The mounting of view management, design problem and bim model, component information query function etc..
Described two, the device that three-dimensional engineering data dynamically associates also includes model management module 10, described model management mould The bim model 7 that block 10 is used for by two, three-dimensional engineering data composite system generates manages and associates the data base of correlation.
As shown in figure 3, due to also including model management using by the device that described two, three-dimensional engineering data dynamically associates Module, described model management module is used for the bim model management being generated by two, three-dimensional engineering data composite system and closes The related data base of connection.System built-in files and documents management module, it is possible to achieve the effective control of photo information, including but do not limit Control in control of authority, Version Control, editing mode etc., bim model then can dynamic with design document, construction information etc. close Connection, thus realizing the dynamic management to design document, construction information, and realizes the Dynamic Maintenance of incidence relation.
The 3d model that described model management module 10 is additionally operable to bim model 7 shows;
The display of described bim model 7 includes amplifying, reduces, translates, roaming, rendering, hiding, cutting.
Due to using by bim model management and collaborative design management subsystem tight association, can make full use of collaborative The powerful performance of work platformses, realizes the on-demand customization of business.
Described two, three-dimensional engineering data composite system also includes quality management module 11, described quality management module 11 include defect management submodule 13 and on-line monitoring submodule 12.
Described defect management submodule 13 is used for the bim model generating by two, three-dimensional engineering data composite system 7, the 3d model of the bim model 7 of the problem being existed by sectional drawing or viewport display.
Described on-line monitoring submodule 12 is used for monitoring issue handling process: the 3d of the bim model 7 of problem including existing Model interaction sectional drawing or positioning viewport.
By bim model, can very easily carry out quality problems in line standard, find out the 3d model going wrong Access, and by sectional drawing or viewport management realize engineering problem three-dimensional display.Qualitative problems of construction can be in threedimensional model On clearly indicate, be highly convenient for carrying out engineering quality control.
Described two, the device that three-dimensional engineering data dynamically associates also includes information inquiry module 8, described information enquiry module 8 are used for associating the engineering needed for incidence relation inquiry of the related engineering data of described two-dimensional engineering drawing by three-dimensional bim model 7 Data.
As shown in figure 4, inquire about at any time in practical application scene in that context it may be convenient in three-dimensional scenic each relevant design and Construction information is it is also possible to being realized the inquiry to 3d model and browsed by two-dimentional drawing.
Described two, the device that three-dimensional engineering data dynamically associates also includes model measurement module, described model measurement module For measuring and marking the graphic attribute of bim model 7, described graphic attribute includes the area of figure, length, vertical, level, angle Degree.
Bim model management is the Core Feature of this module, the bim model being generated by bim Lightweight Technology, can carry out Convenient bim model management, bim model is associated with data base's, the display function of bim model: such as amplifies, reduces, translating, overflowing Swim, render, hiding, cutting etc..
Described two, the device that three-dimensional engineering data dynamically associates also includes a key export module 9, a described key export module 9 are used for deriving revit model by revit plug-in unit one key.
Due to a key export module, a described key are also included using the device that described two, three-dimensional engineering data dynamically associates Export module is used for deriving revit model by revit plug-in unit one key, and the present invention is provided in the industry the most efficiently from master cast light weight Change platform, lightweight data can be derived by one key from revit design document, can take out of almost in the light weighed model of derivation All attribute datas, and the customized development of lightweight platform can be realized according to service needed.
Bim model lightweight platform due to providing is directly to derive from revit, does not lose any critical data, derives Effect substantially completely consistent with revit model (color, display effect etc.), general data participant can be made thoroughly to break away from peace The worry of dress revit design software, improves the safety of the device that two, three-dimensional engineering data dynamically associates.
From the point of view of being directed to the velocity test of bim model lightweight platform by certain owner's unit, platform has on display speed There is significant advantage, system can easily carry out treatment inquiry, and query time is usually no more than 1 second.Model and literary composition The linkage time of shelves is usually no more than 0.5 second, improves the two, dynamic property of three-dimensional engineering data composite system.
According to the requirement in market, " bim collaborative design management subsystem " (abbreviation bims) puts down as the basis of coordinated management Platform is customized completing, and can complete effective management of this bim project.By relevant documentations such as system complete design, constructions Storage and distribution, achievable phased Achievements management, design schedule management, design alteration management, bim bis- three-dimensional linkage, bim specialty The functions such as track race storehouse (component base) management.
Operation principle: the present invention passes through to include drawing relating module, synchronistic model module, data relating module, described figure Paper relating module is used for first step: drawing associated steps: the three-dimensional bim model of two-dimensional engineering drawing association, described synchronistic model Module is used for second step: synchronistic model step: by two-dimensional engineering drawing basic point, two-dimensional engineering drawing synchronous three-dimensional bim mould Type, described data relating module is used for third step: data associated steps: two-dimensional engineering drawing described in three-dimensional bim model interaction Related engineering data simultaneously forms lightweight bim model, in the application, by initially setting up three-dimensional bim model and Two-dimensional Engineering Incidence relation between drawing, then realizes the synchronization of X-Y scheme paper and three-dimensional bim model, after blocking by drawing basic point to it Set up the incidence relation between three-dimensional bim model and each engineering data, engineering data can be carried out easily by bim model Inquiry, improves two, the three-dimensional engineering data composite system level of informatization, and the present invention solves prior art due to lacking Design documentation information system management based on bim model is it is impossible to can recall phase by the positioning for correspondence position in bim model The design documentation answered and engineering data, thus the two, problem of three-dimensional linkage cannot be realized, have the level of informatization high, dynamic Safeguard convenient, customized development, the on-demand customization realizing business, the Advantageous Effects that safe, dynamic property is good.
The with conspicuous characteristics of the present invention is in particular in:
1) the automatic lightweight of bim model, is derived automatically from, and is easy to apply and manages.
2) real-time searching of bim component information and attribute display.
3) the three-dimensional engineering data of the two of bim model is browsed with lookup with dynamically associating of model.
4) by stages of bim model, point specialty display.
5) the conventional function of browse of bim model.
In a word, the invention provides in the industry the most efficiently from master cast lightweight platform, can be from revit design document One key derives lightweight data, can take almost all attribute data out of in the light weighed model of derivation, and can be according to business need Realize the customized development of lightweight platform.
Bim model management and collaborative design management subsystem tight association, can make full use of collaboration platform simultaneously Powerful performance, realize the on-demand customization of business.
From the point of view of being directed to the velocity test of bim model lightweight platform by certain owner's unit, platform has on display speed There is significant advantage.
System can easily carry out treatment inquiry, and query time is usually no more than 1 second.Model and the connection of document The dynamic time is usually no more than 0.5 second.
The bim model lightweight platform being provided is directly to derive from revit, does not lose any critical data, derivation Effect substantially completely consistent with revit model (color, display effect etc.), can make general data participant thoroughly break away from installation The worry of revit design software.
Using technical scheme, or those skilled in the art, under the inspiration of technical solution of the present invention, designs Go out similar technical scheme, and reach above-mentioned technique effect, all fall into protection scope of the present invention.

Claims (10)

1. a kind of device being dynamically associated based on BIM (bim) lightweight two, three-dimensional engineering data, its feature exists In, comprising:
Drawing relating module, associates three-dimensional bim model for two-dimensional engineering drawing;
Synchronistic model module, for by two-dimensional engineering drawing basic point, two-dimensional engineering drawing synchronous three-dimensional bim model;
Data dynamically associates module, for the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction and formed Lightweight bim model.
2. according to claim 1 dynamically associate device it is characterised in that described data dynamically associates module includes mould Type management module, described model management module is used for the bim model pipe generating by two, three-dimensional engineering data composite system Manage and associate the data base of correlation.
3. according to claim 2 dynamically associate device it is characterised in that described model management module is additionally operable to bim mould The 3d model of type shows.
4. according to claim 3 dynamically associate device it is characterised in that the display of described bim model include amplify, contracting Little, translate, roam, rendering, hiding, cutting.
5. according to claim 1 dynamically associate device it is characterised in that described data dynamically associates module also includes Quality management module.
6. according to claim 5 dynamically associate device it is characterised in that described quality management module includes defect management Submodule and on-line monitoring submodule;
Described defect management submodule is used for the bim model generating by two, three-dimensional engineering data composite system, by cutting The 3d model of the bim model of problem of figure or viewport display presence;
Described on-line monitoring submodule is used for monitoring issue handling process: the 3d model pass of the bim model of problem including existing Connection sectional drawing or positioning viewport.
7. according to claim 1 described dynamically associate device it is characterised in that described data dynamically associates module bag Include information inquiry module, described information enquiry module is used for related by two-dimensional engineering drawing described in three-dimensional bim model interaction The engineering data needed for incidence relation inquiry of engineering data.
8. according to claim 1 described dynamically associate device it is characterised in that described two, three-dimensional engineering data moves State relating module also includes model measurement module, and described model measurement module is used for measuring and mark the graphic attribute of bim model, Described graphic attribute includes the area of figure, length, vertical, level, angle.
9. according to claim 1 dynamically associate device it is characterised in that described two, three-dimensional engineering data dynamically associates Module also includes a key export module, and a described key export module is used for deriving revit model by revit plug-in unit one key.
10. a kind of method being dynamically associated based on BIM lightweight two, three-dimensional engineering data is it is characterised in that include Step:
1) pass through drawing relating module and two-dimensional engineering drawing is associated three-dimensional bim model, realize the first step of drawing association;
2) synchronistic model module passes through two-dimensional engineering drawing basic point, by two-dimensional engineering drawing synchronous three-dimensional bim model;Realize synchronous The second step of model;
3) data dynamically associates module and by the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction and is formed gently Quantify the third step of bim model realization data association;
4) generate bim model management through model management module and associate the data base of correlation, and show the 3d model of bim model Including: amplify, reduce, translating, roaming, rendering, hiding, cutting;
5) the defect management submodule of quality management module manages the 3d mould of the bim model of problem of sectional drawing or viewport display presence Type;The 3d model interaction sectional drawing of the bim model of problem or positioning that the on-line monitoring submodule monitoring of quality management module exists Viewport;
6) pass through the association of the related engineering data of two-dimensional engineering drawing described in three-dimensional bim model interaction via information inquiry module Engineering data needed for relational query;
7) model measurement module measures and marks the graphic attribute of bim model, and described graphic attribute includes the area of figure, length Degree, vertical, level, angle;
8) revit model is derived by revit plug-in unit one key by a key export module.
CN201610780683.6A 2016-08-31 2016-08-31 Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight Pending CN106354945A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610780683.6A CN106354945A (en) 2016-08-31 2016-08-31 Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610780683.6A CN106354945A (en) 2016-08-31 2016-08-31 Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight

Publications (1)

Publication Number Publication Date
CN106354945A true CN106354945A (en) 2017-01-25

Family

ID=57857296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610780683.6A Pending CN106354945A (en) 2016-08-31 2016-08-31 Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight

Country Status (1)

Country Link
CN (1) CN106354945A (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107247757A (en) * 2017-05-31 2017-10-13 上海建工四建集团有限公司 Construction project document classification storage and retrieval method and system based on BIM
CN107358401A (en) * 2017-06-09 2017-11-17 上海嘉实(集团)有限公司 Intelligent management system/method, readable storage medium storing program for executing and the terminal of construction project
CN107729065A (en) * 2017-11-02 2018-02-23 港珠澳大桥管理局 The method and system of a kind of 3 D monitoring
CN107766410A (en) * 2017-09-04 2018-03-06 上海中建东孚投资发展有限公司 A kind of architecture information extraction and format conversion method based on BIM threedimensional models
CN107862151A (en) * 2017-11-20 2018-03-30 中铁第四勘察设计院集团有限公司 A kind of gate intelligence aided design system
CN108256831A (en) * 2018-02-02 2018-07-06 北京筑业志远软件开发有限公司 The method that Engineering documents Management is carried out based on visualization BIM models
CN108898668A (en) * 2018-06-29 2018-11-27 陕西心像信息科技有限公司 The creation of the mapped system of two-dimentional drawing and threedimensional model and Map Searching method
CN109191567A (en) * 2018-09-03 2019-01-11 北京许继电气有限公司 Quick VR model modelling approach and system based on industrial initial designs data
CN109410331A (en) * 2018-11-15 2019-03-01 中铁第六勘察设计院集团有限公司 Shield-tunneling construction BIM management platform architecture method is built based on WebGL
CN109446717A (en) * 2018-11-15 2019-03-08 中铁第六勘察设计院集团有限公司 Based on two three-dimensional linkage methods of exhibiting of BIM plus 3DGIS linear engineering
CN109508396A (en) * 2018-09-28 2019-03-22 上海嘉实(集团)有限公司 A kind of method of three peacekeepings two-dimensional space picture one key switching
CN109657085A (en) * 2018-12-13 2019-04-19 深圳市毕美科技有限公司 A kind of drawing linkage access method and device
CN110335247A (en) * 2019-05-30 2019-10-15 广东民航机场建设有限公司 Defect positioning method, device, equipment and storage medium based on BIM model
CN110619128A (en) * 2018-06-19 2019-12-27 中国石化工程建设有限公司 Construction method of digital factory
CN110688692A (en) * 2019-08-27 2020-01-14 水利部水利水电规划设计总院 Two-three-dimensional linkage and superposition display method based on structured BIM model
CN111143478A (en) * 2019-12-05 2020-05-12 中国石油工程建设有限公司 Two-three-dimensional file association method based on lightweight model and engineering object bit number
CN111191311A (en) * 2019-12-25 2020-05-22 深圳市华阳国际工程设计股份有限公司 Efficient image examination method, efficient image examination system, terminal and readable storage medium
CN111950049A (en) * 2020-07-01 2020-11-17 中铁二院工程集团有限责任公司 Rapid BIM design method for contact network
CN111985035A (en) * 2020-08-27 2020-11-24 成都建工装饰装修有限公司 BIM-based achievement display method and device for campus reduction system and storage medium
CN112150611A (en) * 2020-09-21 2020-12-29 同济大学建筑设计研究院(集团)有限公司 Problem component calibration method and device, computer equipment and storage medium
CN113626899A (en) * 2021-07-27 2021-11-09 北京优比智成建筑科技有限公司 Navisthrocks-based model and drawing synchronous display method, device, equipment and medium
CN113688445A (en) * 2020-05-19 2021-11-23 中交二公局第三工程有限公司 Method for manufacturing engineering data three-dimensional index map
CN114091151A (en) * 2021-11-15 2022-02-25 国网江苏省电力有限公司扬州供电分公司 BIM model-based substation auxiliary equipment linkage logic verification method
CN114186984A (en) * 2022-02-17 2022-03-15 中国建筑西南设计研究院有限公司 Two-dimensional and three-dimensional integrated collaborative design system for architectural design enterprise
EP3980253A4 (en) * 2019-06-06 2023-07-05 Bluebeam, Inc. Methods and systems for establishing a linkage between a three-dimensional electronic design file and a two-dimensional design document
CN117251923A (en) * 2023-11-15 2023-12-19 深圳市四方智源科技有限公司 BIM model and two-dimensional drawing bidirectional parallel response type design method and system
CN113688445B (en) * 2020-05-19 2024-04-19 中交二公局第三工程有限公司 Method for making engineering data three-dimensional index map

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104252558A (en) * 2014-07-02 2014-12-31 哈尔滨工业大学 BIM (Building Information Modeling) platform-based numerical control machining pretreatment method of non-standard building enclosure component
CN104680320A (en) * 2014-12-03 2015-06-03 上海同筑信息科技有限公司 BIM-based project management system and method
CN104680322A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 Project acceptance system and method based on BIM
CN105868440A (en) * 2016-03-21 2016-08-17 扬州大学 Construction engineering data modeling method based on BIM (Building Information Modeling) technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104252558A (en) * 2014-07-02 2014-12-31 哈尔滨工业大学 BIM (Building Information Modeling) platform-based numerical control machining pretreatment method of non-standard building enclosure component
CN104680320A (en) * 2014-12-03 2015-06-03 上海同筑信息科技有限公司 BIM-based project management system and method
CN104680322A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 Project acceptance system and method based on BIM
CN105868440A (en) * 2016-03-21 2016-08-17 扬州大学 Construction engineering data modeling method based on BIM (Building Information Modeling) technology

Cited By (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107247757A (en) * 2017-05-31 2017-10-13 上海建工四建集团有限公司 Construction project document classification storage and retrieval method and system based on BIM
CN107358401A (en) * 2017-06-09 2017-11-17 上海嘉实(集团)有限公司 Intelligent management system/method, readable storage medium storing program for executing and the terminal of construction project
CN107358401B (en) * 2017-06-09 2021-04-13 上海嘉实(集团)有限公司 Intelligent management system/method for building project, readable storage medium and terminal
CN107766410A (en) * 2017-09-04 2018-03-06 上海中建东孚投资发展有限公司 A kind of architecture information extraction and format conversion method based on BIM threedimensional models
CN107729065B (en) * 2017-11-02 2021-07-20 港珠澳大桥管理局 Three-dimensional monitoring method and system
CN107729065A (en) * 2017-11-02 2018-02-23 港珠澳大桥管理局 The method and system of a kind of 3 D monitoring
CN107862151A (en) * 2017-11-20 2018-03-30 中铁第四勘察设计院集团有限公司 A kind of gate intelligence aided design system
CN108256831B (en) * 2018-02-02 2021-07-30 北京筑业志远软件开发有限公司 Method for managing engineering data based on visual BIM model
CN108256831A (en) * 2018-02-02 2018-07-06 北京筑业志远软件开发有限公司 The method that Engineering documents Management is carried out based on visualization BIM models
CN110619128A (en) * 2018-06-19 2019-12-27 中国石化工程建设有限公司 Construction method of digital factory
CN110619128B (en) * 2018-06-19 2024-03-15 中国石化工程建设有限公司 Construction method of digital factory
CN108898668A (en) * 2018-06-29 2018-11-27 陕西心像信息科技有限公司 The creation of the mapped system of two-dimentional drawing and threedimensional model and Map Searching method
CN109191567A (en) * 2018-09-03 2019-01-11 北京许继电气有限公司 Quick VR model modelling approach and system based on industrial initial designs data
CN109508396A (en) * 2018-09-28 2019-03-22 上海嘉实(集团)有限公司 A kind of method of three peacekeepings two-dimensional space picture one key switching
CN109446717A (en) * 2018-11-15 2019-03-08 中铁第六勘察设计院集团有限公司 Based on two three-dimensional linkage methods of exhibiting of BIM plus 3DGIS linear engineering
CN109410331A (en) * 2018-11-15 2019-03-01 中铁第六勘察设计院集团有限公司 Shield-tunneling construction BIM management platform architecture method is built based on WebGL
CN109657085A (en) * 2018-12-13 2019-04-19 深圳市毕美科技有限公司 A kind of drawing linkage access method and device
CN110335247A (en) * 2019-05-30 2019-10-15 广东民航机场建设有限公司 Defect positioning method, device, equipment and storage medium based on BIM model
CN110335247B (en) * 2019-05-30 2021-12-10 广东省机场管理集团有限公司工程建设指挥部 BIM (building information modeling) -based defect positioning method, device, equipment and storage medium
EP3980253A4 (en) * 2019-06-06 2023-07-05 Bluebeam, Inc. Methods and systems for establishing a linkage between a three-dimensional electronic design file and a two-dimensional design document
CN110688692B (en) * 2019-08-27 2022-05-17 水利部水利水电规划设计总院 Two-three-dimensional linkage and superposition display method based on structured BIM model
CN110688692A (en) * 2019-08-27 2020-01-14 水利部水利水电规划设计总院 Two-three-dimensional linkage and superposition display method based on structured BIM model
CN111143478A (en) * 2019-12-05 2020-05-12 中国石油工程建设有限公司 Two-three-dimensional file association method based on lightweight model and engineering object bit number
CN111191311A (en) * 2019-12-25 2020-05-22 深圳市华阳国际工程设计股份有限公司 Efficient image examination method, efficient image examination system, terminal and readable storage medium
CN113688445B (en) * 2020-05-19 2024-04-19 中交二公局第三工程有限公司 Method for making engineering data three-dimensional index map
CN113688445A (en) * 2020-05-19 2021-11-23 中交二公局第三工程有限公司 Method for manufacturing engineering data three-dimensional index map
CN111950049A (en) * 2020-07-01 2020-11-17 中铁二院工程集团有限责任公司 Rapid BIM design method for contact network
CN111950049B (en) * 2020-07-01 2023-01-31 中铁二院工程集团有限责任公司 Rapid BIM design method for contact network
CN111985035A (en) * 2020-08-27 2020-11-24 成都建工装饰装修有限公司 BIM-based achievement display method and device for campus reduction system and storage medium
CN111985035B (en) * 2020-08-27 2021-03-23 成都建工装饰装修有限公司 BIM-based achievement display method and device for campus reduction system and storage medium
CN112150611B (en) * 2020-09-21 2023-05-26 同济大学建筑设计研究院(集团)有限公司 Method and device for calibrating problematic component, computer equipment and storage medium
CN112150611A (en) * 2020-09-21 2020-12-29 同济大学建筑设计研究院(集团)有限公司 Problem component calibration method and device, computer equipment and storage medium
CN113626899A (en) * 2021-07-27 2021-11-09 北京优比智成建筑科技有限公司 Navisthrocks-based model and drawing synchronous display method, device, equipment and medium
CN113626899B (en) * 2021-07-27 2022-07-26 北京优比智成建筑科技有限公司 Navisthrocks-based model and drawing synchronous display method, device, equipment and medium
CN114091151B (en) * 2021-11-15 2023-03-31 国网江苏省电力有限公司扬州供电分公司 BIM model-based substation auxiliary equipment linkage logic verification method
CN114091151A (en) * 2021-11-15 2022-02-25 国网江苏省电力有限公司扬州供电分公司 BIM model-based substation auxiliary equipment linkage logic verification method
CN114186984B (en) * 2022-02-17 2022-05-06 中国建筑西南设计研究院有限公司 Two-dimensional and three-dimensional integrated collaborative design system for architectural design enterprise
CN114186984A (en) * 2022-02-17 2022-03-15 中国建筑西南设计研究院有限公司 Two-dimensional and three-dimensional integrated collaborative design system for architectural design enterprise
CN117251923A (en) * 2023-11-15 2023-12-19 深圳市四方智源科技有限公司 BIM model and two-dimensional drawing bidirectional parallel response type design method and system
CN117251923B (en) * 2023-11-15 2024-03-12 深圳市四方智源科技有限公司 BIM model and two-dimensional drawing bidirectional parallel response type design method and system

Similar Documents

Publication Publication Date Title
CN106354945A (en) Device and method for dynamic association of two-dimensional and three-dimensional engineering data based on building information modeling lightweight
CN102750618B (en) A kind of comprehensive pipeline of metro construction aided management system and implementation method
US10127507B2 (en) Project management system providing interactive issue creation and management
CN105046328B (en) A kind of three-dimensional visualization bridge defect information acquisition management system and method
CN111382214B (en) Comprehensive pipe rack operation and maintenance management system based on 3DGIS BIM
CN104680320A (en) BIM-based project management system and method
JP4738067B2 (en) CAD data creation apparatus and method
CN109885626A (en) Urban construction digital archives intelligent management system based on structural data and BIM model
Re Cecconi et al. Leveraging BIM for digital built environment asset management
CN108256831B (en) Method for managing engineering data based on visual BIM model
CN103885788A (en) Dynamic WEB 3D virtual reality scene construction method and system based on model componentization
WO2021121098A1 (en) Three-dimensional model application method and system for nuclear power engineering modular construction
CN107071001A (en) Intelligent transportation Web information sharing service platform framework method
CN107436785B (en) Revit software information interaction system and interaction method based on information system
CN103226779A (en) Road logistics price index
CN110110072A (en) A kind of method, system, terminal and storage medium generating interactive electronic handbook
CN112016903A (en) Three-dimensional assembly operation instruction data management platform and work flow thereof
US20180136793A1 (en) Visual work instructions for assembling product
Zheng Analysis of collaborative design and construction collaborative mechanism of cloud bim platform construction project based on green computing technology
JP2007026135A (en) Program management chart creation support system
CN109559085B (en) Approval method based on BIM lightweight model and terminal equipment
CN109213480A (en) A kind of method, storage medium, equipment and system for developing the back-stage management page
Pogorelskiy et al. Automation for structured cabling system in data centers using Building Information Modelling
CN107038732A (en) A kind of safe pictorialization software systems of engineering construction field
CN110780737A (en) ERP enterprise information management and panoramic VR combined system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170125