CN106094495A - Intelligent electronic equipment of transformer substation timing tracking accuracy and the method for testing of punctual precision - Google Patents

Intelligent electronic equipment of transformer substation timing tracking accuracy and the method for testing of punctual precision Download PDF

Info

Publication number
CN106094495A
CN106094495A CN201610420556.5A CN201610420556A CN106094495A CN 106094495 A CN106094495 A CN 106094495A CN 201610420556 A CN201610420556 A CN 201610420556A CN 106094495 A CN106094495 A CN 106094495A
Authority
CN
China
Prior art keywords
time
tester
tested ied
ied equipment
integrated automation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610420556.5A
Other languages
Chinese (zh)
Other versions
CN106094495B (en
Inventor
彭志强
张小易
霍雪松
张琦兵
杨明
李虎成
樊海锋
夏杰
郑明忠
袁宇波
高磊
卜强生
宋亮亮
刘玙
宋爽
杨毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610420556.5A priority Critical patent/CN106094495B/en
Publication of CN106094495A publication Critical patent/CN106094495A/en
Application granted granted Critical
Publication of CN106094495B publication Critical patent/CN106094495B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G04HOROLOGY
    • G04GELECTRONIC TIME-PIECES
    • G04G7/00Synchronisation

Abstract

The invention discloses a kind of intelligent electronic equipment of transformer substation timing tracking accuracy and the method for testing of punctual precision, the method of testing of intelligent electronic equipment of transformer substation timing tracking accuracy: step 1, by integrated automation of transformation stations tester pair time interface be connected with standard time source, tested IED equipment is connected with internal clock source, station, the hard pressing plate upper and lower end that overhauls of tested IED equipment is connected with the positive and negative end of the idle contact of integrated automation of transformation stations tester respectively;When step 2, integrated automation of transformation stations tester are carried out pair by standard time source, when tested IED equipment is carried out pair by internal clock source, station;Step 3, integrated automation of transformation stations tester close at T1 time trigger idle contact;Step 4, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T2;Step 5, the absolute value of calculating T1 T2, be the timing tracking accuracy of tested IED equipment.Method of testing is simple and convenient, and measuring accuracy is high.

Description

Intelligent electronic equipment of transformer substation timing tracking accuracy and the method for testing of punctual precision
Technical field
The present invention relates to a kind of intelligent electronic equipment of transformer substation timing tracking accuracy and the method for testing of punctual precision.
Background technology
The accuracy of power system time synchronized is to ensure that Operation of Electric Systems controls and the important foundation bar of accident analysis Part, its Core Feature is to provide time synchronized function services for transient state, dynamic, steady state data collection and electric network fault analysis.Become Power station clock synchronization system provides time service source for secondary device in station, at present for intelligent electronic device (IED) time synchronized essence The test of degree and punctual precision lacks simple and convenient method of testing.
Summary of the invention
For the problems referred to above, the present invention provides a kind of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision Method of testing, method of testing is simple and convenient, and measuring accuracy is high, can apply to substation secondary device factory inspection and acceptance and tests and existing Field Acceptance Test.
For realizing above-mentioned technical purpose, reaching above-mentioned technique effect, the present invention is achieved through the following technical solutions:
The method of testing of intelligent electronic equipment of transformer substation timing tracking accuracy, it is characterised in that comprise the steps:
Step 1, by integrated automation of transformation stations tester pair time interface be connected with standard time source, tested IED is set For being connected with the internal clock source, station of transformer station, the maintenance hard pressing plate upper end of tested IED equipment is surveyed with the integrated automation of transformation stations The anode of the idle contact of examination instrument is connected, by the maintenance hard pressing plate lower end of tested IED equipment and integrated automation of transformation stations tester Idle contact negative terminal be connected;
When step 2, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by station When internal clock source is carried out pair;
Step 3, integrated automation of transformation stations tester close at T1 time trigger idle contact;
Step 4, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T2;
Step 5, the absolute value of calculating T1 T2, be the timing tracking accuracy of tested IED equipment.
Intelligent electronic equipment of transformer substation is kept time the method for testing of precision, it is characterised in that comprise the steps:
Step a, by integrated automation of transformation stations tester pair time interface be connected with standard time source, tested IED is set For being connected with the internal clock source, station of transformer station, the maintenance hard pressing plate upper end of tested IED equipment is surveyed with the integrated automation of transformation stations The anode of the idle contact of examination instrument is connected, by the maintenance hard pressing plate lower end of tested IED equipment and integrated automation of transformation stations tester Idle contact negative terminal be connected;
When step b, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by station When internal clock source is carried out pair;
Step c, disconnect the internal clock source, station of tested IED equipment, make tested IED equipment enter punctual pattern;
Step d, integrated automation of transformation stations tester close at T3 time trigger idle contact;
Step e, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T4;
Step f, the absolute value of calculating T3 T4, be the punctual precision of tested IED equipment.
The invention has the beneficial effects as follows:
The present invention provides one to utilize IED overhaul of the equipments hard pressing plate to open into, concatenation integrated automation of transformation stations tester Outputing idle contact, the Guan Bi controlling to output idle contact makes IED equipment generation SOE event come testing time synchronization accuracy and punctual essence The method of testing of degree, can solve the test of substation secondary device factory inspection and acceptance and onsite acceptance test without effectively surveying by the method The problem of trial work section, improves testing efficiency and measuring accuracy.
Accompanying drawing explanation
Fig. 1 is the structural representation of the method for testing of intelligent electronic equipment of transformer substation timing tracking accuracy of the present invention;
Fig. 2 is that intelligent electronic equipment of transformer substation of the present invention is kept time the structural representation of method of testing of precision.
Detailed description of the invention
With specific embodiment, technical solution of the present invention is described in further detail below in conjunction with the accompanying drawings, so that ability The technical staff in territory can be better understood from the present invention and can be practiced, but illustrated embodiment is not as the limit to the present invention Fixed.
The method of testing of intelligent electronic equipment of transformer substation timing tracking accuracy, comprises the steps:
Step 1 as it is shown in figure 1, by integrated automation of transformation stations tester pair time interface be connected with standard time source, will Tested IED equipment (Substation IED equipment includes measure and control device, protective relaying device, intelligent terminal, combining unit etc.) and power transformation The internal clock source, station stood is connected, by the sky overhauling hard pressing plate upper end and integrated automation of transformation stations tester of tested IED equipment The anode of contact is connected, by the idle contact overhauling hard pressing plate lower end and integrated automation of transformation stations tester of tested IED equipment Negative terminal be connected.
Wherein standard time source receives satellite time source, external outputting standard time, integrated automation of transformation stations tester By pair time interface accept standard time source pair time signal, pair time precision higher than the time precision of IEC equipment, transformer station is comprehensive Automatic test instrument is connected with standard time source by hardwire IRIG B code.
When step 2, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by station When internal clock source is carried out pair;
Step 3, integrated automation of transformation stations tester close at T1 time trigger idle contact, it is preferable that during idle contact Guan Bi Between more than overhaul the hard pressing plate stabilization time.It addition, for the ease of calculating and reducing error, be preferably provided whole moment second, i.e. power transformation Comprehensive automation tester of standing closes at whole second T1 time trigger idle contact.
Step 4, tested IED equipment receive idle contact closure signal, produce SOE (logout) record, during SOE record Between be T2, can by IED device liquid crystal check SOE record the time or check on supervisory control of substation backstage SOE record the time.
Step 5, the absolute value of calculating T1 T2, be the timing tracking accuracy of tested IED equipment.
Corresponding, intelligent electronic equipment of transformer substation is kept time the method for testing of precision, comprises the steps:
Step a, by integrated automation of transformation stations tester pair time interface be connected with standard time source, tested IED is set For being connected with the internal clock source, station of transformer station, the maintenance hard pressing plate upper end of tested IED equipment is surveyed with the integrated automation of transformation stations The anode of the idle contact of examination instrument is connected, by the maintenance hard pressing plate lower end of tested IED equipment and integrated automation of transformation stations tester Idle contact negative terminal be connected;
When step b, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by station When internal clock source is carried out pair;
Step c, disconnect the internal clock source, station of tested IED equipment, make tested IED equipment enter punctual pattern, such as Fig. 2 institute Show;
Step d, integrated automation of transformation stations tester close at T3 time trigger idle contact.Preferably, during idle contact Guan Bi Between more than overhaul the hard pressing plate stabilization time.It addition, for the ease of calculating and reducing error, be preferably provided whole moment second, i.e. power transformation Comprehensive automation tester of standing closes at whole second T3 time trigger idle contact.
Step e, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T4;
Step f, the absolute value of calculating T3 T4, be the punctual precision of tested IED equipment.
The present invention provides one to utilize IED overhaul of the equipments hard pressing plate to open into, concatenation integrated automation of transformation stations tester Outputing idle contact, the Guan Bi controlling to output idle contact makes IED equipment generation SOE event come testing time synchronization accuracy and punctual essence The method of testing of degree, can solve the test of substation secondary device factory inspection and acceptance and onsite acceptance test without effectively surveying by the method The problem of trial work section, improves testing efficiency and measuring accuracy.Method of testing is simple and convenient, and measuring accuracy is high, can apply to become Power station secondary device factory inspection and acceptance test and onsite acceptance test.
These are only the preferred embodiments of the present invention, not thereby limit the scope of the claims of the present invention, every utilize this Equivalent structure or equivalence flow process that bright description and accompanying drawing content are made convert, or it is relevant to be directly or indirectly used in other Technical field, be the most in like manner included in the scope of patent protection of the present invention.

Claims (6)

1. the method for testing of intelligent electronic equipment of transformer substation timing tracking accuracy, it is characterised in that comprise the steps:
Step 1, by integrated automation of transformation stations tester pair time interface be connected with standard time source, by tested IED equipment with The internal clock source, station of transformer station is connected, by the maintenance hard pressing plate upper end of tested IED equipment and integrated automation of transformation stations tester The anode of idle contact be connected, by the sky overhauling hard pressing plate lower end and integrated automation of transformation stations tester of tested IED equipment The negative terminal of contact is connected;
When step 2, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by time in station When Zhong Yuan is carried out pair;
Step 3, integrated automation of transformation stations tester close at T1 time trigger idle contact;
Step 4, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T2;
Step 5, the absolute value of calculating T1 T2, be the timing tracking accuracy of tested IED equipment.
The method of testing of intelligent electronic equipment of transformer substation timing tracking accuracy the most according to claim 1, it is characterised in that Idle contact closing time is more than overhauling the hard pressing plate stabilization time.
The method of testing of intelligent electronic equipment of transformer substation timing tracking accuracy the most according to claim 2, it is characterised in that The T1 moment is whole moment second.
4. intelligent electronic equipment of transformer substation is kept time the method for testing of precision, it is characterised in that comprise the steps:
Step a, by integrated automation of transformation stations tester pair time interface be connected with standard time source, by tested IED equipment with The internal clock source, station of transformer station is connected, by the maintenance hard pressing plate upper end of tested IED equipment and integrated automation of transformation stations tester The anode of idle contact be connected, by the sky overhauling hard pressing plate lower end and integrated automation of transformation stations tester of tested IED equipment The negative terminal of contact is connected;
When step b, integrated automation of transformation stations tester are carried out pair by standard time source, tested IED equipment is by time in station When Zhong Yuan is carried out pair;
Step c, disconnect the internal clock source, station of tested IED equipment, make tested IED equipment enter punctual pattern;
Step d, integrated automation of transformation stations tester close at T3 time trigger idle contact;
Step e, tested IED equipment receive idle contact closure signal, produce SOE record, and the SOE record time is T4;
Step f, the absolute value of calculating T3 T4, be the punctual precision of tested IED equipment.
Intelligent electronic equipment of transformer substation the most according to claim 4 is kept time the method for testing of precision, it is characterised in that sky connects Point closing time is more than overhauling the hard pressing plate stabilization time.
Intelligent electronic equipment of transformer substation the most according to claim 5 is kept time the method for testing of precision, it is characterised in that during T3 Carve as whole moment second.
CN201610420556.5A 2016-06-15 2016-06-15 The test method of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision Active CN106094495B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610420556.5A CN106094495B (en) 2016-06-15 2016-06-15 The test method of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610420556.5A CN106094495B (en) 2016-06-15 2016-06-15 The test method of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision

Publications (2)

Publication Number Publication Date
CN106094495A true CN106094495A (en) 2016-11-09
CN106094495B CN106094495B (en) 2018-06-19

Family

ID=57846211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610420556.5A Active CN106094495B (en) 2016-06-15 2016-06-15 The test method of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision

Country Status (1)

Country Link
CN (1) CN106094495B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107703926A (en) * 2017-11-13 2018-02-16 国网江苏省电力公司电力科学研究院 A kind of network system protects fast cut back multi-point control time method of testing
CN107769836A (en) * 2017-09-13 2018-03-06 长光卫星技术有限公司 Satellite General automatic test platform and its data interactive method
CN112737877A (en) * 2020-12-25 2021-04-30 国网江苏省电力有限公司苏州供电分公司 Secondary equipment time setting state monitoring method and system
CN113567852A (en) * 2021-08-10 2021-10-29 武汉映瑞电力科技有限公司 Device and method for testing time deviation and time keeping precision of relay protection device
CN114063435A (en) * 2021-11-17 2022-02-18 国网四川省电力公司广安供电公司 Time synchronization instrument, and clock device detection method and system based on time synchronization instrument

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006234544A (en) * 2005-02-24 2006-09-07 Toshiba Corp Time synchronizer of supervisory control system
CN101242317A (en) * 2008-02-28 2008-08-13 江苏电力调度通信中心 Time device precision and stability monitoring method
CN102315985A (en) * 2011-08-30 2012-01-11 广东电网公司电力科学研究院 Time synchronization precision test method for intelligent device adopting IEEE1588 protocols
CN102315928A (en) * 2011-08-30 2012-01-11 广东电网公司电力科学研究院 Test method of IED network clock synchronization precision based on GOOSE mechanism
CN105450323A (en) * 2015-11-11 2016-03-30 杭州和利时自动化有限公司 SOE time synchronization control method and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006234544A (en) * 2005-02-24 2006-09-07 Toshiba Corp Time synchronizer of supervisory control system
CN101242317A (en) * 2008-02-28 2008-08-13 江苏电力调度通信中心 Time device precision and stability monitoring method
CN102315985A (en) * 2011-08-30 2012-01-11 广东电网公司电力科学研究院 Time synchronization precision test method for intelligent device adopting IEEE1588 protocols
CN102315928A (en) * 2011-08-30 2012-01-11 广东电网公司电力科学研究院 Test method of IED network clock synchronization precision based on GOOSE mechanism
CN105450323A (en) * 2015-11-11 2016-03-30 杭州和利时自动化有限公司 SOE time synchronization control method and system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107769836A (en) * 2017-09-13 2018-03-06 长光卫星技术有限公司 Satellite General automatic test platform and its data interactive method
CN107769836B (en) * 2017-09-13 2020-04-17 长光卫星技术有限公司 Satellite universal automatic test platform and data interaction method thereof
CN107703926A (en) * 2017-11-13 2018-02-16 国网江苏省电力公司电力科学研究院 A kind of network system protects fast cut back multi-point control time method of testing
CN112737877A (en) * 2020-12-25 2021-04-30 国网江苏省电力有限公司苏州供电分公司 Secondary equipment time setting state monitoring method and system
CN113567852A (en) * 2021-08-10 2021-10-29 武汉映瑞电力科技有限公司 Device and method for testing time deviation and time keeping precision of relay protection device
CN114063435A (en) * 2021-11-17 2022-02-18 国网四川省电力公司广安供电公司 Time synchronization instrument, and clock device detection method and system based on time synchronization instrument
CN114063435B (en) * 2021-11-17 2023-02-28 国网四川省电力公司广安供电公司 Time synchronization instrument, and clock device detection method and system based on time synchronization instrument

Also Published As

Publication number Publication date
CN106094495B (en) 2018-06-19

Similar Documents

Publication Publication Date Title
CN106094495B (en) The test method of intelligent electronic equipment of transformer substation timing tracking accuracy and punctual precision
CN103105550B (en) A kind of intelligent relay protection device detection method and system
CN103885438B (en) The Auto-Test System of a kind of transformer station measuring and controlling equipment and method
CN102053235A (en) On-site steady-state accuracy verification system for electronic current transformer and verification method thereof
CN102928810A (en) System and method for evaluating accuracy of digital electric energy meter
CN104020374A (en) Intelligent substation secondary equipment site-wide simulation test system
CN110401692A (en) A kind of automatic Acceptance Test System of supervisory control of substation information integral and method
CN203069774U (en) System for evaluating accuracy of digital electric energy meter
CN110161331B (en) Detection platform for primary and secondary fusion complete equipment and control method
CN105159282A (en) Process level simulation system and closed-loop testing method of intelligent transformer substation measuring and control device
CN202384838U (en) Secondary system real-time simulation testing platform for total station of intelligent transformer substation
CN102662152A (en) Electronic type mutual inductor as well as system and method for verifying merging unit
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN104215838A (en) Remote nuclear phase method for intelligent substation
CN105137240A (en) Merging unit quantity measurement simulation system for intelligent transformer station, and closed-loop testing method
CN102680807A (en) Optical fiber digitized remote phase-checking system and phase-checking method thereof
CN202886585U (en) On-line test device for voltage/current transformer
CN102866378B (en) Voltage or current transformer on-line test device and voltage or current transformer on-line test method
CN106054000A (en) Interval merging unit power factor angle consistency on-site test system and method
CN206223953U (en) A kind of electronic mutual inductor transient test device based on RTDS real-time simulations
CN103645392A (en) Method for realizing device test protection through recording and playback
CN111062825A (en) Low-voltage fault diagnosis and rapid power restoration method based on mobile App
CN104502748A (en) Transformer station integrated automatic test system
CN109002030B (en) Flexible direct current protection test method based on FT3 message switching value position acquisition
CN201742169U (en) Digital real-time testing analyzer of secondary system in transformer station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant