CN106088602A - A kind of construction of super highrise building elevator material-receiving device - Google Patents

A kind of construction of super highrise building elevator material-receiving device Download PDF

Info

Publication number
CN106088602A
CN106088602A CN201610582732.5A CN201610582732A CN106088602A CN 106088602 A CN106088602 A CN 106088602A CN 201610582732 A CN201610582732 A CN 201610582732A CN 106088602 A CN106088602 A CN 106088602A
Authority
CN
China
Prior art keywords
splicing
construction
steelframe
right angle
elastic buffer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610582732.5A
Other languages
Chinese (zh)
Other versions
CN106088602B (en
Inventor
尚梅
周尚琪
马世轩
王刚刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
Original Assignee
尚梅
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 尚梅 filed Critical 尚梅
Priority to CN201610582732.5A priority Critical patent/CN106088602B/en
Publication of CN106088602A publication Critical patent/CN106088602A/en
Application granted granted Critical
Publication of CN106088602B publication Critical patent/CN106088602B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

nullThe invention discloses a kind of construction of super highrise building elevator material-receiving device,The long right-angle side of right angle trigonometry steelframe is installed on high-rise building body of wall,The two ends of right angle trigonometry steelframe upper surface are fixedly installed elastic buffer member,The center of right angle trigonometry steelframe is fixed with rotation dish,It is installed with hydraulic jack on rotation dish,Material receiving center is installed in hydraulic jack top,When the object to be transported of elevator being carried out splicing,Hydraulic jack is retracted,The lower surface of material receiving supports and is arranged on described elastic buffer member,After object splicing waiting,Hydraulic jack rises,Material receiving is rotatable under the driving of rotating disk,The present invention arranges elastic buffer supporting body by taper retainer,Buffering effect during more preferably splicing can be improved,After being capable of splicing, object is directly transported to building,Improve convenience and the stability of splicing,Ensure that the safety of Super High splicing.

Description

A kind of construction of super highrise building elevator material-receiving device
Technical field
The present invention relates to a kind of construction of super highrise building elevator material-receiving device, belong to technical field of building construction.
Background technology
Along with becoming increasingly prosperous of China's capital construction, large quantities of high levels and high-rise building continue to bring out, the height of building Degree grows with each passing day, and brings sizable difficulty to the application of building hoist.Building hoist is high-building construction construction Middle by one of personnel or the building materials necessary equipment being transported to designated floor, provide convenience for construction.Building hoist Safe handling, is related to progress and the quality of construction, there is also bigger potential safety hazard, it has also become engineering construction simultaneously One of emphasis of safety manufacture supervising.
And when using elevator to carry out transporting object, need between elevator and building, arrange transportation route, mesh Before, for common buildings high level, general employing arranges the mode of steel pipe scaffold to realize between elevator and building Transport material.But, for high-rise building, this structure has the biggest potential safety hazard, and, setting up scaffold needs Want substantial amounts of manpower and materials, and when splicing, for heavier rigid objects, it is easy to scaffold is produced impact Power, causes the overall structure of scaffold to loosen, and the safety of builder in serious threat, although start at present to occur in that a kind of tool Have a high-rise material receiving of Buffer Unit, but this structure after splicing in-convenience in use, it is difficult to realize rapidly and efficiently Object transport, accordingly, it would be desirable to a kind of high-rise building elevator material-receiving device of design, in order to improve stationarity and the side of splicing Just property.
Summary of the invention
The present invention is directed to existing technical problem, it is provided that a kind of construction of super highrise building elevator material-receiving device, it is therefore an objective to After the safety of raising splicing and splicing, the convenience of transport, intends to solve the problem that prior art exists.
For achieving the above object, the present invention provides following technical scheme: a kind of construction of super highrise building elevator splicing fills Putting, it includes right angle trigonometry steelframe, material receiving, elastic buffer member, rotation dish, hydraulic jack and locking expansion bolt, It is characterized in that, the long right-angle side of described right angle trigonometry steelframe uses described locking expansion bolt to be fixedly installed on Super High and builds On walling body, the two ends of the upper surface of described right angle trigonometry steelframe are fixedly installed multiple described elastic buffer member, described directly The center of the upper surface of angle triangle steelframe is fixedly installed rotation dish, described rotation dish is fixedly installed hydraulic jack, institute The center stating material receiving is fixedly installed on the top of described hydraulic jack, when needing to carry out the object to be transported of elevator During splicing, described hydraulic jack is retracted, and the lower surface of described material receiving supports and is arranged on described elastic buffer member, when After object splicing waiting, described hydraulic jack rises, and described material receiving is rotatable under the driving of rotating disk.
Further, as preferably, the hypotenuse of described right angle trigonometry steelframe welds with upper right-angle side right angle and is provided with hog frame, It is fixedly installed auxiliary support on the construction wall of the lower section of described right angle trigonometry steelframe, hinged on described auxiliary support is provided with Auxiliary hydraulic cylinder, the upper end thereof of described auxiliary hydraulic cylinder is arranged on the top of the hypotenuse of described right angle trigonometry steelframe, described bullet Property Buffer Unit include tapered steel seat, rigidity retainer, elastic buffer supporting body, upper cylindrical seat and location steel bushing, wherein, described The lower tapered end of tapered steel seat is fixed support and is arranged on the upper right-angle side of described right angle trigonometry steelframe, arranges in described tapered steel seat Having described rigidity retainer, in the circumference of the large awl end of described rigidity retainer, array is provided with multiple groove, in each groove Being provided with elastic buffer supporting body, the upper surface of described elastic buffer carrier exceeds the large end face of described rigidity retainer, institute Stating and be fixedly installed location steel bushing on the lower surface of cylindrical seat, described location steel bushing is fastened in described rigidity retainer, with Just fixing described elastic buffer supporting body, when splicing, the lower surface of described material receiving supports and is arranged on described upper cylindrical seat Upper surface on.
Further, as preferably, described elastic buffer supporting body is elastomeric rubber bodies, and described high elastic rubber body Inside it is provided with steel wire reinforcing mat.
Further, as preferably, on the lower surface between the upper surface of described material receiving and described elastic buffer member It is provided with weight sensor, and described weight sensor is connected with alarm.
Further, as preferably, described material receiving is circular material receiving.
Further, as preferably, described rotation dish uses direct driving motor to drive.
Further, as preferably, the quantity of the groove on described rigidity retainer is 8-16.
Further, as preferably, present invention additionally comprises video monitoring module, described video monitoring module be arranged on described in connect The top of material platform, in order to splicing process is monitored management.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention arranges elastic buffer supporting body by taper retainer, it is possible to increase more preferably buffering effect during splicing, Meanwhile, rotation dish and hydraulic jack it are provided with, it is possible to after realizing splicing, object is directly transported to building, improve The convenience of splicing and stability, it is ensured that the safety of Super High splicing, and, it is also provided with weight sensor and video prison Control module, it is achieved that the real-time monitoring to splicing process, the safety further ensuring construction of super highrise building is carried out.
Accompanying drawing explanation
Fig. 1 is the structural representation of a kind of construction of super highrise building elevator material-receiving device of the present invention;
Fig. 2 is the structural representation of the elastic buffer member of a kind of construction of super highrise building elevator material-receiving device of the present invention;
Wherein, 1, high-rise building body of wall, 2, locking expansion bolt, 3, auxiliary support, 4, auxiliary hydraulic cylinder, 5, hog frame, 6, Right angle trigonometry steelframe, 7, material receiving, 8, elastic buffer member, 9, hydraulic jack, 10, tapered steel seat, 11, rigidity keeps Frame, 12, elastic buffer supporting body, 13, upper cylindrical seat, 14, location steel bushing, 15, rotation dish.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
Referring to Fig. 1-2, the present invention provides a kind of technical scheme: a kind of construction of super highrise building elevator material-receiving device, It includes right angle trigonometry steelframe 6, material receiving 7, elastic buffer member, rotation dish 15, hydraulic jack 9 and locking expansion bolt 2, it is characterised in that the long right-angle side of described right angle trigonometry steelframe 6 uses described locking expansion bolt 2 to be fixedly installed on superelevation On layer construction wall 1, the two ends of the upper surface of described right angle trigonometry steelframe 6 are fixedly installed multiple described elastic buffer member, The center of the upper surface of described right angle trigonometry steelframe 6 is fixedly installed rotation dish 15, and described rotation dish 15 is fixedly installed liquid Pressure jack 9, the center of described material receiving 7 is fixedly installed on the top of described hydraulic jack, when needing elevator When object to be transported carries out splicing, described hydraulic jack is retracted, and the lower surface of described material receiving supports and is arranged on described bullet Property Buffer Unit on, after object splicing waiting, described hydraulic jack rises, and described material receiving is at rotating disk Drive lower rotatable.
In the present embodiment, the hypotenuse of described right angle trigonometry steelframe welds with upper right-angle side right angle and is provided with hog frame 5, institute Auxiliary support 3, hinged setting on described auxiliary support 3 it is fixedly installed on the construction wall of the lower section stating right angle trigonometry steelframe 6 Auxiliary hydraulic cylinder 4, the upper end thereof of described auxiliary hydraulic cylinder 4 is had to be arranged on the top of the hypotenuse of described right angle trigonometry steelframe 6, institute State elastic buffer member and include tapered steel seat 10, rigidity retainer 11, elastic buffer supporting body 12, upper cylindrical seat 13 and location steel Set 14, wherein, the lower tapered end of described tapered steel seat 10 is fixed support and is arranged on the upper right-angle side of described right angle trigonometry steelframe, institute Being provided with described rigidity retainer 11 in stating tapered steel seat 10, in the circumference of the large awl end of described rigidity retainer 11, array is arranged Having multiple groove, be provided with elastic buffer supporting body 12 in each groove, the upper surface of described elastic buffer carrier 12 exceeds The large end face of described rigidity retainer 11, the lower surface of described upper cylindrical seat 13 is fixedly installed location steel bushing 14, described fixed Position steel bushing 14 be fastened in described rigidity retainer 11, in order to fix described elastic buffer supporting body 12, when splicing, described in connect The lower surface of material platform supports and is arranged on the upper surface of described upper cylindrical seat.
Wherein, in order to improve the bearing capacity of elastic caching supporting body, described elastic buffer supporting body is elastomeric rubber It is provided with steel wire reinforcing mat in body, and described high elastic rubber body.Described material receiving and the upper table of described elastic buffer member It is provided with weight sensor on lower surface between face, and described weight sensor is connected with alarm.Described material receiving is Circular material receiving.In order to reduce the volume of rotation dish, improving rotating torque, described rotation dish uses direct driving motor to drive.Institute The quantity stating the groove on rigidity retainer is 8-16.
Additionally, in order to carry out complete monitoring, improve the safety of construction, present invention additionally comprises video monitoring module, described Video monitoring module is arranged on the top of described material receiving, in order to splicing process is monitored management.
The present invention arranges elastic buffer supporting body by taper retainer, it is possible to increase more preferably buffering effect during splicing Really, meanwhile, rotation dish and hydraulic jack it are provided with, it is possible to after realizing splicing, object is directly transported to building, carry The convenience of high splicing and stability, it is ensured that the safety of Super High splicing, and, it is also provided with weight sensor and regards Frequently monitoring module, it is achieved that the real-time monitoring to splicing process, the safety further ensuring construction of super highrise building is carried out.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, permissible Understand and these embodiments can be carried out multiple change without departing from the principles and spirit of the present invention, revise, replace And modification, the scope of the present invention be defined by the appended.

Claims (8)

1. a construction of super highrise building elevator material-receiving device, it includes right angle trigonometry steelframe, material receiving, elastic buffer group Part, rotation dish, hydraulic jack and locking expansion bolt, it is characterised in that the long right-angle side of described right angle trigonometry steelframe is adopted Being fixedly installed on high-rise building body of wall with described locking expansion bolt, the two ends of the upper surface of described right angle trigonometry steelframe are solid Surely being provided with multiple described elastic buffer member, the center of the upper surface of described right angle trigonometry steelframe is fixedly installed rotation dish, Being fixedly installed hydraulic jack on described rotation dish, the center of described material receiving is fixedly installed on described hydraulic jack Top, when needing the object to be transported of elevator is carried out splicing, described hydraulic jack is retracted, under described material receiving Surface support is arranged on described elastic buffer member, and after object splicing waiting, described hydraulic jack rises, and Described material receiving is rotatable under the driving of rotating disk.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described right angle The hypotenuse of triangle steelframe welds with upper right-angle side right angle and is provided with hog frame, the construction wall of the lower section of described right angle trigonometry steelframe On be fixedly installed auxiliary support, the hinged auxiliary hydraulic cylinder that is provided with, the upper end of described auxiliary hydraulic cylinder on described auxiliary support The top of the hinged hypotenuse being arranged on described right angle trigonometry steelframe, described elastic buffer member includes that tapered steel seat, rigidity keep Frame, elastic buffer supporting body, upper cylindrical seat and location steel bushing, wherein, the lower tapered end of described tapered steel seat is fixed support and is arranged on On the upper right-angle side of described right angle trigonometry steelframe, being provided with described rigidity retainer in described tapered steel seat, described rigidity keeps In the circumference of the large awl end of frame, array is provided with multiple groove, is provided with elastic buffer supporting body, described bullet in each groove The upper surface of property buffer carrier exceeds the large end face of described rigidity retainer, and the lower surface of described upper cylindrical seat is fixedly installed Location steel bushing, described location steel bushing is fastened in described rigidity retainer, in order to fixes described elastic buffer supporting body, works as splicing Time, the lower surface of described material receiving supports and is arranged on the upper surface of described upper cylindrical seat.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 2, it is characterised in that: described elasticity Buffering supporting body is elastomeric rubber bodies, and is provided with steel wire reinforcing mat in described high elastic rubber body.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described splicing Weight sensor, and described weight sensor it is provided with on lower surface between the upper surface of platform and described elastic buffer member It is connected with alarm.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described splicing Platform is circular material receiving.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described rotation Dish uses direct driving motor to drive.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 2, it is characterised in that: described rigidity The quantity of the groove on retainer is 8-16.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: also include regarding Frequently monitoring module, described video monitoring module is arranged on the top of described material receiving, in order to splicing process is monitored pipe Reason.
CN201610582732.5A 2016-07-23 2016-07-23 A kind of construction of super highrise building lift material-receiving device Expired - Fee Related CN106088602B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610582732.5A CN106088602B (en) 2016-07-23 2016-07-23 A kind of construction of super highrise building lift material-receiving device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610582732.5A CN106088602B (en) 2016-07-23 2016-07-23 A kind of construction of super highrise building lift material-receiving device

Publications (2)

Publication Number Publication Date
CN106088602A true CN106088602A (en) 2016-11-09
CN106088602B CN106088602B (en) 2018-01-16

Family

ID=57448867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610582732.5A Expired - Fee Related CN106088602B (en) 2016-07-23 2016-07-23 A kind of construction of super highrise building lift material-receiving device

Country Status (1)

Country Link
CN (1) CN106088602B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269004A (en) * 2017-07-03 2017-10-20 大连理工大学 A kind of device and method constructed for green concrete
CN107859339A (en) * 2017-11-14 2018-03-30 中建三局第建设工程有限责任公司 A kind of synchronous hoisting device and method for box beam support steel corbel
CN107905379A (en) * 2017-10-27 2018-04-13 中国建筑第八工程局有限公司 Totally-enclosed layer construction method in high-rise building Core Walls Structure
CN108840206A (en) * 2018-09-14 2018-11-20 南通四建集团有限公司 A kind of construction of super highrise building elevator material-receiving device
CN108910760A (en) * 2018-08-08 2018-11-30 北京鼎翰科技有限公司 A kind of high-building construction elevator material-receiving device
CN109100232A (en) * 2018-09-06 2018-12-28 中建三局第三建设工程有限责任公司 The experimental rig and application method of cone vertical bearing capacity are climbed for detecting bridge tower
CN113833271A (en) * 2021-09-06 2021-12-24 郝文涛 A hold and hang device for construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB838244A (en) * 1957-11-14 1960-06-22 Ace Machinery Ltd Improvements in or relating to power operated guided skip hoists
CN104801625A (en) * 2015-05-19 2015-07-29 中达电机股份有限公司 Automatic material receiving device for punching machine
CN204754248U (en) * 2015-07-02 2015-11-11 中国建筑第八工程局有限公司 Super high -rise building construction elevator regularization connects material platform
CN204781975U (en) * 2015-05-26 2015-11-18 中国建筑第八工程局有限公司 Concrete buffering connects hopper
CN204778237U (en) * 2015-07-17 2015-11-18 中建八局第二建设有限公司 Can have enough to meet need construction elevator layer door connects material platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB838244A (en) * 1957-11-14 1960-06-22 Ace Machinery Ltd Improvements in or relating to power operated guided skip hoists
CN104801625A (en) * 2015-05-19 2015-07-29 中达电机股份有限公司 Automatic material receiving device for punching machine
CN204781975U (en) * 2015-05-26 2015-11-18 中国建筑第八工程局有限公司 Concrete buffering connects hopper
CN204754248U (en) * 2015-07-02 2015-11-11 中国建筑第八工程局有限公司 Super high -rise building construction elevator regularization connects material platform
CN204778237U (en) * 2015-07-17 2015-11-18 中建八局第二建设有限公司 Can have enough to meet need construction elevator layer door connects material platform

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269004A (en) * 2017-07-03 2017-10-20 大连理工大学 A kind of device and method constructed for green concrete
CN107269004B (en) * 2017-07-03 2019-10-22 大连理工大学 A kind of device and method for green concrete construction
CN107905379A (en) * 2017-10-27 2018-04-13 中国建筑第八工程局有限公司 Totally-enclosed layer construction method in high-rise building Core Walls Structure
CN107859339A (en) * 2017-11-14 2018-03-30 中建三局第建设工程有限责任公司 A kind of synchronous hoisting device and method for box beam support steel corbel
CN108910760A (en) * 2018-08-08 2018-11-30 北京鼎翰科技有限公司 A kind of high-building construction elevator material-receiving device
CN109100232A (en) * 2018-09-06 2018-12-28 中建三局第三建设工程有限责任公司 The experimental rig and application method of cone vertical bearing capacity are climbed for detecting bridge tower
CN109100232B (en) * 2018-09-06 2023-12-05 中建三局第三建设工程有限责任公司 Testing device for detecting vertical bearing capacity of climbing cone of bridge tower and using method
CN108840206A (en) * 2018-09-14 2018-11-20 南通四建集团有限公司 A kind of construction of super highrise building elevator material-receiving device
CN108840206B (en) * 2018-09-14 2024-01-12 南通四建集团有限公司 Material receiving device of super high-rise building construction lifter
CN113833271A (en) * 2021-09-06 2021-12-24 郝文涛 A hold and hang device for construction

Also Published As

Publication number Publication date
CN106088602B (en) 2018-01-16

Similar Documents

Publication Publication Date Title
CN106088602A (en) A kind of construction of super highrise building elevator material-receiving device
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
CN208650862U (en) A kind of anti-collapse suspension device of constructing tunnel
CN104213651B (en) A kind of replaceable energy dissipation component of shear wall foundation and energy-dissipating structure
CN105971272A (en) Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method
CN205000974U (en) A tire formula automatic rising equipment rack for tunnel excavation construction
CN205242885U (en) Lightweight concrete prefabricated staircase connection structure
CN105464217B (en) A kind of adaptive slip rubber support and its replacing options
CN106368714A (en) Tire type automatic lifting assembly rack for tunnel excavation construction
CN206999277U (en) A kind of wallboard turning device
CN210407857U (en) On-spot demonstration operation panel that electric power marketing was used
CN206693630U (en) A kind of concreting servicing unit
CN214194611U (en) High-strength foundation structure
CN106224645A (en) The collector pipe structure conveniently transported and bury underground
CN217030199U (en) Device for fixing pump pipe
CN211341789U (en) Wall form reinforcing tool
CN204174938U (en) A kind of concrete rotates carriage
CN211314232U (en) Portable two lining platform trucks slant strutting arrangement
CN208378287U (en) A kind of simple vertical transport equipment of architecture construction
CN205875410U (en) A hang module system all for tube structure room panel construction
CN215593733U (en) Building bridge reinforcing construction device
CN210118149U (en) Anti-collapse supporting equipment for non-metal mine mining
CN206091681U (en) Go up suspension type hanging wheel transmission
CN215402820U (en) Spliced integral hoisting platform
CN211141359U (en) Mechanical equipment hoisting frame for mine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170329

Address after: 710054 School of management, Xi'an University of Science And Technology, Xi'an, Yanta Road, Shaanxi, China

Applicant after: Xi'an University of Science and Technology

Address before: 710054 School of management, Xi'an University of Science And Technology, Xi'an, Yanta Road, Shaanxi, China

Applicant before: Shang Mei

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180116