CN106351371A - Manufacturing and construction process of curtain keel - Google Patents
Manufacturing and construction process of curtain keel Download PDFInfo
- Publication number
- CN106351371A CN106351371A CN201610892247.8A CN201610892247A CN106351371A CN 106351371 A CN106351371 A CN 106351371A CN 201610892247 A CN201610892247 A CN 201610892247A CN 106351371 A CN106351371 A CN 106351371A
- Authority
- CN
- China
- Prior art keywords
- draconis
- curtain
- construction technology
- joist
- curtain skeleton
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The invention relates to a manufacturing and construction process of a curtain keel. The manufacturing and construction process comprises a keel manufacturing step and a connector mounting step which are simultaneously implemented as well as a keel walling step, an insulation board mounting step, an aluminum alloy hanging piece mounting step and a curtain plane materiel mounting step subsequently, and in the keel walling step, a manufactured keel is fixedly connected with a mounted connector on a wall through a bolt. The manufacturing and construction process has the advantages that a construction period is shortened, cross operation is reduced, potential safety hazards and potential quality hazards are reduced, and additionally, the attractive appearance of a curtain is facilitated.
Description
Technical field
The invention belongs to building curtain wall technical field, particularly a kind of curtain skeleton manufacture construction technology.
Background technology
Bartlit curtain wall technique, is carried out in main body alien invasion according to the main work progress of specification, and Os Draconis are whole stone
The load-bearing main body of material curtain wall, thus Os Draconis welding is mostly important one in stone curtain wall technological process.Existing Os Draconis are common
Technological process is:
Surveying setting-out → installation of embedded parts → adaptor installation → column installation → warming plate installation → crossbeam installation → aluminum
Installation → the cleaning of the installation of alloy suspension member → stone material facestock.However, above-mentioned technique has the disadvantages that
Shortcoming one: increased fire hazard, common process welding all completes (aerial work) in the scope of operation, in the past any
All there is the situation that sparks flying off in all directions in engineering, the generation that cannot avoid, easily cause fire not in place of starting to exchange fire, and is welded in conventional example
The main cause occurring for fire;
Shortcoming two: solder skip situation generally occurs, in terms of previous experiences, Os Draconis scope of operation solder skip situation happens occasionally, for example:
It is related to operation blind spot position, such as hanging basket marginal position, scaffold faces side position it is contemplated that there being certain danger during individual work
Property, or lazy causing solder skip, scope of operation operative employee changes, or has the discontinuity work surface of time interval, also easily makes
Become solder skip, work high above the ground ratio itself is relatively hazardous, high-altitude welding more dangerous it is extremely difficult to ensure that welding quality reaches target call;
Shortcoming three: Os Draconis quality is difficult to ensure card, steel joist welding process easily causes Os Draconis to deform, and reduces to a certain extent
Keel installation precision, causes very big difficulty to the flatness of follow-up facestock installation surface, or even quality problems, shadow
Ring overall appearance;
Shortcoming four: efficiency is low, centre keel unwrapping wire is installed, and transom unwrapping wire is installed, two procedures, and unwrapping wire amount is big, and is height
Idle job, installation rate is slow, while impact efficiency, increased a lot of unsafe factors.
Therefore, how traditional pattern to be broken, reduce the time of elevation construction or lead to because of agent structure impact
The phenomenon that construction cannot be carried out, is current urgent problem.
Content of the invention
It is an object of the invention to provide a kind of curtain skeleton manufactures construction technology, it has the saving duration, reduces to intersect and make
Industry, the advantage reducing potential safety hazard, reducing hidden danger of quality, are conducive to the attractive in appearance of curtain wall outward appearance simultaneously.
For achieving the above object, the present invention takes technical scheme below:
A kind of curtain skeleton manufactures construction technology, and it includes the Os Draconis manufacturing step simultaneously carrying out and adaptor installs step
Suddenly, wall step, warming plate installation steps, aluminium alloy suspension member installation steps, curtain wall facestock installation steps and on follow-up Os Draconis;
In wall step on this Os Draconis, the Os Draconis and the adaptor mounted on body of wall that have manufactured are bolted to connection.
Further, described Os Draconis manufacturing process includes:
A. cutting manufactures main joist and secondary joist on request, and bores suspension member hole at secondary joist two ends;
B. according to curtain wall lattice height on main joist labelling secondary joist position, and secondary joist is welded on relevant position.
Further, in described step a, the suspension member hole of described secondary joist is by being fixed at the perforating mold below drilling tool
Open up, this perforating mold includes baffle plate and two gripper shoes between two baffle plates of both sides, the height of this baffle plate is higher than
The height of this gripper shoe;This drilling tool is centrally located between two gripper shoes, and equal with the distance of two baffle plates;Two baffle plates
The distance between more than described secondary joist length.
Further, described curtain skeleton manufactures construction technology and also includes step c: after described secondary joist welding finishes,
Alignment is carried out to described main joist.
Further, the alignment in described step c is carried out by straightening mould, and this straightening mould includes the support of both sides
Frame, is provided with the alignment plate of level above two bracing frames, described skeleton frame is located on two bracing frames, and on this main joist top
Face is provided with jack.
Further, described curtain skeleton manufactures construction technology and also includes step d: the main joist after alignment is struck
Welding slag, secondly brush anti-corrosive primer, then brush aluminium paint.
Further, in described step a, described main joist and secondary joist are cut by angle steel blank cutter.
Further, described adaptor installation steps include: surveying setting-out, install built-in fitting, install described adaptor.
Further, described adaptor and described built-in fitting pass through to be welded to connect;Or described adaptor is pre-buried with described
Part is fixedly connected by t type bolt, and the termination of described t type bolt is located in the chute of described built-in fitting.
Further, described curtain wall facestock is aluminium sheet or stone material.
The invention has the beneficial effects as follows: the present invention is compared with traditional handicraft:
1) surveying setting-out: traditional handicraft must release centre keel line, and eject transom ink after centre keel installation
Line, increased unwrapping wire operation, and the present invention only need to put centre keel line.
2) operation adjustment: traditional handicraft all process steps mutually restrict, and surveying setting-out completes, and carry out installation of embedded parts, carry out
Adaptor and main joist are installed, and main joist mounting and adjusting can carry out the positioning welding of secondary joist after finishing.And present invention measurement
The welding of unwrapping wire, installation of embedded parts and primary and secondary skeletal frame is synchronously carried out, and secondary joist weld interval is saved out, decrease operation it
Between restriction.
3) efficacy problems: the mode of secondary joist after the first main joist of traditional handicraft, essentially work high above the ground, with the present invention's
Ground welding is compared, and efficiency is very low.
4) safety problem: traditional handicraft operation generally existing high-altitude welding disaster hidden-trouble, face electric problem, the such as scope of operation does not collect
Medium easily cause primary line long, two-wire is not in place etc. common face electric problem, welding amount in high-altitude is big, during personal height operation
Between long safety problem, start to exchange fire not in place, or even the problem that cannot be carried out starting to exchange fire can be found everywhere, disaster hidden-trouble highlights;And this
Bright avoid the problems referred to above.
5) quality problems: traditional handicraft work high above the ground welding, inevitably produce Os Draconis deformation, be difficult to carry out effective school
Directly, affect Os Draconis precision;Although transom good line of ink marker of bullet etc., due to being work high above the ground it is impossible to ensure the level of Os Draconis
Precision, left and right Os Draconis length;The quality problems of weld seam highlight, and weld seam is uneven, not full, or even solder skip, leaves to engineering
Very big hidden danger;Anti-corrosion not in place cannot avoid.The problem more than present invention all can avoid, every procedure, strictly effectively, flowing water
Lineman makees, and it is convenient to check, sets up successive check, and finds that the underproof NonConforming Parts Area that enters, it is ensured that product qualified rate, improves
Overall Os Draconis quality.
Brief description
Fig. 1 is the process flow diagram of the present invention.
Fig. 2 is the structural representation of the perforating mold of the present invention.
Fig. 3 is the structural representation of the straightening mould of the present invention.
Specific embodiment
With reference to the accompanying drawings and examples, the specific embodiment of the present invention is further described, following examples are only
For clearly technical scheme being described it is impossible to limit the scope of the invention with this.
As indicated with 1, the present invention provides a kind of curtain skeleton to manufacture construction technology, for aluminium sheet or stone curtain wall.The present invention
Os Draconis be main joist and secondary joist, this main joist is welded with multiple secondary joists vertical with main joist.Curtain skeleton of the present invention
Manufacture construction technology includes wall step in the Os Draconis manufacturing step simultaneously carrying out and adaptor installation steps, and follow-up Os Draconis
Suddenly, warming plate installation steps, aluminium alloy suspension member installation steps, curtain wall facestock installation steps.In wall step on this Os Draconis, manufacture
Good Os Draconis are bolted to connection with adaptor mounted on body of wall.
It can be seen that (one), primary and secondary skeletal frame connector of the present invention are welded on terrestrial operation, significantly ensure that welding
Quality;(2), primary and secondary skeletal frame of the present invention is installed and is not affected by centre keel installation process, and installation effectiveness and speed are accelerated;(3), originally
The Os Draconis welding of invention can be carried out with surveying setting-out, installation of embedded parts simultaneously, and several operations carry out decreasing between operation simultaneously
Mutual restriction degree;(4), keel installation process of the present invention only need to hang vertical line, and portraitlandscape Os Draconis position exists
Ground completes.
To sum up: the present invention is distinguished as with the maximum of common process, operation field factories as far as possible, energy terrestrial operation is never
Upper wall operation, carries out factory management, runs, and carries out Os Draconis and walks " keel element pattern ", greatly improves efficiency, ensure that
Quality, decrease many unsafe factors, quality drawback, save effective duration, create more large project profit.
Specifically, this Os Draconis manufacturing process includes:
A. pass through the cutting of angle steel blank cutter on request and manufacture main joist and secondary joist, angle steel blank cutter is fixed on ground,
Carry out insulation processing and face electricity, fixing grinding tool is carried out in angle steel blank cutter front end, be standard primary and secondary tread apart from fracture position
Degree, angle steel only need to be pushed ahead and be withstood grinding tool is exactly required primary and secondary Os Draconis length, and foot steps on blank cutter operating pedal cut-out angle steel,
Sparks flying off in all directions for superseded conventional cutter, and cutting is inaccurate, the low technique of work efficiency.
Then bore suspension member hole at the secondary joist two ends of well cutting.Preferably, as shown in Fig. 2 in this step a, this secondary joist
Suspension member hole opened up by being fixed at the perforating mold of drilling tool 1 lower section, this perforating mold includes the baffle plate 2 of both sides and is located at two
Two gripper shoes 3 between individual baffle plate 2, the height of this baffle plate 2 is higher than the height of this gripper shoe 3.This drilling tool 1 is centrally located at two
Between gripper shoe 3 and equal with the distance of two baffle plates 2.The distance between two baffle plates 2 are more than the length of this secondary joist.
For example: secondary joist length 50cm, suspension member hole middle-range side 50mm, drilling tool bench drill is fixed on perforating mold centre position, hole middle-range platform
20cm in brill, in both sides in bench drill, the position of 450mm, welding baffle 2, so can be moved by left and right in gripper shoe 3
The mach secondary joist of angle steel fracture before dynamic, is punched, convenient and swift, accurately.
B. according to curtain wall lattice height on main joist labelling secondary joist position.Specifically, primary and secondary skeletal frame simultaneously enters
Scale area, same size can use the machine frame two ends manufactured in advance to block alignment, carries out scale line according to secondary joist frame bar,
Indicate secondary joist position.Several welders operation simultaneously, the line reserved by last process, on the premise of getting hold of level, by primary and secondary
Os Draconis are welded, and project management department can whole check, terrestrial operation work is simple, and speed is quick, and difficulty of construction is little, check power in addition
Degree is big, greatly improves weldquality and speed of welding.
After Os Draconis welding finishes, meeting without exception produces different degrees of deformation.Wall welding master on traditional handicraft Os Draconis
Secondary joist, the welding of high temperature, can cause the moderate finite deformation of Os Draconis, and the Os Draconis after upper wall cannot correct it is easy to cause facestock
The inadequate problem of the hanging piece for stone adjustment amount of installation process, makes surface stone material uneven, or makes suspension member not enter groove to eventually form
The potential safety hazard such as come off, and also can affect the installation effect of facestock to a great extent.Therefore, curtain skeleton manufacture construction of the present invention
Technique also includes step c: after the welding of this secondary joist finishes, carries out alignment to this main joist.Straightening mould is passed through in described alignment
Carry out, as shown in figure 3, this straightening mould includes the bracing frame 4 of both sides, above two bracing frames 4, be provided with the alignment plate 5 of level,
This main joist 6 is erected on two bracing frames 4, and is provided with jack 7 in this main joist 6 top surface, can be accurate to by guiding ruler detection,
The application of this technique can be installed to curtain wall facestock and be brought great aesthetic.The present invention carries out alignment to deformation Os Draconis, this
Sample is greatly improved the precision of Os Draconis processing naturally.
Preferably, curtain skeleton manufacture construction technology of the present invention also includes step d: the main joist after alignment is carried out striking weldering
Slag, secondly brush anti-corrosive primer, then brush aluminium paint.After the complete welding slag of bucketing, the Os Draconis situations such as solder skip of discovery, slag inclusion directly enter
Enter NonConforming Parts Area and wait for secondary operations.The Os Draconis that preservative treatment finishes enter finished product area, according to different size, code of classifying
Put, carry out Sign Board, wait to be installed.
In the Os Draconis course of processing, associated adaptor installation steps have been finished, finished product Os Draconis can directly on
Wall, according to the Keel Line put well, transom scale level etc. completes in terrestrial operation, only need to get hold of perpendicularity and be
Can.Specifically, this adaptor installation steps includes: surveying setting-out, installs built-in fitting, installs this adaptor.If this is pre-buried
Part is slot type embedded part, and this adaptor is fixedly connected by t type bolt with this built-in fitting, and the termination of this t type bolt is pre-buried positioned at this
In the chute of part, overhead welding does not almost have.If this built-in fitting is board-like embedded part, this adaptor passes through welding with this built-in fitting
Connect, welding capacity is few.Laterally secondary joist only need to be fastened with bolt, drastically increases speed of application it is ensured that fire safety, high-altitude
Job safety and decrease hidden danger of quality.
Positive effect of the present invention is:
1 The present invention reduces fire risk.
2nd, in the present invention, unwrapping wire can synchronously be carried out with Os Draconis processing and welding, greatly improves keel installation efficiency.
3rd, while ground welding of the present invention can welding finish after alignment Os Draconis so that Os Draconis welding deformation on ground
Eliminate, significantly decrease Os Draconis deformation it is ensured that the flatness of Os Draconis is so that Os Draconis precision increases, facestock flatness
More easy to control, be conducive to the overall appearance after installing.
4th, the present invention effectively reduces solder skip, improves welding quality.
5th, quality control of the present invention is convenient, and operation achieves huge conversion spatially.
6th, security risk of the present invention reduces, and 80% work high above the ground is switched to terrestrial operation, reduces cross-operation simultaneously
The risk brought.
7th, the present invention can save the duration: structure need not be waited to pay my department, after only need to carrying out checking unwrapping wire, you can on ground
It is processed machine welding.
The above, be only the preferred forms of the present invention, non-the present invention is imposed any restrictions, every according to the present invention
Technical spirit, to implementing any simple modification, change and the equivalent transformation that are made above, all still falls within technical solution of the present invention
Protection domain in.
Claims (10)
1. a kind of curtain skeleton manufactures construction technology it is characterised in that it includes the Os Draconis manufacturing step carrying out and switching simultaneously
Wall step, warming plate installation steps, aluminium alloy suspension member installation steps, curtain wall facestock in part installation steps, and follow-up Os Draconis
Installation steps;In wall step on this Os Draconis, the Os Draconis and the mounted adaptor on body of wall that have manufactured are bolted even
Connect.
2. curtain skeleton according to claim 1 manufacture construction technology it is characterised in that: described Os Draconis manufacturing process bag
Include:
A. cutting manufactures main joist and secondary joist on request, and bores suspension member hole at secondary joist two ends;
B. according to curtain wall lattice height on main joist labelling secondary joist position, and secondary joist is welded on relevant position.
3. curtain skeleton according to claim 2 manufacture construction technology it is characterised in that: in described step a, described dragon
The suspension member hole of bone is opened up by the perforating mold being fixed at below drilling tool, and this perforating mold includes the baffle plate of both sides and is located at two
Two gripper shoes between individual baffle plate, the height of this baffle plate is higher than the height of this gripper shoe;This drilling tool is centrally located at two supports
Between plate and equal with the distance of two baffle plates;The distance between two baffle plates are more than the length of described secondary joist.
4. curtain skeleton according to Claims 2 or 3 manufacture construction technology it is characterised in that: also include step c: described
After secondary joist welding finishes, alignment is carried out to described main joist.
5. curtain skeleton according to claim 4 manufacture construction technology it is characterised in that: the alignment in described step c is led to
Cross straightening mould to carry out, this straightening mould includes the bracing frame of both sides, above two bracing frames, be provided with the alignment plate of level, described
Skeleton frame is located on two bracing frames, and is provided with jack in this main joist top surface.
6. curtain skeleton according to claim 5 manufacture construction technology it is characterised in that: also include step d: after alignment
Main joist carry out striking welding slag, secondly brush anti-corrosive primer, then brush aluminium paint.
7. curtain skeleton according to claim 6 manufacture construction technology it is characterised in that: in described step a, by angle steel
Blank cutter cuts described main joist and secondary joist.
8. curtain skeleton according to claim 1 manufacture construction technology it is characterised in that: described adaptor installation steps bag
Include: surveying setting-out, built-in fitting is installed, described adaptor is installed.
9. curtain skeleton according to claim 8 manufacture construction technology it is characterised in that: described adaptor is pre-buried with described
Part passes through to be welded to connect;Or described adaptor is fixedly connected by t type bolt with described built-in fitting, the end of described t type bolt
Head is located in the chute of described built-in fitting.
10. curtain skeleton according to claim 1 manufacture construction technology it is characterised in that: described curtain wall facestock is aluminium sheet
Or stone material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610892247.8A CN106351371A (en) | 2016-10-13 | 2016-10-13 | Manufacturing and construction process of curtain keel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610892247.8A CN106351371A (en) | 2016-10-13 | 2016-10-13 | Manufacturing and construction process of curtain keel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106351371A true CN106351371A (en) | 2017-01-25 |
Family
ID=57866528
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610892247.8A Pending CN106351371A (en) | 2016-10-13 | 2016-10-13 | Manufacturing and construction process of curtain keel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106351371A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110805185A (en) * | 2019-11-20 | 2020-02-18 | 大同煤矿集团有限责任公司 | Installation method of large-span curved surface special-shaped stone curtain wall |
CN110984446A (en) * | 2019-12-17 | 2020-04-10 | 天邑昊建筑装饰工程有限公司 | Efficient curtain wall installation method |
CN111321815A (en) * | 2020-03-11 | 2020-06-23 | 张学付 | Construction process for installing and fixing rock wool board of heat-insulating layer of building outer wall |
CN111576691A (en) * | 2020-06-02 | 2020-08-25 | 中建八局第二建设有限公司 | Frame type glass curtain wall mounting method and glass curtain wall system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101289893A (en) * | 2008-01-21 | 2008-10-22 | 沈英 | Pottery clay plate curtain wall crossbeam-free mounting structure |
CN201423398Y (en) * | 2009-06-25 | 2010-03-17 | 鹿泉市地方公路管理站 | Steel moulding plate shaping machine |
CN101824895A (en) * | 2010-02-08 | 2010-09-08 | 北京建工集团有限责任公司 | Drily hung vitrolite wall surface decoration system and construction method thereof |
CN102995907A (en) * | 2011-12-14 | 2013-03-27 | 上海中建八局装饰有限责任公司 | Assembled type unit framework installing method |
CN104769195A (en) * | 2014-04-04 | 2015-07-08 | 杨东佐 | Combined wall body and construction method thereof |
CN104805938A (en) * | 2014-01-23 | 2015-07-29 | 深圳市方大建科集团有限公司 | Stone curtain wall and method for assembling and mounting stone curtain wall |
CN104989018A (en) * | 2015-06-23 | 2015-10-21 | 上海龙人建设集团有限公司 | Non-welding stone curtain wall mounting structure and method |
CN205237597U (en) * | 2015-12-10 | 2016-05-18 | 苏州科冈迪数控设备有限公司 | Section bar boring grab |
-
2016
- 2016-10-13 CN CN201610892247.8A patent/CN106351371A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101289893A (en) * | 2008-01-21 | 2008-10-22 | 沈英 | Pottery clay plate curtain wall crossbeam-free mounting structure |
CN201423398Y (en) * | 2009-06-25 | 2010-03-17 | 鹿泉市地方公路管理站 | Steel moulding plate shaping machine |
CN101824895A (en) * | 2010-02-08 | 2010-09-08 | 北京建工集团有限责任公司 | Drily hung vitrolite wall surface decoration system and construction method thereof |
CN102995907A (en) * | 2011-12-14 | 2013-03-27 | 上海中建八局装饰有限责任公司 | Assembled type unit framework installing method |
CN104805938A (en) * | 2014-01-23 | 2015-07-29 | 深圳市方大建科集团有限公司 | Stone curtain wall and method for assembling and mounting stone curtain wall |
CN104769195A (en) * | 2014-04-04 | 2015-07-08 | 杨东佐 | Combined wall body and construction method thereof |
CN104989018A (en) * | 2015-06-23 | 2015-10-21 | 上海龙人建设集团有限公司 | Non-welding stone curtain wall mounting structure and method |
CN205237597U (en) * | 2015-12-10 | 2016-05-18 | 苏州科冈迪数控设备有限公司 | Section bar boring grab |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110805185A (en) * | 2019-11-20 | 2020-02-18 | 大同煤矿集团有限责任公司 | Installation method of large-span curved surface special-shaped stone curtain wall |
CN110984446A (en) * | 2019-12-17 | 2020-04-10 | 天邑昊建筑装饰工程有限公司 | Efficient curtain wall installation method |
CN111321815A (en) * | 2020-03-11 | 2020-06-23 | 张学付 | Construction process for installing and fixing rock wool board of heat-insulating layer of building outer wall |
CN111321815B (en) * | 2020-03-11 | 2021-08-24 | 日照汇新墙体建材科技有限公司 | Construction process for installing and fixing rock wool board of heat-insulating layer of building outer wall |
CN111321815B8 (en) * | 2020-03-11 | 2021-12-10 | 日照汇新墙体建材科技有限公司 | Construction process for installing and fixing rock wool board of heat-insulating layer of building outer wall |
CN111576691A (en) * | 2020-06-02 | 2020-08-25 | 中建八局第二建设有限公司 | Frame type glass curtain wall mounting method and glass curtain wall system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106351371A (en) | Manufacturing and construction process of curtain keel | |
CN110984446A (en) | Efficient curtain wall installation method | |
CN103758265B (en) | A kind of irregular facade rack type GRC curtain wall and installation method thereof | |
CN102979312B (en) | Indoor aluminum honeycomb board suspended ceiling reverse installation technology | |
CN104912340A (en) | Construction method for double-curve triangular aluminum plate unit type hanging ceiling | |
CN102312541A (en) | Vertical-surface stone dry-hang installing system | |
CN203684632U (en) | Telescopic type welding operation platform | |
CN204691296U (en) | Spigot-and-socket building is faced frontier defense and is protected | |
CN102359242A (en) | Vertical-face stone dry-hanging mounting structure | |
CN211923193U (en) | Convenient keel structure of furred ceiling board | |
CN102777042A (en) | Installation technology of connecting board type inner separation wall | |
CN102966235A (en) | Carrying tool | |
CN202148665U (en) | Dry-hanging installation system for facade stones | |
CN103835516A (en) | H-type steel beam installation gap adjusting device and use method thereof | |
CN102493620A (en) | Through long folded fastener type wall body connecting piece of heat insulation integrated plate and mounting method thereof | |
CN105089194A (en) | Ceiling conversion layer self-prolonged hanging device and construction method thereof | |
CN202148664U (en) | Stone material dry-hang mounting structure of vertical surface | |
CN203343586U (en) | Cutter hanging guiding tracks during H-shaped steel flange cutting | |
CN208220087U (en) | A kind of cladding aluminum alloy framework | |
CN204703542U (en) | The assembled passage of a kind of Construction of Steel Structure regularization | |
CN202899532U (en) | Connecting component for low carbon plate adhesive clamping combination | |
CN204142254U (en) | A kind of interior decoration surveying setting-out device | |
CN209799104U (en) | Aluminum veneer curtain wall installation appurtenance | |
CN210563080U (en) | Novel outer wrapping type glass railing | |
CN204983335U (en) | Furred ceiling is staple bolt device for conversion layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170125 |
|
RJ01 | Rejection of invention patent application after publication |