CN103615075A CN201310612775.XA CN201310612775A CN103615075A CN 103615075 A CN103615075 A CN 103615075A CN 201310612775 A CN201310612775 A CN 201310612775A CN 103615075 A CN103615075 A CN 103615075A
Authority
CN
China
Prior art keywords
concrete
split bolt
sloping roof
forming method
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310612775.XA
Other languages
Chinese (zh)
Other versions
CN103615075B (en
Inventor
张鹏飞
刘学民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201310612775.XA priority Critical patent/CN103615075B/en
Publication of CN103615075A publication Critical patent/CN103615075A/en
Application granted granted Critical
Publication of CN103615075B publication Critical patent/CN103615075B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to a concrete sloping roof continuous casting forming method. The concrete sloping roof continuous casting forming method comprises the following steps: (1) a sloping roof timber formwork and a bottom plate are erected on a framework where a top steel bar and a bottom steel bar are well erected, a split bolt is arranged, the lower end of the split bolt is fixedly mounted on the sloping roof timber formwork through a batten rib and a split steel plate, and the split bolt is perpendicular to the sloping roof timber formwork; (2) an L-shaped rebar hook is placed at the upper end of the split bolt; (3) a steel wire gauze is hung on the L-shaped rebar hook in a pulling mode, a steel channel which can control the roof concrete thickness is fixed at the top end of the split bolt through a nut, and the steel channel tightly abuts against the L-shaped rebar hook; (4) sloping roof concrete is poured continuously. According to the concrete sloping roof continuous casting forming method, since the common split bolt, the steel wire gauze and the positioning steel channel are mainly used and effectively combined, operation is simple, and the design is reasonable; continuous pouring can be conducted in the downward direction of a sloping roof, so that the common problems of accumulation and uncompactedness during concrete placement are avoided, and construction efficiency is effectively improved.

Description

Concrete sloping roof continuous pouring forming method
Technical field
The invention belongs to oblique roofing forming field, especially a kind of concrete sloping roof continuous pouring forming method.
Background technology
In building operations, building for landscape hardwork or recreational facilities especially, for attractive in appearance and meet certain style characteristic, its roofing is often designed to oblique roofing, requires to adopt reinforced concrete cast-in-situ to make simultaneously.Because some roofing slope is too steep, pouring concrete is just very difficult.Existing to have way be to utilize manually concrete to pat on oblique roofing, and this method is time-consuming, and the oblique roofing leakiness of moulding is of poor quality; Exactly concrete is carried out to interrupted pour with pump truck downwards from top, inclined-plane in addition, can make like this concrete produce segregation, wayward, scene also needs many people to carry out coordinative construction, revises in time levelling, and the also danger close of constructing.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, a kind of concrete sloping roof continuous pouring forming method is provided, this forming method is simple to operate, reasonable in design, can upwards carry out continuous pouring from oblique roofing below, avoided piling up in pouring concrete, uncompacted common fault, has effectively improved efficiency of construction.
The present invention solves its technical problem and is achieved through the following technical solutions:
A concrete sloping roof continuous pouring forming method, its forming method comprises the steps:
(1), first on the framework that has set up top reinforcement and bottom layer of the reinforcing steel, install oblique roofing wooden form and base plate, then along gradient direction, in a row arrange split bolt, split bolt lower end adopts flitch rib and to drawing steel plate to be packed on oblique roofing wooden form, split bolt is perpendicular to oblique roofing wooden form;
(2), in the upper end of split bolt, lay L-type Reinforced hook, a parallel-segment of L-type Reinforced hook is connected with split bolt spot welding, and the vertical section of L-type Reinforced hook is parallel with split bolt;
, on L-type Reinforced hook, draw extension gauze wire cloth, the oblique placement of gauze wire cloth, gauze wire cloth bottom and bottom layer of the reinforcing steel fasten with wiring.Finally, at the fixing channel-section steel that can control roofing concrete thickness of nut for top of split bolt, this channel-section steel and L-type Reinforced hook hold out against;
(4), in cast, during oblique roofing concrete, from roofing below, up divide band to carry out continuous pouring,, until roof moulding, after concrete setting, is carried out maintenance, concrete sloping roof continuous pouring is complete.
And the vertical section length of L-type Reinforced hook is identical with the top reinforcement thickness of oblique roofing.
Advantage of the present invention and beneficial effect are:
This concrete sloping roof continuous pouring forming method mainly adopts common split bolt, wire gauze and location channel-section steel to be made with effect combination, simple to operate, reasonable in design, can upwards carry out continuous pouring from oblique roofing below, avoided piling up in pouring concrete, uncompacted common fault, has effectively improved efficiency of construction.
Accompanying drawing explanation
Fig. 1 is the oblique roofing schematic diagram of constructing with the present invention.
The specific embodiment
Below by specific embodiment, the invention will be further described, and following examples are descriptive, is not determinate, can not limit protection scope of the present invention with this.
A concrete sloping roof continuous pouring forming method, its forming method comprises the steps:
(1), first on the framework that has set up top reinforcement 10 and bottom layer of the reinforcing steel 6, install oblique roofing wooden form 7 and base plate 5, then along gradient direction, in a row arrange split bolt 1, split bolt lower end adopts flitch rib 9 and to drawing steel plate 8 to be packed on oblique roofing wooden form, split bolt is perpendicular to oblique roofing wooden form;
(2), in the upper end of split bolt, lay L-type Reinforced hook 2, a parallel-segment of L-type Reinforced hook is connected with split bolt spot welding, and the vertical section of L-type Reinforced hook is parallel with split bolt, and the vertical section length of L-type Reinforced hook is identical with the top reinforcement thickness of oblique roofing;
, on L-type Reinforced hook, draw and hang gauze wire cloth 4, the oblique placement of gauze wire cloth, gauze wire cloth bottom and bottom layer of the reinforcing steel fasten with wiring.Finally, at the fixing channel-section steel 3 that can control roofing concrete thickness of nut for top of split bolt, this channel-section steel and L-type Reinforced hook hold out against; Play and prevent that wire gauze displacement, the phenomenon coming off from occurring;
(4), connecting bolt is divided into some pouring belts along gradient direction by concrete, bandwidth does not produce during with pouring concrete to pile up and is as the criterion, when the oblique roofing concrete of cast, from roofing below, up divide band to carry out continuous pouring, until roof moulding, after concrete setting, carry out maintenance, concrete sloping roof continuous pouring is complete.In split bolt and wire gauze Transducers Embedded in Concrete, the removable lower recycling of location channel-section steel.

Claims (2)

1. a concrete sloping roof continuous pouring forming method, is characterized in that: this forming method comprises the steps:
(1), first on the framework that has set up top reinforcement and bottom layer of the reinforcing steel, install oblique roofing wooden form and base plate, then along gradient direction, in a row arrange split bolt, split bolt lower end adopts flitch rib and to drawing steel plate to be packed on oblique roofing wooden form, split bolt is perpendicular to oblique roofing wooden form;
(2), in the upper end of split bolt, lay L-type Reinforced hook, a parallel-segment of L-type Reinforced hook is connected with split bolt spot welding, and the vertical section of L-type Reinforced hook is parallel with split bolt;
, on L-type Reinforced hook, draw extension gauze wire cloth, the oblique placement of gauze wire cloth, gauze wire cloth bottom and bottom layer of the reinforcing steel fasten with wiring.Finally, at the fixing channel-section steel that can control roofing concrete thickness of nut for top of split bolt, this channel-section steel and L-type Reinforced hook hold out against;
(4), in cast, during oblique roofing concrete, from roofing below, up divide band to carry out continuous pouring,, until roof moulding, after concrete setting, is carried out maintenance, concrete sloping roof continuous pouring is complete.
2. concrete sloping roof continuous pouring forming method according to claim 1, is characterized in that: the vertical section length of described L-type Reinforced hook is identical with the top reinforcement thickness of oblique roofing.
CN201310612775.XA 2013-11-26 2013-11-26 The continuous casting forming method of concrete sloping roof Active CN103615075B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310612775.XA CN103615075B (en) 2013-11-26 2013-11-26 The continuous casting forming method of concrete sloping roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310612775.XA CN103615075B (en) 2013-11-26 2013-11-26 The continuous casting forming method of concrete sloping roof

Publications (2)

Publication Number Publication Date
CN103615075A true CN103615075A (en) 2014-03-05
CN103615075B CN103615075B (en) 2016-07-06

Family

ID=50165790

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310612775.XA Active CN103615075B (en) 2013-11-26 2013-11-26 The continuous casting forming method of concrete sloping roof

Country Status (1)

Country Link
CN (1) CN103615075B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018674A (en) * 2014-06-10 2014-09-03 中机环建集团有限公司 Concrete pouring process for large-angel sloping roof
CN106284875A (en) * 2016-08-31 2017-01-04 中冶天工集团有限公司 The concrete device for trapping of heavy grade roofing and construction method
CN110424640A (en) * 2019-07-29 2019-11-08 北京崇建工程有限公司 A kind of construction method of Sloping roof concrete structure
CN111155758A (en) * 2020-02-25 2020-05-15 中国建筑第四工程局有限公司 Tool type super-gradient inclined roof construction template and construction method
CN114108800A (en) * 2021-12-09 2022-03-01 中国一冶集团有限公司 Steel wire mesh framing cabin for cornice board concrete pouring and pouring construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1990014476A1 (en) * 1989-05-23 1990-11-29 Nittedal Torvindustri A/S Element for turfed roofs
JPH07300951A (en) * 1994-09-30 1995-11-14 Jiyoushin Kengiyou Kk Method for constructing roof top of various building
CN1525028A (en) * 2003-09-17 2004-09-01 李军掴 Reinforced concrete roof laying technology and dedicated vacuum tube
CN201649459U (en) * 2010-04-23 2010-11-24 王世杰 Slope roof cast-in-place concrete structure
CN103046697A (en) * 2013-01-23 2013-04-17 中国三冶集团有限公司第二建筑工程公司 Construction method of 25-40-degree concrete pitched roofs

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1990014476A1 (en) * 1989-05-23 1990-11-29 Nittedal Torvindustri A/S Element for turfed roofs
JPH07300951A (en) * 1994-09-30 1995-11-14 Jiyoushin Kengiyou Kk Method for constructing roof top of various building
CN1525028A (en) * 2003-09-17 2004-09-01 李军掴 Reinforced concrete roof laying technology and dedicated vacuum tube
CN201649459U (en) * 2010-04-23 2010-11-24 王世杰 Slope roof cast-in-place concrete structure
CN103046697A (en) * 2013-01-23 2013-04-17 中国三冶集团有限公司第二建筑工程公司 Construction method of 25-40-degree concrete pitched roofs

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
何斌,耿波: "1:1坡度的别墅斜屋面混凝土浇捣施工技术", 《建筑施工》, vol. 32, no. 12, 31 December 2010 (2010-12-31), pages 1226 - 1227 *
岳国峰,姜卫强,王晓春: "槽钢组合模板在护坡混凝土施工中的应用", 《黑龙江水专学报》, vol. 30, no. 3, 30 September 2003 (2003-09-30), pages 112 - 113 *
张进湘,刘一智: "某住宅楼钢筋混凝土斜屋面施工技术", 《陕西建筑》, 30 September 2011 (2011-09-30), pages 24 - 26 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018674A (en) * 2014-06-10 2014-09-03 中机环建集团有限公司 Concrete pouring process for large-angel sloping roof
CN104018674B (en) * 2014-06-10 2015-10-21 中机环建集团有限公司 The concrete casting building technology of wide-angle pitched roof
CN106284875A (en) * 2016-08-31 2017-01-04 中冶天工集团有限公司 The concrete device for trapping of heavy grade roofing and construction method
CN106284875B (en) * 2016-08-31 2019-05-03 中冶天工集团有限公司 The concrete device for trapping and construction method of heavy grade roofing
CN110424640A (en) * 2019-07-29 2019-11-08 北京崇建工程有限公司 A kind of construction method of Sloping roof concrete structure
CN111155758A (en) * 2020-02-25 2020-05-15 中国建筑第四工程局有限公司 Tool type super-gradient inclined roof construction template and construction method
CN114108800A (en) * 2021-12-09 2022-03-01 中国一冶集团有限公司 Steel wire mesh framing cabin for cornice board concrete pouring and pouring construction method

Also Published As

Publication number Publication date
CN103615075B (en) 2016-07-06

Similar Documents

Publication Publication Date Title
CN202170600U (en) Anti-segregation device for concrete pouring of large-angle sloping roof
CN103290967B (en) A kind of multi-ribbed hollow composite floor slab and manufacture method
CN103615075A (en) Concrete sloping roof continuous casting forming method
CN201943045U (en) Automatic-moving hydraulic cantilever gantry concrete placement device for wave wall
CN201943347U (en) Mounting structure for plastic formwork of frame column
CN106065681A (en) Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology
CN110374321A (en) A kind of assembled waffle beam superstructure gang form and construction method
CN109487955A (en) A kind of precast concrete column in-situ cast-in-place construction method
CN105952154B (en) A kind of concrete-pouring template stent
CN106703271A (en) Anti-floating construction method for hollow floor core molds
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
CN104831932A (en) Construction technology for high-grade concrete column base
CN209482709U (en) A kind of in-situ concrete wall subsiding crack typified form
CN108086674A (en) A kind of roof boarding hangs the construction method of mould and roof boarding
CN204899064U (en) Heavy grade slope roofing cast in situ concrete construction equipment
CN206956979U (en) A kind of Linear shear wall with fore-set
CN103722613A (en) Construction method for vertically casting and mounting four-foot hollow block in seawall wave resistance engineering
CN107100322B (en) Post stretching vertical prestressing cast-in-place concrete rod structure and construction method
CN205857697U (en) The anti-form bracing constructing device hanging template
CN104234088A (en) Post-cast strip structure of prefabricated double-layer laminate basement external wall panel and construction procedure
CN103628684B (en) A kind of construction method of simultaneously watering build floor and shear wall
CN215629452U (en) Pull rod-free mobile trolley construction device for frame bridge
CN202596161U (en) Combined formwork device of HR heavy type gantry and reinforced concrete temporary structural column
CN204212302U (en) A kind of hollowcore slab light pipe float Structure
CN209799122U (en) Cavity floor member

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant