CN106297528A CN201610944081.XA CN201610944081A CN106297528A CN 106297528 A CN106297528 A CN 106297528A CN 201610944081 A CN201610944081 A CN 201610944081A CN 106297528 A CN106297528 A CN 106297528A
Authority
CN
China
Prior art keywords
lane
training
room
fully
return air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610944081.XA
Other languages
Chinese (zh)
Inventor
王慎谦
彭飞
王勇
陈善文
江孟夏
张�杰
邸泽民
丰国红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaibei Industrial Building Design Institute Co Ltd
Original Assignee
Huaibei Industrial Building Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Industrial Building Design Institute Co Ltd filed Critical Huaibei Industrial Building Design Institute Co Ltd
Priority to CN201610944081.XA priority Critical patent/CN106297528A/en
Publication of CN106297528A publication Critical patent/CN106297528A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B25/00Models for purposes not provided for in G09B23/00, e.g. full-sized devices for demonstration purposes
    • G09B25/02Models for purposes not provided for in G09B23/00, e.g. full-sized devices for demonstration purposes of industrial processes; of machinery

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a kind of coal mine production safety real training and warning educational system, including Teaching-building, ground physical agility training field and groundwater simulation mine on the ground;Described groundwater simulation mine includes the big lane of horizontal return air, longitudinal air way, it is positioned at described longitudinal air way side and is parallel to general pick work surface, fully mechanized workface, personnel channel and the auxiliary shaft passage in the described big lane of horizontal return air, being positioned at fully-mechanized mining working, blast mining face and the refuge chamber of described longitudinal air way opposite side;Described fully-mechanized mining working and described blast mining face are parallel to the described big lane of horizontal return air, and described refuge chamber is parallel to described longitudinal air way;Also including being parallel to main channel, described horizontal return air great Xiang Ji lane, one end of main channel, described machine lane is positioned at described longitudinal air way side, and the other end of main channel, described machine lane is positioned at the opposite side of described longitudinal air way.Student carries out underground work without the coal mine bases exploited on the spot, can fully, be fully completed underground work real training.

Description

A kind of coal mine production safety real training and warning educational system
Technical field
The present invention relates to a kind of coal production training system technical field, particularly a kind of coal mine production safety real training and police Show educational system.
Background technology
Student teaching is to allow student obtain perceptual knowledge and the technical ability instructional mode as main purpose, is skilled talents Cultivate important step, be to complete teaching task, it is achieved professional colleges training objective comprehensively, formed Characteristics of Running main way Footpath;It is to cultivate to adapt to enterprise demand, makes student have the Main Means of skilled talents of Comprehensive Vocation Ability.Pay much attention to real Training teaching, improves teaching quality conscientiously, cultivates high-quality skilled talents for coal mine production system, builds coal production system System training base is the most necessary;Coal mine production system training base of the prior art, mainly relies on the colliery exploited on the spot Base, or by the coal mine production system of partial simulation, make student's energy sense of reality combining closely to theory and practice, reach Preferably teaching efficiency;Rely on the coal mine bases exploited on the spot to give training, not only can affect student conventional life and Study, and there is certain security risk;And by the coal mine production system of partial simulation, be then difficult to fully, all sidedly Represent the production operation process involved by coal mine production system and all kinds of production status.
Summary of the invention
In order to overcome the deficiencies in the prior art, the invention provides a kind of coal mine production safety real training and warning department of education System, it is possible to real embodiment coal production environment and system, and coal mine production safety real training and warning education can be directly in campuses Inside carrying out, student carries out underground work without the coal mine bases exploited on the spot, can fully, be fully completed underground work Real training.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of coal mine production safety real training and warning educational system, including Teaching-building on the ground, ground physical agility training field and Groundwater simulation mine;Described groundwater simulation mine includes the big lane of horizontal return air and is perpendicular to the Longitudinal Wind in the described big lane of horizontal return air Lane;Described groundwater simulation mine also includes being positioned at described longitudinal air way side and being parallel to the general pick work in the described big lane of horizontal return air Make face, fully mechanized workface, personnel channel and auxiliary shaft passage;Described groundwater simulation mine also include being positioned at described longitudinal air way another The fully-mechanized mining working of side, blast mining face and refuge chamber, described fully-mechanized mining working and described blast mining face are parallel to described The laterally big lane of return air, described refuge chamber is parallel to described longitudinal air way;Described groundwater simulation mine also includes being parallel to described Laterally main channel, return air great Xiang Ji lane, one end of main channel, described machine lane is positioned at described longitudinal air way side, described machine lane master The other end of passage is positioned at the opposite side of described longitudinal air way;The described big lane of horizontal return air, described general pick work surface, described comprehensive pick Work surface, described personnel channel and described auxiliary shaft passage are respectively positioned on below the Teaching-building of described ground, described longitudinal air way, described Fully-mechanized mining working, described blast mining face, described refuge chamber and main channel, described machine lane are positioned at described longitudinal air way opposite side Part be respectively positioned on below the physical agility training field of described ground.
As the further improvement of technique scheme, described general pick work surface and described fully mechanized workface are positioned at described horizontal stroke To the side in the big lane of return air, described personnel channel and described auxiliary shaft passage are positioned at the opposite side in the described big lane of horizontal return air, and institute State fully mechanized workface between the described big lane of horizontal return air and described general pick work surface, described personnel channel be positioned at described laterally Between the big lane of return air and described auxiliary shaft passage;The described longitudinal air way of one end connection in the described big lane of horizontal return air, described horizontal time The other end connection ventilation well head in Feng great lane;One end of described general pick work surface connects described longitudinal air way, described general pick work The other end in face connects described fully mechanized workface by the first connection roadway;One end of described fully mechanized workface connects described Longitudinal Wind Lane, the other end of described fully mechanized workface connects the described big lane of horizontal return air by the second connection roadway;The one of described personnel channel End connects described longitudinal air way, and the other end of described personnel channel connects the first hoistway stair;One end of described auxiliary shaft passage is even Logical described longitudinal air way, the other end connection auxiliary well head room of described auxiliary shaft passage.
As the further improvement of technique scheme, described blast mining face is positioned at described fully-mechanized mining working and described machine Between main channel, lane;Described blast mining face one end connects described longitudinal air way, and the described blast mining face other end passes through first Connection main channel, described machine lane, branch road machine lane;Described fully-mechanized mining working one end connects described longitudinal air way, described fully-mechanized mining working The other end is by the second connection main channel, described machine lane, branch road machine lane;Described refuge chamber is positioned at described longitudinal air way and described Between one branch road machine lane, and the connection main channel, described machine lane, one end of described refuge chamber, the other end of described refuge chamber is even Logical described longitudinal air way.
As the further improvement of technique scheme, main channel, described machine lane is towards one end of described ground Teaching-building Tilting connection ground, porch on the ground, main channel, described machine lane is provided with winch, and main channel, described machine lane is additionally provided with Signal chamber.
As the further improvement of technique scheme, described ground Teaching-building is four-layer structure, and middle part is provided with Interior courtyard.
Compared with prior art, the invention has the beneficial effects as follows:
A kind of coal mine production safety real training provided by the present invention and warning educational system, be collection safety of coal mines practice Teaching, the practical operation of down-hole simulation tunnel and security warning education integration scheme, be directed not only to routine building, structure, to Draining, electrically and multiple technical fields such as air conditioner ventilation, also introduces the technological incorporation in the fields such as mining, machine choosing, mine electromechanics Wherein, it is possible to real embodiment coal production environment and system, by the coal mine production system of simulation, student is made sense of reality to arrive Combining closely of theory and practice, reaches preferable teaching efficiency.
One aspect of the present invention decreases student and practises security risk, and student can practise in campus on the spot;On the other hand solve Determine problems in teaching of integrating theory with practice, deepened the degree of understanding of student.
Accompanying drawing explanation
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
Fig. 1 is a kind of coal mine production safety real training of the present invention and the structural representation of warning educational system;
Fig. 2 is the structural representation of groundwater simulation mine of the present invention;
Fig. 3 is the ground floor structural representation of ground of the present invention Teaching-building;
Fig. 4 is the second layer structural representation of ground of the present invention Teaching-building;
Fig. 5 is the third layer structural representation of ground of the present invention Teaching-building;
Fig. 6 is the four-layer structure schematic diagram of ground of the present invention Teaching-building.
Detailed description of the invention
It is the structural representation of one specific embodiment of the present invention referring to figs. 1 through Fig. 6, Fig. 1 to Fig. 6.
As shown in Figures 1 to 6, a kind of coal mine production safety real training and warning educational system, including Teaching-building on the ground 100, ground physical agility training field 200 and groundwater simulation mine 300;Described groundwater simulation mine 300 includes the big lane of horizontal return air 310 With the longitudinal air way 320 being perpendicular to the described big lane of horizontal return air 310;Described groundwater simulation mine 300 also includes being positioned at described indulging To air way 320 side and be parallel to the general pick work surface 330 in the described big lane of horizontal return air 310, fully mechanized workface 340, Ren Yuantong Road 350 and auxiliary shaft passage 360;Described groundwater simulation mine 300 also includes that being positioned at described the comprehensive of longitudinal air way 320 opposite side adopts work Making face 370, blast mining face 380 and refuge chamber 390, described fully-mechanized mining working 370 and described blast mining face 380 are parallel to The described big lane of horizontal return air 310, described refuge chamber 390 is parallel to described longitudinal air way 320;Described groundwater simulation mine 300 Also including being parallel to main channel, described horizontal return air big Xiang310Ji lane 301, one end of main channel, described machine lane 301 is positioned at institute Stating longitudinal air way 320 side, the other end of main channel, described machine lane 301 is positioned at the opposite side of described longitudinal air way 320;Described horizontal stroke To the big lane of return air 310, described general pick work surface 330, described fully mechanized workface 340, described personnel channel 350 and described auxiliary shaft lead to Road 360 is respectively positioned on below described ground Teaching-building 100, and described longitudinal air way 320, described fully-mechanized mining working 370, described big gun are adopted The part that work surface 380, described refuge chamber 390 and main channel, described machine lane 301 are positioned at described longitudinal air way 320 opposite side is equal It is positioned at below described ground physical agility training field 200.
Specifically, described general pick work surface 330 and described fully mechanized workface 340 are positioned at the described big lane of horizontal return air 310 Side, described personnel channel 350 and described auxiliary shaft passage 360 are positioned at the opposite side in the described big lane of horizontal return air 310, and described comprehensive Pick work surface 340 is between the described big lane of horizontal return air 310 and described general pick work surface 330, and described personnel channel 350 is positioned at Between the described big lane of horizontal return air 310 and described auxiliary shaft passage 360;One end connection in the described big lane of horizontal return air 310 is described vertical To air way 320, the other end connection ventilation well head 311 in the described big lane of horizontal return air 310;One end of described general pick work surface 330 Connecting described longitudinal air way 320, the other end of described general pick work surface 330 connects described comprehensive pick work by the first connection roadway 331 Make face 340;One end of described fully mechanized workface 340 connects described longitudinal air way 320, the other end of described fully mechanized workface 340 The described big lane of horizontal return air 310 is connected by the second connection roadway 341;One end of described personnel channel 350 connects described Longitudinal Wind Lane 320, the other end of described personnel channel 350 connects the first hoistway stair 351;One end connection institute of described auxiliary shaft passage 360 State longitudinal air way 320, the other end connection auxiliary well head room 361 of described auxiliary shaft passage 360.The described big lane of horizontal return air 310 is used The second hoistway stair 312 are also connected in the one end connecting described ventilation well head 311;Described fully mechanized workface 340 is additionally provided with work Between tool 342, described Tool Room 342 connects the 3rd hoistway stair 343;Described personnel channel 350 is additionally provided with absorbing well, absorption well 352, pump Room 353 and electric substation 354;It is provided with shaft bottom ingate 362 between described auxiliary shaft passage 360 and described auxiliary well head room 361;Institute Stating auxiliary shaft passage 360 and connect described personnel channel 350 by the 3rd connection roadway 363, described auxiliary shaft passage 360 is by the 4th contact Lane 364 connects main channel, described machine lane 301.Described blast mining face 380 is positioned at described fully-mechanized mining working 370 and described machine lane master Between passage 301;Described blast mining face 380 one end connects described longitudinal air way 320, described blast mining face 380 other end Main channel, described machine lane 301 is connected by the first branch road machine lane 381;Described fully-mechanized mining working 370 one end connects described Longitudinal Wind Lane 320, described fully-mechanized mining working 370 other end connects main channel, described machine lane 301 by the second branch road machine lane 371;Described keep away Difficult chamber 390 is between described longitudinal air way 320 and described first branch road machine lane 381, and one end of described refuge chamber 390 Connecting main channel, described machine lane 301, the other end of described refuge chamber 390 connects described longitudinal air way 320.Described refuge chamber It is additionally provided with air compressor machine chamber 391 in 390, is provided with between described first branch road machine lane 381 and described second branch road machine lane 371 Hydraulic power unit chamber 372 and movable gas pumping station 373, described first branch road machine lane 381 and described second branch road machine lane 371 On be provided with some drill sites 382.Main channel, described machine lane 301 tilts communicatively towards one end of described ground Teaching-building 100 Face, porch on the ground, main channel, described machine lane 301 is provided with winch 303, and main channel, described machine lane 301 is additionally provided with letter Number chamber 302.
Specifically, described ground Teaching-building 100 is four-layer structure, and middle part is provided with interior courtyard;Teach in described ground Learn the ground floor of building 100 to be provided with combine and adopt fully-mechanized digging machine electricity jumbo dismounting Training Room 111, numerical control and intermetallic composite coating real training Workshop 112 and mining conveying real training workshop 113.In the second layer of described ground Teaching-building 100, it is provided with mining feed open Close Training Room 121, mine lighting and signal Training Room 122, mining power supply unit Training Room 123, winch Training Room 124, hydraulic pressure Pumping plant Training Room 125, Electrical Equipments of Coal Mine dismounting Training Room 126, colliery electrician's basic skill Training Room 127, water pump Training Room 128, mine vacuum magnetic starter Training Room 129, electric traction practical training room, colliery 1210, mine hoisting Training Room 1211 and coal Electric drill integrated protection room 1212.Mine maintenance fitter's real training workshop it is provided with in the third layer of described ground Teaching-building 100 131, coal separation laboratory 132, mine rescue Training Room 133, safety blasting Training Room 134, security monitoring Training Room 135, mine dust Preventing and treating Training Room 136, gas pumping station laboratory 137, gas drainage under suction drill site laboratory 138, gas preventing and control simulation laboratory 139, mining geology Training Room 1310, rock mechanics laboratory 1311, ore deposit pressure Training Room 1312, Gas explosion burns determination experiment room 1313, ventilation safety instrument and meter room 1314, fire extinguishing Training Room 1315, ventilation instrument calibration room 1316 and mine ventilation technology Training Room 1317.4th floor of described ground Teaching-building 100 is provided with security warning room 141, mech-electric experiment room 142, Safety of coal mines model room 143, ventilation laboratory 144, blasting experiment room 145, gas explosion laboratory 146, emergency care of trauma experiment Room 147, coal mining laboratory 148, driving laboratory 149 and Lifting Convey laboratory 1410.
Above-mentioned coal mine production safety real training and warning educational system comprehensive simulating training field, general work post training base, coal Special work post practical operation base, ore deposit, security warning educational base, fitness training field, in one, provide the reality of abundance for student's study Practise place and required equipment, adapt to the needs of coal mine professional real training completely, the operating ability of student can be improved comprehensively so that it is Becoming collection teaching, real training, verification of professional technical ability and serve the multifunctional large-scale training base of one, student passes through in base to learn Habit is fully able to skillfully grasp machine maintenance, operation, or even the various technical ability that whole colliery is run, and institute completely can be classroom Move into training base, to improve enterprise security training quality and pre-internship time level, it is also possible to in-depth reform in education and teaching is carried out Integration, Separate Levels Teaching, the cultivation for high technical ability talents provides solid teaching hardwares guarantee.
Additionally, above-mentioned coal mine production safety real training and warning educational system also provide good training for the on-job worker in colliery Instruction and again place of education;The wherein preventing and treating of mine disaster, the analysis of multiple accident, further to colliery of worker can be deepened Solve and understanding, play a good role to reducing security incident.
Preferably enforcement to the present invention is illustrated above, and certainly, the present invention can also use and above-mentioned enforcement The form that mode is different, those of ordinary skill in the art are in the conversion of the equivalent made on the premise of spirit of the present invention Or change accordingly, all should belong in protection scope of the present invention.

Claims (10)

1. a coal mine production safety real training and warning educational system, it is characterised in that: include Teaching-building, ground physical ability on the ground Training place and groundwater simulation mine;Described groundwater simulation mine includes the big lane of horizontal return air and is perpendicular to the described big lane of horizontal return air Longitudinal air way;Described groundwater simulation mine also includes being positioned at described longitudinal air way side and being parallel to the described big lane of horizontal return air General pick work surface, fully mechanized workface, personnel channel and auxiliary shaft passage;Described groundwater simulation mine also includes being positioned at described longitudinal direction The fully-mechanized mining working of air way opposite side, blast mining face and refuge chamber, described fully-mechanized mining working and described blast mining face are flat Row is in the described big lane of horizontal return air, and described refuge chamber is parallel to described longitudinal air way;Described groundwater simulation mine also includes putting down Row is in main channel, described horizontal return air great Xiang Ji lane, and one end of main channel, described machine lane is positioned at described longitudinal air way side, institute The other end of main channel, Shu Ji lane is positioned at the opposite side of described longitudinal air way;The described big lane of horizontal return air, described general pick work surface, Described fully mechanized workface, described personnel channel and described auxiliary shaft passage are respectively positioned on below the Teaching-building of described ground, described longitudinal direction Air way, described fully-mechanized mining working, described blast mining face, described refuge chamber and main channel, described machine lane are positioned at described Longitudinal Wind The part of lane opposite side is respectively positioned on below the physical agility training field of described ground.
A kind of coal mine production safety real training the most according to claim 1 and warning educational system, it is characterised in that: described general Pick work surface and described fully mechanized workface are positioned at the side in the described big lane of horizontal return air, described personnel channel and described auxiliary shaft passage It is positioned at the opposite side in the described big lane of horizontal return air, and described fully mechanized workface is positioned at the described big lane of horizontal return air and described general pick work Making between face, described personnel channel is between the described big lane of horizontal return air and described auxiliary shaft passage;The described big lane of horizontal return air One end connect described longitudinal air way, the described big lane of horizontal return air the other end connection ventilation well head;Described general pick work surface One end connects described longitudinal air way, and the other end of described general pick work surface connects described fully mechanized workface by the first connection roadway; One end of described fully mechanized workface connects described longitudinal air way, and the other end of described fully mechanized workface is connected by the second connection roadway The described big lane of horizontal return air;One end of described personnel channel connects described longitudinal air way, the other end connection of described personnel channel First hoistway stair;One end of described auxiliary shaft passage connects described longitudinal air way, the other end connection auxiliary shaft of described auxiliary shaft passage Heapstead.
A kind of coal mine production safety real training the most according to claim 2 and warning educational system, it is characterised in that: described horizontal stroke The one end being used for connecting described ventilation well head to the big lane of return air also connects the second hoistway stair;Described fully mechanized workface is additionally provided with Tool Room, described Tool Room connection the 3rd hoistway stair;Described personnel channel is additionally provided with absorbing well, absorption well, pump house and electric substation;Institute State and be provided with shaft bottom ingate between auxiliary shaft passage and described auxiliary well head room;Described auxiliary shaft passage is connected by the 3rd connection roadway Described personnel channel, described auxiliary shaft passage is by the 4th connection roadway connection main channel, described machine lane.
A kind of coal mine production safety real training the most according to claim 1 and warning educational system, it is characterised in that: described big gun Mining face is between described fully-mechanized mining working and main channel, described machine lane;Described blast mining face one end connects described longitudinal direction Air way, the described blast mining face other end is by the first connection main channel, described machine lane, branch road machine lane;Described fully-mechanized mining working one End connects described longitudinal air way, and the described fully-mechanized mining working other end is by the second connection main channel, described machine lane, branch road machine lane;Institute State refuge chamber between described longitudinal air way and described first branch road machine lane, and one end connection of described refuge chamber is described Main channel, machine lane, the other end of described refuge chamber connects described longitudinal air way.
A kind of coal mine production safety real training the most according to claim 4 and warning educational system, it is characterised in that keep away described in: Difficult chamber is additionally provided with air compressor machine chamber, between described first branch road machine lane and described second branch road machine lane, is provided with hydraulic pump Stand and be provided with some drill sites on chamber and movable gas pumping station, described first branch road machine lane and described second branch road machine lane.
A kind of coal mine production safety real training the most according to claim 1 and warning educational system, it is characterised in that: described machine Main channel, lane tilts connection ground, porch on the ground, main channel, described machine lane towards one end of described ground Teaching-building Being provided with winch, main channel, described machine lane is additionally provided with signal chamber.
A kind of coal mine production safety real training the most according to claim 1 and warning educational system, it is characterised in that: describedly Upper Teaching-building is four-layer structure, and middle part is provided with interior courtyard;The ground floor of described ground Teaching-building is provided with comprehensive Adopt fully-mechanized digging machine electricity jumbo dismounting Training Room, numerical control and intermetallic composite coating real training workshop and mining conveying real training workshop.
A kind of coal mine production safety real training the most according to claim 7 and warning educational system, it is characterised in that: described The second layer of Teaching-building is provided with mining feed switch Training Room, mine lighting and signal Training Room, mining power supply on the ground Equipment Training Room, winch Training Room, hydraulic power unit Training Room, Electrical Equipments of Coal Mine dismounting Training Room, colliery electrician's basic skill Training Room, water pump Training Room, mine vacuum magnetic starter Training Room, electric traction practical training room, colliery, mine hoisting Training Room With electric coal drill integrated protection room.
A kind of coal mine production safety real training the most according to claim 7 and warning educational system, it is characterised in that: described The third layer of Teaching-building is provided with mine maintenance fitter's real training workshop, coal separation laboratory, mine rescue Training Room, peace on the ground Full explosion Training Room, security monitoring Training Room, mine dust preventing and treating Training Room, gas pumping station laboratory, gas drainage under suction drill site are real Test room, gas preventing and control simulation laboratory, mining geology Training Room, rock mechanics laboratory, ore deposit pressure Training Room, Gas explosion burns mensuration Laboratory, ventilation safety instrument and meter room, fire extinguishing Training Room, ventilation instrument calibration room and mine ventilation technology Training Room.
A kind of coal mine production safety real training the most according to claim 7 and warning educational system, it is characterised in that: in institute State and the 4th floor of Teaching-building on the ground is provided with security warning room, mech-electric experiment room, safety of coal mines model room, experiment of ventilating Room, blasting experiment room, gas explosion laboratory, emergency care of trauma laboratory, coal mining laboratory, driving laboratory and Lifting Convey are real Test room.
CN201610944081.XA 2016-10-26 2016-10-26 A kind of coal mine production safety real training and warning educational system Pending CN106297528A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610944081.XA CN106297528A (en) 2016-10-26 2016-10-26 A kind of coal mine production safety real training and warning educational system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610944081.XA CN106297528A (en) 2016-10-26 2016-10-26 A kind of coal mine production safety real training and warning educational system

Publications (1)

Publication Number Publication Date
CN106297528A true CN106297528A (en) 2017-01-04

Family

ID=57720074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610944081.XA Pending CN106297528A (en) 2016-10-26 2016-10-26 A kind of coal mine production safety real training and warning educational system

Country Status (1)

Country Link
CN (1) CN106297528A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109448484A (en) * 2018-11-10 2019-03-08 山西能源学院 A kind of experiment and tutoring system for simulating down-hole coal excavation tunnel fully mechanized mining overall process

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102146804A (en) * 2011-01-30 2011-08-10 江西省煤炭工业科学研究所 Coal mine underground refuge chamber with double safeguard function
CN203347800U (en) * 2013-05-24 2013-12-18 煤炭工业济南设计研究院有限公司 Underground coal mine temporary refuge chamber arrangement structure
CN204738831U (en) * 2015-06-17 2015-11-04 中国矿业大学银川学院 Mine simulation air pipeline test equipment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102146804A (en) * 2011-01-30 2011-08-10 江西省煤炭工业科学研究所 Coal mine underground refuge chamber with double safeguard function
CN203347800U (en) * 2013-05-24 2013-12-18 煤炭工业济南设计研究院有限公司 Underground coal mine temporary refuge chamber arrangement structure
CN204738831U (en) * 2015-06-17 2015-11-04 中国矿业大学银川学院 Mine simulation air pipeline test equipment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张云星: "煤炭高职院校建设校内模拟矿井的实践与探讨", 《职业教育研究》 *
王秀民 等: "《井巷工程定额与预算》", 30 June 2014, 机械工业出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109448484A (en) * 2018-11-10 2019-03-08 山西能源学院 A kind of experiment and tutoring system for simulating down-hole coal excavation tunnel fully mechanized mining overall process
CN109448484B (en) * 2018-11-10 2024-04-26 山西能源学院 Experiment and teaching system for simulating comprehensive mining whole process of underground coal mining roadway

Similar Documents

Publication Publication Date Title
CN205259940U (en) Four arms top anchor rod drilling carriage
CN102425442B (en) Variable-frequency regulation ventilation system and method for coal mining area
CN205259938U (en) Anchor rod drilling carriage of four arms group
CN109448487B (en) Coal mine gas explosion disaster virtual emergency drilling method and system
CN203745218U (en) Simulation excavation apparatus of tunnel pipe roof construction method
CN109448484B (en) Experiment and teaching system for simulating comprehensive mining whole process of underground coal mining roadway
CN107146515A (en) A kind of mine production system comprehensive demonstration simulation model
CN105427732B (en) A kind of physical model for being used to demonstrate sublevel caving method without sill pillar
CN1821548A (en) Mine natural disaster simulating system
CN106297528A (en) A kind of coal mine production safety real training and warning educational system
CN207526524U (en) A kind of mining rescue robot
CN206249771U (en) A kind of multifunction teaching mine
CN207037966U (en) Development machine practical operation system is used in one kind teaching
CN104196446A (en) Six-arm full hydraulic anchor rod and anchor cable drill carriage used in cooperation with continuous miner
CN201344033Y (en) Remote console of tunneling machine
CN103879892B (en) A kind of laser orientation system being applicable to tower crane and carrying on construction work at night
CN203288151U (en) Small practical oil drilling teaching drilling rig
CN203374282U (en) Head sheave chamber arrangement structure of mine underground grounded multi-rope lifting system
CN206946740U (en) A kind of VR helmets are shown, the drill jumbo analog machine of free degree platform
CN206092003U (en) Production real standard in colliery is with simulation underworkings structure
CN101819726A (en) Mobile intelligent type driver pile test device capable of flexibly assembling multiple garage types
CN209447353U (en) A kind of experiment and tutoring system for simulating down-hole coal excavation tunnel fully mechanized mining overall process
CN102787803A (en) Full-hydraulic multi-functional strip mine drilling machine
CN110985129B (en) Coal and gas outburst catastrophe identification method for coal mining working face
CN204060790U (en) Coal and gas prominent monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104