CN106180345A - A kind of high intensity or the inductile material hot formed method of hollow unit low pressure - Google Patents
A kind of high intensity or the inductile material hot formed method of hollow unit low pressure Download PDFInfo
- Publication number
- CN106180345A CN106180345A CN201610549347.0A CN201610549347A CN106180345A CN 106180345 A CN106180345 A CN 106180345A CN 201610549347 A CN201610549347 A CN 201610549347A CN 106180345 A CN106180345 A CN 106180345A
- Authority
- CN
- China
- Prior art keywords
- pipe
- electrode
- switch
- pressure
- sealing punch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000000463 material Substances 0.000 title claims abstract description 34
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000007789 sealing Methods 0.000 claims abstract description 48
- 239000002826 coolant Substances 0.000 claims abstract description 26
- 238000000465 moulding Methods 0.000 claims abstract description 23
- 238000005516 engineering process Methods 0.000 claims description 7
- 238000009423 ventilation Methods 0.000 claims description 6
- 239000003989 dielectric material Substances 0.000 claims description 5
- 230000006835 compression Effects 0.000 claims description 4
- 238000007906 compression Methods 0.000 claims description 4
- 238000001816 cooling Methods 0.000 claims description 4
- 239000007788 liquid Substances 0.000 claims description 3
- 238000010438 heat treatment Methods 0.000 abstract description 5
- 239000007789 gas Substances 0.000 description 15
- 239000012530 fluid Substances 0.000 description 6
- 229910000838 Al alloy Inorganic materials 0.000 description 4
- 229910001069 Ti alloy Inorganic materials 0.000 description 2
- 238000007493 shaping process Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 229910000851 Alloy steel Inorganic materials 0.000 description 1
- 229910000861 Mg alloy Inorganic materials 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 229910045601 alloy Inorganic materials 0.000 description 1
- 239000000956 alloy Substances 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005489 elastic deformation Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000010791 quenching Methods 0.000 description 1
- 230000000171 quenching effect Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D26/00—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces
- B21D26/02—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces by applying fluid pressure
- B21D26/033—Deforming tubular bodies
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D26/00—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces
- B21D26/02—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces by applying fluid pressure
- B21D26/033—Deforming tubular bodies
- B21D26/041—Means for controlling fluid parameters, e.g. pressure or temperature
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D26/00—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces
- B21D26/02—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces by applying fluid pressure
- B21D26/033—Deforming tubular bodies
- B21D26/045—Closing or sealing means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D26/00—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces
- B21D26/02—Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces by applying fluid pressure
- B21D26/033—Deforming tubular bodies
- B21D26/047—Mould construction
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D37/00—Tools as parts of machines covered by this subclass
- B21D37/16—Heating or cooling
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Shaping Metal By Deep-Drawing, Or The Like (AREA)
- Mounting, Exchange, And Manufacturing Of Dies (AREA)
- Moulds For Moulding Plastics Or The Like (AREA)
Abstract
The present invention relates to a kind of high intensity or the inductile material hot formed method of hollow unit low pressure.Comprising the following steps: mould prepares, initial pipe prepares, and selects the suitably initial pipe of size, and blank end is sealed by left sealing punch and right sealing punch, moves on to the most together specify position;Left electrode moves to right electrode contact with initial pipe, adjusts air relief valve, and on and off switch closes, and mold is descending, promotes pipe to shape further, controls air pressure inside, until mould Guan Bi;Pressurize, continues to pipe to shape;On and off switch disconnects, and opens cooling medium switch, and to the internal logical cooling medium of pipe, retrogressing is taken out to not affecting drip molding, opened mould, takes out drip molding;Providing the benefit that: when solving existing apparatus and process forming high intensity or inductile hollow unit, resistance of deformation is big, and drip molding evenness of wall thickness difference and d type precision are the highest, easily rupture, and efficiency is low with the problem that cannot synchronize to carry out heat treatment.
Description
Technical field
The present invention relates to machinery production field, become particularly to a kind of high intensity or inductile material hollow unit low pressure heat
The method of shape.
Background technology
The composite bending modulus high due to hollow section component and modulus of rigidity are it is considered to be realize structure lightened optimal knot
Configuration formula.It is widely used in the industries such as Aeronautics and Astronautics, automobile and bicycle.Fluid internal pressure shapes the elder generation being to process this class A of geometric unitA
Enter forming technique.The know-why that fluid internal pressure shapes is initial blank inside to apply high pressure medium make blank cross section week
Length increases and shapes the hollow member of different cross section form.The essence of its deformation is parison swell deformation.But this kind of distorted pattern
Formula has limitation, it is impossible to or the shaping of plasticity relatively low material higher for intensity, and its reason shows as following several respects:
One, for needing the material of phase transformation strengthening cannot realize heat treatment in forming process.
Two, in order uniquely to deform, to be only possible to order about tubing when driving force, only pressure reach the highest complete due to intrinsic pressure
Shape, it is therefore necessary to be equipped with special high-power supercharger, simultaneously by superhigh pressure sealing technical limitations, form high strength or low mould
During property material hollow unit, difficulty is the biggest.Additionally, for providing enough mold clamping force, it is necessary to use large-tonnage equipment.The problems referred to above
Significantly hinder the engineer applied of this technology.
Its three, mainly produce required odd-shaped cross section by dilatancy owing to fluid internal pressure shapes, and expand change
Shape pattern belongs to double tensile stress state, for the material that plasticity is relatively low, easily ruptures, this skill when thus be accordingly used in Al alloys andMg alloys
There is the biggest defect in art.
Its four, the most relatively low for its elastic modelling quantity of Materials with High Strength, during shaping, elastic return is violent, and room temperature fluid internal pressure becomes
The form accuracy of shape it is difficult to ensure that.
There is scholar to propose hot interior pressing formation, although the method solves the problem of forming limit, but exacerbate wall thickness not
Equal problem, and the restriction of heated medium supercharger and the restriction of gases at high pressure safety problem, be unsuitable for engineer applied.
For these reasons, transfer being bent into primary deformable pattern to, change fluid internal pressure and shape to be expanded to uniquely become
The drawback of shape pattern, and make full use of the intrinsic pressure rising certainly that member section change in high temperature volumetric expansion and forming process causes
Characteristic provides driving force for deformation, it is to avoid under traditional handicraft depend on supercharger unduly, drip molding springback capacity is big, form accuracy
The problem that low and evenness of wall thickness is poor, reduces technology difficulty, widens the technique scope of application, and improving forming quality is the former of the present invention
Power.
Summary of the invention
The purpose of the present invention is aiming at the drawbacks described above that prior art exists, it is provided that a kind of high intensity or inductile material
The hot formed method of hollow unit low pressure, it mainly solves existing apparatus and process forming high intensity or inductile hollow unit
Time, resistance of deformation is big, and drip molding evenness of wall thickness difference and d type precision are the highest, easily rupture, efficiency low with cannot same stepping
The problem of row heat treatment.
A kind of high intensity that the present invention mentions or the inductile material hot formed method of hollow unit low pressure, including following step
Rapid:
Step one: mould prepares, first designs corresponding left electrode (2), left sealing punch (3), mold according to Components Shape
(15), right electrode (16), right sealing punch (17) and lower mold (21), described mold (15) and upper table (11) are even
Connecing, lower mold (21) is connected with lower table (1);Left sealing punch (3) is switched by Filled Dielectrics passage (5) and cooling medium
(4) it is connected with outside cooling medium source (6), simultaneously by check valve (7), air relief valve (8) and air inlet switch (10) and outside gas
Body medium source (9) connects;Right sealing punch (17) has pressure release passage (19) and is connected with relief valve (18);Left electrode (2) and
Right electrode (16) is connected with power supply (14) by wire (12) and on and off switch (13);
Step 2: initial pipe prepares, selects the suitably initial pipe of size, and wherein, the section girth of initial pipe is equal to
0.5-1.5 times of whole drip molding perimeter of section, and initial pipe length is more than part length;
Step 3: blank end is sealed by left sealing punch (3) and right sealing punch (17), moves on to specify position the most together;
Step 4: left electrode (2) moves to contact with initial pipe with right electrode (16), wherein, left electrode is arranged on left sealing and rushes
The right side of head, and right electrode is arranged on the left side of right sealing punch;
Step 5: adjust air relief valve (8), pressure is reduced to concrete technology desired value, then opens air inlet switch (10) to pipe
Internal ventilation body medium;
Step 6: on and off switch (13) closes, moves to the pipe entirety sealing energising in the die cavity of lower mold (21), and mobile
Time is less than 60 seconds;
Step 7: mold (15) is descending, compression pipe brings it about flexural deformation, and pipe sectional area reduces therewith, internal pressure
Power raises further, promotes pipe to shape further, whole during control air pressure inside by relief valve (18), until mould
Guan Bi;
Step 8: pressurize, continues to pipe to shape;
Step 9: on and off switch (13) disconnects, opens cooling medium switch (4), and to the internal logical cooling medium of pipe, pressure increases to
Relief valve is opened, and gas flow and ventilation duration meet drip molding cooling technological requirement simultaneously;
Step 10: close cooling medium switch (4), left sealing punch (3), right sealing punch (17), left electrode (2) and right electrode
(16) retreat to not affecting drip molding taking-up, open mould, take out drip molding (22).
Preferably, in above-mentioned step 5, reducing to 0 ~ 50MPa for Materials with High Strength pressure, inductile material pressure reduces to 0
~40MPa。
Preferably, above-mentioned power supply is pulse current power supply
Preferably, the specific bit in step 3 is set to lower mold (21) or is easy to connect electrode zone.
Preferably, above-mentioned initial pipe (20) uses high-strength material or inductile material.
Preferably, above-mentioned cooling medium source (6) is cryogenic gas or liquid;Gas medium is room temperature air or low wet
Body.
The invention has the beneficial effects as follows:
One, makes full use of the intrinsic pressure increase that temperature own in technical process raises and change in volume causes and drives as deformation
Power, it is not necessary to optional equipment supercharger, technique is simple, low cost;
Its two, use and there is the cooling medium of certain pressure directly in mold cavity, component quenched, advantageously ensure that
The geometric accuracy of drip molding, and improve process efficiency;
Its three, owing to the deformation pattern of this technique is based on flexural deformation, it is to avoid the unfavorable shadow that under high temperature, hardenability value reduces
Ringing, drip molding evenness of wall thickness is good, and the technique suitability is strong;
Its four, quenched in hollow section member cavity by cooling medium, owing to medium directly contacts with component, cooling
Speed is fast and uniform, and performance is the best;
Its five, under hot forming, elastic deformation is extremely low, and drip molding is easily guaranteed that almost without resilience, drip molding form accuracy;
Its six, by large power supply directly to heating of pipe blank, speed is fast, and thermal losses is low, overcomes traditional hot fluid internal pressure
Forming efficiency is low, it is impossible to the shortcoming meeting engineer applied;
The present invention is reasonable in design, reliable operation, effect notable, has stronger promotional value.
Accompanying drawing explanation
Fig. 1 is the structural representation of the mould of the present invention;
Fig. 2 is the A-A structure chart of the mould of the present invention;
Fig. 3 is mould matched moulds and quenching principle schematic diagram;
Fig. 4 is the B-B structure chart of Fig. 3;
In upper figure: lower table 1, left electrode 2, left sealing punch 3, cooling medium switch 4, Filled Dielectrics passage 5, cooling medium
Source 6, check valve 7, air relief valve 8, gas medium source 9, air inlet switch 10, upper table 11, wire 12, on and off switch 13, power supply
14, mold 15, right electrode 16, right sealing punch 17, relief valve 18, pressure release passage 19, initial pipe 20, lower mold 21, one-tenth
Shape part 22.
Detailed description of the invention
1-2 referring to the drawings, the invention will be further described:
A kind of high intensity that the present invention mentions or inductile material hollow unit low pressure thermal forming device, including left electrode 2, Zuo Mi
Envelope drift 3, mold 15, right electrode 16, right sealing punch 17 and lower mold 21, is characterized in that: described mold 15 is with upper
Workbench 11 connects, and lower mold 21 is connected with lower table 1;Left sealing punch 3 is opened by Filled Dielectrics passage 5 and cooling medium
Close 4 to be connected with outside cooling medium source 6, simultaneously by check valve 7, air relief valve 8 and air inlet switch 10 and extraneous gas medium source 9
Connect;Right sealing punch 17 has pressure release passage 19 and is connected with relief valve 18;Left electrode 2 and right electrode 16 are by wire 12 He
On and off switch 13 is connected with power supply 14;
By left sealing punch 3 and right sealing punch 17 to initial pipe 20 end seal, and move on to specify position;Left electrode 2
Move to right electrode 16 contact with initial pipe 20, and left electrode 2 is arranged on the right side of left sealing punch 3, and right electrode 16 sets
Put the left side at right sealing punch 17.
The section girth of above-mentioned initial pipe 20 is equal to 0.5-1.5 times of whole drip molding perimeter of section.
Above-mentioned on and off switch 13 closes, and quickly the pipe entirety sealing energising is moved in the die cavity of lower mold 21,
Wherein, traveling time is less than 60 seconds.
It is descending that above-mentioned mold 15 presses setting curve, and compression pipe brings it about flexural deformation, and pipe sectional area is therewith
Reduce, internal pressure raise, promote pipe to shape, whole during pass through relief valve 18 control air pressure inside.
Referring to the drawings 3-4, a kind of high intensity that the present invention mentions or the inductile material hot formed side of hollow unit low pressure
Method, comprises the following steps:
Step one: mould prepares, first designs corresponding left electrode 2, left sealing punch 3, mold 15, the right side according to Components Shape
Electrode 16, right sealing punch 17 and lower mold 21, above-mentioned same as the prior art, this does not repeats.Mold 15 and upper table
11 connect, and lower mold 21 is connected with lower table 1.Left sealing punch 3 by Filled Dielectrics passage 5 and cooling medium switch 4 with
Outside cooling medium source 6 connects, and is connected with extraneous gas medium source 9 by check valve 7, air relief valve 8 and air inlet switch 10 simultaneously.
Right sealing punch 17 has pressure release passage 19 and is connected with relief valve 18.Left electrode 2 and right electrode 16 are by wire 12 and power supply
Switch 13 is connected with power supply 14.
Step 2: initial pipe prepares, selects the suitably initial pipe of size, and its main points are the cross section week of initial pipe
The section girth of long and whole drip molding is close, and the section girth of general initial pipe should be equal to drip molding perimeter of section at end
0.5-1.5 times.Initial pipe length should be greater than part length, it is ensured that has enough sealing areas and electrode contact region.
Step 3: blank end is sealed by left sealing punch 3 and right sealing punch 17, moves on to specify position the most together.
Sealing means is same as the prior art, and this does not repeats.
Step 4: left electrode 2 moves to contact with pipe with right electrode 16, its main points are that left electrode should be at left sealing punch
Right side, and right electrode i.e. should ensure in the left side of right sealing punchl a It is less thanl b 。
Step 5: adjust air relief valve 8, pressure is reduced to concrete technology desired value, then opens air inlet switch 10 to pipe
Internal ventilation body medium.Its main points are for typically to reduce to 0 ~ 50MPa for Materials with High Strength pressure, and inductile material pressure typically reduces to
0~40MPa。
Step 6: on and off switch 13 closes, and quickly the pipe entirety sealing energising is moved in the die cavity of lower mold 21,
Its main points are that traveling time is less than 60 seconds.Along with the carrying out of energising, blank temperature constantly raises, under the flow stress of material
Fall, elongation percentage improves, and pipe internal gas expanded by heating simultaneously, air pressure constantly raises.
Step 7: it is descending that mold 15 presses technique initialization curve, compression pipe brings it about flexural deformation, pipe sectional area
Reducing therewith, internal pressure raises further, promotes pipe to shape further, whole during control inside by relief valve 18
Air pressure maximum is in concrete technology claimed range, until mould Guan Bi.
Step 8: pressurize certain time, its main points are that pressurize continues to pipe to shape.
Step 9: on and off switch 13 disconnects, opens cooling medium switch 4, to the internal logical cooling medium of pipe, and continues one
Fixing time, its main points are that pressure increases to relief valve unlatching also, and gas flow and ventilation duration meet drip molding cooling technique simultaneously
Requirement.
Step 10: close cooling medium switch 4, after left sealing punch 3, right sealing punch 17, left electrode 2 and right electrode 16
Retreat to not affect drip molding take out, open mould, take out drip molding 22.
Wherein, the power supply that the present invention mentions is large power supply, and large power supply is current range 0-5000000A, voltage
The power supply of scope 0-36V, power supply is pulse current power supply, pulse frequency 0-10000Hz, amplitude 0-100000A, voltage range 0-
The power supply of 100000V.
Specific bit in step 3 be set to lower mold 21 or just be connected electrode zone;Specific bit in step 3 is set to down
The interior die cavity of mould 21;Specific bit in step 3 is set to be easy to connect electrode zone;
The high-strength material of initial pipe employing or inductile material, high-strength material is high-strength steel or titanium alloy, and high-strength steel is
22MnB5, titanium alloy is TC4;Inductile material is aluminium alloy or magnesium alloy, aluminium alloy be 2000 be, 5000 be 6000 be or
7000 line aluminium alloys;
Cooling medium is cryogenic gas or liquid, and gas medium is room temperature air or cryogenic gas, and gas medium is cryogenic gas.
Claims (6)
1. high intensity or the inductile material hot formed method of hollow unit low pressure, is characterized in that comprising the following steps:
Step one: mould prepares, first designs corresponding left electrode (2), left sealing punch (3), mold according to Components Shape
(15), right electrode (16), right sealing punch (17) and lower mold (21), described mold (15) and upper table (11) are even
Connecing, lower mold (21) is connected with lower table (1);Left sealing punch (3) is switched by Filled Dielectrics passage (5) and cooling medium
(4) it is connected with outside cooling medium source (6), simultaneously by check valve (7), air relief valve (8) and air inlet switch (10) and outside gas
Body medium source (9) connects;Right sealing punch (17) has pressure release passage (19) and is connected with relief valve (18);Left electrode (2) and
Right electrode (16) is connected with power supply (14) by wire (12) and on and off switch (13);
Step 2: initial pipe prepares, selects the suitably initial pipe of size, and wherein, the section girth of initial pipe is equal to
0.5-1.5 times of whole drip molding perimeter of section, and initial pipe length is more than part length;
Step 3: blank end is sealed by left sealing punch (3) and right sealing punch (17), moves on to specify position the most together;
Step 4: left electrode (2) moves to contact with initial pipe with right electrode (16), wherein, left electrode is arranged on left sealing and rushes
The right side of head, and right electrode is arranged on the left side of right sealing punch;
Step 5: adjust air relief valve (8), pressure is reduced to concrete technology desired value, then opens air inlet switch (10) to pipe
Internal ventilation body medium;
Step 6: on and off switch (13) closes, moves to the pipe entirety sealing energising in the die cavity of lower mold (21), and mobile
Time is less than 60 seconds;
Step 7: mold (15) is descending, compression pipe brings it about flexural deformation, and pipe sectional area reduces therewith, internal pressure
Power raises further, promotes pipe to shape further, whole during control air pressure inside by relief valve (18), until mould
Guan Bi;
Step 8: pressurize, continues to pipe to shape;
Step 9: on and off switch (13) disconnects, opens cooling medium switch (4), and to the internal logical cooling medium of pipe, pressure increases to
Relief valve is opened, and gas flow and ventilation duration meet drip molding cooling technological requirement simultaneously;
Step 10: close cooling medium switch (4), left sealing punch (3), right sealing punch (17), left electrode (2) and right electrode
(16) retreat to not affecting drip molding taking-up, open mould, take out drip molding (22).
High intensity the most according to claim 1 or the inductile material hot formed method of hollow unit low pressure, is characterized in that:
In above-mentioned step 5, reducing to 0 ~ 50MPa for high-strength material pressure, inductile material pressure reduces to 0 ~ 40MPa.
High intensity the most according to claim 1 or the inductile material hot formed method of hollow unit low pressure, is characterized in that:
Described power supply is pulse current power supply.
High intensity the most according to claim 1 or the inductile material hot formed method of hollow unit low pressure, is characterized in that:
Specific bit in step 3 is set to lower mold (21) or is easy to connect electrode zone.
High intensity the most according to claim 1 or the inductile material hot formed method of hollow unit low pressure, is characterized in that:
Described initial pipe (20) uses high-strength material or inductile material.
High intensity the most according to claim 1 or the inductile material hot formed method of hollow unit low pressure, is characterized in that:
Described cooling medium source (6) is cryogenic gas or liquid.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610549347.0A CN106180345B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or the hot formed method of inductile material hollow unit low pressure |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610549347.0A CN106180345B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or the hot formed method of inductile material hollow unit low pressure |
CN201410329790.8A CN104162948B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or inductile material hollow unit low pressure thermal forming device and method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410329790.8A Division CN104162948B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or inductile material hollow unit low pressure thermal forming device and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106180345A true CN106180345A (en) | 2016-12-07 |
CN106180345B CN106180345B (en) | 2018-07-20 |
Family
ID=51907026
Family Applications (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610568082.9A Pending CN106180347A (en) | 2014-07-11 | 2014-07-11 | A kind of hollow unit low pressure thermal forming device |
CN201610549347.0A Expired - Fee Related CN106180345B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or the hot formed method of inductile material hollow unit low pressure |
CN201610568064.0A Expired - Fee Related CN106180346B (en) | 2014-07-11 | 2014-07-11 | A kind of low pressure thermal forming device |
CN201410329790.8A Active CN104162948B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or inductile material hollow unit low pressure thermal forming device and method |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610568082.9A Pending CN106180347A (en) | 2014-07-11 | 2014-07-11 | A kind of hollow unit low pressure thermal forming device |
Family Applications After (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610568064.0A Expired - Fee Related CN106180346B (en) | 2014-07-11 | 2014-07-11 | A kind of low pressure thermal forming device |
CN201410329790.8A Active CN104162948B (en) | 2014-07-11 | 2014-07-11 | A kind of high intensity or inductile material hollow unit low pressure thermal forming device and method |
Country Status (1)
Country | Link |
---|---|
CN (4) | CN106180347A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107597966A (en) * | 2017-10-11 | 2018-01-19 | 南京工程学院 | A kind of pneumatic hot forming process for quenching of unimach complex component and device |
CN108787846A (en) * | 2018-05-31 | 2018-11-13 | 安徽扬子职业技术学院 | A kind of accurate molding machine of high-strength vehicle chassis part |
CN109175061A (en) * | 2018-07-25 | 2019-01-11 | 南京航空航天大学 | A kind of the electricity auxiliary heating forming device and method of dissimilar material complex section pipe fitting |
CN109465322A (en) * | 2018-11-09 | 2019-03-15 | 南京航空航天大学 | A kind of pulse current pulsating heating gas pressure compacting device and method of less-deformable alloy pipe fitting |
CN109926486A (en) * | 2017-12-18 | 2019-06-25 | 哈尔滨工业大学 | Ti2The hot gas pressure compacting of AlNb based alloy hollow thin-wall component and heat-treating methods |
CN110446567A (en) * | 2017-03-30 | 2019-11-12 | 住友重机械工业株式会社 | Formation system |
CN111438254A (en) * | 2020-04-10 | 2020-07-24 | 哈尔滨工业大学 | Hot air expansion-active air cooling forming device and forming method for closed-section integral pipe fitting |
CN112051144A (en) * | 2020-08-13 | 2020-12-08 | 北京航空航天大学 | Pure electro-plasticity auxiliary thermal forming process for hard-material-state high-strength aluminum alloy |
WO2021077514A1 (en) * | 2019-10-25 | 2021-04-29 | 大连理工大学 | Large-size thin-wall ring housing inflation hot-bending forming device and method |
CN114192602A (en) * | 2021-12-14 | 2022-03-18 | 大连理工大学 | Overlapping progressive forming method for high-performance multi-element NiAl-based alloy pipe fitting |
CN114653806A (en) * | 2022-03-01 | 2022-06-24 | 哈尔滨工业大学(威海) | Preforming method for high-strength steel variable-diameter tubular part |
CN115301835A (en) * | 2022-08-24 | 2022-11-08 | 凌云吉恩斯科技有限公司 | Hot stamping manufacturing method of tubular part |
US11873537B2 (en) | 2017-12-20 | 2024-01-16 | Bayerische Motoren Werke Aktiengesellschaft | Method for producing a profiled component, and profiled component |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104525746B (en) * | 2015-01-06 | 2016-11-02 | 哈尔滨工业大学(威海) | A kind of quickly heating and forming integrated device and method |
CN106311857B (en) * | 2015-12-21 | 2017-11-07 | 青岛世冠装备科技有限公司 | A kind of swollen manufacturing process of complex section hollow member low pressure upsetting |
CN106623577B (en) * | 2016-09-27 | 2018-08-17 | 贺州学院 | A kind of wave hydraulic loaded method |
CA3058115A1 (en) * | 2017-03-30 | 2018-10-04 | Sumitomo Heavy Industries, Ltd. | Forming apparatus |
CN107597944A (en) * | 2017-10-23 | 2018-01-19 | 江苏界达特异新材料股份有限公司 | The hydroforming sealing device of steel pipe |
CN107671165A (en) * | 2017-10-25 | 2018-02-09 | 江苏界达特异新材料股份有限公司 | The bulging device of internal high pressure forming pipe fitting |
JP7240411B2 (en) * | 2018-10-01 | 2023-03-15 | 住友重機械工業株式会社 | Expansion molding device |
CN113510176B (en) * | 2020-04-10 | 2024-01-19 | 初冠南 | Pressurizing upsetting forming device |
CN111451351B (en) * | 2020-04-30 | 2022-08-09 | 初冠南 | Forming and integrating method for tubular part |
CN111957808A (en) * | 2020-06-24 | 2020-11-20 | 上海凌云工业科技有限公司凌云汽车技术分公司 | Cavity pipe fitting bending forming method and shape pasting bending die |
CN113020391B (en) * | 2021-03-04 | 2022-05-03 | 北京航空航天大学 | Ultrahigh-pressure forming method and device for high-temperature alloy fluid medium |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050186302A1 (en) * | 2004-02-24 | 2005-08-25 | Sungwoo Hitech Co., Ltd. | Warm hydro-forming device |
CN101342559A (en) * | 2007-05-23 | 2009-01-14 | 株式会社和信 | Hot forming apparatus and hot forming method |
JP2009220141A (en) * | 2008-03-14 | 2009-10-01 | Marujun Co Ltd | Method and apparatus for manufacturing pipe product |
CN101767461A (en) * | 2008-12-30 | 2010-07-07 | 陈占聪 | Inner and outer heating forming process for composition material tubing |
TW201208849A (en) * | 2010-08-17 | 2012-03-01 | Chaun Choung Technology Corp | Method for manufacturing a pressed heat pipe |
CN103521588A (en) * | 2013-10-28 | 2014-01-22 | 哈尔滨工业大学 | Current-assisted titanium alloy bellows hot-forming tool and method |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01166919A (en) * | 1987-12-23 | 1989-06-30 | Fuji Heavy Ind Ltd | Manufacture of turbular composite material |
JP4461626B2 (en) * | 2001-03-15 | 2010-05-12 | Jfeスチール株式会社 | Manufacturing method of steel pipe for hydroforming having strain aging |
CN102228932B (en) * | 2011-04-22 | 2013-02-13 | 哈尔滨工业大学 | Forming method for improving stepped hollow reducing pipe wall thickness uniformity |
-
2014
- 2014-07-11 CN CN201610568082.9A patent/CN106180347A/en active Pending
- 2014-07-11 CN CN201610549347.0A patent/CN106180345B/en not_active Expired - Fee Related
- 2014-07-11 CN CN201610568064.0A patent/CN106180346B/en not_active Expired - Fee Related
- 2014-07-11 CN CN201410329790.8A patent/CN104162948B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050186302A1 (en) * | 2004-02-24 | 2005-08-25 | Sungwoo Hitech Co., Ltd. | Warm hydro-forming device |
CN101342559A (en) * | 2007-05-23 | 2009-01-14 | 株式会社和信 | Hot forming apparatus and hot forming method |
JP2009220141A (en) * | 2008-03-14 | 2009-10-01 | Marujun Co Ltd | Method and apparatus for manufacturing pipe product |
CN101767461A (en) * | 2008-12-30 | 2010-07-07 | 陈占聪 | Inner and outer heating forming process for composition material tubing |
TW201208849A (en) * | 2010-08-17 | 2012-03-01 | Chaun Choung Technology Corp | Method for manufacturing a pressed heat pipe |
CN103521588A (en) * | 2013-10-28 | 2014-01-22 | 哈尔滨工业大学 | Current-assisted titanium alloy bellows hot-forming tool and method |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110446567A (en) * | 2017-03-30 | 2019-11-12 | 住友重机械工业株式会社 | Formation system |
CN110446567B (en) * | 2017-03-30 | 2021-03-02 | 住友重机械工业株式会社 | Molding system |
CN107597966A (en) * | 2017-10-11 | 2018-01-19 | 南京工程学院 | A kind of pneumatic hot forming process for quenching of unimach complex component and device |
CN107597966B (en) * | 2017-10-11 | 2019-04-12 | 南京工程学院 | A kind of pneumatic hot forming process for quenching of unimach complex component |
CN109926486A (en) * | 2017-12-18 | 2019-06-25 | 哈尔滨工业大学 | Ti2The hot gas pressure compacting of AlNb based alloy hollow thin-wall component and heat-treating methods |
WO2019119711A1 (en) * | 2017-12-18 | 2019-06-27 | 哈尔滨工业大学 | Hot metal gas forming and heat treatment method for thin-walled hollow ti2alnb-based alloy component |
US10688552B2 (en) | 2017-12-18 | 2020-06-23 | Harbin Institute Of Technology | Method of hot gas forming and hear treatment for a Ti2AlNb-based alloy hollow thin-walled component |
US11873537B2 (en) | 2017-12-20 | 2024-01-16 | Bayerische Motoren Werke Aktiengesellschaft | Method for producing a profiled component, and profiled component |
CN108787846A (en) * | 2018-05-31 | 2018-11-13 | 安徽扬子职业技术学院 | A kind of accurate molding machine of high-strength vehicle chassis part |
CN109175061A (en) * | 2018-07-25 | 2019-01-11 | 南京航空航天大学 | A kind of the electricity auxiliary heating forming device and method of dissimilar material complex section pipe fitting |
CN109465322A (en) * | 2018-11-09 | 2019-03-15 | 南京航空航天大学 | A kind of pulse current pulsating heating gas pressure compacting device and method of less-deformable alloy pipe fitting |
WO2021077514A1 (en) * | 2019-10-25 | 2021-04-29 | 大连理工大学 | Large-size thin-wall ring housing inflation hot-bending forming device and method |
US11413672B2 (en) | 2019-10-25 | 2022-08-16 | Dalian University Of Technology | Apparatus and method for forming large-scale thin-walled ring shell by hot-press bending with internal gas pressure |
CN111438254A (en) * | 2020-04-10 | 2020-07-24 | 哈尔滨工业大学 | Hot air expansion-active air cooling forming device and forming method for closed-section integral pipe fitting |
CN111438254B (en) * | 2020-04-10 | 2021-09-17 | 哈尔滨工业大学 | Hot air expansion-active air cooling forming device and forming method for closed-section integral pipe fitting |
CN112051144A (en) * | 2020-08-13 | 2020-12-08 | 北京航空航天大学 | Pure electro-plasticity auxiliary thermal forming process for hard-material-state high-strength aluminum alloy |
CN114192602A (en) * | 2021-12-14 | 2022-03-18 | 大连理工大学 | Overlapping progressive forming method for high-performance multi-element NiAl-based alloy pipe fitting |
CN114653806A (en) * | 2022-03-01 | 2022-06-24 | 哈尔滨工业大学(威海) | Preforming method for high-strength steel variable-diameter tubular part |
CN114653806B (en) * | 2022-03-01 | 2023-12-22 | 哈尔滨工业大学(威海) | Preforming method for high-strength steel reducing tubular part |
CN115301835A (en) * | 2022-08-24 | 2022-11-08 | 凌云吉恩斯科技有限公司 | Hot stamping manufacturing method of tubular part |
CN115301835B (en) * | 2022-08-24 | 2023-08-29 | 凌云吉恩斯科技有限公司 | Hot stamping manufacturing method of tubular part |
Also Published As
Publication number | Publication date |
---|---|
CN106180345B (en) | 2018-07-20 |
CN106180347A (en) | 2016-12-07 |
CN106180346B (en) | 2018-06-12 |
CN106180346A (en) | 2016-12-07 |
CN104162948B (en) | 2016-08-24 |
CN104162948A (en) | 2014-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104162948B (en) | A kind of high intensity or inductile material hollow unit low pressure thermal forming device and method | |
CN102284588B (en) | Device for improving forming limit of plate | |
CN102632125B (en) | Plate differential temperature hydroforming device capable of realizing radial pressurizing and hydraulic blank pressing | |
CN102248056A (en) | Method for improving sheet forming limit | |
CN103464562B (en) | Cavity low-internal-pressure manufacturing process | |
CN106311857B (en) | A kind of swollen manufacturing process of complex section hollow member low pressure upsetting | |
CN108856441B (en) | Pipe thermal medium internal pressure forming method based on molten glass | |
CN105855336B (en) | Car body of aluminum alloy abnormal shape variable cross-section tubing structural member thermo shaping method | |
CN104525676B (en) | Gas bulging hot formation segmentation strengthening process of boron steel tube | |
CN107297412A (en) | The quick air pressure expanding method of thermal state metal sheet material | |
CN103753119A (en) | Lightweight wall panel superplastic forming production method | |
CN107639172A (en) | It is a kind of while realize manufacturing process and device that pipe end shrink mouth thickens | |
CN105921584A (en) | Air pressure bulging method of ultrahigh-strength steel hollow component | |
CN102641936A (en) | Tubing bulging device and method using internal heating and pressing | |
CN110064690B (en) | Beneficial wrinkle prefabricating method for improving high-pressure forming limit in pipe | |
CN104525746A (en) | Rapid heating and forming integrated device and method | |
CN101885031B (en) | Die for controlling forming of asymmetric complex-curved rebar forge piece by using movable damping block | |
CN111451351B (en) | Forming and integrating method for tubular part | |
CN204545086U (en) | The gases at high pressure bulging hot forming segmentation strengthening mould of boron steel steel pipe | |
CN106048478A (en) | Forming and strengthening method for aluminum lithium alloy plate, strengthened aluminum lithium alloy component and die | |
CN105964722B (en) | A kind of high strength alumin ium alloy pipe fitting solution treatment and granule medium cold forming method | |
CN116140450A (en) | Superplastic air-expanding forming die capable of feeding and method | |
CN205966832U (en) | Aluminum alloy automobile pipe fitting attitude hydraulic forming production line that newly quenches | |
CN107262643A (en) | A kind of lower blanking type precision forging device and method of high rib pulse current effect of thin plate | |
CN204276693U (en) | The gases at high pressure bulging hot-forming die of boron steel steel pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20180604 Address after: 528000 Foshan, Shunde, Guangdong Ronggui Rong Li neighborhood committee, new middle road 18, two floor. Applicant after: Foshan Shunde District Xin Qing hardware and Plastic Co., Ltd. Address before: 257000 North Road, Dongying District, Dongying, Shandong Province, No. 188 Applicant before: Chu Guannan |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180720 Termination date: 20200711 |
|
CF01 | Termination of patent right due to non-payment of annual fee |