CN106337570B - 钢管注浆快速加固柱结构及施工方法 - Google Patents
钢管注浆快速加固柱结构及施工方法 Download PDFInfo
- Publication number
- CN106337570B CN106337570B CN201611007496.0A CN201611007496A CN106337570B CN 106337570 B CN106337570 B CN 106337570B CN 201611007496 A CN201611007496 A CN 201611007496A CN 106337570 B CN106337570 B CN 106337570B
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- half outsourcing
- pipe
- injected hole
- rod structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 139
- 239000010959 steel Substances 0.000 title claims abstract description 139
- 230000002787 reinforcement Effects 0.000 title claims abstract description 35
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 238000012946 outsourcing Methods 0.000 claims abstract description 89
- 239000011440 grout Substances 0.000 claims abstract description 28
- 238000000034 method Methods 0.000 claims abstract description 27
- 238000009434 installation Methods 0.000 claims abstract description 8
- 239000011150 reinforced concrete Substances 0.000 claims description 19
- 108010010803 Gelatin Proteins 0.000 claims description 18
- 238000001035 drying Methods 0.000 claims description 18
- 229920000159 gelatin Polymers 0.000 claims description 18
- 239000008273 gelatin Substances 0.000 claims description 18
- 235000019322 gelatine Nutrition 0.000 claims description 18
- 235000011852 gelatine desserts Nutrition 0.000 claims description 18
- 238000007569 slipcasting Methods 0.000 claims description 15
- 238000003032 molecular docking Methods 0.000 claims description 6
- 239000000203 mixture Substances 0.000 claims description 2
- 239000000463 material Substances 0.000 abstract description 8
- 238000003466 welding Methods 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 abstract description 3
- 238000009415 formwork Methods 0.000 abstract description 2
- 238000005728 strengthening Methods 0.000 abstract description 2
- 230000010412 perfusion Effects 0.000 description 4
- 239000004567 concrete Substances 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 2
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 229910000679 solder Inorganic materials 0.000 description 2
- 229920000049 Carbon (fiber) Polymers 0.000 description 1
- 229920002472 Starch Polymers 0.000 description 1
- 230000032683 aging Effects 0.000 description 1
- 239000004917 carbon fiber Substances 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 235000019698 starch Nutrition 0.000 description 1
- 239000008107 starch Substances 0.000 description 1
- 230000035882 stress Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611007496.0A CN106337570B (zh) | 2016-11-16 | 2016-11-16 | 钢管注浆快速加固柱结构及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611007496.0A CN106337570B (zh) | 2016-11-16 | 2016-11-16 | 钢管注浆快速加固柱结构及施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106337570A CN106337570A (zh) | 2017-01-18 |
CN106337570B true CN106337570B (zh) | 2019-04-26 |
Family
ID=57841938
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611007496.0A Active CN106337570B (zh) | 2016-11-16 | 2016-11-16 | 钢管注浆快速加固柱结构及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106337570B (zh) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106906953B (zh) * | 2017-04-24 | 2019-04-02 | 山东科技大学 | 一种可预先施加围压的混凝土柱及其制作方法、加固方法 |
CN107810778A (zh) * | 2017-10-31 | 2018-03-20 | 绍兴文理学院元培学院 | 一种可调节的树木支架 |
CN107989392A (zh) * | 2017-11-27 | 2018-05-04 | 山东电力工业锅炉压力容器检验中心有限公司 | 一种输变电钢筋水泥杆破损损伤加固方法 |
CN108181178B (zh) * | 2017-12-18 | 2020-02-21 | 山东科技大学 | 破碎围岩预应力锚注加固模拟试验装置及试验方法 |
CN108412518B (zh) * | 2018-05-11 | 2024-03-29 | 沈阳建筑大学 | 一种具有定向定层注浆功能的双套筒钻杆及其施工方法 |
CN108798063B (zh) * | 2018-08-28 | 2023-06-30 | 国网山东省电力公司电力科学研究院 | 一种钢筋混凝土电杆钢板圈损伤加固装置及加固方法 |
CN109212030B (zh) * | 2018-10-12 | 2021-01-19 | 华北水利水电大学 | 一种钢管混凝土柱密实度精准检测装置 |
CN112081407A (zh) * | 2020-09-22 | 2020-12-15 | 中国建筑第四工程局有限公司 | 一种加固钢筋混凝土框架柱的装置及施工方法 |
CN114482596B (zh) * | 2021-12-25 | 2023-05-16 | 韶关市中群建设有限公司 | 老城区旧楼翻新改造技术方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101463653A (zh) * | 2008-12-30 | 2009-06-24 | 上海勘测设计研究院 | 一种加固混凝土杆件的方法 |
CN201535065U (zh) * | 2009-08-31 | 2010-07-28 | 中建三局第三建设工程有限责任公司 | 一种现浇混凝土柱用外圆轻质木块模板体系 |
US20130014468A1 (en) * | 2011-07-14 | 2013-01-17 | Ehsani Mohammad R | Restoration methods for structural components |
JP2013253467A (ja) * | 2012-05-09 | 2013-12-19 | Chika Hishida | 中空パイプ補強シート及び中空パイプ補強工法 |
CN203808504U (zh) * | 2014-03-28 | 2014-09-03 | 中国建筑第六工程局有限公司 | 一种自制圆柱形模板加固装置 |
CN105484514A (zh) * | 2015-12-16 | 2016-04-13 | 桂林理工大学 | 一种加固钢筋混凝土圆形墩柱的方法 |
CN206158226U (zh) * | 2016-11-16 | 2017-05-10 | 沈阳建筑大学 | 钢管注浆快速加固柱结构 |
-
2016
- 2016-11-16 CN CN201611007496.0A patent/CN106337570B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101463653A (zh) * | 2008-12-30 | 2009-06-24 | 上海勘测设计研究院 | 一种加固混凝土杆件的方法 |
CN201535065U (zh) * | 2009-08-31 | 2010-07-28 | 中建三局第三建设工程有限责任公司 | 一种现浇混凝土柱用外圆轻质木块模板体系 |
US20130014468A1 (en) * | 2011-07-14 | 2013-01-17 | Ehsani Mohammad R | Restoration methods for structural components |
JP2013253467A (ja) * | 2012-05-09 | 2013-12-19 | Chika Hishida | 中空パイプ補強シート及び中空パイプ補強工法 |
CN203808504U (zh) * | 2014-03-28 | 2014-09-03 | 中国建筑第六工程局有限公司 | 一种自制圆柱形模板加固装置 |
CN105484514A (zh) * | 2015-12-16 | 2016-04-13 | 桂林理工大学 | 一种加固钢筋混凝土圆形墩柱的方法 |
CN206158226U (zh) * | 2016-11-16 | 2017-05-10 | 沈阳建筑大学 | 钢管注浆快速加固柱结构 |
Also Published As
Publication number | Publication date |
---|---|
CN106337570A (zh) | 2017-01-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106337570B (zh) | 钢管注浆快速加固柱结构及施工方法 | |
CN104790424B (zh) | 风力发电塔基础环基础的加固系统及其加固方法 | |
CN203514315U (zh) | 一种桩与桩帽间的加强型连接结构 | |
CN104631433B (zh) | 箱形钢板咬合连续墙结构体系的施工工艺 | |
CN205839767U (zh) | 一种深基坑钢管/混凝土复合内支撑结构 | |
CN105201530A (zh) | 用于岩石隧道衬砌大裂缝的修补加固方法 | |
CN103882869A (zh) | 一种用于基坑围护的斜向支撑桩结构及其施工方法 | |
CN203222809U (zh) | 一种输电线路杆塔预应力混凝土管桩基础 | |
CN202202326U (zh) | 一种高强度混凝土预制管桩接桩构造 | |
CN103015414A (zh) | 一种预制混凝土后注浆桩及注浆工艺 | |
CN104762967B (zh) | 一种改进的锚杆静压桩的封桩装置及施工方法 | |
CN209838429U (zh) | 一种后锚盾构衬砌支护结构 | |
CN206158226U (zh) | 钢管注浆快速加固柱结构 | |
CN201050062Y (zh) | 砂层土加固件 | |
CN104060606B (zh) | 一种组合拼接管桩及其接桩方法 | |
CN110144894A (zh) | 一种桩端注浆微型钢管静压桩 | |
CN202139587U (zh) | 封闭式锥形端头钢管桩 | |
CN204510215U (zh) | 用于基坑施工的钢平台 | |
CN207331709U (zh) | 深厚填土边坡的网状支挡结构 | |
CN103498573B (zh) | 增设带边框钢支撑的既有框架加固方法 | |
CN202881986U (zh) | 单桩竖向静载试验桩头钢筋连接节点 | |
CN102518129A (zh) | 后压浆预应力空心方桩及制作方法 | |
CN204780892U (zh) | 一种高强度的管桩裂缝补强结构 | |
CN202989911U (zh) | 一种预制混凝土后注浆桩 | |
CN212270943U (zh) | 一种预制拼装式钢砼组合支撑桩 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Li Ming Inventor after: Zhou Zhijun Inventor after: Gao Jian Inventor after: He Xiaoxiang Inventor before: Li Ming Inventor before: Gao Jian Inventor before: He Xiaoxiang |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20231015 Address after: 315016 Chehe Village, Shiqi Street, Haishu District, Ningbo City, Zhejiang Province Patentee after: Zhejiang Shutao Construction Co.,Ltd. Address before: 110168 Liaoning province Shenyang Hunnan Hunnan Road No. 9 Patentee before: SHENYANG JIANZHU University |