CN114855789A - Construction method for broken pile treatment of engineering pile in soft soil area - Google Patents

Construction method for broken pile treatment of engineering pile in soft soil area Download PDF

Info

Publication number
CN114855789A
CN114855789A CN202210306891.8A CN202210306891A CN114855789A CN 114855789 A CN114855789 A CN 114855789A CN 202210306891 A CN202210306891 A CN 202210306891A CN 114855789 A CN114855789 A CN 114855789A
Authority
CN
China
Prior art keywords
pile
section
steel casing
concrete
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210306891.8A
Other languages
Chinese (zh)
Inventor
陈宝弟
章奕峰
柯芽香
陈悦
阮从军
陈志涛
崔静见
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Biaoli Construction Group Co ltd
Original Assignee
Biaoli Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Biaoli Construction Group Co ltd filed Critical Biaoli Construction Group Co ltd
Priority to CN202210306891.8A priority Critical patent/CN114855789A/en
Publication of CN114855789A publication Critical patent/CN114855789A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/64Repairing piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to the technical field of pile breaking treatment, and relates to a pile breaking treatment construction method for engineering piles in a soft soil area, which comprises the following steps: construction preparation, leveling a field, and measuring the center of an excavated hole; digging a first section of hole, crushing if meeting the pile body, transporting out along with earthwork, and placing a first section of steel casing after forming the hole; continuously excavating a next section of hole by downward exploration, placing a next section of steel casing after hole forming, wherein the diameter of the next section of steel casing is smaller than that of the previous section of steel casing; gradually descending to the pile fracture part to form a complete pile hole; placing concrete sleeves section by section in the pile hole, hanging a corresponding section of steel casing when placing a section of concrete sleeve, and sequentially pushing until the steel casing is completely pulled out; and placing a steel reinforcement cage and pouring pile body concrete. The construction method for treating broken engineering piles in soft soil areas has the advantages of low cost, simplicity, convenience, practicability, safety and reliability.

Description

Construction method for broken pile treatment of engineering pile in soft soil area
Technical Field
The invention belongs to the technical field of pile breaking treatment, and relates to a construction method for pile breaking treatment of engineering piles in a soft soil area.
Background
The soil quality of coastal areas is poor, and basements of high-rise buildings are often puzzled by silt or silt clay in construction. Especially, the quality of the engineering pile is affected by carelessness during foundation pit enclosure, earth excavation and transportation, especially in thin-wall prestressed pipe pile engineering, the engineering pile is inclined by a light person, and the pile is broken in serious cases. According to several engineering surveys, engineering piles are broken due to instability of foundation pits, excavator collision and soil carrying of automobiles, and the broken parts are generally 2-6 m below the elevation of the effective pile top (namely the pit bottom). At present, the solution of the engineering pile fracture only adopts post treatment of pile repair or anchor static pressure pile, the cost is high, and the construction period is long.
Disclosure of Invention
The invention provides a construction method for treating broken engineering piles in soft soil areas, which aims at the difference of the prior art and has the advantages of low cost, simplicity, convenience, practicability, safety and reliability.
In order to solve the above technical problems, the object of the present invention is achieved by the following technical solutions:
the construction method for treating broken piles of engineering piles in soft soil areas comprises the following steps:
(1) construction preparation, leveling a field, and measuring the center of an excavated hole;
(2) digging a first section of hole, crushing if meeting the pile body, transporting out along with earthwork, and placing a first section of steel casing after forming the hole;
(3) continuously excavating a next section of hole by downward exploration, if meeting the pile body, crushing, carrying out along with the earth, placing a next section of steel casing after hole forming, wherein the diameter of the next section of steel casing is smaller than that of the previous section of steel casing;
(4) repeating the step (3), and gradually descending to the pile fracture part to form a complete pile hole;
(5) placing concrete sleeves section by section in the pile hole, hanging a corresponding section of steel casing when placing a section of concrete sleeve, filling sand around the concrete sleeve for fixation, and sequentially recurrently pulling out the steel casing to complete the installation of the concrete sleeve;
(6) and placing a steel reinforcement cage and pouring pile body concrete.
In the construction method for treating broken engineering piles in the soft soil area, when construction preparation is carried out in the step (1), if the engineering piles are obviously inclined, the broken engineering piles can be judged, the broken parts can be moved to the most prominent positions (generally between 2 and 6 meters) according to the deep layer of the foundation pit enclosure, and the centers of the excavation holes are generally the positions of the piles entering the soil.
In the construction method for pile breaking treatment of engineering piles in the soft soil area, in the steps (2) and (3), the steel casing is rolled into a circular casing by a steel plate, the thickness of the steel plate is 3-5 mm, and preferably, the steel plate is an A3 steel plate. In the steps (2) and (3), after the steel casing is placed, checking and adjusting the verticality of the upper casing and the lower casing, and then continuously digging holes.
In the construction method for treating broken engineering piles in the soft soil area, the height of the steel casing is 800-1200 mm, the diameter of the steel casing is 1000-1800 mm, and the diameter of the next section of steel casing is 80-120 mm smaller than that of the previous section of steel casing. Preferably, the height of the steel casing is 1000mm, the minimum diameter of the steel casing is 1000mm, and the diameter difference between adjacent steel casings is 100 mm.
In the construction method for treating broken piles of engineering piles in the soft soil area, the excavation depth of the first section of hole is smaller than the height of the first section of steel casing; preferably, after the first section of steel casing is placed, the upper end face of the first section of steel casing is 100-200 mm higher than the ground. After placement, the edge of the first section of steel casing is slightly above the ground to prevent surface water from flowing into the hole during operation.
In the construction method for treating broken piles of engineering piles in the soft soil area, whether the pile body is complete or not is judged through small strain detection in the construction process, the small strain detection is carried out when the pile is dug to the pile breaking elevation, the next section of steel casing is stopped to be placed after the small strain judgment that the pile body is complete, the small strain detection can accurately judge the depth of the broken part, and a reliable basis is provided for repair work.
In the construction method for treating broken engineering piles in the soft soil area, when the concrete pipe piles are connected, the reinforcement cage extends to the position of less than 1000mm of breakage, and can form a whole after concrete is poured so as to ensure the bearing capacity of the pile body; when the concrete filling pile is connected, the reinforcement cage is overlapped with the original pile by more than 1000mm, after the hole is formed, the crack condition needs to be checked, and loose concrete slag is chiseled off to enable the section of the pile to be flat. Cleaning, then placing the steel bars, and pouring concrete. Ensuring the newly poured concrete to be compact.
In the construction method for treating broken engineering piles in the soft soil area, when concrete pipe piles are connected, the concrete grade used for concrete pouring is higher than the concrete strength of the bearing platform by one level; when the concrete pouring pile is connected, the concrete mark used for concrete pouring is higher than the concrete strength of the pile body of the concrete pouring pile by one level, and a layer of cement mortar is paved at the bottom of the hole.
Compared with the prior art, the invention has the following beneficial effects:
1. the invention provides a novel construction method for treating broken engineering piles, which utilizes multi-stage steel casing to downwards probe step by step to form pile holes, has the advantages of well-ordered working procedures, low cost, simplicity, convenience, practicability, safety and reliability, and is particularly suitable for breaking prestressed pipe piles and cast-in-place piles caused by unstable foundation pit supporting, excavator collision and soil transportation of automobiles in soft soil areas. The construction method effectively solves the problem of repairing the broken engineering pile, because the hole digging of the steel casing is safe and reliable, and the used machines are portable, the construction method is easy to popularize, if the pile is broken more, the construction method can be simultaneously operated in groups (the spacing distance is more than 4m), the construction period can be obviously shortened, and the cost is only about one tenth of that of pile repairing.
2. The steel casing can be used in a turnover mode, and the steel casing is few in related equipment, so that the steel casing is economical and applicable, and is convenient and flexible to install and dismantle. The hole can be assembled and implemented no matter how deep or shallow, and the adaptability is strong.
3. The invention can accurately judge the depth of the broken part through small strain detection, and can intuitively and accurately drill the pile and dig the hole to the broken part of the pile. As long as the key links are emphasized, the safe construction and the pile repair quality are reliably guaranteed.
4. The hole forming process is gradual, the steel casing is used for protection, the diameter and the depth of a hole to be dug are limited, and the hole is a round hole, so that accidents such as collapse can be avoided.
Drawings
FIG. 1 construction process flow
Detailed Description
The present invention is further described in the following description of the specific embodiments, which is not intended to limit the invention, but various modifications and improvements can be made by those skilled in the art based on the basic idea of the invention, but the scope of the invention is within the scope of the invention as long as they do not depart from the basic idea of the invention.
Referring to fig. 1, the specific construction process of the embodiment is as follows:
1. preparation of construction materials
A steel plate casing with the thickness of 3mm to 5mm and the diameter of phi 1000mm to phi 1800mm, a manual winch, a kalopanax septempunctata, a chisel, an air compressor, an air pick, a plumb bob, a measuring tape, an inserted vibrator, a water pump and commercial concrete.
2. Preparation for construction
And (4) finishing the steel casing (surface smoothness, weld seam repair, firmness of the hanging ring and the like), counting the quantity and specification and ensuring the matching. The concrete sleeves are put into the field and stacked orderly for use.
And (5) leveling the field, and measuring the center of the excavated hole.
3. Digging hole and installing first section of steel casing
And digging holes with the same diameter of the steel casing, wherein the depth of each hole is 800mm, and if the pile body is broken in case of meeting, the pile body is transported out along with earthwork. After the hole is formed, the steel protective cylinder can be installed, and the edge of the steel protective cylinder is slightly higher than the ground so as to prevent surface water from flowing into the hole during operation.
4. Continuously digging hole and installing steel protective cylinder
And (5) continuously digging holes with the depth of 1000mm, crushing the pile body if meeting, trimming and forming the holes, and installing a second section of steel casing. The manual winch for well digging is adopted to hoist the earthwork, and the rope, the lifting hook and the connecting part of the artificial winch need to be checked at any time and replaced in time if damaged. The removed earth and stone should be transported away from the hole opening in time, and should not be stacked within 1m around the hole opening, and the driving of the motor vehicle should not affect the safety of the well wall. Repeating the processes, and sequentially recurrently obtaining the fracture position of the pile.
5. Small strain detection
And when the pile is dug to the height mark of the broken pile, removing concrete slag and accumulated water, flattening the surface, and performing small strain detection. And after the lower pile body is detected to be complete through small strain, the follow-up operation is continued.
6. Mounting concrete sleeve
And hanging the prefabricated concrete sleeve section by section, replacing a section of steel casing when the concrete sleeve is installed, and hanging the steel casing out by a winch. And filling sand around the concrete sleeve for fixing. And sequentially recursing until the steel casing is completely pulled out, and finishing the installation of the concrete sleeve.
7. Installation steel reinforcement cage
And (4) mounting the prefabricated concrete sleeve in place, hoisting the reinforcement cage, and then carrying out concealed engineering acceptance of the reinforcement cage.
8. Pouring pile body
And pouring pile body concrete after acceptance. When the precast pile is connected, the reinforcement cage extends to a fracture of less than 1000 mm; when the cast-in-place pile is connected, the reinforcement cage is overlapped with the original pile by more than 1000 mm. When the pile body concrete is poured, the concrete must pass through the chute. When the height exceeds 3m, a stringing barrel is used. The concrete is compacted by an inserted vibrator.
9. Quality control
The quality requirements of the raw materials are as follows: the materials such as the related steel plate, the steel wire rope, the steel bar and the like meet the national standard and have the qualification certificate.
The steel casing is installed in a leveling mode, and the deviation between the center line of the walling crib and the center line of the pile is not larger than 20 mm. The central line of the concrete sleeve is consistent with the central line of the engineering pile, the deviation of the axial line is less than 50mm, and the deviation of the effective diameter of the section of the pile body is plus 50 to minus 0 mm.
Strictly executing the number of concrete structure reinforcement design specifications as GB50367-2006 and the number of concrete structure construction quality acceptance specifications as GB50704-2002, and executing the building construction safety inspection standard GJ59-99 in the construction process.

Claims (9)

1. The construction method for treating broken engineering piles in the soft soil area is characterized by comprising the following steps:
(1) construction preparation, leveling a field, and measuring the center of an excavated hole;
(2) digging a first section of hole, crushing if meeting the pile body, transporting out along with earthwork, and placing a first section of steel casing after forming the hole;
(3) continuously excavating a next section of hole by downward exploration, if meeting the pile body, crushing, carrying out along with the earth, placing a next section of steel casing after hole forming, wherein the diameter of the next section of steel casing is smaller than that of the previous section of steel casing;
(4) repeating the step (3), and gradually descending to the pile fracture part to form a complete pile hole;
(5) placing concrete sleeves section by section in the pile hole, hanging a corresponding section of steel casing when placing a section of concrete sleeve, filling sand around the concrete sleeve for fixation, and sequentially recurrently pulling out the steel casing to complete the installation of the concrete sleeve;
(6) and placing a steel reinforcement cage and pouring pile body concrete.
2. The construction method for broken pile processing in engineering piles in soft soil areas according to claim 1, wherein whether the pile body is complete or not is judged through small strain detection in the construction process, the small strain detection is carried out when the pile body is dug to the pile breaking elevation, and the placement of the next section of steel casing is stopped after the small strain judgment that the pile body is complete.
3. The construction method for pile-breaking treatment of engineering piles in soft soil areas according to claim 1, wherein the steel casing is a circular casing made of steel plates, and the thickness of the steel plates is 3mm to 5 mm.
4. The construction method for pile breaking treatment of the engineering pile in the soft soil area according to claim 1, wherein the height of the steel casing is 800-1200 mm, the diameter of the steel casing is 1000-1800 mm, and the diameter of the next section of the steel casing is 80-120 mm smaller than that of the previous section of the steel casing.
5. A soft soil area engineering pile broken pile processing construction method as claimed in claim 1, wherein the height of the steel casing is 1000mm, the minimum diameter of the steel casing is 1000mm, and the diameter difference of adjacent steel casings is 100 mm.
6. The construction method for pile-breaking treatment of engineering piles in soft soil areas according to claim 1, wherein the excavation depth of the first section of hole is smaller than the height of the first section of steel casing.
7. A soft soil area engineering pile broken pile processing construction method as claimed in claim 5, wherein after the first section of steel casing is placed, the upper end face of the first section of steel casing is 100-200 mm higher than the ground.
8. The construction method for pile-breaking treatment of engineering piles in soft soil areas according to claim 1, wherein when a concrete pipe pile is connected, the reinforcement cage extends to a breaking position of less than 1000 mm; when the concrete filling pile is connected, the reinforcement cage is overlapped with the original pile by more than 1000 mm.
9. The construction method for pile-breaking treatment of engineering piles in soft soil areas according to claim 1, wherein when connecting concrete pipe piles, the concrete grade used for concrete pouring is one level higher than the concrete strength of a bearing platform; when the concrete pouring pile is connected, the concrete mark used for concrete pouring is higher than the concrete strength of the pile body of the concrete pouring pile by one level, and a layer of cement mortar is paved at the bottom of the hole.
CN202210306891.8A 2022-03-25 2022-03-25 Construction method for broken pile treatment of engineering pile in soft soil area Pending CN114855789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210306891.8A CN114855789A (en) 2022-03-25 2022-03-25 Construction method for broken pile treatment of engineering pile in soft soil area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210306891.8A CN114855789A (en) 2022-03-25 2022-03-25 Construction method for broken pile treatment of engineering pile in soft soil area

Publications (1)

Publication Number Publication Date
CN114855789A true CN114855789A (en) 2022-08-05

Family

ID=82629793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210306891.8A Pending CN114855789A (en) 2022-03-25 2022-03-25 Construction method for broken pile treatment of engineering pile in soft soil area

Country Status (1)

Country Link
CN (1) CN114855789A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733048A (en) * 2023-08-10 2023-09-12 中建四局建设发展有限公司 Pile splicing structure of soft soil foundation filling pile and construction method thereof

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3780975A (en) * 1971-11-23 1973-12-25 L Turzillo Means for producing cast-in-place structures in situ
CN103526747A (en) * 2013-09-26 2014-01-22 浙江钱塘江水利建筑工程公司 Construction method for impact holing of filling pile in tidal environment
CN103953054A (en) * 2014-04-01 2014-07-30 中铁大桥局集团第一工程有限公司 Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof
CN106284314A (en) * 2016-08-31 2017-01-04 中冶建工集团有限公司 Karst landform spiral-digging pore cast-in-place pile construction method
JP2018119385A (en) * 2017-01-27 2018-08-02 三谷セキサン株式会社 Sc pile having axial reinforcement, method for manufacturing sc pile having axial reinforcement, and method for exposing axial reinforcement of sc pile
CN108914932A (en) * 2018-07-16 2018-11-30 中建四局第建筑工程有限公司 A kind of pile for prestressed pipe pile connection construction method and device
CN109056706A (en) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 A kind of Karst Geological Landscape poured pile base construction method
CN109083182A (en) * 2018-09-25 2018-12-25 中铁二十三局集团第三工程有限公司 Collapsible loess super long large diameter pile foundation churning driven dry method construction method
CN110872842A (en) * 2019-11-27 2020-03-10 甘肃建投建设有限公司 Saturated sand rock stratum occlusive water-stop pile supporting system and construction method thereof
CN111395322A (en) * 2020-04-07 2020-07-10 中铁十二局集团建筑安装工程有限公司 Construction method for rotary digging cast-in-place pile under karst landform
CN212052725U (en) * 2020-02-28 2020-12-01 江西建工第一建筑有限责任公司 Karst cave area stake construction structures
CN112523202A (en) * 2020-11-23 2021-03-19 中冶交通建设集团有限公司 Broken pile treatment construction method for cast-in-situ bored pile
CN113404042A (en) * 2021-07-06 2021-09-17 中铁二十局集团第六工程有限公司 Bridge pile position construction method
CN113445498A (en) * 2021-02-05 2021-09-28 中铁八局集团有限公司 Construction process of karst hole pile foundation in complex geology
CN114164823A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Pile foundation construction method in high-fill foundation

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3780975A (en) * 1971-11-23 1973-12-25 L Turzillo Means for producing cast-in-place structures in situ
CN103526747A (en) * 2013-09-26 2014-01-22 浙江钱塘江水利建筑工程公司 Construction method for impact holing of filling pile in tidal environment
CN103953054A (en) * 2014-04-01 2014-07-30 中铁大桥局集团第一工程有限公司 Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof
CN106284314A (en) * 2016-08-31 2017-01-04 中冶建工集团有限公司 Karst landform spiral-digging pore cast-in-place pile construction method
JP2018119385A (en) * 2017-01-27 2018-08-02 三谷セキサン株式会社 Sc pile having axial reinforcement, method for manufacturing sc pile having axial reinforcement, and method for exposing axial reinforcement of sc pile
CN108914932A (en) * 2018-07-16 2018-11-30 中建四局第建筑工程有限公司 A kind of pile for prestressed pipe pile connection construction method and device
CN109056706A (en) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 A kind of Karst Geological Landscape poured pile base construction method
CN109083182A (en) * 2018-09-25 2018-12-25 中铁二十三局集团第三工程有限公司 Collapsible loess super long large diameter pile foundation churning driven dry method construction method
CN110872842A (en) * 2019-11-27 2020-03-10 甘肃建投建设有限公司 Saturated sand rock stratum occlusive water-stop pile supporting system and construction method thereof
CN212052725U (en) * 2020-02-28 2020-12-01 江西建工第一建筑有限责任公司 Karst cave area stake construction structures
CN111395322A (en) * 2020-04-07 2020-07-10 中铁十二局集团建筑安装工程有限公司 Construction method for rotary digging cast-in-place pile under karst landform
CN112523202A (en) * 2020-11-23 2021-03-19 中冶交通建设集团有限公司 Broken pile treatment construction method for cast-in-situ bored pile
CN113445498A (en) * 2021-02-05 2021-09-28 中铁八局集团有限公司 Construction process of karst hole pile foundation in complex geology
CN113404042A (en) * 2021-07-06 2021-09-17 中铁二十局集团第六工程有限公司 Bridge pile position construction method
CN114164823A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Pile foundation construction method in high-fill foundation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄茂兴;: "探讨不良地质条件下桩基工程接桩的施工方案", 中国高新技术企业, no. 24, pages 138 - 139 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733048A (en) * 2023-08-10 2023-09-12 中建四局建设发展有限公司 Pile splicing structure of soft soil foundation filling pile and construction method thereof

Similar Documents

Publication Publication Date Title
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN111456019A (en) Safe construction method for foundation pit excavation
CN110387879B (en) Concrete cast-in-place pile construction method for hydraulically vibrating and hammering immersed tube
CN111335306A (en) Rapid construction method for deep and thick hard rock section drilled pile
CN112030956A (en) Karst stratum bored pile construction method
CN104480929B (en) A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement
CN113174961B (en) Foundation pit slope supporting method
CN111395322A (en) Construction method for rotary digging cast-in-place pile under karst landform
CN113216832A (en) Water-mill drilling construction method for pile hole in karst area
CN106948347B (en) Pile pulling method and pile pulling system
CN112411530A (en) Construction method for controlling verticality of sea-filling stratum casing secant pile
CN112012197A (en) Manual hole digging pile and construction method thereof
CN111236208A (en) Underground diaphragm wall foundation pit construction method
CN114855789A (en) Construction method for broken pile treatment of engineering pile in soft soil area
CN114045854A (en) Bridge pile foundation composite construction method under complex geological condition
CN106968252B (en) Pile pulling recharging method and pile pulling recharging system
JP2019148070A (en) Construction method of underground structure
CN111535305A (en) Construction method of cast-in-situ bored pile for air well
CN115217112A (en) Deep foundation pit construction method
CN114837209A (en) Construction method of deep sand layer large-diameter pile foundation in karst development area
CN111705790A (en) Large-diameter bottom expanding construction method for firm rock mass machinery
CN112726565A (en) Construction method for rotary digging pile penetrating through construction waste
CN111676960A (en) Construction method for pre-splicing stirrups of large rectangular piles in complex site
CN111411634A (en) Method for manual hole digging pile operation on slope
CN113123793B (en) Weak stratum vertical shaft derrick structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination