CN106223961A - A kind of coal mine return air big lane passing fault tunneling construction method - Google Patents

A kind of coal mine return air big lane passing fault tunneling construction method Download PDF

Info

Publication number
CN106223961A
CN106223961A CN201610615757.0A CN201610615757A CN106223961A CN 106223961 A CN106223961 A CN 106223961A CN 201610615757 A CN201610615757 A CN 201610615757A CN 106223961 A CN106223961 A CN 106223961A
Authority
CN
China
Prior art keywords
return air
slip casting
rock
fault
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610615757.0A
Other languages
Chinese (zh)
Other versions
CN106223961B (en
Inventor
张伟
相啸宇
马植胜
彭伟
李俊鸿
胡新献
惠永岗
宗树新
计鹏举
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Haohua Energy Resource Co Ltd
Original Assignee
Beijing Haohua Energy Resource Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Haohua Energy Resource Co Ltd filed Critical Beijing Haohua Energy Resource Co Ltd
Priority to CN201610615757.0A priority Critical patent/CN106223961B/en
Publication of CN106223961A publication Critical patent/CN106223961A/en
Application granted granted Critical
Publication of CN106223961B publication Critical patent/CN106223961B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices, or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

The present invention provides a kind of coal mine return air big lane passing fault tunneling construction method, comprises the following steps: step S1, and driving detours, and detours according to original tunnelling, detours vertical with fault strike;Step S2, reserved rock emits, and calculates and designs rock and emit;Step S3, slip casting, first carry out material selection, then calculate grouting amount, then carry out drilling design, then orifice tube be designed and fix, last slip casting;Compared with prior art, the present invention has following beneficial effect: ensure that return air big lane passing fault passes through;Ensure that passing fault smooth construction, it is ensured that personal safety and property safety and mine ventilation system are quickly formed, it is ensured that mine safety production.

Description

A kind of coal mine return air big lane passing fault tunneling construction method
Technical field
The present invention is a kind of coal mine return air big lane passing fault tunneling construction method.
Background technology
It is domestic that red Qing Liang colliery is positioned at Dalate Banner, Ordos City, Inner Mongolia Autonomous Region, is subordinated to tower the highest Le mining area. Designed mine capacity: 6.0Mt/a;Showing according to geologic information, 3-1 return air big lane average thickness is about 4.87m, and coal seam is pushed up Slate is mainly conglomerate and siltstone, and local is fine sandstone or kern stone, and base plate lithology is mainly Sandy Silt, mud Rock, local are medium-fine sand rock, and DF14 tomography is normal fault, drop H=17m, 65 ° of inclination angle, and balkstone is mud stone, conglomerate and portion Dividing conglomerate, base plate is sandstone.
Tomography is being met along the tunneling process of top in the big lane of red celebrating beam coal mine return air, meets head on roof fall.Coal seam, place is 3-1 Coal, nature of coal seam thickness 2.90~6.85m, average 5.10m.Minable thickness 2.86~6.85m, average 4.87m, from inbreak situation Seeing that roof is Sandy Silt, at the fall of ground of place, rear portion is whole enzymatic method, meets tomography and enter rock gangway at roof fall.At roof fall Tunnel, rear portion uses anchor net and just sprays supporting, and drift section is rectangle, surveys a width of 5.8m in tunnel, high 4m.Employing development machine is executed Work, development machine rear portion is arranged ribbon conveyer, is colloid air duct at conveyer brattice way spandrel arch.
Development machine is when carrying out a new circulation tunneling construction, and part rock has just been tunneled in the portion of side, right side that meets head on, and driving opening is Perpendicular row strip, open rear section is a crushed zone, thinks, crushed zone, under rock pressure and hydrops effect, breaks through Weak location rock stratum, forms infundibulate and emits top opening.Meet head on, after roof fall, to form Gangue at opening part, withstand funnel openings, make Obtaining roof fall and do not continue extension, spoil is based on broken cash and cobblestone.
Drilling tomography, bore position is in the big lane of return air and meets head on, and apart from left side 1.1m, top board 3.3m, top rade 1 °, bores The long 8.8m in hole;Boring 0-4.1m section is coal seam, and boring 4.1-6.5m section is mud stone, and boring 6.5-8.8m section is packsand;Meet head on Water yield starts as 9.5m3/ h, present water consumption is about 4m3/ h, tomography DF14, drop 17m, 60 ° of inclination angle, move towards big with return air Lane angle 35 °.
3-1 return air big lane, red Qing Liang colliery penetrating ground has the spies such as watery is strong, lithology weak, geologic condition are complicated Point, discloses tomography according to reality and shows, in 3-1 return air big lane, driving runs into DF14 tomography to 1227, and fault strike is 145 °, with Tunnelling direction becomes 35 ° of angles, and 65 ° of inclination angle, drop is about 17m, and turn-off is 2.5m.Tomography norm al discharge rate is 4m3/h.Top Plate is broken and top board trickle is big, and roadway construction anchor cable and anchor pole lost efficacy.When tunneling construction, meet head on right side, to form a tomography Broken breach, breach funneling shape, under the effect of rock gravity and hydrops pressure, broken;Breach is constantly gushed out spoil, gives Construction brings difficulty, and driving speed is slow, and existing anchor rete cord spray supporting construction is difficult and can not play its due supporting effect, Bringing bigger hidden danger to 3-1 return air big lane construction safety, construction speed causes and has a strong impact on, and spoil with cobblestone and mud stone is Main.Simultaneously as the big lane of 3-1 return air is responsible for whole mine 3-1 coal ventilating system, logical for ensureing that full ore deposit realizes full blast pressure as early as possible Wind system, needs accelerating construction progress, meets ventilation needs, and construction safety.Ore deposit side research determine the big lane of 3-1 return air, meet head on to North is stepped back and is constructed at 29m, and 3-1 return air big lane return air detours, and is perpendicular to tomography driving.For construction safety and property safety, special This have developed a kind of coal mine return air big lane passing fault tunneling construction method.
Summary of the invention
The deficiency existed for prior art, it is an object of the present invention to provide a kind of coal mine return air big lane passing fault tunneling construction Method, to solve the problem proposed in above-mentioned background technology, the present invention is easy to use, it is simple to operation, good stability, reliability High.
To achieve these goals, the present invention is to realize by the following technical solutions: a kind of coal mine return air big lane mistake Tomography tunneling construction method, comprises the following steps:
Step S1, driving detours, and detours according to original tunnelling, detours vertical with fault strike;
Step S2, reserved rock emits, and calculates and designs rock and emit;
Step S3, slip casting, first carry out material selection, then calculate grouting amount, then carry out drilling design, right aperture after Mouth pipe is designed and fixes, last slip casting.
Further, in step s 2, according to formulaCalculate the thickness that only magmatic rock emits;
In formula: B is rock plug thickness;
P is final grouting pressure;
S is rock cap basal area;
λ is overload factor, and λ takes 1.1-1.2;
[τ] is that rock allows shearing strength;
L is tunnel-surrounding length.
Further, in the material of step S3 selects, needing to use single slurry and dual slurry, wherein single slurry uses and moulds Property early injection pulp material;
Dual slurry uses cement and waterglass mixing, wherein:
Cement: P.O 42.5 Portland cement;
Waterglass: modulus M=2.8~3.1, concentration 30~35 ° of Be'.
Further, in step s3, grouting amount calculates according to grouting amount formula:
Q=A × β × η × V;
In formula: the total injection rate of Q serosity (m3);
A serosity super diffusion consumption coefficient takes 1.5;
β serosity volumetric efficiency 0.9;
η fault belt average crack rate 10%;
The rock mass volume that V is noted, m3
The rock mass volume V=S × L noted;
In formula: S is by the basal area of note rock mass;
L is by note rock mass length.
Further, in step s3, drilling design refers to use twice pore-forming mode, and hole termination depth is according to boreholes drilling Result determines that tomography thickness, horizontal drilling length exceed tomography highest distance position 5m.
Further, in step s3, orifice tube is designed and fixes:
Orifice tube uses diameter 70mm welded tube, and single long 6m, 7 unilateral band high pressure flanges, side is threaded, remaining hole Mouth pipe, is bilateral screw thread, and flange side adds solder joint;
Orifice tube is fixing in two steps, and the first step enters in boring under orifice tube bond pad locations twines fiber crops, second step slip casting Carrying out full packages to fix, second step terminates, and solidifies more than 8h, after bulge test, carries out secondary pore-forming.
Further, the mode of slip casting is the most single slurry then dual slurry;
In single slurry, first pour plasticity early injection pulp material into massing machine, after stirring, pour stock tank into, at note Under the effect of stock pump, introduced in boring by high pressure valve and orifice valves;
In dual slurry, first pour cement and water into massing machine, after stirring, pour stock tank into, waterglass is introduced In grouting pump, under the effect of grouting pump, introduced in boring by high pressure valve and orifice valves;
When slip casting, grouting pressure is 2~2.5 times of hydrostatic pressure;
Slip casting should carry out setting-out experiment, the sealing of testing bore holes and safety before starting, the force value of setting-out experiment is 1.2~1.5 times of final grouting pressure, when stable 15min is without exception, can start formal mortar depositing construction.
When grouting pressure reaches final grouting pressure value, furnishing 1 grade (16L/min), low discharge voltage stabilizing 20min, this brill can be terminated The slip casting work in hole.
Beneficial effects of the present invention: a kind of coal mine return air big lane passing fault tunneling construction method of the present invention, it is ensured that return Feng great lane passing fault passes through;Ensure that passing fault smooth construction, it is ensured that personal safety and property safety and mine ventilation system System is quickly formed, it is ensured that mine safety production.
Detailed description of the invention
For the technological means making the present invention realize, creation characteristic, reach purpose and be easy to understand with effect, below in conjunction with Detailed description of the invention, is expanded on further the present invention.
The present invention provides a kind of technical scheme: a kind of coal mine return air big lane passing fault tunneling construction method, including following step Rapid:
Step S1, driving detours, and detours according to original tunnelling, detours vertical with fault strike;
Step S2, reserved rock emits, and calculates and designs rock and emit;
Step S3, slip casting, first carry out material selection, then calculate grouting amount, then carry out drilling design, right aperture after Mouth pipe is designed and fixes, last slip casting.
In step s 2, according to formulaCalculate the thickness that only magmatic rock emits;
In formula: B is rock plug thickness;
P is final grouting pressure;
S is rock cap basal area;
λ is overload factor, and λ takes 1.1-1.2;
[τ] is that rock allows shearing strength;
L is tunnel-surrounding length.
In the material of step S3 selects, needing to use single slurry and dual slurry, wherein single slurry uses plasticity early injection Pulp material;
Dual slurry uses cement and waterglass mixing, wherein:
Cement: P.O 42.5 Portland cement;
Waterglass: modulus M=2.8~3.1, concentration 30~35 ° of Be'.
Further, in step s3, grouting amount calculates according to grouting amount formula:
Q=A × β × η × V;
In formula: the total injection rate of Q serosity (m3);
A serosity super diffusion consumption coefficient takes 1.5;
β serosity volumetric efficiency 0.9;
η fault belt average crack rate 10%;
The rock mass volume that V is noted, m3
The rock mass volume V=S × L noted;
In formula: S is by the basal area of note rock mass;
L is by note rock mass length.
In step s3, drilling design refers to use twice pore-forming mode, and hole termination depth determines according to boreholes drilling result Tomography thickness, horizontal drilling length exceedes tomography highest distance position 5m.
In step s3, orifice tube is designed and fixes:
Orifice tube uses diameter 70mm welded tube, and single long 6m, 7 unilateral band high pressure flanges, side is threaded, remaining aperture Pipe, is bilateral screw thread, and flange side adds solder joint;
Orifice tube is fixing in two steps, and the first step enters in boring under orifice tube bond pad locations twines fiber crops, second step slip casting Carrying out full packages to fix, second step terminates, and solidifies more than 8h, after bulge test, carries out secondary pore-forming.
The mode of slip casting is the most single slurry then dual slurry;
In single slurry, first pour plasticity early injection pulp material into massing machine, after stirring, pour stock tank into, at note Under the effect of stock pump, introduced in boring by high pressure valve and orifice valves;
In dual slurry, first pour cement and water into massing machine, after stirring, pour stock tank into, waterglass is introduced In grouting pump, under the effect of grouting pump, introduced in boring by high pressure valve and orifice valves;
When slip casting, grouting pressure is 2~2.5 times of hydrostatic pressure;
Slip casting should carry out setting-out experiment, the sealing of testing bore holes and safety before starting, the force value of setting-out experiment is 1.2~1.5 times of final grouting pressure, when stable 15min is without exception, can start formal mortar depositing construction.
When grouting pressure reaches final grouting pressure value, furnishing 1 grade (16L/min), low discharge voltage stabilizing 20min, this brill can be terminated The slip casting work in hole.
Ensure that return air big lane passing fault passes through;Ensure that passing fault smooth construction, it is ensured that personal safety and property Safety and mine ventilation system are quickly formed, it is ensured that mine safety production.
As one embodiment of the present of invention: when constructing in lane big to 3-1 return air, with specific reference to following steps:
Step S1, driving detours, and detours according to original tunnelling, detours vertical with fault strike.
Step S2, reserved rock emits, and calculates and designs rock and emit;Thickness B=8.4 × 3.14 × 2.7 that only magmatic rock emits2×1.1/ 0.5×(3.14×2.7+5.4+1.4×2)≈26m。
Step S3, slip casting, first carry out material selection, then calculate grouting amount, then carry out drilling design, right aperture after Mouth pipe is designed and fixes, last slip casting;
In the material of step S3 selects, needing to use single slurry and dual slurry, wherein single slurry uses plasticity early injection Pulp material;
Dual slurry uses cement and waterglass mixing, wherein:
Cement: P.O 42.5 Portland cement;
Waterglass: modulus M=2.8~3.1, concentration 30~35 ° of Be'.
Further, in step s3, grouting amount calculates according to grouting amount formula:
Q=A × β × η × V;
In formula: the total injection rate of Q serosity (m3);
A serosity super diffusion consumption coefficient takes 1.5;
β serosity volumetric efficiency 0.9;
η fault belt average crack rate 10%;
The rock mass volume that V is noted, m3
The rock mass volume V=S × L noted;
In formula: S is by the basal area of note rock mass;
L is by note rock mass length.
When calculating grouting amount, slip casting tunnel is Semicircular tunnel, clear height 4.1m, and high wide 5.4m, according to probing feelings Condition speculates, it is contemplated that width is 2.4m, and drilling depth exceedes crushed zone 5m, then be about 7.4m by slip casting rock mass length.Dilation angle Calculate by 5m.
S=π r2=3.14 × 6.72≈141m2
V=S × L=141 × 7.4 ≈ 1043m3
Q=A × β × η × V=1.5 × 0.9 × 10% × 1043 ≈ 140m3
Single slurry, dual slurry are by 80% and 20% calculating of total grouting amount, then single slurry is 112m3, dual slurry grouting amount For 28m3
In step s3, drilling design refers to use twice pore-forming mode, boring to use 2 pore-forming modes, opening diameter For 75mm, hole depth 25m, whole bore dia 50mm, hole termination depth determines tomography thickness, horizontal drilling length according to boreholes drilling result Exceed tomography highest distance position 5m.
When boring, boring is arranged in reserved rock cap and is evenly arranged with fault belt interface, drill with ferrule under the left and right sides Hole is outwards from the horizontal by 2 ° of angles, and remaining boring is outwards from the horizontal by 3 ° of angles.
In step s3, orifice tube is designed and fixes:
Orifice tube uses diameter 70mm welded tube, and single long 6m, 7 unilateral band high pressure flanges, side is threaded, remaining aperture Pipe, is bilateral screw thread, and flange side adds solder joint;
Orifice tube is fixing in two steps, and the first step enters in boring under orifice tube bond pad locations twines fiber crops, second step slip casting Carrying out full packages to fix, second step terminates, and solidifies more than 8h, after bulge test, carries out secondary pore-forming.
The mode of slip casting is the most single slurry then dual slurry;
In single slurry, first pour plasticity early injection pulp material into massing machine, after stirring, pour stock tank into, at note Under the effect of stock pump, introduced in boring by high pressure valve and orifice valves;
In dual slurry, first pour cement and water into massing machine, after stirring, pour stock tank into, waterglass is introduced In grouting pump, under the effect of grouting pump, introduced in boring by high pressure valve and orifice valves;
Grouting pressure is one of factor affecting serosity effect, and when grouting pressure is too small, grout mixing reduces, rock mass Not reaching intended consolidation effect, when grouting pressure is excessive, grout mixing expands, and causes serosity to waste.
Grouting pressure is 2~2.5 times of hydrostatic pressure, tunnel absolute altitude be 970m, 3-1 coal water level elevation be 1384.79~ 1451.21m, hydrostatic pressure is 4.2Mpa, and design final grouting pressure is 8.4~10.5Mpa.
Slip casting should carry out packer permeability test, the sealing of test system and safety before starting, the force value of setting-out experiment is 1.2~1.5 times of final grouting pressure, i.e. 10.1~12.6Mpa, when stable 15min is without exception, formal slip casting can be started and execute Work.
When grouting pressure reaches final grouting pressure value, when i.e. 8.4~10.5Mpa, furnishing 1 grade (16L/min), low discharge voltage stabilizing 20min, can terminate the slip casting work in this hole.
By this method, by taking strong technical measures and organiztion measure to ensure that red Qing Liang colliery 3-1 return air The smooth construction of big lane passing fault.Use and detour and grouting program in the construction of 3-1 coal, it is ensured that 3-1 return air big lane passing fault is suitable Profit is passed through;Detoured erection U-shaped steel canopy and grouting and reinforcing scheme by return air of taking to construct, designed by drift section optimization and The measures such as the optimization design of support form, it is ensured that passing fault smooth construction, it is ensured that personal safety and property safety and mine lead to Wind system is quickly formed, it is ensured that mine safety production.
The ultimate principle of the present invention and principal character and advantages of the present invention are more than shown and described, for this area skill For art personnel, it is clear that the invention is not restricted to the details of above-mentioned one exemplary embodiment, and without departing substantially from the present invention spirit or In the case of basic feature, it is possible to realize the present invention in other specific forms.Therefore, no matter from the point of view of which point, all should be by Embodiment regards exemplary as, and is nonrestrictive, the scope of the present invention by claims rather than on state Bright restriction, it is intended that include all changes fallen in the implication of equivalency and scope of claim in the present invention In.
Although moreover, it will be appreciated that this specification is been described by according to embodiment, but the most each embodiment only wraps Containing an independent technical scheme, this narrating mode of description is only that for clarity sake those skilled in the art should Description can also be formed those skilled in the art through appropriately combined as an entirety, the technical scheme in each embodiment May be appreciated other embodiments.

Claims (7)

1. a coal mine return air big lane passing fault tunneling construction method, it is characterised in that: comprise the following steps:
Step S1, driving detours, and detours according to original tunnelling, detours vertical with fault strike;
Step S2, reserved rock emits, and calculates and designs rock and emit;
Step S3, slip casting, first carry out material selection, then calculate grouting amount, then carry out drilling design, then to orifice tube It is designed and fixes, last slip casting.
A kind of big lane of coal mine return air the most according to claim 1 passing fault tunneling construction method, it is characterised in that: in step In S2, according to formulaCalculate the thickness that only magmatic rock emits;
In formula: B is rock plug thickness;
P is final grouting pressure;
S is rock cap basal area;
λ is overload factor, and λ takes 1.1-1.2;
[τ] is that rock allows shearing strength;
L is tunnel-surrounding length.
A kind of big lane of coal mine return air the most according to claim 1 passing fault tunneling construction method, it is characterised in that: in step During the material of S3 selects, needing to use single slurry and dual slurry, wherein single slurry uses plasticity early injection pulp material;
Dual slurry uses cement and waterglass mixing, wherein:
Cement: P.O 42.5 Portland cement;
Waterglass: modulus M=2.8~3.1, concentration 30~35 ° of Be'.
A kind of big lane of coal mine return air the most according to claim 1 passing fault tunneling construction method, it is characterised in that: in step In S3, grouting amount calculates according to grouting amount formula:
Q=A × β × η × V;
In formula: the total injection rate of Q serosity (m3);
A serosity super diffusion consumption coefficient takes 1.5;
β serosity volumetric efficiency 0.9;
η fault belt average crack rate 10%;
The rock mass volume that V is noted, m3
The rock mass volume V=S × L noted;
In formula: S is by the basal area of note rock mass;
L is by note rock mass length.
A kind of big lane of coal mine return air the most according to claim 1 passing fault tunneling construction method, it is characterised in that: in step In S3, drilling design refers to use twice pore-forming mode, and hole termination depth determines tomography thickness according to boreholes drilling result, and level is bored Enter length and exceed tomography highest distance position 5m.
A kind of big lane of coal mine return air the most according to claim 1 passing fault tunneling construction method, it is characterised in that: in step In S3, orifice tube is designed and fixes:
Orifice tube uses diameter 70mm welded tube, single long 6m, 7 unilateral band high pressure flanges, and side is threaded, remaining orifice tube, Being bilateral screw thread, flange side adds solder joint;
Orifice tube is fixing in two steps, and the first step enters in boring under orifice tube bond pad locations twines fiber crops, and second step slip casting is carried out Full packages is fixed, and second step terminates, and solidifies more than 8h, after bulge test, carries out secondary pore-forming.
A kind of big lane of coal mine return air the most according to claim 6 passing fault tunneling construction method, it is characterised in that: slip casting Mode is the most single slurry then dual slurry;
In single slurry, first pour plasticity early injection pulp material into massing machine, after stirring, pour stock tank into, at grouting pump Effect under, introduced in boring by high pressure valve and orifice valves;
In dual slurry, first pour cement and water into massing machine, after stirring, pour stock tank into, waterglass is introduced slip casting In pump, under the effect of grouting pump, introduced in boring by high pressure valve and orifice valves;
When slip casting, grouting pressure is 2~2.5 times of hydrostatic pressure;
Slip casting should carry out setting-out experiment, the sealing of testing bore holes and safety before starting, the force value of setting-out experiment is slip casting 1.2~1.5 times of final pressure, when stable 15min is without exception, can start formal mortar depositing construction.
When grouting pressure reaches final grouting pressure value, furnishing 1 grade (16L/min), low discharge voltage stabilizing 20min, this boring can be terminated Slip casting works.
CN201610615757.0A 2016-07-28 2016-07-28 A kind of coal mine return air main entry passing fault tunneling construction method Active CN106223961B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610615757.0A CN106223961B (en) 2016-07-28 2016-07-28 A kind of coal mine return air main entry passing fault tunneling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610615757.0A CN106223961B (en) 2016-07-28 2016-07-28 A kind of coal mine return air main entry passing fault tunneling construction method

Publications (2)

Publication Number Publication Date
CN106223961A true CN106223961A (en) 2016-12-14
CN106223961B CN106223961B (en) 2018-11-06

Family

ID=57535523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610615757.0A Active CN106223961B (en) 2016-07-28 2016-07-28 A kind of coal mine return air main entry passing fault tunneling construction method

Country Status (1)

Country Link
CN (1) CN106223961B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837333A (en) * 2017-01-17 2017-06-13 济宁矿业集团有限公司霄云煤矿 A kind of fully-mechanized mining working pre-tunnel laneway road formula passing fault method
CN107939435A (en) * 2017-12-17 2018-04-20 北京昊华能源股份有限公司 A kind of coal road dash system
CN109057850A (en) * 2018-08-27 2018-12-21 神木县隆德矿业有限责任公司 A kind of novel load-carrying air crossing and return air detour piercing technique
CN113605913A (en) * 2021-09-01 2021-11-05 东莞理工学院 Rock underground passage construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936008A (en) * 2010-09-30 2011-01-05 东北大学 Rock slope three-dimensional model and block slide analysis method
CN102704950A (en) * 2012-06-21 2012-10-03 山东黄金矿业(莱州)有限公司三山岛金矿 Support method used in passing water guide fracture structure in mine exploration
CN103016027A (en) * 2013-01-21 2013-04-03 中南大学 Tunnel or roadway excavating method under weak and broken complicated geological conditions
CN104389516A (en) * 2014-10-15 2015-03-04 武汉高铁桩工科技有限公司 Squeezing enlarging cast-in-situ bored pile hole forming method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936008A (en) * 2010-09-30 2011-01-05 东北大学 Rock slope three-dimensional model and block slide analysis method
CN102704950A (en) * 2012-06-21 2012-10-03 山东黄金矿业(莱州)有限公司三山岛金矿 Support method used in passing water guide fracture structure in mine exploration
CN103016027A (en) * 2013-01-21 2013-04-03 中南大学 Tunnel or roadway excavating method under weak and broken complicated geological conditions
CN104389516A (en) * 2014-10-15 2015-03-04 武汉高铁桩工科技有限公司 Squeezing enlarging cast-in-situ bored pile hole forming method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837333A (en) * 2017-01-17 2017-06-13 济宁矿业集团有限公司霄云煤矿 A kind of fully-mechanized mining working pre-tunnel laneway road formula passing fault method
CN107939435A (en) * 2017-12-17 2018-04-20 北京昊华能源股份有限公司 A kind of coal road dash system
CN109057850A (en) * 2018-08-27 2018-12-21 神木县隆德矿业有限责任公司 A kind of novel load-carrying air crossing and return air detour piercing technique
CN113605913A (en) * 2021-09-01 2021-11-05 东莞理工学院 Rock underground passage construction method

Also Published As

Publication number Publication date
CN106223961B (en) 2018-11-06

Similar Documents

Publication Publication Date Title
CN105651132B (en) Directional static blasting construction method for foundation pit stratum and combined guiding device for directional static blasting construction method
CN108678769A (en) Deep Gateway anchor note cuts top master control and stays lane method
CN108071405B (en) A kind of brutal method for protecting support such as coal mine rectangular shaped roadways top plate
CN109098714A (en) A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three
CN104632220B (en) Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN102182471B (en) Advance support method for coal mine tunnel high-risk area
CN106223961A (en) A kind of coal mine return air big lane passing fault tunneling construction method
CN103821538B (en) J-type horizontal assistant branched hole surface advance grouting paste-making method
CN105545353B (en) A kind of Man-made False construction method based on paste body filling
CN111734482A (en) Method for reducing damage by utilizing gangue cementation and bag grouting combined support
CN102071940A (en) Construction method for mine shaft through multilayer goaf
CN104033151A (en) Safe mining method of ten million-ton mine under complicated conditions of dual-system coal seams
CN104370508B (en) A kind of mine floor grouting in rock mass reinforcement means and grouting serous fluid
CN105781551A (en) Horizontal strip type mixed filling mining method applicable to three-underground orebody mining
CN108487924B (en) A kind of reinforcement means of soft coal level gob side entry driving thin coal pillar
CN103306713A (en) Networking reinforcement method for cross drilling holes of outburst coal seam
CN106979012A (en) Hidden conduit pipe Comprehensive Treatment method in shaft of vertical well freezing hole
CN112240221B (en) Gas extraction method based on directional long drill hole
CN104763434A (en) Non-coal-pillar double tunneling method
CN102878874A (en) Deep-hole pre-splitting blasting grouting method
CN109057798A (en) A kind of wall type filling mining method suitable for gently inclined phosphate body bed
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
Xue et al. Deformation failure mechanism and application of the backfill along the goaf-side retained roadway
CN109611146A (en) A kind of unrestrained grouting method of absciss layer water
CN104265294A (en) Coal pillar-free mining technology for blasting mining face of steeply dipping seam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant