CN106089027B - A kind of construction method using anti-well rig maintenance drop shaft - Google Patents
A kind of construction method using anti-well rig maintenance drop shaft Download PDFInfo
- Publication number
- CN106089027B CN106089027B CN201610393560.7A CN201610393560A CN106089027B CN 106089027 B CN106089027 B CN 106089027B CN 201610393560 A CN201610393560 A CN 201610393560A CN 106089027 B CN106089027 B CN 106089027B
- Authority
- CN
- China
- Prior art keywords
- drop shaft
- former
- well
- pass
- drilling machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 35
- 238000012423 maintenance Methods 0.000 title claims abstract description 29
- 238000005553 drilling Methods 0.000 claims abstract description 60
- 239000004567 concrete Substances 0.000 claims abstract description 57
- 230000008093 supporting effect Effects 0.000 claims abstract description 13
- 238000001514 detection method Methods 0.000 claims abstract description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 17
- 239000010959 steel Substances 0.000 claims description 17
- 239000004576 sand Substances 0.000 claims description 14
- 239000000463 material Substances 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 210000001258 synovial membrane Anatomy 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 2
- 239000011435 rock Substances 0.000 abstract description 4
- 238000000034 method Methods 0.000 description 5
- 235000019994 cava Nutrition 0.000 description 3
- 230000006378 damage Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 239000000654 additive Substances 0.000 description 2
- 230000000996 additive effect Effects 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 239000011178 precast concrete Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 229910052500 inorganic mineral Inorganic materials 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 239000011707 mineral Substances 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/28—Enlarging drilled holes, e.g. by counterboring
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/04—Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Geochemistry & Mineralogy (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Physics & Mathematics (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Revetment (AREA)
- Earth Drilling (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention discloses a kind of construction method using anti-well rig maintenance drop shaft, includes the following steps:(1) former pass space structure detection;(2) former pass is filled according to the result of detection of gained in step (1);(3) raising boring is carried out to the former pass after step (2) filling using anti-well drilling machine and forms new pass;(4) supporting is carried out to the new drop shaft borehole wall drilled in step (3).Master operation of the present invention no longer needs well operations under personnel, when carrying out borehole wall supporting, is controlled country rock, and not only anti-well drilling machine drilling concrete does not destroy its performance, but also has ensured the personal safety of staff.
Description
Technical field
The present invention relates to drilling applications, more particularly to a kind of construction method using anti-well rig maintenance drop shaft.
Background technology
, it is necessary to substantial amounts of drop shaft engineering, the different exploitations of these Project Realizations in well industrial and mineral thing exploits roadway engineering system
Horizontal ore is concentrated, adjusts the functions such as transport, and the general 50-300m of drop shaft depth, is filled in ore by tippler or belt equipment
During entering drop shaft, ore free-falling, huge impact force damages the drop shaft borehole wall and country rock, produces empty and big
Area caves in, and influences the use of drop shaft, the safety of mine is influenced when serious, it is necessary to repaired.
The restorative procedure of drop shaft generally carries out, it is necessary to which the supportings such as operating personnel are anchored, whitewashed paragraph by paragraph are made from top to bottom
Industry, in the area that caves in, highly larger place, it is necessary to set up scaffold, safety problem cannot solve personnel's operating difficulties at all
Certainly, accident often occurs.
The content of the invention
In view of this, the invention reside in a kind of construction method using anti-well rig maintenance drop shaft is provided, master operation is not
Well operations under personnel are needed again, when carrying out borehole wall supporting, are controlled country rock, and not only anti-well drilling machine drilling concrete is not broken
Its bad performance, and ensured the personal safety of staff.
To solve the above problems, the present invention adopts the following technical scheme that:A kind of construction using anti-well rig maintenance drop shaft
Method, includes the following steps:
(1) former pass space structure detection;
(2) former pass is filled according to the result of detection of gained in step (1);
(3) raising boring is carried out to the former pass after step (2) filling using anti-well drilling machine and forms new drop shaft well
Cylinder;
(4) supporting is carried out to the new drop shaft borehole wall drilled in step (3).
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (1) include the following steps:
(a) lift is installed on the top of former drop shaft, using ultrasonic meter along former pass from top to bottom to original
Pass carries out profile scanning one by one;
(b) data obtained in step (a) are analyzed, calculates former drop shaft spatial volume, and draw out former drop shaft
The space structure shape of pit shaft.
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (2) include the following steps:
(a1) anti-well drilling machine is installed, and anti-well borer drill rod is protected;
(b1) former pass is filled.
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (a1) concretely comprise the following steps:In the upper end of former drop shaft
Well head installs drilling machine girder steel, anti-well drilling machine is then installed on drilling machine girder steel, and anti-well borer drill rod is transferred to former drop shaft
Lower end well head, is then wrapped up anti-well borer drill rod with casing, and is filled between anti-well borer drill rod outer wall and internal surface of sleeve pipe
Grit material.
The above-mentioned construction method using anti-well rig maintenance drop shaft, casing is plastic tube.
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (b1) include the following steps:
(i) lower end port of the annular space between sleeve outer wall and the former drop shaft borehole wall, Ran Houxiang are blocked with plug members
Fine sand is filled with former pass;
(ii) grey tremie pipe is slipped in brattice way handling, then according to the former drop shaft space body calculated in step (b)
Product precast concrete, then carries out concrete filling to former pass paragraph by paragraph, until concrete filling body upper surface distance is bored
Machine girder steel lower part is greater than or equal to 0.3m and is less than or equal to 0.5m, then refills anti-well drilling machine basis concrete, and make
Anti- well drilling machine basis is closely connected with concrete filling body with drilling machine girder steel.Anti- well drilling machine basis is formed anti-with concrete filling body
The concrete foundation on well drilling machine basis forms anti-well drilling machine basis with drilling machine girder steel, wherein, drilling machine girder steel is seated in coagulation soil matrix
On plinth.Concrete foundation is higher than filling concrete strength.
The above-mentioned construction method using anti-well rig maintenance drop shaft, when the former pass close to former drop shaft lower end well head does not have
When having destroyed, fine sand is filled to the position for the well section lower end well head 1m that is damaged apart from former drop shaft, and fine sand filling length is more than or waits
In 5m;To the concrete used in former pass progress concrete filling marked as C10-20。
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (3) concretely comprise the following steps:It is filled in step (ii)
When concrete setting and intensity in former pass reach design requirement, plug members are removed, releases and is filled in former pass
The fine sand filled out, then installs reaming bit in the lower end of anti-well borer drill rod, reaming from bottom to top, until former drop shaft upper end well
Mouthful, new pass drilling is completed.Since the concrete conditions such as the well depth of each drop shaft, hole diameter are different, it is filled in difference and slips
The set strength of well shaft inner concrete will be determined according to each pass concrete condition, usually select the coagulation of low grade
Soil fills pass.
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (4) include the following steps:
(I) the anti-well drilling machine in dismantling step (3), lift and hanging scaffold are installed on new pass top, are checked new
The safe condition of pass, is handled local unstable formation and concrete and supporting;
(II) new drop shaft inner wall is poured.
The above-mentioned construction method using anti-well rig maintenance drop shaft, step (II) concretely comprise the following steps:Using hydraulic pressure synovial membrane
Mode progressively pours new drop shaft inner wall from bottom to top.
The beneficial effects of the invention are as follows:
1. the present invention is a kind of formed using concrete backfill, anti-well drill drilling after drop shaft covers the Synthetic for building the borehole wall again
Reason method, wherein master operation no longer need well operations under personnel, and when carrying out borehole wall supporting, country rock has been controlled,
And anti-well drilling machine drilling concrete does not destroy its performance, while the secure personal safety of staff.
2. the construction period of the invention is shorter, and new drilled drop shaft wellbore stability, easy supporting.
Brief description of the drawings
Fig. 1 is the present invention showing using the construction method Central Plains pass space structure detection of anti-well rig maintenance drop shaft
It is intended to;
Fig. 2 is schematic diagram of the present invention using anti-well drilling machine installation in the construction method of anti-well rig maintenance drop shaft;
Fig. 3 is the present invention showing using the former pass fill concrete in the construction method of anti-well rig maintenance drop shaft
It is intended to;
Fig. 4 is schematic diagram of the present invention using anti-well drilling machine reaming drilling in the construction method of anti-well rig maintenance drop shaft;
Fig. 5 is schematic diagram of the present invention using new drop shaft borehole wall supporting in the construction method of anti-well rig maintenance drop shaft.
In figure:1- original pass;2- ultrasonic meters;3- lifts;The anti-well drilling machines of 4-;5- drilling machine girder steels;6- is anti-
Well borer drill rod;7- casings;8- reaming bits;The new pass of 9-;10- hanging scaffolds;11- concrete filling bodies.
Embodiment
Scheme in the present invention to clearly illustrate, is given below preferred embodiment and is described with reference to the accompanying drawings.
As shown in Figures 1 to 3, the present invention is that one kind utilizes concrete pair using the construction method of anti-well rig maintenance drop shaft
Former pass 1 is backfilled, and is then recycled anti-4 drilling well of well drilling machine to form new pass 9 and carry out set to new drop shaft and is built
The drop shaft comprehensive processing method of the borehole wall, it is comprised the following steps that:
(1) due to after former drop shaft fall damage its structural form can vary widely, thus before being administered to it
The space structure shape of former drop shaft need to be understood, i.e., former 1 space structure of pass is detected, concretely comprised the following steps:
(a) lift 3 is installed on the top of former drop shaft, hanging ultrasonic meter 2 using lift 3 is allowed to slip along original
Well shaft 1 carries out profile scanning one by one to former pass 1 from top to bottom, to obtain the space structure in relation to former pass 1
The data of shape, as shown in Figure 1;
(b) data obtained in step (a) are analyzed, calculates former drop shaft spatial volume, and draw out former drop shaft
The space structure shape of pit shaft 1.
(2) cave in and produce cavity since large area has occurred in the former drop shaft borehole wall, it is whole in order to be carried out to the former drop shaft borehole wall
Body reparation, backfills former pass 1 using concrete in of the invention, to obtain the relatively stable drop shaft borehole wall,
Therefore former pass 1 is filled according to the result of detection of gained in step (1), it is concretely comprised the following steps;
(a1) in view of the present invention is crept into using anti-well drilling machine 4, in order to easy for construction, backfilled to former pass 1
Before, first anti-well drilling machine 4 is installed in place, as shown in Fig. 2, installing drilling machine girder steel 5, Ran Hou in the upper end well head of former drop shaft
Anti- well drilling machine 4 is installed on drilling machine girder steel 5, and anti-well borer drill rod 6 is transferred to the lower end well head of former drop shaft, but due to concrete
In additive may produce corrosion to anti-well borer drill rod 6, and anti-well borer drill rod 6 can be influenced after concrete setting
Rotate, therefore wrapped up anti-well borer drill rod 6 with casing 7, and filled slightly between anti-6 outer wall of well borer drill rod and 7 inner wall of casing
Sand material material, its middle sleeve 7 are plastic tube, select PVC plastic pipe to be used as casing 7 in the present embodiment, using set in this step
Pipe 7 protects anti-well borer drill rod 6, its first purpose is to prevent the additive in concrete to anti-well borer drill rod 6
Corrosion and the rotation easy to the anti-well borer drill rod 6 of raising boring process in subsequent step, another object is that being carried for raising boring
For guide hole, consequently facilitating that entirely constructs is smoothed out;
(b1) after installing anti-well drilling machine 4 and properly protecting to anti-well borer drill rod 6, you can to former pass 1 into
Row filling, as shown in figure 3, its specific steps includes:
(i) concrete to avoid being filled in former pass 1 leaks to influences subsequent construction elsewhere, it will usually
The lower end port of the annular space between 7 outer wall of casing and the former drop shaft borehole wall is blocked using plug members, and in order to anti-
Only concrete bonds together with plug members and is not easy to the dismounting of plug members, and former pass 1 is being carried out with concrete
Before backfill, it will usually be filled with fine sand into former pass 1, the height that is filled with of its medium-fine sand can be according to close to former drop shaft lower end
The destruction situation of the former pass 1 of well head determines, when the former pass 1 close to former drop shaft lower end well head is without destroyed
When, fine sand is filled to the position for the well section lower end well head 1m that is damaged apart from former drop shaft, and fine sand filling length is greater than or equal to 5m;
(ii) grey tremie pipe being slipped using winch handling in brattice way, the wherein internal diameter of tremie pipe is greater than or equal to 150mm,
Then according to the former drop shaft spatial volume precast concrete calculated in step (b), then former pass 1 is carried out paragraph by paragraph
Concrete filling, until the position of 11 upper surface distance borehole drilling rig girder steel of concrete filling body, 5 lower part 0.5m, then refills anti-well
Drilling machine basis concrete, and anti-well drilling machine basis is closely connected with concrete filling body with drilling machine girder steel 5, reach and undertake expansion
The ability of hole load.The concrete foundation that anti-well drilling machine basis concrete filling body is formed forms anti-well with drilling machine girder steel 5 and bores
Machine basis, wherein, drilling machine girder steel 5 is seated in concrete foundation.Concrete foundation is higher than filling concrete strength.This example
In, to concrete used in former pass 1 progress concrete filling marked as C10-20。
(3) raising boring is carried out to the former pass 1 after step (2) filling using anti-well drilling machine 4 and forms new drop shaft
Pit shaft 9:In order to make the concrete of backfill to the former drop shaft borehole wall formed support, using anti-well drilling machine 4 creep into new pass 9 it
It is preceding need and etc. the concrete setting that is filled in former pass 1 in (ii) and intensity reach design requirement, then remove again
Plug members, release the fine sand of filling in former pass 1, then install reaming bit in the lower end of anti-4 drilling rod 6 of well drilling machine
8, reaming from bottom to top, until former drop shaft upper end well head, the new drilling of pass 9 is completed, as shown in Figure 4.Due to each drop shaft
Well depth, the concrete condition such as hole diameter it is different, therefore the set strength for being filled in different pass inner concretes will be according to each
Pass concrete condition determines, usually selects the concrete of low grade to fill pass.
(4) supporting is carried out to the new drop shaft borehole wall drilled in step (3), as shown in figure 5, it is comprised the following steps that:
(I) the anti-well drilling machine 4 in dismantling step (3), installs lift 3 and hanging scaffold 10 on new 9 top of pass, applies
Worker person is using the safe condition that new pass 9 is checked in lift 3 and the new pass 9 of 10 tripping in of hanging scaffold, to part
Unstable formation and concrete are handled and supporting;
(II) progressively pour new drop shaft inner wall from bottom to top by the way of hydraulic pressure synovial membrane, form new ore pass choking-up.
After new ore pass choking-up is formed, you can remove relevant construction equipment, recover charging and ore drawing needed for drop shaft
Equipment, drop shaft is come into operation.
Occur using the present invention to the borehole wall large area cave in and occur cavity former drop shaft carry out maintenance during, to original
Enter pit shaft without personnel when pass 1 carries out the detection of space structure shape, and working as needs construction personnel to enter pass
When, the concrete of backfill has formd the former drop shaft borehole wall reinforcing and filling, is not in caving in for large area, so as to ensure that
The personal safety of construction personnel's quilt, and solve in existing drop shaft restorative procedure in the area that caves in, highly larger place
The problem of construction personnel's operating difficulties.
Above-described embodiment is only intended to clearly illustrate the invention example, and not has to the invention
The restriction of body embodiment.For those of ordinary skill in the field, can also make on the basis of the above description
Other various forms of changes or variation.There is no necessity and possibility to exhaust all the enbodiments.It is all the present invention
Guarantor of any obvious changes or variations extended out within spirit and principle still in the invention claim
Protect among scope.
Claims (7)
1. a kind of construction method using anti-well rig maintenance drop shaft, it is characterised in that include the following steps:
(1) former pass (1) space structure detection, includes the following steps:
(a) lift (3) is installed on the top of former drop shaft, using ultrasonic meter (2) along former pass (1) from top to bottom
Profile scanning one by one is carried out to former pass (1);
(b) data obtained in step (a) are analyzed, calculates former drop shaft spatial volume, and draw out former pass
(1) space structure shape;
(2) former pass (1) is filled according to the result of detection of gained in step (1), included the following steps:
(a1) drilling machine girder steel (5) is installed in the upper end well head of former drop shaft, anti-well drilling machine (4) is then installed on drilling machine girder steel (5),
And transfer anti-well borer drill rod (6) to the lower end well head of former drop shaft, then anti-well borer drill rod (6) is wrapped up with casing (7),
And fill grit material between anti-well borer drill rod (6) outer wall and casing (7) inner wall;
(b1) former pass (1) is filled;
(3) raising boring is carried out to the former pass (1) after step (2) filling using anti-well drilling machine (4) and forms new drop shaft
Pit shaft (9);
(4) supporting is carried out to the new drop shaft borehole wall drilled in step (3).
2. the construction method according to claim 1 using anti-well rig maintenance drop shaft, it is characterised in that casing (7) is
Plastic tube.
3. the construction method according to claim 1 using anti-well rig maintenance drop shaft, it is characterised in that step (b1) is wrapped
Include following steps:
(i) lower end port of the annular space between casing (7) outer wall and the former drop shaft borehole wall is blocked with plug members, then to original
Fine sand is filled with pass (1);
(ii) grey tremie pipe is slipped in brattice way handling, it is then pre- according to the former drop shaft spatial volume calculated in step (b)
Concrete processed, then carries out concrete filling to former pass (1) paragraph by paragraph, until concrete filling body (11) upper surface distance
Drilling machine girder steel (5) lower part is greater than or equal to 0.3m and is less than or equal to 0.5m, then refills anti-well drilling machine basis concrete,
And anti-well drilling machine basis concrete filling body is set closely to be connected with drilling machine girder steel (5).
4. the construction method according to claim 3 using anti-well rig maintenance drop shaft, it is characterised in that slipped when close to original
The former pass (1) of downhole end well head without it is destroyed when, fine sand is filled to the former drop shaft of distance and is damaged well section lower end well head 1m
Position, fine sand filling length be greater than or equal to 5m;The mark of the concrete used in concrete filling is carried out to former pass (1)
Number it is C10-20。
5. the construction method according to claim 3 using anti-well rig maintenance drop shaft, it is characterised in that step (3) has
Body step is:When the concrete setting and intensity being filled in step (ii) in former pass (1) reach design requirement, remove
Plug members, release the fine sand of filling in former pass (1), then install reaming in the lower end of anti-well borer drill rod (6)
Drill bit (8), reaming from bottom to top, until former drop shaft upper end well head, new pass (9) drilling is completed.
6. according to any construction method using anti-well rig maintenance drop shaft of Claims 1 to 5, it is characterised in that step
Suddenly (4) include the following steps:
(I) the anti-well drilling machine (4) in dismantling step (3), in new pass (9) top installation lift (3) and hanging scaffold
(10), check the safe condition of new pass (9), local unstable formation and concrete are handled and supporting;
(II) new drop shaft inner wall is poured.
7. the construction method according to claim 6 using anti-well rig maintenance drop shaft, it is characterised in that step (II) has
Body step is:Progressively pour new drop shaft inner wall from bottom to top by the way of hydraulic pressure synovial membrane.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610393560.7A CN106089027B (en) | 2016-06-06 | 2016-06-06 | A kind of construction method using anti-well rig maintenance drop shaft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610393560.7A CN106089027B (en) | 2016-06-06 | 2016-06-06 | A kind of construction method using anti-well rig maintenance drop shaft |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106089027A CN106089027A (en) | 2016-11-09 |
CN106089027B true CN106089027B (en) | 2018-05-08 |
Family
ID=57448353
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610393560.7A Active CN106089027B (en) | 2016-06-06 | 2016-06-06 | A kind of construction method using anti-well rig maintenance drop shaft |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106089027B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106761822A (en) * | 2016-11-28 | 2017-05-31 | 北京中煤矿山工程有限公司 | Drop shaft technique is repaired in a kind of metal mine backfill prose style free from parallelism slip casting |
CN108626482B (en) * | 2018-04-23 | 2019-10-08 | 西山煤电建筑工程集团有限公司矿建第一分公司 | Utilize the construction method of anti-well drilling machine installation vertical gas pipe |
CN108756889B (en) * | 2018-06-08 | 2019-08-30 | 北京中煤矿山工程有限公司 | Anti- well drilling machine reaming construction broken formation gib method |
CN111852482B (en) * | 2020-07-31 | 2022-04-01 | 湖南科技大学 | Construction method of ore crusher foundation of slip-breaking system engineering below 40m |
CN112523712B (en) * | 2020-12-21 | 2023-11-14 | 吉林大学 | Device and method for repairing damaged well wall |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1252492A1 (en) * | 1983-11-29 | 1986-08-23 | Всесоюзный Научно-Исследовательский И Проектно-Конструкторский Институт По Осушению Месторождений Полезных Ископаемых,Специальным Горным Работам,Рудничной Геологии И Маркшейдерскому Делу | Method of driving an ascending mine working |
CN103527140A (en) * | 2012-10-22 | 2014-01-22 | 洛阳富兴管业有限公司 | Cement pipe dado filling and grouting technology |
CN104912569A (en) * | 2015-06-05 | 2015-09-16 | 中国安全生产科学研究院 | Draw shaft treatment method |
-
2016
- 2016-06-06 CN CN201610393560.7A patent/CN106089027B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1252492A1 (en) * | 1983-11-29 | 1986-08-23 | Всесоюзный Научно-Исследовательский И Проектно-Конструкторский Институт По Осушению Месторождений Полезных Ископаемых,Специальным Горным Работам,Рудничной Геологии И Маркшейдерскому Делу | Method of driving an ascending mine working |
CN103527140A (en) * | 2012-10-22 | 2014-01-22 | 洛阳富兴管业有限公司 | Cement pipe dado filling and grouting technology |
CN104912569A (en) * | 2015-06-05 | 2015-09-16 | 中国安全生产科学研究院 | Draw shaft treatment method |
Non-Patent Citations (1)
Title |
---|
深部溜井垮塌三维探测及其修复方案研究;刘付高;《采矿技术》;20130715;第13卷(第4期);第26-30页 * |
Also Published As
Publication number | Publication date |
---|---|
CN106089027A (en) | 2016-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106089027B (en) | A kind of construction method using anti-well rig maintenance drop shaft | |
CN110206493B (en) | Construction process of full-sleeve full-rotation bored pile | |
CN113445498A (en) | Construction process of karst hole pile foundation in complex geology | |
CN106988302B (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
CN107524142A (en) | A kind of holing with slurry wall protection cast-in-place pile construction method | |
CN102720186B (en) | Underwater once pouring method for variable cross-section bored cast-in-place pile | |
CN109763483B (en) | Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum | |
CN109056706A (en) | A kind of Karst Geological Landscape poured pile base construction method | |
CN110629747A (en) | Full-casing full-rotation construction process for pile foundation under complex geological conditions | |
CN108570983A (en) | The pile base construction method and its casing of non-filler large size solution cavity | |
CN113174961B (en) | Foundation pit slope supporting method | |
CN110158579A (en) | A kind of bored pile construction method | |
JP7292772B2 (en) | External expansion pipe construction method for drilling in the mining zone | |
CN107653878A (en) | Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction | |
CN106703034A (en) | Construction device and construction method for pulling out piles through cooperation of rotating drilling machine and sleeve drill bit | |
CN104005768A (en) | Construction strengthening method for soft geological layer in middle section of vertical shaft | |
CN104264679B (en) | A kind of electric power pylon basis heavy caliber Underwater pile construction method | |
CN105672309A (en) | Encasing method for hole forming of socketed piles at karst terrain through recoverable extra-long steel pile casings | |
CN212052725U (en) | Karst cave area stake construction structures | |
JP2019148070A (en) | Construction method of underground structure | |
CN110670583A (en) | Construction method of manual hole digging pile | |
CN110629756A (en) | Anchor cable removing method | |
CN211113598U (en) | Karst cave handling system for deep foundation pit pile foundation construction in karst area | |
CN114657974A (en) | Method for quickly splicing cast-in-place pile under complex geological condition | |
CN114855789A (en) | Construction method for broken pile treatment of engineering pile in soft soil area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |