CN106245921B - Installation and construction method of concrete hollow partition board - Google Patents

Installation and construction method of concrete hollow partition board Download PDF

Info

Publication number
CN106245921B
CN106245921B CN201610604372.4A CN201610604372A CN106245921B CN 106245921 B CN106245921 B CN 106245921B CN 201610604372 A CN201610604372 A CN 201610604372A CN 106245921 B CN106245921 B CN 106245921B
Authority
CN
China
Prior art keywords
partition plate
installation
concrete hollow
construction method
cement mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610604372.4A
Other languages
Chinese (zh)
Other versions
CN106245921A (en
Inventor
余德浩
马文浩
马志
杨志
贾素辉
陈伟明
陈凡
陈枭靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201610604372.4A priority Critical patent/CN106245921B/en
Publication of CN106245921A publication Critical patent/CN106245921A/en
Application granted granted Critical
Publication of CN106245921B publication Critical patent/CN106245921B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention belongs to the field of building construction, in particular to a construction method for installing a concrete hollow partition plate; the method comprises the following steps: the method comprises the following steps of (1) positioning a partition plate, installing and adjusting a bottom partition plate, and installing and adjusting an upper partition plate, wherein the upper partition plate is hoisted by adopting an electric hoist, the electric hoist is installed on the ground, a sling of the electric hoist sags around a structural beam, the structural beam is provided with a support clamped with the structural beam and a plastic roller installed on the support and used for supporting the sling, and the plastic roller is perpendicular to a plane formed by the slings; by adopting the installation and construction method of the concrete hollow partition board in the technical scheme of the invention, the frequent manual carrying and adjustment are avoided, and the operation is simple, convenient and safe.

Description

A kind of concrete hollow partition plate construction method of installation
Technical field
The invention belongs to the realm of building construction, specifically a kind of concrete hollow partition plate construction method of installation.
Background technique
Current China just vigorously promotes the use environmental protection and energy-saving building, is directed to the energy conservation of wall, concrete hollow partition plate Just gradually substitute traditional masonry, it is excellent that concrete hollow partition plate has under antidetonation sound insulation, land occupation, intensity is good, construction is convenient etc. Point.But in certain steel structure frame buildings, the usual volume of concrete hollow partition plate is very big, so that weight is still heavier, removes Fortune and installation are not directed to the side of concrete hollow partition plate installation there are biggish difficulty in traditional architecture construction method Method, therefore be badly in need of wanting a kind of simple, convenient and safe concrete hollow partition plate construction method of installation.
Summary of the invention
The purpose of the present invention is to provide a kind of simple, convenient and safe concrete hollow partition plate installations Method.
To achieve the goals above, the present invention provides a kind of concrete hollow partition plate construction method of installation, include with Lower step:
A. partition plate is in place,
Unwrapping wire, and partition plate is transported to construction site;
According to design specification, partition plate is cut;
Cement mortar is placed on building foundation, need to partition plate to be mounted be placed on building foundation;
Cement mortar is smeared on the side of partition plate;
B. the installation and adjustment of bottom partition plate,
The partition plate for preparing installation is transported to dress and spells position, and is assembled;
Voussoir is squeezed into partition plate bottom gap, keeps it vertical smooth;
Correct simultaneously stationary partition plate;
C. the installation and adjustment of upper layer partition plate,
Partition plate is sling and is placed to upper layer, splice partition plate and keeps close connection;
N shape steel card is set on partition plate top, the top of n shape steel card is fixed with structural beams;
The flatness of verticality and adjacent partition plate plate face is adjusted by design requirement;
Grouting mends slurry, the entire wall after correction is filled and struck off with cement mortar.
Further, in step A when unwrapping wire, plate thickness two-wire is popped up up and down respectively in the axis of installation partition plate.
Further, partition plate is corrected with crowbar in step B and is prized tightly, squeeze out cement mortar to full from seam.
Further, the voussoir in step B is timber wedge.
Preferably, the partition plate edge is provided with tenon and tongue-and-groove, and the tongue-and-groove first smears water during installation Cement mortar can guarantee the integral strength of partition plate after connection in this way.
Preferably, the vertical piece width of the partition plate is not more than 8mm, to guarantee the cooperation of tenon and tongue-and-groove.
Preferably, the lifting of the partition plate uses electric hoist, and the electric hoist is mounted on ground, electric hoist Hoist cable bypasses structure beam sagging, and the support being clamped with it is provided in the structural beams and installation on the support carries out hoist cable The plastic roller of support, the plane that the plastic roller is formed perpendicular to hoist cable, the plane that the plastic roller is formed perpendicular to hoist cable, this Sample is arranged on the length direction of wall, can be to avoid the frequent installation position for changing electric hoist, while electric hoist will not Occupy the installation space of partition plate.
Hoisting process is had a characteristic that using the concrete hollow partition plate construction method of installation of technical solution of the present invention The position for frequently changing lifting machine is not needed, and lifting machine is not take up the installation space of partition plate, compared to traditional-handwork The mode of lift, it is more efficiently and safe.
Detailed description of the invention
Fig. 1 is the lifting scheme of installation of the embodiment of the present invention.
Wherein, partition plate 1, electric hoist 2, structural beams 3, support 4, plastic roller 5.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments:
The present invention provides a kind of concrete hollow partition plate construction method of installation as shown in Figure 1:, includes following steps:
A. partition plate 1 is in place, and partition plate herein is the concrete hollow partition plate of bulk,
Unwrapping wire pops up plate thickness two-wire in the axis of installation partition plate 1 up and down respectively, while partition plate 1 is transported to construction Scene;
According to design specification, partition plate 1 is cut, cutting is sawed using common hand electric;
Cement mortar is placed on building foundation, need to partition plate 1 to be mounted be placed on building foundation;
Cement mortar is smeared on the side of partition plate 1,1 edge of partition plate is equipped with tenon and tongue-and-groove, and tongue-and-groove is first during installation Cement mortar is smeared, to guarantee the integral strength of partition plate 1 after connecting;
B. the installation and adjustment of bottom partition plate 1,
The partition plate 1 for preparing installation is transported to dress and spells position, and is assembled, is corrected partition plate 1 simultaneously with crowbar when assembled Sled is tight, squeezes out cement mortar to full from seam, the vertical piece width of partition plate 1 is not more than 8mm, herein preferred 6mm, to protect Demonstrate,prove the cooperation of tenon and tongue-and-groove;
Voussoir is squeezed into 1 bottom gap of partition plate, keeps it vertical smooth, and the preferably common timber wedge of voussoir can also be adopted Use blinding;
Correct simultaneously stationary partition plate 1;
C. the installation and adjustment of upper layer partition plate 1,
Partition plate 1 is sling and is placed to upper layer, lifting uses electric hoist 2, and electric hoist 2 is mounted on ground, and electric hoist 2 is hung Rope is sagging around structural beams 3, and structural beams 3 are I-beam, is provided with the support 4 being clamped with it in structural beams 3 and is mounted on branch The plastic roller 5 being supported on seat 4 to hoist cable, support 4 is at U-shaped, and two sides are provided with vertical jagged groove, in order to not Same place is clamped plastic roller 5, adjusts the gradient of plastic roller 5, and it is flat to guarantee that plastic roller 5 is formed perpendicular to hoist cable Face, can be to avoid the frequent installation position for changing electric hoist 2, while electric hoist 2 will not occupy the installation space of partition plate 1, Splice partition plate 1 and keep close connection, piece is likewise not greater than 8mm;
N shape steel card is set on 1 top of partition plate, the top of n shape steel card is fixed with structural beams, preferably with the side being fully welded Formula, the partition plate 1 on every piece of upper layer, carrying out guarantee, there are two n shape steel cards to link, to guarantee bonding strength;
The flatness of verticality and 1 plate face of adjacent partition plate is adjusted by design requirement;
Grouting mends slurry, the entire wall after correction is filled and struck off with cement mortar.
What has been described above is only a preferred embodiment of the present invention, and the common sense such as well known specific structure and characteristic exist in scheme This is not described excessively, it is noted that for those skilled in the art, without departing from the structure of the invention, Several modifications and improvements can also be made, these also should be considered as protection scope of the present invention, these all will not influence the present invention The effect and patent practicability of implementation.

Claims (6)

1. a kind of concrete hollow partition plate construction method of installation, it is characterised in that include following steps:
A. partition plate is in place,
Unwrapping wire, and partition plate is transported to construction site;
According to design specification, partition plate is cut;
Cement mortar is placed on building foundation, need to partition plate to be mounted be placed on building foundation;
Cement mortar is smeared on the side of partition plate;
B. the installation and adjustment of bottom partition plate,
The partition plate for preparing installation is transported to dress and spells position, and is assembled;
Voussoir is squeezed into partition plate bottom gap, keeps it vertical smooth;
Correct simultaneously stationary partition plate;
C. the installation and adjustment of upper layer partition plate,
Partition plate is sling and is placed to upper layer, splice partition plate and keeps close connection;
N shape steel card is set on partition plate top, the top of n shape steel card is fixed with structural beams;
The flatness of verticality and adjacent partition plate plate face is adjusted by design requirement;
Grouting mends slurry, the entire wall after correction is filled and struck off with cement mortar;
The lifting of the partition plate uses electric hoist, and the electric hoist is mounted on ground, and the hoist cable of electric hoist is around under structural beams It hangs down, the support being clamped with it is provided in the structural beams and the plastic roller being supported on the support to hoist cable, institute is installed State the plane that plastic roller is formed perpendicular to hoist cable.
2. concrete hollow partition plate construction method of installation according to claim 1, it is characterised in that: unwrapping wire in step A When, plate thickness two-wire is popped up up and down respectively in the axis of installation partition plate.
3. concrete hollow partition plate construction method of installation according to claim 1, it is characterised in that: use iron in step B Partition plate is corrected and is prized tightly by sled, squeezes out cement mortar to full from seam.
4. concrete hollow partition plate construction method of installation according to claim 1, it is characterised in that: the wedge in step B Block is timber wedge.
5. concrete hollow partition plate construction method of installation according to claim 1, it is characterised in that: the partition wall edges of boards Edge is provided with tenon and tongue-and-groove, and the tongue-and-groove first smears cement mortar during installation.
6. concrete hollow partition plate construction method of installation according to claim 1, it is characterised in that: the partition plate is perpendicular It is not more than 8mm to piece width.
CN201610604372.4A 2016-07-28 2016-07-28 Installation and construction method of concrete hollow partition board Expired - Fee Related CN106245921B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610604372.4A CN106245921B (en) 2016-07-28 2016-07-28 Installation and construction method of concrete hollow partition board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610604372.4A CN106245921B (en) 2016-07-28 2016-07-28 Installation and construction method of concrete hollow partition board

Publications (2)

Publication Number Publication Date
CN106245921A CN106245921A (en) 2016-12-21
CN106245921B true CN106245921B (en) 2019-04-09

Family

ID=57604225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610604372.4A Expired - Fee Related CN106245921B (en) 2016-07-28 2016-07-28 Installation and construction method of concrete hollow partition board

Country Status (1)

Country Link
CN (1) CN106245921B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939052B (en) * 2017-12-07 2020-04-07 贵州微粉纳米技术应用研究院有限责任公司 Installation method of concrete wallboard

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476361A (en) * 2008-12-18 2009-07-08 济南市住宅产业化发展中心 Inner partition plate system and its construction method
US20110179731A1 (en) * 2009-10-27 2011-07-28 Yoichiro Kuroiwa Construction method for wooden house and wall panel
CN102505862A (en) * 2011-11-03 2012-06-20 中山建华墙体材料有限公司 Installing process of lightweight internal partition wallboards
CN102777041A (en) * 2012-07-27 2012-11-14 中山建华墙体材料有限公司 Installation technology of inner separation wall body
CN104153588A (en) * 2014-08-26 2014-11-19 诸城舜昌新型建材有限公司 Installing method for light internal partition wall board

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476361A (en) * 2008-12-18 2009-07-08 济南市住宅产业化发展中心 Inner partition plate system and its construction method
US20110179731A1 (en) * 2009-10-27 2011-07-28 Yoichiro Kuroiwa Construction method for wooden house and wall panel
CN102505862A (en) * 2011-11-03 2012-06-20 中山建华墙体材料有限公司 Installing process of lightweight internal partition wallboards
CN102777041A (en) * 2012-07-27 2012-11-14 中山建华墙体材料有限公司 Installation technology of inner separation wall body
CN104153588A (en) * 2014-08-26 2014-11-19 诸城舜昌新型建材有限公司 Installing method for light internal partition wall board

Also Published As

Publication number Publication date
CN106245921A (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN107673185B (en) Hoisting device and hoisting method for prefabricated assembled concrete external wall panel
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN110562868B (en) Hoisting construction method for unit type glass curtain wall of super high-rise building
CN103911956A (en) Long-span cable stayed bridge steel truss girder mounting method
CN106065681A (en) Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology
CN106245921B (en) Installation and construction method of concrete hollow partition board
CN102505839A (en) Arc-shaped mold plate for casting arc-shaped shear wall of industrial factory building and manufacture method of arc-shaped mold plate
CN104179342A (en) Hanging cage and construction method thereof for mounting profiled steel sheets on steel structural workshop wall surface
CN110512766B (en) Fabricated structure system of steel plate concrete shear wall and construction method thereof
CN216836780U (en) ALC board lifts by crane installation device
CN209353734U (en) For installing the double-track device of curtain wall
CN103982046A (en) Lifting and installation method of buckling restrained braces
CN208415732U (en) Photovoltaic support structure for upright-lockstitching color steel tile roof
CN216865633U (en) Super large glass curtain wall mounting structure
CN205472479U (en) A supplementary transfer device for wallboard
CN104404923A (en) Arch dam bracket template device and construction method based on arch dam bracket template device
CN209797236U (en) Box girder external mold hoisting device
CN209556401U (en) A kind of super high-rise building super large curtain wall unit hydraulic synchronizing lifting system
CN110130601B (en) Integrated decorative heat-insulating assembled enclosure wall plate and mounting method thereof
CN204252082U (en) Arch dam bracket plate device
CN115126254A (en) Construction method of assembled composite floor slab support
CN209397505U (en) One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device
CN209507462U (en) A kind of existing building installation elevator scissors climbing integral hoisting machine
CN217947344U (en) Prefabricated component lifting device
CN207244991U (en) A kind of heavy type stone material lifting paving hoisting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190409