CN106194255A - Tunnel waterproof and water drainage system and method for construction thereof - Google Patents

Tunnel waterproof and water drainage system and method for construction thereof Download PDF

Info

Publication number
CN106194255A
CN106194255A CN201610821516.1A CN201610821516A CN106194255A CN 106194255 A CN106194255 A CN 106194255A CN 201610821516 A CN201610821516 A CN 201610821516A CN 106194255 A CN106194255 A CN 106194255A
Authority
CN
China
Prior art keywords
tunnel
drainage
ring direction
sealing rod
direction drainpipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610821516.1A
Other languages
Chinese (zh)
Other versions
CN106194255B (en
Inventor
张国柱
刘松玉
马海涛
夏才初
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Publication of CN106194255A publication Critical patent/CN106194255A/en
Application granted granted Critical
Publication of CN106194255B publication Critical patent/CN106194255B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel waterproof and water drainage system and method for construction thereof, including the drainage blanket between Tunnel and secondary lining, transition zone and waterproof layer, transverse drain and central drain etc..Wherein, drainage blanket includes permeable gunite concrete, longitudinal drainage pipe, ring direction drainpipe and sealing rod, longitudinal drainage pipe, ring direction drainpipe and sealing rod are fixed on preliminary bracing outer surface, and preliminary bracing is carried out disposal precinct, and pervious concrete is injected in each drainage.It is connected by transverse drain between ring direction drainpipe with central drainage pipe, ultimately forms tunnel drainage system.Transition zone and waterproof layer are made up of the gunite concrete of different gradation, for tunnel water proofing.The present invention utilizes drain pipe and permeable gunite concrete to form tunnel solid drainage channel, and tunnel drainage is effective;Tunnel waterproof and water drainage system is integrated with tunnel structure, and long service performance is good.

Description

Tunnel waterproof and water drainage system and method for construction thereof
Technical field
The present invention relates to a kind of tunnel structure, be specifically related to a kind of tunnel waterproof and water drainage system and method for construction thereof.
Background technology
Percolating water is the modal disease of operation tunnel, and it is aging that Tunnel Infiltration water not only speeds up tunnel structure, shortens tunnel The service life of structure, also add tunnel operation maintenance cost, and threatens the traffic safety in tunnel.Especially at cold district, Tunnel Water Leakage also can cause freezing damage in tunnel, aggravation tunnel structure to destroy;And cause Tunnel wall hanging ice, icy on road, seriously Threaten tunnel traffic safety.Must fundamentally solve treatment technology for tunnel seepage water problems.
Regulation in " vcehicular tunnel design specification ": " when tunnel uses composite lining, supporting in the early stage and secondary lining it Between splash guard and non-woven fabrics should be set, splash guard should use be prone to welding waterproof roll, thickness be not less than 1.0mm;Along lining cutting Hoop should arrange water guide blind pipe behind, and its longitudinal pitch is not more than 20m ".Splash guard is the important defence line of tunnel water proofing, once prevents Water plate destroys, and subsoil water will transmit through splash guard, flows out along construction joint of tunnel, movement joint and structural cracks, forms tunnel Percolating water.Existing anchor bar of waterproof plate in tunnels is the most destroyed in construction and operation, and the reason causing splash guard to destroy is as follows: 1. tunnel Road preliminary bracing is gunite concrete, and gunite concrete surface ridge often occurs or has termination point of anchor rod exposure, can puncture anti- Water plate;2. often there is the changing of the relative positions in Tunnel and secondary lining, often results between preliminary bracing and two lining lining cutting Splash guard tear.The most adjacent splash guard uses hot-melt adhesive paste, connects effect by construction environment, construction level and management level Deng multifactor impact, welding position often occurs that not prison welding is leaned on, and the middle generation changing of the relative positions, forms drainage channel under arms.4. tunnel is worked as During road breaking out of fire, water-proof sheet material easily softens inefficacy.5. water-proof sheet material service life is about 60 years, and tunnel runs and year is limited to 100 Year, splash guard cannot meet tunnel long service requirement.Based on above-mentioned background, research and development novel tunnel guarded drainage technology just becomes urgently Technical problem to be solved.
Summary of the invention
Goal of the invention: in order to overcome the deficiencies in the prior art, the present invention provide a kind of tunnel waterproof and water drainage system and Its method of construction.
Technical scheme: for solving above-mentioned technical problem, the tunnel waterproof and water drainage system of present invention offer and method of construction thereof, bag Include the drainage blanket between Tunnel and secondary lining, transition zone and waterproof layer, transverse drain and Central Drainage Pipe (or gutter) etc..Described drainage blanket includes permeable gunite concrete, longitudinal drainage pipe, ring direction drainpipe and sealing rod, Described longitudinal drainage pipe, ring direction drainpipe and sealing rod are fixed on preliminary bracing outer surface, and preliminary bracing is carried out draining Subregion, described pervious concrete is injected in each drainage, and the coarse aggregate of pervious concrete is porous lightweight aggregate.
Specifically, ring direction drainpipe and sealing rod in described drainage blanket are laid at equal intervals in tunnel axis direction, sealing The installation position of bar aligns with Second Lining Construction seam, and ring direction drainpipe is laid in the centre of adjacent sealing rod;Ring direction drainpipe Being connected by longitudinal drainage pipe with between sealing rod, longitudinal drainage pipe is arranged in " V " shape in ring direction drainpipe both sides, is laid in respectively At arch, tunnel, abutment wall and arch springing;Ring direction drainpipe is directly connected by transverse drain with Central Drainage (or gutter) pipe Connect;Longitudinal drainage pipe and ring direction drainpipe are draining semicanal.
Specifically, heating plant is installed in described ring direction drainpipe or both sides, and described heating plant can be according to antifreeze need Change time realistic.
Specifically, described transition zone is the thickness specified density concrete being injected on drainage blanket.
Specifically, described waterproof layer is the impervious concrete being injected on transition zone.
The present invention proposes the method for construction of above-mentioned tunnel waterproof and water drainage system simultaneously, comprises the following steps:
Step 1, lays ring direction drainpipe, longitudinal drainage pipe and sealing rod on Tunnel surface or country rock surface, Sealing rod is corresponding with the construction joint of secondary lining, and ring direction drainpipe is then positioned at the centre of adjacent sealing rod.Sealing rod is arranged with hoop Water pipe is connected by longitudinal drainage pipe, and longitudinal drainage pipe is arranged in ring direction drainpipe lateral symmetry, arranges in V-shape, and longitudinally row The gradient of water pipe is not less than 2%.Longitudinal drainage pipe is laid at arch, tunnel, abutment wall and arch springing respectively, with sealing rod and hoop Drain pipe carries out disposal precinct to Tunnel outer surface;
Step 2, connects ring direction drainpipe, transverse drain and central drain (or gutter);
Step 3, sprays pervious concrete in each disposal precinct, and the thickness of pervious concrete is less than longitudinal drainage semicanal Radius;
Step 4, sprays thickness specified density concrete at drainage blanket outer surface, as transition zone;
Step 5, sprays certain thickness impervious concrete at transition zone outer surface, as waterproof layer;
Step 6, seals the waterstop at sealing rod and Second Lining Construction seam and pastes, carry out water-proofing treatment;
Step 7, pours into a mould two lining concrete outside waterproof layer.The technical essential of said structure and method of construction is as follows:
1. sealing rod, ring direction drainpipe and longitudinal drainage pipe are laid on Tunnel surface or country rock surface, longitudinally Drain pipe should be tightly connected with sealing rod, and longitudinal drainage pipe top half has osculum, and the latter half is then without osculum;Longitudinally row Water pipe is arranged in ring direction drainpipe lateral symmetry, arranges in V-shape, and the gradient of longitudinal drainage pipe is not less than 2%.Sealing rod and Longitudinal drainage pipe carries out disposal precinct to preliminary bracing surface, and each disposal precinct answers individual drainage.
2. ring direction drainpipe, transverse drain and central drain (or gutter) are connected, in order to ensure waterproof effect, Every plate secondary lining individual drainage, the subsoil water in ring direction drainpipe is in line to central drain (or row by transverse drain Waterside ditch);
3. spraying pervious concrete in each disposal precinct, the thickness of pervious concrete is less than the half of longitudinal drainage semicanal Footpath;
4. above pervious concrete, spray thickness specified density concrete, as transition zone, work progress should control Expulsion pressure and aggregate size, draining concrete permeable hole plug in prevention drainage blanket;
5. spraying certain thickness impervious concrete above transition zone, as waterproof layer, waterproof layer should cover bag comprehensively Wrap up in longitudinal drainage pipe;
6. the waterstop at sealing rod and Second Lining Construction seam is sealed and paste, it is necessary to carry out water-proofing treatment;
7. construction secondary lining concrete.
Inventive principle: lay ring direction drainpipe, longitudinal drainage pipe and sealing rod, shape at Tunnel or country rock surface Become unobstructed drainage network, utilize longitudinal drainage pipe and sealing rod that Tunnel surface carries out disposal precinct, each draining Subsoil water in subregion is without hydraulic connection.Pervious concrete is sprayed, for collecting enclosing in each drainage in disposal precinct Rock crevice water, and be emitted in circle draining pipeline.Drainage network and permeable gunite concrete form the drainage channel of solid, ring Subsoil water in drainage pipeline is immediately discharged in central drain (or gutter) by transverse drain.In order to prevent Water gunite concrete is blocked, sprays thickness specified density concrete, as transition zone above pervious concrete;At transition zone Top injection impervious concrete, as waterproof layer;Drainage channel, transition zone and waterproof layer is utilized to define tunnel water handling system System, this system utilizes the infiltration diversity of different compound gunite concrete, and fixes a drainpipe in gunite concrete structure, Thus formed tunnel injection xoncrete structure from waterproof and water drainage system, tunnel shotcrete layer is i.e. supporting member, is again anti-row Water-bound.At cold district, ring direction drainpipe planted agent installs heater, and the light bone of porous selected by the coarse aggregate of pervious concrete Material, pre-waterproof and water drainage system freezes.
Beneficial effect: the present invention utilizes drainage pipeline, sealing rod and permeable gunite concrete to realize the draining of subregion, tunnel, Drainage effect is good, it is simple to operation maintenance;Ring direction drainpipe directly connects central drain by transverse drain, it is ensured that every plate two Subsoil water in lining is directly discharged in central drain (or gutter), and every plate two lining is independent drainage cell, row Water is effective, facilitates seepage water source to search, facilitates operation maintenance;The infiltration of the different compound gunite concrete of this system utilization is poor The opposite sex, forms permeable shotcrete layer and antiseepage shotcrete layer, it is achieved drainage system and tunnel structure integration, for a long time Military service performance is good, and service life is identical with tunnel lining structure;This drainage system is concrete material, and tunnel fire hazard does not interferes with Its military service performance.Heater is installed in ring direction drainpipe, it is ensured that under cold climate conditions, drainage system is unobstructed does not freezes; Utilize porous lightweight aggregate as coarse aggregate, the frost-heave force that the subsoil water in pervious concrete freezes to produce can be eliminated.
Except invention described above solves the technical problem that, constitutes the technical characteristic of technical scheme and by these skills Outside the advantage that the technical characteristic of art scheme is brought, the tunnel waterproof and water drainage system of the present invention and method of construction thereof can solve its The advantage that the other technologies feature comprised in he technical problem, technical scheme and these technical characteristics bring, will be in conjunction with accompanying drawing It is described in more detail.
Accompanying drawing explanation
Fig. 1 is Fig. 1 tunnel cross section figure of the embodiment of the present invention
Fig. 2 is the drainage blanket plane outspread drawing in Fig. 1
In figure: 1. preliminary bracing;2. drainage blanket;3. transition zone;4. waterproof layer;5. secondary lining;6. longitudinal drainage pipe;7. Transverse drain;8. central drain;9. ring direction drainpipe;10. sealing rod;11. permeable gunite concretes.
Detailed description of the invention
Embodiment:
The tunnel waterproof and water drainage system of the present embodiment as it is shown in figure 1, set gradually in including tunnel preliminary bracing 1, draining Layer 2, transition zone 3, waterproof layer 4 and secondary lining 5, and the transverse drain 7 of tunnel bottom and central drain 8.
Mix as in figure 2 it is shown, drainage blanket 2 is internal containing longitudinal drainage pipe 6, ring direction drainpipe 9, sealing rod 10 and permeable injection Solidifying soil 11.Longitudinal drainage pipe 6 is connected with ring direction drainpipe 9 and sealing rod 10, transverse drain 7 connect ring direction drainpipe 9 and in Centre drain pipe 8.
It is as follows that step is implemented in the construction of said structure:
1. cleaning Tunnel surface or country rock surface, lays sealing rod 10, ring direction drainpipe 9 and longitudinal drainage pipe 6.Connect longitudinal drainage pipe 6, ring direction drainpipe 9 and sealing rod 10;
2. ring direction drainpipe 9, transverse drain 7 and central drain 8 are connected;
3. in the drainage that longitudinal drainage pipe 6 and sealing rod 10 surround, spray pervious concrete 11;
4. thickness specified density concrete is sprayed at drainage blanket 2 outer surface, as transition zone 3;
5. certain thickness impervious concrete is sprayed at transition zone 3 outer surface, as waterproof layer 4;
6. outside waterproof layer, pour into a mould secondary lining 5 concrete.
Above in association with accompanying drawing, embodiments of the present invention are described in detail, but the present invention is not limited to described reality Execute mode.For those of ordinary skill in the art, in the range of the principle and technological thought of the present invention, these are implemented Mode carries out multiple change, revises, replaces and deformation still falls within protection scope of the present invention.

Claims (6)

1. a tunnel waterproof and water drainage system, including the drainage blanket between Tunnel and secondary lining, transition zone and Waterproof layer, it is characterised in that: described drainage blanket includes permeable gunite concrete, longitudinal drainage pipe, ring direction drainpipe and sealing rod, Described longitudinal drainage pipe, ring direction drainpipe and sealing rod are fixed on preliminary bracing outer surface, and preliminary bracing is carried out draining Subregion, described pervious concrete is injected in each drainage, and the coarse aggregate of pervious concrete is porous lightweight aggregate.
Tunnel waterproof and water drainage system the most according to claim 1, it is characterised in that: the ring direction drainpipe in described drainage blanket Laying at equal intervals in tunnel axis direction with sealing rod, the installation position of sealing rod aligns with Second Lining Construction seam, and hoop is arranged Water pipe is laid in the centre of adjacent sealing rod;It is connected by longitudinal drainage pipe between ring direction drainpipe with sealing rod, longitudinal drainage pipe In the V-shaped layout in ring direction drainpipe both sides, longitudinal drainage pipe is laid at arch, tunnel, abutment wall and arch springing;Ring direction drainpipe with Central drain or gutter are directly connected to by transverse drain;Longitudinal drainage pipe and ring direction drainpipe are draining half Pipe.
Tunnel waterproof and water drainage system the most according to claim 2, it is characterised in that: in described ring direction drainpipe or both sides peace Equipped with heating plant.
Tunnel waterproof and water drainage system the most according to claim 1, it is characterised in that: described transition zone is to be injected on drainage blanket Thickness specified density concrete.
Tunnel waterproof and water drainage system the most according to claim 1, it is characterised in that: described waterproof layer is to be injected on transition zone Impervious concrete.
The method of construction of tunnel waterproof and water drainage system the most according to claim 1, it is characterised in that comprise the following steps:
Step 1, lays ring direction drainpipe, longitudinal drainage pipe and sealing rod, sealing on Tunnel surface or country rock surface Bar aligns with the construction joint of secondary lining, and ring direction drainpipe is then positioned at the centre of adjacent sealing rod;Sealing rod and ring direction drainpipe Being connected by longitudinal drainage pipe, longitudinal drainage pipe is arranged in ring direction drainpipe lateral symmetry, arranges in V-shape, and longitudinal drainage pipe The gradient be not less than 2%, longitudinal drainage pipe is laid at arch, tunnel, abutment wall and arch springing respectively, with sealing rod and ring direction drainpipe Tunnel outer surface is carried out disposal precinct;
Step 2, connects ring direction drainpipe, transverse drain and central drain or gutter;
Step 3, sprays pervious concrete in each disposal precinct, and the thickness of pervious concrete is less than the half of longitudinal drainage semicanal Footpath;
Step 4, sprays thickness specified density concrete at drainage blanket outer surface, as transition zone;
Step 5, sprays certain thickness impervious concrete at transition zone outer surface, as waterproof layer;
Step 6, seals the waterstop at sealing rod and Second Lining Construction seam and pastes, carry out water-proofing treatment;
Step 7, pours into a mould two lining concrete outside waterproof layer.
CN201610821516.1A 2016-08-31 2016-09-13 Tunnel waterproof and water drainage system and its method of construction Active CN106194255B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610785329 2016-08-31
CN2016107853292 2016-08-31

Publications (2)

Publication Number Publication Date
CN106194255A true CN106194255A (en) 2016-12-07
CN106194255B CN106194255B (en) 2017-11-03

Family

ID=58067692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610821516.1A Active CN106194255B (en) 2016-08-31 2016-09-13 Tunnel waterproof and water drainage system and its method of construction

Country Status (1)

Country Link
CN (1) CN106194255B (en)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869998A (en) * 2017-03-09 2017-06-20 同济大学 Hydraulic pressure fractured zones tunnel high carries the emergent intelligent drainage system of clearing function
CN107100671A (en) * 2017-05-31 2017-08-29 中铁七局集团第三工程有限公司 A kind of pressure surface shape of tunnel rich water country rock, which drops down, draws drainage mechanism in adfluxion
CN107227974A (en) * 2017-06-20 2017-10-03 中铁十局集团第四工程有限公司 A kind of tunnel-liner discharge structure and water discharge method
CN107780949A (en) * 2017-10-13 2018-03-09 北京工业大学 A kind of steel FRP complex waves card tunnel support method
CN107916945A (en) * 2017-12-07 2018-04-17 中铁岩锋成都科技有限公司 Using the waterproof spray-up structure and its construction method of impervious gunite concrete
CN108222979A (en) * 2017-12-29 2018-06-29 中铁二局第工程有限公司 Rich water karst waterproof and Drainage Construction of Tunnel method
CN108661674A (en) * 2018-07-19 2018-10-16 中国铁路设计集团有限公司 A kind of high hydraulic pressure tunnel sluicing voltage-dropping type is pre-buried to safeguard grouting device
CN109026144A (en) * 2018-07-27 2018-12-18 北京交通大学 A kind of seabed tunnel active control type guarded drainage System Design method and system
CN109281334A (en) * 2018-10-31 2019-01-29 中建科技有限公司 Underground pipe gallery waterproof construction
CN109296389A (en) * 2018-12-10 2019-02-01 潘晓东 A kind of freeway tunnel jet printing type guarded drainage construction and method
CN110130981A (en) * 2019-07-02 2019-08-16 济南市坤鹏技术开发中心 A kind of tunnel construction safe construction method
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110469365A (en) * 2019-08-22 2019-11-19 西南交通大学 A kind of tunnel-liner large area percolating water ejectment device and construction method
WO2019237908A1 (en) * 2018-06-12 2019-12-19 济南城建集团有限公司 Blocking and drainage combined treatment method for water leakage at construction joint of secondary lining of tunnel
CN110761815A (en) * 2019-11-12 2020-02-07 中铁工程设计咨询集团有限公司 Tunnel negative-pressure laying waterproof plate and construction method thereof
CN110878700A (en) * 2019-12-05 2020-03-13 福建鑫远建工有限公司 Tunnel waterproof structure and construction method thereof
CN111271101A (en) * 2020-03-30 2020-06-12 中铁二院工程集团有限责任公司 Tunnel bottom structure system suitable for reconstruction in tunnel operation state and construction method thereof
CN111425249A (en) * 2020-03-30 2020-07-17 中铁二院工程集团有限责任公司 Tunnel wind power drainage system
CN111608727A (en) * 2020-06-08 2020-09-01 哈尔滨工业大学 Cold region mountain tunnel composite drainage system and construction method thereof
CN111963214A (en) * 2020-07-17 2020-11-20 中交一公局集团有限公司 Tunnel molding waterproof construction process
CN112081607A (en) * 2020-10-28 2020-12-15 中国电建集团贵阳勘测设计研究院有限公司 Tunnel primary support and waterproof and drainage combined system and construction method
CN114352308A (en) * 2022-01-13 2022-04-15 中化学交通建设集团有限公司 Tunnel entrance to a cave section is prevented drainage and reinforced structure
CN114412565A (en) * 2022-01-26 2022-04-29 中国有色金属工业昆明勘察设计研究院有限公司 Plugging and dredging device suitable for water burst and mud burst in tunnel

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0898052A1 (en) * 1997-08-15 1999-02-24 Köster Bauchemie Gmbh Method of sealing a subterranean formation against the penetration of water
CN101614129A (en) * 2009-08-10 2009-12-30 招商局重庆交通科研设计院有限公司 The job practices of tunnel waterproof and water drainage system
CN203161255U (en) * 2012-08-22 2013-08-28 中铁二院工程集团有限责任公司 Tunnel network waterproof and drainage structure
CN204312099U (en) * 2014-12-04 2015-05-06 招商局重庆交通科研设计院有限公司 Tunnel Gushing based on environmental protection prevents and treats system
CN204357485U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel double-lining behind ponding crossfire
CN204532378U (en) * 2015-01-27 2015-08-05 中铁二院工程集团有限责任公司 Subway tunneling boring rock tunnel development machine engineering method tunnel water handling constructs
CN204572060U (en) * 2015-02-08 2015-08-19 山西省交通科学研究院 A kind of tunnel in cold area circle draining system
CN204754948U (en) * 2015-06-23 2015-11-11 中交一公局第三工程有限公司 Sea worker's concrete tunnel lining structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0898052A1 (en) * 1997-08-15 1999-02-24 Köster Bauchemie Gmbh Method of sealing a subterranean formation against the penetration of water
CN101614129A (en) * 2009-08-10 2009-12-30 招商局重庆交通科研设计院有限公司 The job practices of tunnel waterproof and water drainage system
CN203161255U (en) * 2012-08-22 2013-08-28 中铁二院工程集团有限责任公司 Tunnel network waterproof and drainage structure
CN204312099U (en) * 2014-12-04 2015-05-06 招商局重庆交通科研设计院有限公司 Tunnel Gushing based on environmental protection prevents and treats system
CN204357485U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel double-lining behind ponding crossfire
CN204532378U (en) * 2015-01-27 2015-08-05 中铁二院工程集团有限责任公司 Subway tunneling boring rock tunnel development machine engineering method tunnel water handling constructs
CN204572060U (en) * 2015-02-08 2015-08-19 山西省交通科学研究院 A kind of tunnel in cold area circle draining system
CN204754948U (en) * 2015-06-23 2015-11-11 中交一公局第三工程有限公司 Sea worker's concrete tunnel lining structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冷向东: "摩洛哥拉塞梅尔隧道防排水施工", 《四川建筑》 *

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869998A (en) * 2017-03-09 2017-06-20 同济大学 Hydraulic pressure fractured zones tunnel high carries the emergent intelligent drainage system of clearing function
CN107100671A (en) * 2017-05-31 2017-08-29 中铁七局集团第三工程有限公司 A kind of pressure surface shape of tunnel rich water country rock, which drops down, draws drainage mechanism in adfluxion
CN107227974A (en) * 2017-06-20 2017-10-03 中铁十局集团第四工程有限公司 A kind of tunnel-liner discharge structure and water discharge method
CN107780949A (en) * 2017-10-13 2018-03-09 北京工业大学 A kind of steel FRP complex waves card tunnel support method
CN107916945A (en) * 2017-12-07 2018-04-17 中铁岩锋成都科技有限公司 Using the waterproof spray-up structure and its construction method of impervious gunite concrete
CN108222979A (en) * 2017-12-29 2018-06-29 中铁二局第工程有限公司 Rich water karst waterproof and Drainage Construction of Tunnel method
CN108222979B (en) * 2017-12-29 2019-11-22 中铁二局第一工程有限公司 Rich water karst waterproof and Drainage Construction of Tunnel method
WO2019237908A1 (en) * 2018-06-12 2019-12-19 济南城建集团有限公司 Blocking and drainage combined treatment method for water leakage at construction joint of secondary lining of tunnel
CN108661674A (en) * 2018-07-19 2018-10-16 中国铁路设计集团有限公司 A kind of high hydraulic pressure tunnel sluicing voltage-dropping type is pre-buried to safeguard grouting device
CN109026144A (en) * 2018-07-27 2018-12-18 北京交通大学 A kind of seabed tunnel active control type guarded drainage System Design method and system
CN109281334A (en) * 2018-10-31 2019-01-29 中建科技有限公司 Underground pipe gallery waterproof construction
CN109296389A (en) * 2018-12-10 2019-02-01 潘晓东 A kind of freeway tunnel jet printing type guarded drainage construction and method
CN109296389B (en) * 2018-12-10 2022-09-23 潘晓东 Spraying type waterproof and drainage structure and method for expressway tunnel
CN110130981A (en) * 2019-07-02 2019-08-16 济南市坤鹏技术开发中心 A kind of tunnel construction safe construction method
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110410144B (en) * 2019-07-18 2024-05-10 中交第二公路勘察设计研究院有限公司 Waterproof and drainage structure of shield tunnel
CN110469365A (en) * 2019-08-22 2019-11-19 西南交通大学 A kind of tunnel-liner large area percolating water ejectment device and construction method
CN110761815A (en) * 2019-11-12 2020-02-07 中铁工程设计咨询集团有限公司 Tunnel negative-pressure laying waterproof plate and construction method thereof
CN110878700A (en) * 2019-12-05 2020-03-13 福建鑫远建工有限公司 Tunnel waterproof structure and construction method thereof
CN111271101A (en) * 2020-03-30 2020-06-12 中铁二院工程集团有限责任公司 Tunnel bottom structure system suitable for reconstruction in tunnel operation state and construction method thereof
CN111425249A (en) * 2020-03-30 2020-07-17 中铁二院工程集团有限责任公司 Tunnel wind power drainage system
CN111608727A (en) * 2020-06-08 2020-09-01 哈尔滨工业大学 Cold region mountain tunnel composite drainage system and construction method thereof
CN111963214A (en) * 2020-07-17 2020-11-20 中交一公局集团有限公司 Tunnel molding waterproof construction process
CN112081607A (en) * 2020-10-28 2020-12-15 中国电建集团贵阳勘测设计研究院有限公司 Tunnel primary support and waterproof and drainage combined system and construction method
CN114352308A (en) * 2022-01-13 2022-04-15 中化学交通建设集团有限公司 Tunnel entrance to a cave section is prevented drainage and reinforced structure
CN114412565A (en) * 2022-01-26 2022-04-29 中国有色金属工业昆明勘察设计研究院有限公司 Plugging and dredging device suitable for water burst and mud burst in tunnel

Also Published As

Publication number Publication date
CN106194255B (en) 2017-11-03

Similar Documents

Publication Publication Date Title
CN106194255B (en) Tunnel waterproof and water drainage system and its method of construction
CN109441535A (en) A kind of tunnel waterproof and water drainage system and its construction method
CN102434175A (en) Tunnel lining self waterproof drainage system
CN110878700B (en) Tunnel waterproof structure and construction method thereof
CN202483588U (en) Self water-proof drainage system of tunnel lining
CN110344879A (en) A kind of tunnel water proofing drainage system
CN107327308A (en) A kind of Railway Tunnel waterproof method
CN105297743B (en) A kind of ground-connecting-wall defect seepage stops discharge structure and its construction method
CN111734457A (en) Construction method of tunnel water-drainage-preventing system
CN208280185U (en) A kind of post-cast strip advanced water-stopping construction
CN106703838A (en) Structure and method for processing plane shaped leaked water in operation tunnel
CN109440951A (en) New-old concrete works intersection stitches waterproof construction and construction technology
CN107575264A (en) A kind of composite material corrugated slab supporting waterproof and water drainage system
CN109208651A (en) Underground engineering super-long structural body deformation joint waterproof/drainage structure construction method and structure
CN109252549A (en) A kind of bentonite waterproof blanket and its construction method for man-made lake wetland
CN104846935B (en) Head-tank treating seepage remodeling method
CN108590752A (en) Draining repair system and its construction method after a kind of underdrain formula tunnel-liner
CN111425250B (en) Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system
CN209397743U (en) New-old concrete works intersection stitches waterproof construction
CN104018858A (en) Novel water stopping structure for tunneling seam in permafrost region
CN111472813A (en) Super-large-span anchor-shotcrete support rock tunnel water-proof and drainage system and construction method
CN204827469U (en) A tunnel for transmission fluid
CN204783063U (en) Doubly -linked encircles tunnel mid -board prevents drainage structures
CN113187487B (en) Construction method of double-layer full-section frozen underground excavation station structure of subway
CN111119927A (en) Tunnel three-dimensional waterproof and drainage system and construction technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant