CN106168028A - A kind of cantilevered reservoir dam template - Google Patents

A kind of cantilevered reservoir dam template Download PDF

Info

Publication number
CN106168028A
CN106168028A CN201610733250.5A CN201610733250A CN106168028A CN 106168028 A CN106168028 A CN 106168028A CN 201610733250 A CN201610733250 A CN 201610733250A CN 106168028 A CN106168028 A CN 106168028A
Authority
CN
China
Prior art keywords
section steel
channel
reservoir dam
stress
protective
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610733250.5A
Other languages
Chinese (zh)
Other versions
CN106168028B (en
Inventor
卢兴明
杨爱军
佘建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Green Environmental Protection Science And Technology Ltd Co
Original Assignee
Nantong Green Environmental Protection Science And Technology Ltd Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Green Environmental Protection Science And Technology Ltd Co filed Critical Nantong Green Environmental Protection Science And Technology Ltd Co
Priority to CN201610733250.5A priority Critical patent/CN106168028B/en
Publication of CN106168028A publication Critical patent/CN106168028A/en
Application granted granted Critical
Publication of CN106168028B publication Critical patent/CN106168028B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages

Abstract

The present invention relates to a kind of cantilevered reservoir dam template, this model sheetinstallat is on the sidewall of inclination or vertical reservoir dam, including stress channel-section steel, protective plate, protective frame, embedded ribs and screw mandrel;Stress channel-section steel is close on the sidewall of reservoir dam, and embedded ribs is perpendicular to stress channel-section steel and is embedded in reservoir dam, and protective plate is placed in protective frame, and protective frame and stress channel-section steel are connected to form U-shape structure;Its innovative point is: be connected by screw mandrel between the end of stress channel-section steel, by embedded ribs as supporting and fuse after one section of dam construction completes embedded ribs by screw mandrel dismounting stress channel-section steel, protective plate and protective frame, stress channel-section steel, protective plate and protective frame upwards stack and carry out by the mode installing embedded ribs behind screw mandrel location additional the construction of next section of reservoir dam.

Description

A kind of cantilevered reservoir dam template
Technical field
The present invention relates to building engineering field, particularly relate to a kind of cantilevered reservoir dam template.
Background technology
In water conservancy structure concreting field, the template casting concrete in bulk that traditional method uses, One piece of maintenance one piece is poured by template in bulk, after concrete reaches design strength, more one by one form removable in bulk, Carrying out block placement the most again, repetition said method, until having poured, uses said method pouring construction numerous and diverse, expense of taking a lot of work Time, pouring quality is difficult to ensure, as curtain, faulting of slab ends, deformation, honeycomb etc. occurs in concrete, and the temperature range of concrete is not The problem such as easy to control.
A kind of adjustable cantilever template as described in China Patent No. 201020046736.X, including template assembly, described Template assembly is arranged on tripod by rear moving device, and described template assembly includes that main back cord, the lower end of described main back cord prop up Support in the rear on moving device, and between described main back cord and described rear moving device, be provided with main back cord diagonal brace, it is characterised in that Described main back cord includes the channel-section steel of two pieces of back-to-back settings, and the bottom surface of channel-section steel is along being longitudinally provided with a row or two exhausting holes;Two pieces of grooves Leaving between steel and connected by multiple bolts between gap, and two blocks of channel-section steels, the two ends of described bolt are each passed through two blocks of channel-section steels On through hole, the middle part of described bolt is cased with steel pipe, the length of described steel pipe equal to the width in the gap between two blocks of channel-section steels, The external diameter of described steel pipe is more than the diameter of described through hole;The upper end of described main back cord diagonal brace is inserted into the channel-section steel of two pieces of back-to-back settings Between gap in, and by the through hole connection on pin and two blocks of channel-section steels, lower end is connected with described rear moving device, the described main back of the body Stupefied diagonal brace is provided with length adjustment device.
Use the template moving formula after above-mentioned adjustable cantilever template is, although in certain degree, solve template exist Horizontal direction raises the problem of interval, but cannot solve template stacking on vertical and displacement, it is impossible to complete along perpendicular To dismounting and superposition problem.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of cantilevered reservoir dam template, solves construction reservoir dam Use template in bulk to pour the slow and common cantilever type form of one piece of construction speed of one piece of maintenance and be unfavorable for vertical dismounting stacking Problem.
For solving above-mentioned technical problem, the technical scheme is that a kind of cantilevered reservoir dam template, this template is pacified It is contained on the sidewall of inclination or vertical reservoir dam, including stress channel-section steel, protective plate, protective frame, embedded ribs and screw mandrel;Stress Channel-section steel is close on the sidewall of reservoir dam, and embedded ribs is perpendicular to stress channel-section steel and is embedded in reservoir dam, and protective plate is placed in In protective frame, protective frame and stress channel-section steel are connected to form U-shape structure;Its innovative point is: pass through between the end of stress channel-section steel Screw mandrel is connected, by embedded ribs as supporting and fuse after one section of dam construction completes embedded ribs dismantle stress by screw mandrel Channel-section steel, protective plate and protective frame, install embedded ribs additional after stress channel-section steel, protective plate and protective frame upwards being stacked and positioning with screw mandrel Mode carry out the construction of next section of reservoir dam;
Described stress channel-section steel is some sections of vertical applied force channel-section steels and the cross-shaped configuration of horizontal force channel-section steel formation, vertical applied force groove Steel and horizontal force channel-section steel are vertical and horizontally arranged respectively along inclined plane or the vertical of reservoir dam, and stress groove sets Being equipped with protective plate installing hole, the end, two ends of stress channel-section steel is respectively arranged with hinged buckle and hinged draw-in groove, by screw mandrel is embedding Enter and in hinged buckle and hinged draw-in groove, stress channel-section steel is connected.
Further, if described protective frame is divided into dried layer up and down, including connecting plate and protective baffle plate;One end of connecting plate with The protective plate installing hole arranged on vertical applied force channel-section steel is connected by bolt, and connecting plate can hinged around with vertical applied force channel-section steel Place's rotation is fixing after carrying out angular adjustment, and the other end of connecting plate is connected with protective baffle plate.
Further, described protective plate is placed on the connecting plate of protective frame, and protective plate is of an L-shaped structure and is multilayer proofing Plate.
Further, described embedded ribs is threaded rod structure, and embedded ribs is perpendicular to the one of horizontal force channel-section steel and embedded ribs End is embedded in reservoir dam, and the other end of embedded ribs is clamped on horizontal force channel-section steel by clamp nut and tapered cup nut, Fusing hole it is provided with on tapered cup nut.
Further, described screw mandrel is for the linking location of stress channel-section steel and the demoulding of stress channel-section steel.
It is an advantage of the current invention that:
1) by using embedding embedded ribs in the concrete dykes and dams poured, by embedded ribs and stress channel-section steel and reservoir dam phase Continuous cropping is the support of whole template, stress channel-section steel be positioned the demoulding by screw mandrel, by fusing embedded ribs and stress channel-section steel it Between the fast quick-detach of cohesive position be positioned at the template of lower section by the construction of reservoir dam above shift-in row in template, improve and execute Work efficiency rate, has saved the use of template;
2) installation multilayer proofing plate on the stress channel-section steel of the demoulding can positioned by screw mandrel, according to the position constructed at a certain layer Construct on protective plate, will be located in the embedded ribs fusing that the protective plate of lower section is connected with constructed reservoir dam, will be located in Stress channel-section steel, protective plate and the protective frame of lower section are connected with the stress channel-section steel of top, are alternately accomplished the reservoir of same level successively The construction of dykes and dams, improves the efficiency of construction of dykes and dams.
Accompanying drawing explanation
The present invention is further detailed explanation with detailed description of the invention below in conjunction with the accompanying drawings.
Fig. 1 is the assembling side elevation that cantilevered reservoir tilts dam template.
Fig. 2 is the assembling side elevation of cantilevered reservoir vertical dam template.
Fig. 3 is the A portion enlarged drawing of cantilevered reservoir dam template.
Fig. 4 is the protective frame front view of cantilevered reservoir dam template.
Detailed description of the invention
The following examples can make professional and technical personnel that the present invention is more fully understood, but the most therefore by this Bright it is limited among described scope of embodiments.
A kind of cantilevered reservoir dam template as shown in Figures 1 to 4, this model sheetinstallat is at inclination or vertical reservoir dam On the sidewall of 1, including stress channel-section steel 2, protective plate 3, protective frame 4, embedded ribs 5 and screw mandrel 6;It is big that stress channel-section steel 2 is close to reservoir On the sidewall on dam 1, embedded ribs 5 is perpendicular to stress channel-section steel 2 and is embedded in reservoir dam 1, and protective plate 3 is placed in protective frame 4, anti- Retaining frame 4 and stress channel-section steel 2 are connected to form U-shape structure;It is connected, by embedded ribs 5 by screw mandrel 6 between the end of stress channel-section steel 2 As supporting and fuse after one section of dam construction completes embedded ribs 5 dismantle stress channel-section steel 2, protective plate 3 and anti-by screw mandrel 6 Retaining frame 4, the mode installing embedded ribs 5 after stress channel-section steel 2, protective plate 3 and protective frame 4 are upwards stacked and positioned with screw mandrel 6 additional is entered The construction of next section of reservoir dam 1 of row.
Stress channel-section steel 2 is some sections of vertical applied force channel-section steels 21 and the cross-shaped configuration of horizontal force channel-section steel 22 formation, vertically Stress channel-section steel 21 and horizontal force channel-section steel 22 vertically set with horizontal direction respectively along inclined plane or the vertical of reservoir dam 1 Putting, on stress groove, 2 are provided with protective plate 23 installing hole, and the end, two ends of stress channel-section steel 2 is respectively arranged with hinged buckle and hinged Draw-in groove, by being connected stress channel-section steel 2 in screw mandrel 6 is embedded in hinged buckle and hinged draw-in groove.
If protective frame 4 is divided into dried layer up and down, including connecting plate 41 and protective baffle plate 42;One end of connecting plate 41 be vertically subject to The protective plate installing hole 23 arranged on power channel-section steel 21 is connected by bolt, and connecting plate 41 can be around the hinge with vertical applied force channel-section steel 21 The place's of connecing rotation is fixing after carrying out angular adjustment, and the other end of connecting plate 41 is connected with protective baffle plate 42.
Protective plate 3 is placed on the connecting plate 41 of protective frame 4, and protective plate 3 is of an L-shaped structure and is multilayer proofing plate.
Embedded ribs 5 is threaded rod structure, and embedded ribs 5 is perpendicular to one end of horizontal force channel-section steel 22 and embedded ribs 5 and is embedded in In reservoir dam 1, the other end of embedded ribs 5 is clamped on horizontal force channel-section steel 22 by clamp nut 7 and tapered cup nut 8, cone Fusing hole it is provided with on shape nut 8.
Screw mandrel 6 is for the linking location of stress channel-section steel 2 and the demoulding of stress channel-section steel 2.
Skilled person will appreciate that of the industry, the present invention is not restricted to the described embodiments, above-described embodiment and explanation The principle that the present invention is simply described described in book, without departing from the spirit and scope of the present invention, the present invention also has Various changes and modifications, these changes and improvements both fall within scope of the claimed invention.Claimed scope Defined by appending claims and equivalent thereof.

Claims (5)

1. a cantilevered reservoir dam template, this model sheetinstallat is on the sidewall of inclination or vertical reservoir dam, including being subject to Power channel-section steel, protective plate, protective frame, embedded ribs and screw mandrel;Stress channel-section steel is close on the sidewall of reservoir dam, and embedded ribs is perpendicular to Stress channel-section steel and being embedded in reservoir dam, protective plate is placed in protective frame, and protective frame and stress channel-section steel are connected to form U-shaped knot Structure;It is characterized in that: be connected by screw mandrel between the end of stress channel-section steel, by embedded ribs as supporting and watering at one section of dam Fuse after having built embedded ribs by screw mandrel dismounting stress channel-section steel, protective plate and protective frame, by stress channel-section steel, protective plate with prevent Retaining frame upwards stacks and carries out the construction of next section of reservoir dam by the mode installing embedded ribs behind screw mandrel location additional;
Described stress channel-section steel is some sections of vertical applied force channel-section steels and the cross-shaped configuration of horizontal force channel-section steel formation, vertical applied force groove Steel and horizontal force channel-section steel are vertical and horizontally arranged respectively along inclined plane or the vertical of reservoir dam, and stress groove sets Being equipped with protective plate installing hole, the end, two ends of stress channel-section steel is respectively arranged with hinged buckle and hinged draw-in groove, by screw mandrel is embedding Enter and in hinged buckle and hinged draw-in groove, stress channel-section steel is connected.
A kind of cantilevered reservoir dam template the most according to claim 1, it is characterised in that: described protective frame is divided into up and down If dried layer, including connecting plate and protective baffle plate;One end of connecting plate leads to the protective plate installing hole of setting on vertical applied force channel-section steel Crossing bolt to be connected, connecting plate can rotate around the hinged place with vertical applied force channel-section steel after carrying out angular adjustment to be fixed, connecting plate The other end is connected with protective baffle plate.
A kind of cantilevered reservoir dam template the most according to claim 1, it is characterised in that: described protective plate is placed in protection On the connecting plate of frame, protective plate is of an L-shaped structure and is multilayer proofing plate.
A kind of cantilevered reservoir dam template the most according to claim 1, it is characterised in that: described embedded ribs is threaded rod Structure, embedded ribs is perpendicular to one end of horizontal force channel-section steel and embedded ribs and is embedded in reservoir dam, and the other end of embedded ribs leads to Cross clamp nut and tapered cup nut is clamped on horizontal force channel-section steel, tapered cup nut is provided with fusing hole.
A kind of cantilevered reservoir dam template the most according to claim 1, it is characterised in that: described screw mandrel is used for stress groove The linking location of steel and the demoulding of stress channel-section steel.
CN201610733250.5A 2016-08-27 2016-08-27 A kind of cantilevered reservoir dam template Active CN106168028B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610733250.5A CN106168028B (en) 2016-08-27 2016-08-27 A kind of cantilevered reservoir dam template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610733250.5A CN106168028B (en) 2016-08-27 2016-08-27 A kind of cantilevered reservoir dam template

Publications (2)

Publication Number Publication Date
CN106168028A true CN106168028A (en) 2016-11-30
CN106168028B CN106168028B (en) 2018-06-26

Family

ID=57376714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610733250.5A Active CN106168028B (en) 2016-08-27 2016-08-27 A kind of cantilevered reservoir dam template

Country Status (1)

Country Link
CN (1) CN106168028B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2045410U (en) * 1989-04-05 1989-10-04 潘昭汉 Portable seft-lift type pulling yoke for shuttering
CN2231274Y (en) * 1994-12-12 1996-07-17 中国水利水电第八工程局 Disassemble and assemble alternatively lifting full cantilever large steel shuttering
JP2003342940A (en) * 2002-05-28 2003-12-03 Marufuji Sheet Piling Co Ltd Bank-body temporary coffering slit mounting construction method in checkdam and protector used for the same
CN203247546U (en) * 2013-04-16 2013-10-23 葛洲坝集团第五工程有限公司 Combined type suspended wall formwork for pouring dam inclined portion
CN204662369U (en) * 2015-06-08 2015-09-23 中国葛洲坝集团第六工程有限公司 A kind of slope cantilever large form
CN206090567U (en) * 2016-08-27 2017-04-12 南通格瑞环保科技有限公司 Cantilever type reservoir dam template

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2045410U (en) * 1989-04-05 1989-10-04 潘昭汉 Portable seft-lift type pulling yoke for shuttering
CN2231274Y (en) * 1994-12-12 1996-07-17 中国水利水电第八工程局 Disassemble and assemble alternatively lifting full cantilever large steel shuttering
JP2003342940A (en) * 2002-05-28 2003-12-03 Marufuji Sheet Piling Co Ltd Bank-body temporary coffering slit mounting construction method in checkdam and protector used for the same
CN203247546U (en) * 2013-04-16 2013-10-23 葛洲坝集团第五工程有限公司 Combined type suspended wall formwork for pouring dam inclined portion
CN204662369U (en) * 2015-06-08 2015-09-23 中国葛洲坝集团第六工程有限公司 A kind of slope cantilever large form
CN206090567U (en) * 2016-08-27 2017-04-12 南通格瑞环保科技有限公司 Cantilever type reservoir dam template

Also Published As

Publication number Publication date
CN106168028B (en) 2018-06-26

Similar Documents

Publication Publication Date Title
CN210766774U (en) Positioning device for steel reinforcement cage and lattice column
CN103306208A (en) Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN203821867U (en) Shear wall body assembling and aligning device
CN209163516U (en) A kind of post-cast strip tool support device
CN107190647A (en) A kind of alignment control apparatus and method suitable for the special-shaped tower of steel construction
CN206090567U (en) Cantilever type reservoir dam template
CN209538694U (en) A kind of aluminum alloy mould plate holder device
CN106168028A (en) A kind of cantilevered reservoir dam template
CN106958233A (en) Hydraulic self-lifting formula cantilever form construction method for pouring Arch Dam Concrete
CN206971725U (en) Hang the erecting device of mould
CN103195079B (en) Installing type template, installing type template group and complete installing type plate device
CN108775147A (en) A kind of wall body casting template supporting construction device
CN105113536A (en) Movable sidewall formwork erecting system for underground structure and construction method of system
CN107299621A (en) A kind of cantilevered building template
CN104563515A (en) Template bracing structure for ultrahigh shear wall and construction method thereof
CN103982049A (en) Wall body assembling straightening device for shear wall
CN103382700B (en) Movable die frame girder device and method suitable for construction of single side widening box girder with large width
CN210369955U (en) Prefabricated external wall panel mounting structure
CN109235709B (en) Full cast-in-place outer wall structure of building
CN210947661U (en) Installation device of socket type overhanging scaffold
CN206971267U (en) The mobile device of underground pipe gallery formwork
CN207331470U (en) A kind of embedded box anchors assembled bracket
CN207160052U (en) A kind of skewback for connecting arcuate bead steel construction
CN206219080U (en) A kind of tower crane
CN205935706U (en) A elevation controlling means for terrace construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A cantilever dam formwork for reservoir

Effective date of registration: 20220628

Granted publication date: 20180626

Pledgee: Jiangsu Rugao Rural Commercial Bank Co.,Ltd. chaidong sub branch

Pledgor: NANTONG GREEN ENVIRONMENTAL PROTECTION TECHNOLOGY CO.,LTD.

Registration number: Y2022980009257

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230606

Granted publication date: 20180626

Pledgee: Jiangsu Rugao Rural Commercial Bank Co.,Ltd. chaidong sub branch

Pledgor: NANTONG GREEN ENVIRONMENTAL PROTECTION TECHNOLOGY CO.,LTD.

Registration number: Y2022980009257

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A cantilever type reservoir dam template

Effective date of registration: 20230608

Granted publication date: 20180626

Pledgee: Jiangsu Rugao Rural Commercial Bank Co.,Ltd. chaidong sub branch

Pledgor: NANTONG GREEN ENVIRONMENTAL PROTECTION TECHNOLOGY CO.,LTD.

Registration number: Y2023980043253