CN106065681A - Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology - Google Patents
Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology Download PDFInfo
- Publication number
- CN106065681A CN106065681A CN201610467328.3A CN201610467328A CN106065681A CN 106065681 A CN106065681 A CN 106065681A CN 201610467328 A CN201610467328 A CN 201610467328A CN 106065681 A CN106065681 A CN 106065681A
- Authority
- CN
- China
- Prior art keywords
- superimposed sheet
- hoard strip
- hoard
- assembled architecture
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/04—Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
Abstract
The invention discloses a kind of building construction technology.Superimposed sheet hoard strip construction method in a kind of based on BIM technology the overall assembled architecture of the present invention, comprises the following steps: levelling, unwrapping wire;Installing independent rack, place joist on independent rack, composition superimposed sheet supports system;Leveling for the first time;Lay adjustable steel beam support means;Lifting superimposed sheet;Leveling for the second time;Stupefied and the film coated plate of quarter bend time is installed;Adjust the stupefied spacing of quarter bend time and holding nut position, make to be in close contact bottom film coated plate and superimposed sheet;Hoard strip concrete pouring construction.In this arrangement and method for construction, adjustable steel beam support means utilizes the independent support system of superimposed sheet as support, it is not necessary to separately sets support, improve efficiency of construction, cost-effective, and do not sink when can guarantee that hoard strip concreting, the technique effect of not spillage.
Description
Technical field
The present invention relates to a kind of building construction technology, particularly in a kind of overall assembled architecture based on BIM technology
Superimposed sheet hoard strip construction method.
Background technology
Along with progress and the development of building trade of science and technology, overall assembled architecture is just widelyd popularize, and laminated floor slab is made
For the main member in overall assembled architecture, having floor construction good integrity, rigidity greatly, does not increase reinforcing bar consumption, saving
The advantages such as template, and superimposed sheet is suitable to industrialized production, it pollutes and waste is significantly less than produced on-site and makes, and meets green and executes
Work and the requirement of green building, and based on BIM technology by the establishment to BUILDINGS MODELS, obtain relative configurations letter more truly
Breath, construction simulation scene so that this method is more preferably realized.
Superimposed sheet is as one of the important component of overall assembled architecture, and usage amount is big;But in relatively large bay, superimposed sheet
Between often use hoard strip to be attached so that how hoard strip supports the problem becoming in the urgent need to address.In order to
Solve the support problem of hoard strip, now invent a kind of adjustable steel beam support means, as depicted in figs. 1 and 2, including underbeam
1 and upper beam 2, described underbeam 1 and upper beam 2 centrage be positioned at same perpendicular, also include connecting upper beam 1 and underbeam 2
Supporting regulation bolt 3, described regulation bolt 3 one end that supports is connected on underbeam 1, and the other end penetrates upper beam 2 and extends upper beam 2 and push up
Face, described upper beam 2 moves up and down along supporting regulation bolt 3;Improve out a kind of adjustable steel beam support system accordingly, at girder steel
On the basis of support means, being erected with a plurality of quarter bend time stupefied 6 on upper beam 2, described quarter bend time stupefied 6 and upper beam 2 are mutually perpendicular to cloth
Putting, described quarter bend time stupefied 6 is provided with the film coated plate 7 for supporting hoard strip, and such adjustable steel beam support system can profit
With the independent rack jacking of superimposed sheet as the support system of hoard strip template, easy construction, quick, safe and reliable and suitable
Strong by property.
Corresponding to this adjustable steel beam support system, the construction of the floor slab back casting band in existing cast-in-place concrete structure is also
Can further optimize design.
Summary of the invention
Present invention aims to the adjustable steel beam support system newly designed, it is provided that a kind of based on BIM technology
Overall assembled architecture in superimposed sheet hoard strip construction method, this construction method use adjustable steel beam support system enter
Row superimposed sheet hoard strip construction, adjustable steel beam support system can utilize the independent support system of superimposed sheet as support,
Without separately setting support, improving efficiency of construction, cost-effective, and do not sink when can guarantee that hoard strip concreting, not spillage.
In order to realize foregoing invention purpose, the invention provides techniques below scheme:
Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology, comprises the following steps:
(1) levelling, unwrapping wire: elevation line is copied and surveys on the vertical member of floor periphery;According to construction drawing location superimposed sheet
Sideline, further according to the nest point of location, superimposed sheet sideline independent rack;
(2) installing independent rack, place joist on independent rack, composition superimposed sheet supports system;
(3) leveling for the first time: joist is carried out leveling;
(4) adjustable steel beam support means is installed: utilize the jacking of independent rack to place adjustable steel beam support means;
(5) lifting superimposed sheet: superimposed sheet is hung on joist;
(6) leveling for the second time: superimposed sheet position is corrected and leveling;
(7) the stupefied and film coated plate of quarter bend time is installed, forms adjustable steel beam support system, i.e. hoard strip and support system;
(8) adjust the stupefied spacing of quarter bend time and holding nut position, make to be in close contact bottom film coated plate and superimposed sheet;
(9) hoard strip concrete pouring construction, the strict ulking thickness controlling concrete in construction.
This construction method utilize adjustable steel beam support means to form the support system of hoard strip, and adjustable steel beam
Support system can utilize the independent rack of superimposed sheet to install and support, it is not necessary to separately sets support, raising efficiency of construction, save into
This;And utilize this adjustable steel beam support system, the position of upper beam can be adjusted and fix so that direct and hoard strip
The film coated plate position of contact is adjustable so that can install by anastrophe when the support installing hoard strip is, is the most first hung by superimposed sheet
After filling in place and leveling, laying adjustable steel beam support means, laying quarter bend time stupefied, finally lay film coated plate, simple to operate
Convenient, efficiency high, supporting & stablizing is reliable, easy accessibility and reusable, will not increase circulation material consumption and hand labor
Amount, the suitability is extremely strong, is beneficial to realize the good quality project of hoard strip.
As preferably, step (2) arranges multiple independent racks in the lower section of superimposed sheet to be installed fixed point, each overlapping
The support system that plate is made up of two row's independent racks supports, and the spacing that described independent rack is arranged along superimposed sheet length direction is
1200-1500mm, the spacing along superimposed sheet lateral arrangement is superimposed sheet width-2 × 200mm.Propping up of the superimposed sheet being arranged so as to
After support body ties up to joist, superimposed sheet stably can be supported, also allow for the follow-up support to hoard strip.
As preferably, described joist is aluminium alloy I-steel joist, and two ends are respectively placed on two independent racks, right
Should be put between the independent rack below superimposed sheet.Described joist is vertical with superimposed sheet length direction, and joist ends and overlapping
The distance of plate end is less than 50mm.
As preferably, step (3) carries out leveling according to elevation line to the joist of independent rack so that joist apical side height
Consistent with superimposed sheet floor height to be installed.
As preferably, the adjustable steel beam support means in step (4) is positioned over the independent rack of hoard strip both sides
In jacking.Adjustable steel beam support means is placed in independent rack, utilizes the independent rack of superimposed sheet to carry out adjustable steel
The installation of beam support means and support so that without separately setting support during hoard strip construction, vacate more construction space, and energy
Improve stock utilization, improve efficiency of construction, cost-effective.
As preferably, step (5) use tower crane or truck crane superimposed sheet is lifted.
Step (6) utilizes the riding position of plumb bob detection superimposed sheet and is corrected and leveling.Use plumb bob detection folded
Plywood installation site is also corrected, and correction end carries out second time leveling.
As preferably, many more than the 100mm of width of the width ratio hoard strip of film coated plate in step (7).By film coated plate
Width arranges bigger than the width of hoard strip, and film coated plate aligns with the centrage of hoard strip, when minimizing pours hoard strip
The phenomenon of spillage, and by twice leveling so that the position of independent rack and superimposed sheet is all in level, then adjustment can
The stupefied spacing of the quarter bend of mode girder steel support means time and holding nut position, make to reach to be in close contact bottom film coated plate and superimposed sheet
State, it is ensured that the smooth construction of hoard strip.
As preferably, carry out before hoard strip pours, having needed the colligation of superimposed sheet upper reinforcement to work, and having completed
Preheating embedding line is constructed, and carries out hoard strip again and pour after concealment acceptance is qualified.
As preferably, hoard strip carries out moisture-keeping maintaining after having poured immediately, and curing time is no less than 7 days.
As preferably, hoard strip maintenance carries out form removal, the support of regulation adjustable steel beam support means bottom after terminating
Nut, makes upper beam decline, and extracts quarter bend time out stupefied, removes adjustable steel beam support means, removes film coated plate.
Compared with prior art, beneficial effects of the present invention:
1, this construction method utilizes adjustable steel beam support means to form the support system of hoard strip, and adjustable steel beam props up
Support system can utilize the independent rack of superimposed sheet to install and support, it is not necessary to separately sets support, raising efficiency of construction, save into
This;And utilize this adjustable steel beam support system, the position of upper beam can be adjusted and fix so that direct and hoard strip
The film coated plate position of contact is adjustable so that can install by anastrophe when the support installing hoard strip is, the most first lays adjustable
Girder steel support means, then it is time stupefied to lay quarter bend, finally lays film coated plate, simple to operation, efficiency is high, and supporting & stablizing is reliable,
Easy accessibility and reusable, will not increase circulation material consumption and manual labor amount, and the suitability is extremely strong, is beneficial to realize cast-in-place
The good quality project of strip;
2, adjustable steel beam support means is placed in independent rack, utilizes the independent rack of superimposed sheet to carry out adjustable steel beam
The installation of support means and support so that without separately setting support during hoard strip construction, vacate more construction space, and can carry
High stock utilization, improve efficiency of construction, cost-effective;
3, being arranged by the width of film coated plate bigger than the width of hoard strip, and film coated plate aligns with the centrage of hoard strip, subtracts
The phenomenon of spillage when pouring hoard strip less, and by twice leveling so that the position of independent rack and superimposed sheet all in
Level, then adjust the stupefied spacing of quarter bend time and the holding nut position of adjustable steel beam support means, make film coated plate and overlapping
The state being in close contact is reached, it is ensured that the smooth construction of hoard strip bottom plate.
Accompanying drawing illustrates:
Fig. 1 is the structural representation of adjustable steel beam support system.
Fig. 2 is the left view of Fig. 1.
Fig. 3 is the schematic diagram of the girder steel support system during hoard strip construction of superimposed sheet of the present invention.
Fig. 4 is the combinative structure schematic diagram of independent rack and joist in Fig. 3.
Fig. 5 is support system schematic diagram during hoard strip construction in embodiment.
Fig. 6 is superimposed sheet hoard strip three-dimensional construction simulation model in overall assembled architecture based on BIM technology.
Labelling in figure: 1-underbeam, 2-upper beam, 3-supports regulation bolt, 4-fore shaft nut, 5-holding nut, 6-quarter bend
Stupefied, 7-film coated plate, 8-independent rack, 9-jacking, 10-aluminium alloy I-steel joist, 11-superimposed sheet.
Detailed description of the invention
Below in conjunction with test example and detailed description of the invention, the present invention is described in further detail.But this should not understood
Scope for the above-mentioned theme of the present invention is only limitted to below example, and all technology realized based on present invention belong to this
The scope of invention.
Embodiment 1
As shown in Figures 1 to 5, superimposed sheet hoard strip construction in based on BIM technology the overall assembled architecture of the present embodiment
Method, utilizes a kind of adjustable steel beam support means and system thereof to carry out the support of hoard strip, and as depicted in figs. 1 and 2, this can
Mode girder steel support means includes that underbeam 1 and upper beam 2, described underbeam 1 and upper beam 2 centrage are positioned at same perpendicular, also
Including the support regulation bolt 3 upper beam 1 and underbeam 2 connected, described regulation bolt 3 one end that supports is connected on underbeam 1, the other end
Penetrate upper beam 2 and extend upper beam 2 end face, corresponding to upper beam 2 end face outside support regulation bolt 3 end be provided with buckling nut
4, for limiting the maximum position moved on upper beam 2, described upper beam 2 moves up and down along supporting regulation bolt 3;And utilize girder steel device
The adjustable steel beam support system drawn, is erected with a plurality of quarter bend time stupefied 6 on upper beam 2, described quarter bend time stupefied 6 and upper beam 2 phase
Being arranged vertically mutually, described quarter bend time stupefied 6 is provided with the film coated plate 7 for supporting hoard strip, utilizes film coated plate to directly support existing
Water strip, and the height of film coated plate is adjusted by the adjustment of the upper beam position of lower end, it is achieved the support to hoard strip;Such
Adjustable steel beam support system may utilize the independent rack support system as hoard strip template of superimposed sheet, its concrete executing
Work step is as follows:
(1) levelling, unwrapping wire: elevation line is copied and surveys on the vertical member of floor periphery;According to construction drawing location superimposed sheet
Sideline, further according to the nest point of location, superimposed sheet sideline independent rack;
(2) installing independent rack 8, place joist on independent rack, composition superimposed sheet supports system;The joist of the present embodiment is aluminum
Alloy I-steel joist 10, the distribution of its two ends is positioned on two independent racks 8, and it is only that correspondence is put in two below superimposed sheet 11
Between staking 8;In the lower section of superimposed sheet to be installed, fixed point arranges multiple independent racks 8, and each superimposed sheet 11 is only by two rows
The support system of staking 8 composition supports, and the spacing that described independent rack 8 is arranged along superimposed sheet 11 length direction is 1500mm,
Spacing along superimposed sheet 11 lateral arrangement is superimposed sheet width-2 × 200mm.The support system of the superimposed sheet being arranged so as to is in peace
After dress joist, superimposed sheet stably can be supported, also allow for the follow-up support to hoard strip;
(3) leveling for the first time: joist is carried out leveling;According to elevation line to the aluminium alloy I-steel joist 10 on independent rack 8
Carry out leveling so that the apical side height of aluminium alloy I-steel joist 10 is consistent with the floor height of superimposed sheet 11 to be installed, and
Holding level;
(4) adjustable steel beam support means is installed: utilize the jacking 9 of independent rack 8 to place adjustable steel beam support means;This can
In the jacking 9 of the independent rack 8 that mode girder steel support means is positioned over hoard strip both sides.Adjustable steel beam support means is put
Put in independent rack, utilize the independent rack of superimposed sheet to carry out installation and the support of adjustable steel beam support means so that be existing
Without separately setting support when watering strip construction, vacate more construction space, and can improve stock utilization, improve efficiency of construction,
Cost-effective;
(5) lifting superimposed sheet: superimposed sheet 11 is hung on aluminium alloy I-steel joist 10;The present embodiment rotates tower crane will overlapping
Plate is lifted on aluminium alloy I-steel joist;
(6) leveling for the second time: the position of superimposed sheet 11 is corrected and leveling;Utilize plumb bob detection superimposed sheet 11 lays position
Put and be corrected and leveling.Using plumb bob detection superimposed sheet installation site and be corrected, correction end carries out second time and adjusts
Flat;
(7) quarter bend time stupefied 6 and film coated plate 7 are installed, form adjustable steel beam support system, i.e. hoard strip support system;This reality
Execute the big 100mm of width of the width ratio hoard strip of the film coated plate 7 of example.The width of film coated plate is arranged the width than hoard strip
Greatly, and film coated plate aligns with the centrage of hoard strip, reduces the phenomenon of spillage when pouring hoard strip, and by twice tune
Flat so that the position of independent rack and superimposed sheet is all in level, then adjusts the quarter bend of adjustable steel beam support means
Stupefied spacing and holding nut position, make the state reaching to be in close contact bottom film coated plate and superimposed sheet, it is ensured that hoard strip suitable
Profit construction;
(8) adjust stupefied 6 spacing of quarter bend time and the position of holding nut 5, make to be in close contact bottom film coated plate 7 and superimposed sheet 11;
(9) hoard strip pouring construction, the strict ulking thickness controlling concrete in construction.
This construction method utilize adjustable steel beam support means to form the support system of hoard strip, and adjustable steel beam
Support system can utilize the independent rack of superimposed sheet to install and support, it is not necessary to separately sets support, raising efficiency of construction, save into
This;And utilize this adjustable steel beam support system, the position of upper beam can be adjusted and fix so that direct and hoard strip
The film coated plate position of contact is adjustable so that can install by anastrophe when the support installing hoard strip is, is the most first hung by superimposed sheet
After filling in place and leveling, laying adjustable steel beam support means, laying quarter bend time stupefied, finally lay film coated plate, simple to operate
Convenient, efficiency high, supporting & stablizing is reliable, easy accessibility and reusable, will not increase circulation material consumption and hand labor
Amount, the suitability is extremely strong, is beneficial to realize the good quality project of hoard strip.
It addition, in the present embodiment, carry out before hoard strip pours, having needed the colligation work of superimposed sheet 11 upper reinforcement
Make, and complete preheating embedding line construction, carry out hoard strip after concealment acceptance is qualified again and pour.
In the present embodiment, hoard strip needs after having poured immediately to carry out moisture-keeping maintaining, and curing time is no less than 7 days.
In the present embodiment, hoard strip maintenance carries out form removal, propping up of regulation adjustable steel beam support means bottom after terminating
Support nut 5, makes upper beam 2 decline, and extracts quarter bend time stupefied 6 out, removes adjustable steel beam support means, removes film coated plate 7.
Embodiment 2
The present embodiment carries out superimposed sheet hoard strip three-dimensional construction simulation in overall assembled architecture based on BIM technology, as Fig. 1-
Shown in Fig. 6, concrete construction procedure is as follows:
(1) levelling, unwrapping wire: elevation line is copied and surveys on the vertical member of floor periphery;According to construction drawing location superimposed sheet
Sideline, further according to the nest point of location, superimposed sheet sideline independent rack;
(2) installing independent rack 8, place joist on independent rack, composition superimposed sheet supports system;The joist of the present embodiment is aluminum
Alloy I-steel joist 10, the distribution of its two ends is positioned on two independent racks 8, and it is only that correspondence is put in two below superimposed sheet 11
Between staking 8;In the lower section of superimposed sheet to be installed, fixed point arranges multiple independent racks 8, and each superimposed sheet 11 is only by two rows
The support system of staking 8 composition supports, and the spacing that described independent rack 8 is arranged along superimposed sheet 11 length direction is 1200mm,
Spacing along superimposed sheet 11 lateral arrangement is superimposed sheet width-2 × 200mm.The support system of the superimposed sheet being arranged so as to is in peace
After dress joist, superimposed sheet stably can be supported, also allow for the follow-up support to hoard strip;Specifically, this independent rack 8 is existing
Some extension type superimposed sheet bracing frames;
(3) leveling for the first time: joist is carried out leveling;According to elevation line to the aluminium alloy I-steel joist 10 on independent rack 8
Carry out leveling so that the apical side height of aluminium alloy I-steel joist 10 is consistent with the floor height of superimposed sheet 11 to be installed, and
Holding level;
(4) adjustable steel beam support means is installed: utilize the jacking 9 of independent rack 8 to place adjustable steel beam support means;This can
In the jacking 9 of the independent rack 8 that mode girder steel support means is positioned over hoard strip both sides.Adjustable steel beam support means is put
Put in independent rack, utilize the independent rack of superimposed sheet to carry out installation and the support of adjustable steel beam support means so that be existing
Without separately setting support when watering strip construction, vacate more construction space, and can improve stock utilization, improve efficiency of construction,
Cost-effective;
(5) lifting superimposed sheet: superimposed sheet 11 is hung on aluminium alloy I-steel joist 10;The present embodiment rotates tower crane will overlapping
Plate is lifted on aluminium alloy I-steel joist;
(6) leveling for the second time: the position of superimposed sheet 11 is corrected and leveling;Utilize plumb bob detection superimposed sheet 11 lays position
Put and be corrected and leveling.Using plumb bob detection superimposed sheet installation site and be corrected, correction end carries out second time and adjusts
Flat;
(7) quarter bend time stupefied 6 and film coated plate 7 are installed, form adjustable steel beam support system, i.e. hoard strip support system;This reality
Execute the big 120mm of width of the width ratio hoard strip of the film coated plate 7 of example.The width of film coated plate is arranged the width than hoard strip
Greatly, and film coated plate aligns with the centrage of hoard strip, reduces the phenomenon of spillage when pouring hoard strip, and by twice tune
Flat so that the position of independent rack and superimposed sheet is all in level, then adjusts the quarter bend of adjustable steel beam support means
Stupefied spacing and holding nut position, make the state reaching to be in close contact bottom film coated plate and superimposed sheet, it is ensured that hoard strip suitable
Profit construction;
(8) adjust stupefied 6 spacing of quarter bend time and the position of holding nut 5, make to be in close contact bottom film coated plate 7 and superimposed sheet 11;
(9) hoard strip pouring construction, the strict ulking thickness controlling concrete in construction.
This construction method utilize adjustable steel beam support means to form the support system of hoard strip, and adjustable steel beam
Support system can utilize the independent rack of superimposed sheet to install and support, it is not necessary to separately sets support, raising efficiency of construction, save into
This;And utilize this adjustable steel beam support system, the position of upper beam can be adjusted and fix so that direct and hoard strip
The film coated plate position of contact is adjustable so that can install by anastrophe when the support installing hoard strip is, is the most first hung by superimposed sheet
After filling in place and leveling, laying adjustable steel beam support means, laying quarter bend time stupefied, finally lay film coated plate, simple to operate
Convenient, efficiency high, supporting & stablizing is reliable, easy accessibility and reusable, will not increase circulation material consumption and hand labor
Amount, the suitability is extremely strong, is beneficial to realize the good quality project of hoard strip.
It addition, in the present embodiment, carry out before hoard strip pours, having needed the colligation work of superimposed sheet 11 upper reinforcement
Make, and complete preheating embedding line construction, carry out hoard strip after concealment acceptance is qualified again and pour.
In the present embodiment, hoard strip needs after having poured immediately to carry out moisture-keeping maintaining, and curing time is no less than 7 days.
In the present embodiment, hoard strip maintenance carries out form removal, propping up of regulation adjustable steel beam support means bottom after terminating
Support nut 5, makes upper beam 2 decline, and extracts quarter bend time stupefied 6 out, removes adjustable steel beam support means, removes film coated plate 7.
All features disclosed in this specification, or disclosed all methods or during step, except mutually exclusive
Feature and/or step beyond, all can combine by any way.
Any feature disclosed in this specification (including any accessory claim, summary and accompanying drawing), unless chatted especially
State, all can be by other equivalences or there is the alternative features of similar purpose replaced.I.e., unless specifically stated otherwise, each feature is only
It it is an example in a series of equivalence or similar characteristics.
Claims (10)
1. superimposed sheet hoard strip construction method in an overall assembled architecture based on BIM technology, it is characterised in that include
Following steps:
(1) levelling, unwrapping wire: elevation line is copied and surveys on the vertical member of floor periphery;According to construction drawing location superimposed sheet
Sideline, further according to the nest point of location, superimposed sheet sideline independent rack;
(2) installing independent rack, place joist on independent rack, composition superimposed sheet supports system;
(3) leveling for the first time: joist is carried out leveling;
(4) adjustable steel beam support means is installed: utilize the jacking of independent rack to place adjustable steel beam support means;
(5) lifting superimposed sheet: superimposed sheet is lifted on joist;
(6) leveling for the second time: superimposed sheet position is corrected and leveling;
(7) the stupefied and film coated plate of quarter bend time is installed, forms adjustable steel beam support system, i.e. hoard strip and support system;
(8) adjust the stupefied spacing of quarter bend time and the position of holding nut, make to be in close contact bottom film coated plate and superimposed sheet;
(9) hoard strip concrete pouring construction, the strict ulking thickness controlling concrete in construction.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that step
Suddenly arranging multiple independent racks in the lower section of superimposed sheet to be installed fixed point in (2), each superimposed sheet is by two row's independent rack groups
The support system become supports, and the spacing that described independent rack is arranged along superimposed sheet length direction is 1200-1500mm, along superimposed sheet
The spacing of lateral arrangement is superimposed sheet width-2 × 200mm.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that institute
Stating joist is aluminium alloy I-steel joist, and its two ends are respectively placed on two independent racks, and correspondence is put in below superimposed sheet
Between adjacent two independent racks.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that step
Suddenly (3) carry out leveling according to elevation line to the joist of independent rack so that at the bottom of joist apical side height and superimposed sheet to be installed
Face is highly consistent.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that step
Suddenly in the jacking of the independent rack that the adjustable steel beam support means in (4) is positioned over hoard strip both sides.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that step
Suddenly (5) use tower crane or truck crane that superimposed sheet is lifted.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 1, it is characterised in that step
Suddenly many more than the 100mm of width of the width ratio hoard strip of film coated plate in (7).
8. according to superimposed sheet hoard strip construction method, its feature in the overall assembled architecture one of claim 1-7 Suo Shu
It is, carries out before hoard strip pours, having needed the colligation of superimposed sheet upper reinforcement to work, and complete preheating embedding line and execute
Work, carries out hoard strip again and pours after concealment acceptance is qualified.
9. according to superimposed sheet hoard strip construction method, its feature in the overall assembled architecture one of claim 1-7 Suo Shu
Being, hoard strip carries out moisture-keeping maintaining after having poured immediately, and curing time is no less than 7 days.
Superimposed sheet hoard strip construction method in overall assembled architecture the most according to claim 9, it is characterised in that
Hoard strip maintenance carries out form removal, the holding nut of regulation adjustable steel beam support means bottom after terminating, make upper beam decline, take out
Go out quarter bend time stupefied, remove adjustable steel beam support means, remove film coated plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610467328.3A CN106065681B (en) | 2016-06-24 | 2016-06-24 | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610467328.3A CN106065681B (en) | 2016-06-24 | 2016-06-24 | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106065681A true CN106065681A (en) | 2016-11-02 |
CN106065681B CN106065681B (en) | 2019-03-22 |
Family
ID=57421133
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610467328.3A Active CN106065681B (en) | 2016-06-24 | 2016-06-24 | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106065681B (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639317A (en) * | 2016-12-23 | 2017-05-10 | 浙江省建工集团有限责任公司 | Prefabricated building complete set constructing technology |
CN107178168A (en) * | 2017-06-16 | 2017-09-19 | 中交航局第工程有限公司 | Cast-in-place surface layer formwork support process |
CN109113192A (en) * | 2018-08-24 | 2019-01-01 | 宁波建工工程集团有限公司 | It is a kind of can bidirectional modulation assembled superimposed sheet seam mortar leakage prevention plugging device |
CN110306707A (en) * | 2019-06-20 | 2019-10-08 | 四川省劲腾环保建材有限公司 | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method |
CN111667751A (en) * | 2020-06-27 | 2020-09-15 | 海南晟基建筑科技有限公司 | Assembled structural model based on BIM |
CN111980400A (en) * | 2020-07-09 | 2020-11-24 | 中国十七冶集团有限公司 | Aluminum alloy template for joint of laminated slab and construction method |
CN112459326A (en) * | 2020-11-27 | 2021-03-09 | 江苏宇辉住宅工业有限公司 | Assembly type laminated slab cast-in-place slab band structure based on BIM technology and construction method |
CN113653234A (en) * | 2021-07-26 | 2021-11-16 | 福建建祥建筑科技有限责任公司 | Floor board installation process convenient to assemble |
CN116411718A (en) * | 2021-12-31 | 2023-07-11 | 中国二十冶集团有限公司 | Template laying device for preventing slurry leakage of post-pouring plate strip of laminated slab and application method of template laying device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2580029Y (en) * | 2002-10-18 | 2003-10-15 | 浙江杭萧钢构股份有限公司 | Adjustable building surface steel formwork support combined piece |
KR100908266B1 (en) * | 2009-02-12 | 2009-07-20 | 주식회사 공간이동 | Height regulation device with handle for steal box abridge |
CN105178603A (en) * | 2015-06-17 | 2015-12-23 | 深圳建业工程集团股份有限公司 | EPS polyphenyl dismantling-exempt template concrete building cover plate construction technology method |
CN105544970A (en) * | 2016-02-01 | 2016-05-04 | 成都市第六建筑工程公司 | Composite floor slab cast-in-place slab fixing device with bottom mold and construction method |
CN105569242A (en) * | 2015-12-28 | 2016-05-11 | 中民筑友有限公司 | Assembling method for composite floor slabs |
-
2016
- 2016-06-24 CN CN201610467328.3A patent/CN106065681B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2580029Y (en) * | 2002-10-18 | 2003-10-15 | 浙江杭萧钢构股份有限公司 | Adjustable building surface steel formwork support combined piece |
KR100908266B1 (en) * | 2009-02-12 | 2009-07-20 | 주식회사 공간이동 | Height regulation device with handle for steal box abridge |
CN105178603A (en) * | 2015-06-17 | 2015-12-23 | 深圳建业工程集团股份有限公司 | EPS polyphenyl dismantling-exempt template concrete building cover plate construction technology method |
CN105569242A (en) * | 2015-12-28 | 2016-05-11 | 中民筑友有限公司 | Assembling method for composite floor slabs |
CN105544970A (en) * | 2016-02-01 | 2016-05-04 | 成都市第六建筑工程公司 | Composite floor slab cast-in-place slab fixing device with bottom mold and construction method |
Non-Patent Citations (1)
Title |
---|
潘鼐: "《建筑施工模板图册》", 31 July 1993 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639317A (en) * | 2016-12-23 | 2017-05-10 | 浙江省建工集团有限责任公司 | Prefabricated building complete set constructing technology |
CN107178168A (en) * | 2017-06-16 | 2017-09-19 | 中交航局第工程有限公司 | Cast-in-place surface layer formwork support process |
CN107178168B (en) * | 2017-06-16 | 2019-03-29 | 中交一航局第一工程有限公司 | Cast-in-place surface layer formwork support process |
CN109113192A (en) * | 2018-08-24 | 2019-01-01 | 宁波建工工程集团有限公司 | It is a kind of can bidirectional modulation assembled superimposed sheet seam mortar leakage prevention plugging device |
CN110306707A (en) * | 2019-06-20 | 2019-10-08 | 四川省劲腾环保建材有限公司 | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method |
CN111667751A (en) * | 2020-06-27 | 2020-09-15 | 海南晟基建筑科技有限公司 | Assembled structural model based on BIM |
CN111980400A (en) * | 2020-07-09 | 2020-11-24 | 中国十七冶集团有限公司 | Aluminum alloy template for joint of laminated slab and construction method |
CN111980400B (en) * | 2020-07-09 | 2022-05-13 | 中国十七冶集团有限公司 | Plugging structure for splicing seam of laminated slab and construction method |
CN112459326A (en) * | 2020-11-27 | 2021-03-09 | 江苏宇辉住宅工业有限公司 | Assembly type laminated slab cast-in-place slab band structure based on BIM technology and construction method |
CN113653234A (en) * | 2021-07-26 | 2021-11-16 | 福建建祥建筑科技有限责任公司 | Floor board installation process convenient to assemble |
CN113653234B (en) * | 2021-07-26 | 2023-04-14 | 福建建祥建筑科技有限责任公司 | Floor board installation process convenient to assemble |
CN116411718A (en) * | 2021-12-31 | 2023-07-11 | 中国二十冶集团有限公司 | Template laying device for preventing slurry leakage of post-pouring plate strip of laminated slab and application method of template laying device |
Also Published As
Publication number | Publication date |
---|---|
CN106065681B (en) | 2019-03-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106065681A (en) | Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology | |
CN105649325B (en) | The adjustable tripod support system of assembly concrete shear wall structure and method | |
CN102392536B (en) | Construction method for long-span hanging vestibule type template support system | |
CN106592965A (en) | Quick support system of high-rise steel structure house composite floor slab | |
CN106193589B (en) | Concrete superelevation heavy type beam and overlapping board combining structure method for supporting | |
CN103410269B (en) | Prestressing without bondn cast-in-place reinforced concrete hollow slab constructing structure and construction method | |
CN204059955U (en) | In-situ reinforced concrete slab template integral type braced structures | |
CN107130720B (en) | PK prestressed concrete overlapped slab construction method | |
CN105569242A (en) | Assembling method for composite floor slabs | |
CN103806647A (en) | Assembly and disassembly process for large-span concrete bidirectional dense rib beam formwork case | |
CN103821361B (en) | Stair studding formwork construction method is built in the gradation improved | |
CN206438529U (en) | Beam and slab type raft foundation formwork support structure | |
CN114770706B (en) | Light T-beam prefabrication equipment and prefabrication installation construction method | |
CN202925721U (en) | Prefabricated superimposed sheet-type concrete shear wall structure | |
CN202324606U (en) | U-shaped force bearing seat | |
CN108661313A (en) | A kind of cast-in-place linkage section mould plate supporting device of tool-type concrete folding plate | |
CN110306707A (en) | It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method | |
CN103615075A (en) | Concrete sloping roof continuous casting forming method | |
CN205875708U (en) | Basement outer wall single -side supporting formwork construction structures based on steel pipe truss | |
CN105839914B (en) | Adjustable steel beam support meanss and system | |
CN205839568U (en) | A kind of cast-in-situ box girder model sheetinstallat structure | |
CN102465605A (en) | Method for building bottom plate steel bar support | |
CN207405882U (en) | A kind of steel bar positioning frame | |
CN102787717B (en) | Self-supporting combined steel template construction method | |
CN107381376B (en) | Device and method for hoisting by utilizing curtain wall embedded part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: No.111 Babao Street, Qingyang District, Chengdu, Sichuan 610000 Patentee after: Chengdu Construction Industry Group Co.,Ltd. Patentee after: CHENGDU SIXTH CONSTRUCTION ENGINEERING Co.,Ltd. OF CDCEG Address before: No.111 Babao Street, Chengdu, Sichuan 610000 Patentee before: CHENGDU CONSTRUCTION ENGINEERING Group Corp. Patentee before: CHENGDU NO.6 CONSTRUCTION ENGINEERING Co. |
|
CP03 | Change of name, title or address |