CN106346161B - A kind of resistance to deformation installation method of swing-type plate shears - Google Patents

A kind of resistance to deformation installation method of swing-type plate shears Download PDF

Info

Publication number
CN106346161B
CN106346161B CN201611064767.6A CN201611064767A CN106346161B CN 106346161 B CN106346161 B CN 106346161B CN 201611064767 A CN201611064767 A CN 201611064767A CN 106346161 B CN106346161 B CN 106346161B
Authority
CN
China
Prior art keywords
welding
wallboard
plate
welded
deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611064767.6A
Other languages
Chinese (zh)
Other versions
CN106346161A (en
Inventor
夏恒严
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI CHANGJIANG MACHINE TOOL MANUFACTURING (GROUP) Co Ltd
Original Assignee
ANHUI CHANGJIANG MACHINE TOOL MANUFACTURING (GROUP) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI CHANGJIANG MACHINE TOOL MANUFACTURING (GROUP) Co Ltd filed Critical ANHUI CHANGJIANG MACHINE TOOL MANUFACTURING (GROUP) Co Ltd
Priority to CN201611064767.6A priority Critical patent/CN106346161B/en
Publication of CN106346161A publication Critical patent/CN106346161A/en
Application granted granted Critical
Publication of CN106346161B publication Critical patent/CN106346161B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23DPLANING; SLOTTING; SHEARING; BROACHING; SAWING; FILING; SCRAPING; LIKE OPERATIONS FOR WORKING METAL BY REMOVING MATERIAL, NOT OTHERWISE PROVIDED FOR
    • B23D15/00Shearing machines or shearing devices cutting by blades which move parallel to themselves
    • B23D15/06Sheet shears
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23DPLANING; SLOTTING; SHEARING; BROACHING; SAWING; FILING; SCRAPING; LIKE OPERATIONS FOR WORKING METAL BY REMOVING MATERIAL, NOT OTHERWISE PROVIDED FOR
    • B23D33/00Accessories for shearing machines or shearing devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of resistance to deformation installation methods of swing-type plate shears, belong to plate shearing machine manufacture field.The installation method of plate shearing machine tool apron of the present invention, plate shearing machine are mainly made of rack, bracket and binder seat, are installed using welding method, main installation steps are as follows: Step 1: wallboard and binder seat are welded into rack;Step 2: installation other component;Step 3: weld brackets and place on the rack, prepare welding;Step 4: to main supporting plate, auxiliary supporting plate spot welding positioning;Step 5: installing lower tool apron and adjusting lower knife body straightness;Step 6: using diagonal welding sequence weld brackets.The present invention is handled by the deformation adjustment after the reasonable arrangement to plate shearing machine mounting process and first layer welding, is solved the problems, such as mutability in plate shearing machine installation process, is extended the service life of equipment.

Description

A kind of resistance to deformation installation method of swing-type plate shears
Technical field
The present invention relates to plate shearing machine technical fields, more specifically to a kind of resistance to deformation installation side of swing-type plate shears Method.
Background technique
Plate shearing machine is used for the shearing of sheet metal, and the shearing power resources of plate shearing machine are cut in hydraulic drive or machine driving When plate, it is necessary to adjust cutter cutting edge and bottom knife sword according to the thickness for the shear strength and sheet metal for being sheared sheet metal Gap between mouthful, and to keep the uniformity in gap.If gap is different or blade itself has certain deformation, into When row sheet shearing, it is easy to situations such as causing uneven notch, sheet deformation generation.Especially for the biggish plate of thickness Material, if cutter itself there are deformation problems, can generate stress concentration, when shearing it is possible that cutting edge cracks situation.
In the installation process of plate shearing machine, what service life subsequent for cutter was affected is the packaging technology of tool apron, Because general binder seat and lower tool apron are assembled into rack by welding procedure, in the welding process, thermal deformation pair is welded Installation accuracy is affected, and therefore, if welding procedure is unreasonable, may directly influence the subsequent of plate shearing machine and use the longevity Life.
It is big why the tool apron of plate shearing machine welds installation difficulty, main reason is that its length is larger, generally in 2m or more, Deformation is caused to be difficult to control.Such as the binder seat in plate shearing machine, length is big, and thickness is small, when welding, is easy to out in the middle part of tool apron Arch or outer bulgy phenomenon in existing, certainly, the external presentation of this phenomenon are not to protrude very much, may but for installation requirement It is serious to deviate from standard.Therefore, how to arrange welded and installed technique for the precision of plate shearing machine tool apron and the tune of deformation It is whole to be particularly important.
Summary of the invention
1. technical problems to be solved by the inivention
It is an object of the invention to overcome the shortcomings of to be easy deformation in plate shearing machine installation process in the prior art, one is provided The resistance to deformation installation method of kind swing-type plate shears, the present invention pass through the reasonable arrangement and first layer to plate shearing machine mounting process Deformation adjustment processing after welding, solves the problems, such as mutability in plate shearing machine installation process, extends the service life of equipment.
2. technical solution
In order to achieve the above objectives, technical solution provided by the invention are as follows:
A kind of resistance to deformation installation method of swing-type plate shears of the invention manufactures installation process are as follows:
Step 1: welding supporting beam, binder seat between two wallboards, rack is formed;
Step 2: mounting tool post, oil cylinder, kicker cylinder, backgauge frame on the rack;Binder cylinder is installed on binder seat;
Step 3: weld brackets, the bracket being welded are lifted on the wallboard of rack, and adjust the position of bracket;
Step 4: the junction spot welding in main supporting plate and the first wallboard positions;Then to auxiliary supporting plate and second wallboard Junction carries out spot welding positioning;Then successively to main supporting plate and the second wallboard, auxiliary supporting plate and the first wallboard in junction spot welding Positioning;
Step 5: knife holder mechanism under installing on the workbench of bracket, adjusts the straight line of lower knife body in lower knife holder mechanism Degree;
Step 6: carrying out first layer welding according to the diagonal welding sequence in step 4, after welding, detects and adjust The straightness of lower knife body carries out second layer welding according to first layer welding sequence, is welded by the second layer and carry out deformation adjustment;
Step 7: completing the installation of operating device, fluid pressure line, distribution line.
As further improvement of the present invention, in step 1 during welding binder seat, first to binder seat and rack Spot welding positioning is carried out, first layer welding is then carried out;The straightness that upper base plate in binder seat is detected after welding, is welded using the second layer Tap into row deformation adjustment.
As further improvement of the present invention, spot welding sequence in step 1 are as follows: from the first wallboard of outside spot welding and the seat of honour The junction of plate, then from the junction of outside spot welding the second wallboard and upper base plate;The first wallboard and the seat of honour are welded from interior measuring point again The junction of plate, the then junction of spot welding the second wallboard and upper base plate.
As further improvement of the present invention, in the first layer welding in step 1, using alternating expression welding method pair Wallboard exterior portion is welded, alternating expression welding sequence are as follows:
A, it is spot welded in upper and lower combine of the first wallboard and upper base plate, then welds the middle part of the second wallboard and upper base plate Binding site;
B, the middle part binding site of the first wallboard and upper base plate is welded;
C, the upper and lower binding site of the second wallboard and upper base plate is welded.
As further improvement of the present invention, when welding progress deformation adjustment using the second layer, if upper base plate evagination, Second layer welding is then carried out on the inside of wallboard;If arch in upper base plate, carries out second layer welding on the outside of wallboard.
As further improvement of the present invention, knife rest described in step 2 is mounted on knife rest balance staff, by oil cylinder and Backhaul oil cylinders drive knife rest to swing around knife rest balance staff.
As further improvement of the present invention, binder cylinder described in step 2 is set in qually spaced in binder seat bottom, and It is bolted;Spring is connected on the piston shaft of binder cylinder.
As further improvement of the present invention, bracket described in step 3 is mainly by workbench, main supporting plate and auxiliary branch When board group is at, welding, tool apron adjustable plate is first welded on the table, then workbench, main supporting plate and auxiliary supporting plate are welded on one It rises, the workbench after welding is horizontally situated.
As further improvement of the present invention, lower knife body described in step 5 is fixed on lower tool apron, and the lower tool apron is logical It crosses outer drawing bolt and interior supporting bolt is connect with tool apron adjustable plate, pass through outer drawing bolt and interior supporting bolt adjusts the straight line of lower knife body Degree.
As further improvement of the present invention, in step 6 after completing first time to welded corner joint, lower knife body is detected Straightness adjusts the Size of welds of main supporting plate and the second wallboard junction according to testing result.
3. beneficial effect
Using technical solution provided by the invention, compared with prior art, have the following beneficial effects:
(1) the resistance to deformation installation method of a kind of swing-type plate shears of the invention passes through the reasonable peace to assembling, welding procedure Row, is mounted together each component of plate shearing machine, and reduce deformation and internal stress by the interaction of welding procedure, from And when welding being overcome to install tool apron deformation difficult point, improve welding quality, deformation when eliminating shear cutter use and answer Power concentration phenomenon extends the service life of cutter and equipment;
(2) the resistance to deformation installation method of a kind of swing-type plate shears of the invention, using alternating expression welding method to binder seat It is welded, more conducively welds the mutual correction of thermal deformation;The welding for carrying out the other side is welded on if it is advanced side, by It is longer in whole weld seam, it is possible that whole deformation, and be difficult to correct;And alternating expression welding method is used, due to centre In the presence of interruption part, weld seam is relatively short, and one side deformation quantity is less, on the other hand in staggeredly welding process can mutually into Row thermal deformation correction, facilitates the raising of welding quality;In addition, the adjusting of interior arch or evagination deformation is carried out using two layers of welding, Stress existing for upper base plate is greatly reduced, straightness is guaranteed;
(3) the resistance to deformation installation method of a kind of swing-type plate shears of the invention, when carrying out the welding of bracket, using diagonal Welding procedure helps to eliminate deformation dislocation;It is first to weld main supporting plate, main supporting plate is to workbench when carrying out every time to fillet welding Play main support, auxiliary supporting plate only further increases structural strength, therefore, it is necessary to be first to weld main supporting plate, it is ensured that its Positional accuracy and structural stability, and then guarantee the position precision of workbench or more tool apron, improve integral solder quality.
Detailed description of the invention
Fig. 1 is the installation procedure figure of plate shearing machine;
Fig. 2 is the cross section structure schematic diagram of plate shearing machine;
Fig. 3 is the distributing position schematic diagram of plate shearing machine cornice sheathing;
Fig. 4 is the structural schematic diagram of binder seat;
Fig. 5 is alternating expression welding method schematic diagram;
Fig. 6 is the structural schematic diagram of bracket;
Fig. 7 is the structural schematic diagram of lower knife holder mechanism;
Fig. 8 is the outer position distribution schematic diagram for drawing bolt and interior supporting bolt.
Label declaration in schematic diagram: 1, rack;11, the first wallboard;12, the second wallboard;13, knife rest;14, knife rest is put Axis;15, supporting beam;2, bracket;21, workbench;22, supporting plate is assisted;23, main supporting plate;24, transverse slat;25, lower knife holder mechanism; 251, tool apron adjustable plate;252, supporting plate is fed;253, lower tool apron;254, lower knife body;255, outer drawing bolt;256, interior supporting bolt; 26, stiffening plate;3, binder seat;31, upper base plate;32, binder connecting plate;33, binder cylinder.
Specific embodiment
To further appreciate that the contents of the present invention, the present invention is described in detail in conjunction with the accompanying drawings and embodiments.
Embodiment 1
In conjunction with Fig. 2, plate shearing machine generally comprise by two wallboards and support beam group at rack, the binder that is connected with wallboard Seat, knife rest, oil cylinder etc., although structure is more conventional, its installation process is affected for the service life of equipment, this reality It applies example and provides a kind of resistance to deformation installation method of swing-type plate shears, such as Fig. 1, detailed process are as follows:
Step 1: welding supporting beam 15, binder seat 3 between two wallboards, rack 1 is formed.
As shown in figure 3, wallboard includes the first wallboard 11 and the second wallboard 12, first two wallboards are fixed with rack, then Supporting beam 15 is welded, binder seat 3 is then welded.In 3 welding process of binder seat, it is fixed that spot welding first is carried out to binder seat 3 and rack 1 Position, i.e., be fixed on binder seat 3 between two wallboards, then carries out first layer welding;Upper base plate in binder seat 3 is detected after welding 31 straightness is welded using the second layer and carries out deformation adjustment.
As shown in figure 4, binder seat 3 is mainly composed of upper base plate 31 and binder connecting plate 32, the two forms T junction Structure, wherein binder connecting plate 32 is primarily used to installation feeding pressure mechanism, and upper base plate 31 is then for fixing binder connecting plate 32, it is fixed on the rack it.Upper cutter head is often to be mounted on the rack close to the position of upper base plate 31, if upper base plate 31 welds Deformation is larger when connecing, and entire rack can be made all to there is stress concentration phenomenon, causes structural strength insufficient, when in use, it is easy to It cracks;It is affected to shear effect, in some instances it may even be possible to will appear sword and split phenomenon, seriously affect cutter and equipment and use the longevity Life.Therefore, it is necessary to draw to guarantee whole welding quality using second layer welding.
It is worth noting that when welding progress deformation adjustment using the second layer, if 31 evagination of upper base plate, i.e. upper base plate 31 Middle part is protruded to the side for deviateing rack, then second layer welding is carried out on the inside of wallboard, and leg can be to 31 1 lateral deviation of upper base plate It moves;If arch in upper base plate 31, i.e. 31 middle part of upper base plate is recessed to the side close to rack, then second layer weldering is carried out on the outside of wallboard It connects.The paving open area that will increase leg after second layer welding is reached due to the difference of welding position and is aligned the seat of honour from different directions The purpose of plate 31 guarantees welding quality to allow.
In addition, if 31 deformation quantity of upper base plate is larger, two layers of weldering can be carried out to supporting beam 15 before carrying out second layer welding It connects.The main function of supporting beam 15 is reinforcement structure intensity, and the front and rear sides of rack are distributed in binder seat 3, in deformation In biggish situation, simple by the weld seam adjusting to binder seat 3 is difficult to that it is made to restore shape, and by supporting beam 15 Two layers of welding, can be adjusted with internal stress, facilitate the release of stress, reduce influence of the supporting beam to deformation.
Step 2: mounting tool post 13, oil cylinder, kicker cylinder, backgauge frame in rack 1;Binder cylinder is installed on binder seat 3 33。
The knife rest 13 is mounted on knife rest balance staff 14, drives knife rest 13 around knife rest balance staff 14 by oil cylinder and backhaul oil cylinders It swings, oil cylinder and kicker cylinder carry out sheet shearing for driving knife rest 13 to move, by the upper knife body on knife rest 13;On backgauge frame Equipped with striker plate, for controlling panel length.Binder cylinder 33 is set in qually spaced in 3 bottom of binder seat, and is bolted;? Spring is connected on the piston shaft of binder cylinder 33.Binder cylinder 33 prevents the plate in shear history from misplacing for compressing plate.Such as There is deformation in fruit binder seat 3, on the one hand plate can be made to have certain deformation during binder, on the other hand will lead to wallboard Faint deformation is generated, and knife rest 13 is mounted on wallboard, influences machining accuracy and cutting-tool's used life.
Step 3: weld brackets 2, the bracket 2 being welded are lifted on the wallboard of rack 1, and adjust the position of bracket 2 It sets.
As shown in fig. 6, the main function of bracket 2 is to carry lower tool apron, mainly by workbench 21, main supporting plate 23 and auxiliary branch Plate 22 forms.When welding, tool apron adjustable plate 251 is first welded on workbench 21, then by workbench 21, main supporting plate 23 and assist branch Plate 22 welds together, and the workbench 21 after welding is horizontally situated.
Main supporting plate 23 is vertically arranged, and auxiliary supporting plate 22 can be vertically arranged, and also tiltable is arranged, since it primarily serves auxiliary Supporting role is not specifically limited.
In order to increase structural strength, it is connected with transverse slat 24 in the bottom position of main supporting plate 23 and auxiliary supporting plate 22, the transverse slat 24 can prevent main supporting plate 23 when welding and assist the internally deformation of supporting plate 22, have certain thermal deformation supporting role.
Step 4: needing to carry out spot welding positioning after step 3 adjustment good position.Since bracket overall dimensions are larger, become Shape very little, main deformation appear in deformation caused by positional shift when first layer welds, and therefore, it is necessary to determine in spot welding Good welding position.When specific operation, spot welding is carried out using diagonal welding manner, in the junction of main supporting plate 23 and the first wallboard 11 Spot welding positioning;Then spot welding positioning is carried out to the junction of auxiliary supporting plate 22 and the second wallboard 12;Then successively to main supporting plate 23 It is positioned with the second wallboard 12, auxiliary supporting plate 22 and the first wallboard 11 in junction spot welding.
Step 5: knife holder mechanism 25 under installing on the workbench 21 of bracket 2, adjusts lower knife body in lower knife holder mechanism 25 254 straightness.
Step 6: carrying out first layer welding according to the diagonal welding sequence in step 4, after welding, detects and adjust The straightness of lower knife body 254 carries out second layer welding according to first layer welding sequence, is welded by the second layer and carry out deformation tune It is whole;
Step 7: completing the installation of operating device, fluid pressure line, distribution line and rest part, step can be according to normal Rule method is operated, and is repeated no more.
The present invention is mounted together each component of plate shearing machine, Er Qietong by the reasonable arrangement to assembling, welding procedure The interaction for crossing two layers of welding procedure reduces deformation and internal stress, thus the difficult point that tool apron deforms when welding being overcome to install, Welding quality is improved, deformation and stress concentration phenomenon when shear cutter uses is eliminated, extends making for cutter and equipment Use the service life.
Embodiment 2
A kind of resistance to deformation installation method of swing-type plate shears of the present embodiment, basic process is same as Example 1, no It is with place: spot welding sequence in step 1 are as follows: from the junction of the first wallboard of outside spot welding 11 and upper base plate 31, then from outer The junction of the second wallboard of side point weldering 12 and upper base plate 31;The junction of the first wallboard 11 and upper base plate 31 is welded from interior measuring point again, Then the junction of the second wallboard of spot welding 12 and upper base plate 31.
Embodiment 3
In conjunction with Fig. 5, a kind of resistance to deformation installation method of swing-type plate shears of the present embodiment, basic process and embodiment 2 It is identical, the difference is that: in the welding of first layer in step 1, using alternating expression welding method to wallboard exterior portion into Row welding, alternating expression welding sequence are as follows:
A, it is spot welded in upper and lower combine of the first wallboard 11 and upper base plate 31, then welds the second wallboard 12 and upper base plate 31 middle part binding site;
B, the middle part binding site of the first wallboard of welding 11 and upper base plate 31;
C, the upper and lower binding site of the second wallboard of welding 12 and upper base plate 31.
First in the position of a side wall panel, 1. place is welded, and centre forms spaced points;Then in the position of wallboards of the other side 2. place is welded, it is complementary 1. to locate welding formation with position;Then in position, 3. place is welded, 4. last welding position is located, Which both can be shortened weld seam, reduce thermal deformation, and the thermal deformation of two sides can be made to cancel out each other, and obtain preferable welding matter Amount.
The welding for carrying out the other side again if it is first progress side welding, since whole weld seam is longer, it is possible that whole The bodily form becomes, and is difficult to correct;And alternating expression welding method is used, and since centre has interruption part, weld seam is relatively short, and one Aspect deformation quantity is less, and there are certain cooling meat times;On the other hand heat can be mutually carried out in staggeredly welding process Straightening facilitates the raising of welding quality.
Embodiment 4
A kind of resistance to deformation installation method of swing-type plate shears of the present embodiment, basic process is same as Example 3, no It is with place:
In conjunction with Fig. 6, when carrying out the welding of bracket in step 3, in order to guarantee the structural strength of main supporting plate 23, in main branch It is welded with stiffening plate 26 between plate 23 and workbench 21, forms a triangle between main supporting plate 23, workbench 21 and stiffening plate 26 Structure.
In specific welding, after having welded main supporting plate 23, adjust the position of stiffening plate 26, it is settable its with main supporting plate 23 Angle be 38 °, may be alternatively provided as the other angles value in 30~48 °, be not specifically limited;Then 26 spot welding of stiffening plate is determined Position, then carry out seam to two and weld.
Since strength support to be played acts on, and it is connect with workbench 21, so need angle between 30~48 °, If angle is excessive, the lateral bearing component that can be shared becomes larger, and longitudinal load-bearing component becomes smaller, and what can be played stablizes support Effect less, therefore will make limitation to angle.
When specifically used, the form of two pieces of scoreboards also can be used as structural reinforcing plate, but using the welding process of scoreboard It is more troublesome, it is not easy to control whole deformation, therefore, operate relatively complicated, it is difficult to it achieves the desired results, specifically used Shi Kegen According to the structure type for needing to select stiffening plate.
Embodiment 5
A kind of resistance to deformation installation method of swing-type plate shears of the present embodiment, basic process is same as Example 4, no It is with place:
In conjunction with Fig. 7, Fig. 8, lower knife body 254 is fixed on lower tool apron 253 in step 5, lower 253 top of tool apron be fixed with into Expect supporting plate 252, tool apron adjustable plate 251 is welded on 21 upper surface of workbench, and the lower tool apron 253 is by outer drawing bolt 255 and interior supports Bolt 256 is connect with tool apron adjustable plate 251.Wherein, outer drawing bolt 255 can tense lower tool apron 253 to the right;Interior supporting bolt 256 can resist lower tool apron 253 to the left;The straight line of lower knife body 254 is adjusted by outer drawing bolt 255 and interior supporting bolt 256 Degree, while the position of lower knife body 254 can be adjusted, change the spacing of upper knife body and lower knife body, adapts to cutting for different-thickness plate It cuts.
In the second layer welding process of step 6, need to carry out the adjustment of Size of welds, the adjustment according to testing result It is mainly reflected in the adjustment of Size of welds at main supporting plate 23.Supporting plate is assisted due to existing, when carrying out second layer welding, usually Leg is deviated to main supporting plate side, so that biggish paving open area, the i.e. exterior surface area of leg are obtained, to overcome existing Faint thermal deformation.
Schematically the present invention and embodiments thereof are described above, description is not limiting, institute in attached drawing What is shown is also one of embodiments of the present invention, and actual structure is not limited to this.So if the common skill of this field Art personnel are enlightened by it, without departing from the spirit of the invention, are not inventively designed and the technical solution Similar frame mode and embodiment, are within the scope of protection of the invention.

Claims (6)

1. a kind of resistance to deformation installation method of swing-type plate shears, it is characterised in that: its process are as follows:
Step 1: welding supporting beam, binder seat (3) between two wallboards, formed rack (1);In welding binder seat (3) process In, spot welding positioning first is carried out to binder seat (3) and rack (1), then carries out first layer welding;Binder seat (3) are detected after welding The straightness of middle upper base plate (31) is welded using the second layer and carries out deformation adjustment;Spot welding sequence are as follows: from the first wallboard of outside spot welding (11) with the junction of upper base plate (31), then from the junction of the second wallboard of outside spot welding (12) and upper base plate (31);Again from The junction of the first wallboard of inside spot welding (11) and upper base plate (31), the then knot of the second wallboard of spot welding (12) and upper base plate (31) At conjunction;Wallboard exterior portion is welded using alternating expression welding method in first layer welding, alternating expression welding sequence are as follows:
A, upper and lower combine in the first wallboard (11) and upper base plate (31) is spot welded, and then welds the second wallboard (12) and the seat of honour The middle part binding site of plate (31);
B, the middle part binding site of the first wallboard (11) and upper base plate (31) is welded;
C, the upper and lower binding site of the second wallboard (12) and upper base plate (31) is welded;
Step 2: mounting tool post (13), oil cylinder, kicker cylinder, backgauge frame on rack (1);Binder cylinder is installed on binder seat (3) (33);
Step 3: weld brackets (2), the bracket (2) being welded are lifted on the wallboard of rack (1), and adjust bracket (2) Position;The bracket (2) mainly be made of workbench (21), main supporting plate (23) and auxiliary supporting plate (22), and when welding, elder generation is working Tool apron adjustable plate (251) are welded on platform (21), then workbench (21), main supporting plate (23) and auxiliary supporting plate (22) are welded on one It rises, the workbench (21) after welding is horizontally situated;
Step 4: the junction spot welding in main supporting plate (23) and the first wallboard (11) positions;Then to auxiliary supporting plate (22) and the The junction of two wallboards (12) carries out spot welding positioning;Then successively to main supporting plate (23) and the second wallboard (12), auxiliary supporting plate (22) it is positioned with the first wallboard (11) in junction spot welding;
Step 5: knife holder mechanism (25) under being installed on the workbench (21) of bracket (2), under adjusting in lower knife holder mechanism (25) The straightness of cutter hub (254);
Step 6: carrying out first layer welding according to the diagonal welding sequence in step 4, after welding, detects and adjust and cut The straightness of body (254) carries out second layer welding according to first layer welding sequence, is welded by the second layer and carry out deformation adjustment;
Step 7: completing the installation of operating device, fluid pressure line, distribution line.
2. a kind of resistance to deformation installation method of swing-type plate shears according to claim 1, it is characterised in that: utilizing second When layer welding carries out deformation adjustment, if upper base plate (31) evagination, second layer welding is carried out on the inside of wallboard;If upper base plate (31) Interior arch then carries out second layer welding on the outside of wallboard.
3. a kind of resistance to deformation installation method of swing-type plate shears according to claim 1, it is characterised in that: institute in step 2 It states knife rest (13) to be mounted on knife rest balance staff (14), be put by oil cylinder and kicker cylinder driving knife rest (13) around knife rest balance staff (14) It is dynamic.
4. a kind of resistance to deformation installation method of swing-type plate shears according to claim 1, it is characterised in that: institute in step 2 It states binder cylinder (33) and is set in qually spaced in binder seat (3) bottom, and be bolted;Connect on the piston shaft of binder cylinder (33) It is connected to spring.
5. a kind of resistance to deformation installation method of swing-type plate shears according to claim 1, it is characterised in that: institute in step 5 It states lower knife body (254) to be fixed on lower tool apron (253), which passes through outer drawing bolt (255) and interior supporting bolt (256) it is connect with tool apron adjustable plate (251), lower knife body (254) is adjusted by outer drawing bolt (255) and interior supporting bolt (256) Straightness.
6. a kind of resistance to deformation installation method of swing-type plate shears according to claim 1, it is characterised in that: in step 6 After first time is completed to welded corner joint, the straightness of lower knife body (254) is detected, adjusts main supporting plate (23) and second according to testing result The Size of welds of wallboard (12) junction.
CN201611064767.6A 2016-11-28 2016-11-28 A kind of resistance to deformation installation method of swing-type plate shears Active CN106346161B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611064767.6A CN106346161B (en) 2016-11-28 2016-11-28 A kind of resistance to deformation installation method of swing-type plate shears

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611064767.6A CN106346161B (en) 2016-11-28 2016-11-28 A kind of resistance to deformation installation method of swing-type plate shears

Publications (2)

Publication Number Publication Date
CN106346161A CN106346161A (en) 2017-01-25
CN106346161B true CN106346161B (en) 2019-05-07

Family

ID=57862335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611064767.6A Active CN106346161B (en) 2016-11-28 2016-11-28 A kind of resistance to deformation installation method of swing-type plate shears

Country Status (1)

Country Link
CN (1) CN106346161B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB965823A (en) * 1962-03-14 1964-08-06 Steel Construction & Eng Co Improvements in or relating to guillotines and press brakes
CN201102100Y (en) * 2007-10-26 2008-08-20 安徽省三力机床制造有限公司 Hydraulic pendulum right angle plane shear
CN204277064U (en) * 2014-12-25 2015-04-22 安徽华东机床制造有限公司 A kind of lock formula plate shearing machine
CN205129056U (en) * 2015-11-02 2016-04-06 江苏三工钢结构有限公司 Hydraulic pendulum plate shears

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204277065U (en) * 2014-12-25 2015-04-22 安徽华东机床制造有限公司 A kind of swing-type plate shears

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB965823A (en) * 1962-03-14 1964-08-06 Steel Construction & Eng Co Improvements in or relating to guillotines and press brakes
CN201102100Y (en) * 2007-10-26 2008-08-20 安徽省三力机床制造有限公司 Hydraulic pendulum right angle plane shear
CN204277064U (en) * 2014-12-25 2015-04-22 安徽华东机床制造有限公司 A kind of lock formula plate shearing machine
CN205129056U (en) * 2015-11-02 2016-04-06 江苏三工钢结构有限公司 Hydraulic pendulum plate shears

Also Published As

Publication number Publication date
CN106346161A (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN101687541B (en) Aircraft structural element located at the interface between a wing and the fuselage
JP2010503541A5 (en)
CN102632344A (en) Welding deformation control process for ship superstructure
CN102922200B (en) Welding tool for inclined ladder of crane
CN101758333A (en) Control method of digging machine movable arm welding predeformation
CN106425351B (en) A kind of mounting process of shear machine knife blade
CN204657793U (en) A kind of device preventing Steel plate bridge unit making welding deformation
CN104057189A (en) Novel U-shaped cross section component, special jig frame and processing and setting method
CN106346161B (en) A kind of resistance to deformation installation method of swing-type plate shears
CN106378483B (en) A kind of machining manufacture of plate shearing machine
CN106425336B (en) A kind of processing technology of large hydraulic plate shearing machine rack
CN107671400A (en) A kind of handle of a knife weld jig
CN106346160B (en) A kind of packaging technology of plate shearing machine rack
CN106514025B (en) A kind of integral processing method of Frame of hydraulic steel plate shearer
CN111571072A (en) Welding precision control method for box-type slender beam
CN204565511U (en) A kind of pull bar otic placode fast accurate assembly tool
CN207508577U (en) Steel box-girder web assembly simple frock
CN106584032B (en) A kind of processing method of roller type machinery plate shearing machine supporting mechanism
CN209407908U (en) A kind of cutting grinding device of brightwork
CN210147089U (en) Novel angle steel cutting machine
CN203124999U (en) Lifting positioning system of marine multifunctional automation branch pipe accessory assembling mash welder
CN202291589U (en) Chamfering scissors for push-pull type pickling machine set
CN207272677U (en) A kind of bar frame alignment welding cut-out production line
CN220921319U (en) Special adjusting tool for processing trestle truss
CN106735500B (en) A kind of mechanical plate shearing machine and its processing method using supported at three point

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant