CN106223619A - Building pours uses dump skip - Google Patents

Building pours uses dump skip Download PDF

Info

Publication number
CN106223619A
CN106223619A CN201610565534.8A CN201610565534A CN106223619A CN 106223619 A CN106223619 A CN 106223619A CN 201610565534 A CN201610565534 A CN 201610565534A CN 106223619 A CN106223619 A CN 106223619A
Authority
CN
China
Prior art keywords
storage bin
bin hopper
dump skip
steel
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610565534.8A
Other languages
Chinese (zh)
Inventor
焦炳烨
张连中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201610565534.8A priority Critical patent/CN106223619A/en
Publication of CN106223619A publication Critical patent/CN106223619A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/025Buckets specially adapted for use with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

The invention discloses a kind of building and pour use dump skip, including the steel funnel being made up of storage bin hopper and steel pipe, the discharging opening of described storage bin hopper is fixedly installed steel pipe;The other end of steel pipe is fixing connects a valve, the other end socket conveying pipeline of described valve.Described conveying pipeline is rubber tube.By valve, steel funnel and plastic tube are connected as entirety, conveniently move integrally dump skip and be easy to construction, simultaneously, plastic tube is that rubber tube is easily buied, and the wear-resistant rotproofness of rubber tube can repeated multiple times use, rubber tube also has elasticity, and when pouring, the convenient oral area controlling rubber tube makes it be directed in template to be poured, and simple to operate is easily controlled.This dump skip simple in construction, easily makes, and material requested is easy to get, it is possible to reuse, and simple to operate can use the most flexibly, thus saves a large amount of men hoisting efficiency of construction, reduces construction cost.

Description

Building pours uses dump skip
Technical field
The invention belongs to the realm of building construction, the ring beam and construction column concrete being specifically related to secondary structure in construction waters Build or other pouring material construction time use dump skip.
Background technology
In construction, the ring beam and construction column concrete of secondary structure or other pouring material are to use steel funnel and wooden unload Hopper completes to pour, and steel funnel separates with wooden blowpit, and often pouring a position will be with artificial mobile wooden discharging Groove, time-consuming takes a lot of work, and production efficiency is relatively low, affects construction speed, and wooden blowpit to be easily damaged repeat usage low, increase is executed Work cost, uses the steel funnel separated and wooden blowpit to pour and bring inconvenience to construction.
Summary of the invention
In order to improve work efficiency, saving labour force, easy-unloading is constructed, and the present invention provides a kind of building to pour and uses discharging Bucket, this dump skip connects rubber conveying pipeline by valve, by pouring in Valve controlling steel hopper at the discharging opening of steel hopper Material is directly poured pouring in material inputs template to be poured by rubber conveying pipeline.Rubber conveying pipeline is connected to steel material As overall thus be moved easily on Dou, and conveying pipeline uses rubber tube to have the wear-resistant feature such as corrosion-resistant to be hardly damaged repetition Utilization rate is higher, and rubber tube has elasticity easy conveniently moving when pouring and discharging opening alignment is treated formwork for placing.
This invention is achieved through the following technical solutions:
Building pours uses dump skip, and including steel funnel, described steel funnel includes storage bin hopper and steel pipe, and described storage bin hopper is the end of by Plate, left plate, right plate, top board and back side panel enclose structure and form, and the front end of storage bin hopper is provided with a discharging opening, on the rear end of storage bin hopper Portion offers a charging door;The discharging opening of described storage bin hopper is fixedly installed described steel pipe;The other end of described steel pipe fixes connection one Valve, the other end socket conveying pipeline of described valve.
Further, being moved easily in order to reuse, described conveying pipeline is rubber tube simultaneously.
Further, lifting by crane for convenience and prevent pouring material simultaneously and spill in steel funnel, the top board of described storage bin hopper is solid Surely arranging a hanger, the both sides, back side panel top of described storage bin hopper are respectively fixedly installed a hanger and lay respectively at described charging door Both sides;It is fixedly installed steel wire rope on described each hanger, and the steel wire rope being positioned on the hanger of storage bin hopper charging door both sides is than storage On hopper top board, the steel wire rope on hanger is short, to ensure that steel funnel has certain angle of inclination when slinging.
Further, manual grasping, the left plate of described storage bin hopper and right plate are respectively fixedly installed a handle for convenience.
Further, described steel pipe is fixed with described standard.
Beneficial effects of the present invention:
The dump skip of the present invention is connected as entirety steel funnel by valve and conveying pipeline, has poured rear at a position Just lower dump skip is moved integrally next one position to be poured;Conveying pipeline uses rubber tube anticorrosive anti-wear can be suitable for weight Multiple use, rubber tube has the elastic convenient discharging opening that adjusts makes its alignment template pour.This dump skip simple in construction, easily Make, reusable, save construction material;In work progress simple to operate, job site can use flexibly;Can overall turn Move and save labour force, improve work efficiency, reduce construction cost.
Accompanying drawing explanation
Fig. 1 is to build to pour to use dump skip structural representation;
Description of reference numerals:
1-steel funnel;11-storage bin hopper;111-charging door;112-hanger;
113-handle;12-steel pipe;2-valve;3-conveying pipeline.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing, the present invention is described in further detail.
As it is shown in figure 1, building pours uses dump skip, including steel funnel 1, described steel funnel 1 includes storage bin hopper 11 and steel pipe 12.Described storage bin hopper 11 pours material for storage, and it is enclosed structure by base plate, left plate, right plate, top board and back side panel and forms.Storage The mould material that the front end of hopper 11 is provided with in a discharging opening storage bin hopper 11 flows out from this discharging opening, the upper rear end of storage bin hopper 11 Offer a charging door 111 for pouring into mould material.The top board of described storage bin hopper 11 is fixedly installed a hanger 112, described storage The both sides, back side panel top of hopper 11 are respectively fixedly installed a hanger 112, two hangers 112 points on the back side panel of storage bin hopper 11 It is not positioned at the both sides of charging door on described storage bin hopper 11.It is fixedly installed steel wire rope (not shown) on described each hanger 112, And the steel wire rope that is positioned on the hanger of storage bin hopper charging door 111 both sides is shorter than the steel wire rope on storage bin hopper top board hanger, to ensure steel Funnel 1 has certain angle of inclination when slinging, prevent pouring material and spill from the charging door 111 of steel funnel.Described storage bin hopper 11 Left plate and right plate on be respectively fixedly installed a handle 113, the setting of handle 113 makes dump skip at mobile or casting process In facilitate operator to grasp handle 113 to control dump skip position.
The discharging opening 111 of described storage bin hopper is fixedly installed described steel pipe 12, and in the present embodiment, steel pipe 12 is welded in storage bin hopper The discharging opening of 11 is solid and reliable.The other end of described steel pipe 12 is fixing connects a valve 2, in the present embodiment, described steel pipe 12 with Described valve 2 is welded and fixed.The other end socket conveying pipeline 3 of described valve 2, in the present embodiment, conveying pipeline 3 colligation is at valve 2 On.Described conveying pipeline 3 is that rubber tube is wear-resistant corrosion-resistant, and has elasticity and make operator easily move conveying pipeline 3 thus defeated The mouth of pipe alignment of material pipe 3 pours in needing the template poured.On described steel pipe 12 weld valve 2, valve 2 again with conveying pipeline 3 connect, and valve 2 pours, easily in flowing into template as the mould material in on-off control storage bin hopper 11 by conveying pipeline 3 Operation.Conveying pipeline 3 uses rubber tube the most wear-resistant corrosion-resistant, and have elasticity make operator easily move conveying pipeline 3 thus Pouring in the mouth of pipe of conveying pipeline 3 is directed at the template needing to pour, conveying pipeline 3 is socketed on valve 2, when conveying pipeline 3 damages In bad time, easily dismounts.This dump skip simple in construction, easily prepares, and is connected as one by 2 steel funnels 1 of valve and conveying pipeline 3 Entirety, can rely on plant equipment easily overall easily mobile discharge bucket in operation process, use manpower and material resources sparingly, it is ensured that construction Progress, and this dump skip recycling rate of waterused is high, can effectively reduce construction cost.
It is as follows that this building pours the step carrying out pouring with dump skip:
The first step, closes valve 2, and the material then poured by needs loads in steel funnel 1.
Second step, penetrates the hanger of steel funnel by wire-rope sling.On storage bin hopper, the steel wire rope of charging door 111 both sides should compare Steel wire rope on storage bin hopper end face is short, to ensure that steel funnel 11 has certain angle of inclination when slinging, prevents from pouring material from steel Spread out in funnel 11.
3rd step, will be equipped with pouring the position that the dump skip of material winches to need to pour, conveying pipeline 3 mouth of pipe with crane gear In alignment template, open valve 2 and can start to pour.
4th step, closes valve, dump skip winches to ground after having poured, repeat the above steps carries out next position Pour.
In the construction of relatively traditional architecture the ring beam and construction column concrete of secondary structure or other pouring material be use steel funnel and Wooden blowpit completes to pour, and steel funnel separates with wooden blowpit, and often pouring a position will be with artificial mobile wood Matter blowpit, time-consuming takes a lot of work, and production efficiency is relatively low, and wooden blowpit repeat usage is low, fragile, brings many to construction Inconvenience.The dump skip of the present invention uses steel funnel to combine one entirety of formation with rubber tube, simplifies operational procedure, it is simple to Operation, time saving and energy saving, and processing and fabricating material is easy to get, and reusable, significantly reduce construction cost.

Claims (5)

1. a building pours with dump skip, it is characterised in that: include that steel funnel, described steel funnel include storage bin hopper and steel pipe, Described storage bin hopper is enclosed structure by base plate, left plate, right plate, top board and back side panel and forms, and the front end of storage bin hopper is provided with a discharging opening, The upper rear end of storage bin hopper offers a charging door;The discharging opening of described storage bin hopper is fixedly installed described steel pipe;Described steel pipe another One end is fixing connects a valve, the other end socket conveying pipeline of described valve.
Building the most according to claim 1 pours with dump skip, it is characterised in that: described conveying pipeline is rubber tube.
Building the most according to claim 1 pours with dump skip, it is characterised in that: the top board of described storage bin hopper is fixedly installed One hanger, the both sides, back side panel top of described storage bin hopper are respectively fixedly installed a hanger and lay respectively at the two of described charging door Side;It is fixedly installed steel wire rope on described each hanger, and the steel wire rope being positioned on the hanger of storage bin hopper charging door both sides compares storage bin hopper On top board, the steel wire rope on hanger is short.
Building the most according to claim 1 pours with dump skip, it is characterised in that: the left plate of described storage bin hopper and right side A handle respectively it is fixedly installed on plate.
Building the most according to claim 1 pours with dump skip, it is characterised in that: described steel pipe is solid with described standard Fixed.
CN201610565534.8A 2016-07-18 2016-07-18 Building pours uses dump skip Pending CN106223619A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610565534.8A CN106223619A (en) 2016-07-18 2016-07-18 Building pours uses dump skip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610565534.8A CN106223619A (en) 2016-07-18 2016-07-18 Building pours uses dump skip

Publications (1)

Publication Number Publication Date
CN106223619A true CN106223619A (en) 2016-12-14

Family

ID=57530939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610565534.8A Pending CN106223619A (en) 2016-07-18 2016-07-18 Building pours uses dump skip

Country Status (1)

Country Link
CN (1) CN106223619A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424986A (en) * 2020-05-08 2020-07-17 中国二十二冶集团有限公司 Concrete pouring and conveying device in high-altitude narrow capping space and construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201835532U (en) * 2010-11-01 2011-05-18 刘永强 Concrete grouting hopper
CN201850770U (en) * 2010-03-26 2011-06-01 周树新 Concrete conveyer
CN202012201U (en) * 2011-01-25 2011-10-19 刘立新 Building mortar bucket
CN202176116U (en) * 2011-07-07 2012-03-28 中建五局土木工程有限公司 Mortar and concrete conveying device
CN203546724U (en) * 2013-11-04 2014-04-16 中山银河管道有限公司 Auxiliary grouting device for PCCP
CN203947778U (en) * 2014-04-10 2014-11-19 田艺儿 A kind of concrete aggregate bucket
CN204059977U (en) * 2014-07-30 2014-12-31 中煤第五建设有限公司 Mortar dump skip
CN204456894U (en) * 2015-02-15 2015-07-08 河北联合大学 Simple and easy pressure grouting device
CN204728711U (en) * 2015-05-23 2015-10-28 黄慎想 A kind of grouting machine
CN204781979U (en) * 2015-06-17 2015-11-18 中交一公局第四工程有限公司 Self -compaction slabstone concrete distributing device
CN204983666U (en) * 2015-05-11 2016-01-20 中天建设集团有限公司 High altitude slurry matter transport hopper
CN205172032U (en) * 2015-12-02 2016-04-20 东莞胜特建筑科技开发有限公司 A concrete device for repairing wall body

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201850770U (en) * 2010-03-26 2011-06-01 周树新 Concrete conveyer
CN201835532U (en) * 2010-11-01 2011-05-18 刘永强 Concrete grouting hopper
CN202012201U (en) * 2011-01-25 2011-10-19 刘立新 Building mortar bucket
CN202176116U (en) * 2011-07-07 2012-03-28 中建五局土木工程有限公司 Mortar and concrete conveying device
CN203546724U (en) * 2013-11-04 2014-04-16 中山银河管道有限公司 Auxiliary grouting device for PCCP
CN203947778U (en) * 2014-04-10 2014-11-19 田艺儿 A kind of concrete aggregate bucket
CN204059977U (en) * 2014-07-30 2014-12-31 中煤第五建设有限公司 Mortar dump skip
CN204456894U (en) * 2015-02-15 2015-07-08 河北联合大学 Simple and easy pressure grouting device
CN204983666U (en) * 2015-05-11 2016-01-20 中天建设集团有限公司 High altitude slurry matter transport hopper
CN204728711U (en) * 2015-05-23 2015-10-28 黄慎想 A kind of grouting machine
CN204781979U (en) * 2015-06-17 2015-11-18 中交一公局第四工程有限公司 Self -compaction slabstone concrete distributing device
CN205172032U (en) * 2015-12-02 2016-04-20 东莞胜特建筑科技开发有限公司 A concrete device for repairing wall body

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424986A (en) * 2020-05-08 2020-07-17 中国二十二冶集团有限公司 Concrete pouring and conveying device in high-altitude narrow capping space and construction method

Similar Documents

Publication Publication Date Title
CN202390843U (en) Fixing platform of guide pipe for pouring cast pile
CN106087698B (en) Portable construction operation platform of bored pile
CN102102365A (en) Slurry protection wall bored pile concrete casting device
CN203583655U (en) Inspection well dredging and cleaning machine
CN109736572A (en) The secondary structure concreting method of limited space and device
CN207419261U (en) A kind of stayed bridge pylon cable concrete distributing device
CN106223619A (en) Building pours uses dump skip
CN102352628A (en) Cast-in-place pile concrete guide pipe mounting and dismounting device and construction method thereof
CN208329633U (en) A kind of construction concrete conveyance tower crane hopper
CN206681013U (en) A kind of high slope large-span concrete position in storehouse rotates and pours device
CN215168139U (en) Concrete overhead hoist
CN207072028U (en) Small-sized mixing station with enhanced feature
CN212866902U (en) Inclined three-way pipe for pouring concrete in funnel tank
CN205527498U (en) Utilize pulley system's hoist and mount and conveyer
CN209721363U (en) A kind of lifting pipeline auxiliary device
CN211974377U (en) Concrete distributing device
CN204551442U (en) A kind of reinforcing bar cage hoisting movable hook
JP7370213B2 (en) Concrete pouring hopper
CN208748610U (en) A kind of slope stone masonry raw material construction masonry integrated apparatus
CN202368985U (en) Material shifting funnel
KR101315006B1 (en) Supply Device of Concrete Mortar for Transmission Iron Tower Base
CN205036086U (en) A hopper for concreting
CN206144161U (en) Equipment of pouring little component concrete is exclusively used in
CN203394060U (en) Concrete transporting device for bridge construction
CN213709105U (en) Asphalt transportation turnover device for building construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161214

RJ01 Rejection of invention patent application after publication