CN106088602A - A kind of construction of super highrise building elevator material-receiving device - Google Patents
A kind of construction of super highrise building elevator material-receiving device Download PDFInfo
- Publication number
- CN106088602A CN106088602A CN201610582732.5A CN201610582732A CN106088602A CN 106088602 A CN106088602 A CN 106088602A CN 201610582732 A CN201610582732 A CN 201610582732A CN 106088602 A CN106088602 A CN 106088602A
- Authority
- CN
- China
- Prior art keywords
- splicing
- construction
- steelframe
- right angle
- elastic buffer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
- E04G21/30—Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Types And Forms Of Lifts (AREA)
Abstract
nullThe invention discloses a kind of construction of super highrise building elevator material-receiving device,The long right-angle side of right angle trigonometry steelframe is installed on high-rise building body of wall,The two ends of right angle trigonometry steelframe upper surface are fixedly installed elastic buffer member,The center of right angle trigonometry steelframe is fixed with rotation dish,It is installed with hydraulic jack on rotation dish,Material receiving center is installed in hydraulic jack top,When the object to be transported of elevator being carried out splicing,Hydraulic jack is retracted,The lower surface of material receiving supports and is arranged on described elastic buffer member,After object splicing waiting,Hydraulic jack rises,Material receiving is rotatable under the driving of rotating disk,The present invention arranges elastic buffer supporting body by taper retainer,Buffering effect during more preferably splicing can be improved,After being capable of splicing, object is directly transported to building,Improve convenience and the stability of splicing,Ensure that the safety of Super High splicing.
Description
Technical field
The present invention relates to a kind of construction of super highrise building elevator material-receiving device, belong to technical field of building construction.
Background technology
Along with becoming increasingly prosperous of China's capital construction, large quantities of high levels and high-rise building continue to bring out, the height of building
Degree grows with each passing day, and brings sizable difficulty to the application of building hoist.Building hoist is high-building construction construction
Middle by one of personnel or the building materials necessary equipment being transported to designated floor, provide convenience for construction.Building hoist
Safe handling, is related to progress and the quality of construction, there is also bigger potential safety hazard, it has also become engineering construction simultaneously
One of emphasis of safety manufacture supervising.
And when using elevator to carry out transporting object, need between elevator and building, arrange transportation route, mesh
Before, for common buildings high level, general employing arranges the mode of steel pipe scaffold to realize between elevator and building
Transport material.But, for high-rise building, this structure has the biggest potential safety hazard, and, setting up scaffold needs
Want substantial amounts of manpower and materials, and when splicing, for heavier rigid objects, it is easy to scaffold is produced impact
Power, causes the overall structure of scaffold to loosen, and the safety of builder in serious threat, although start at present to occur in that a kind of tool
Have a high-rise material receiving of Buffer Unit, but this structure after splicing in-convenience in use, it is difficult to realize rapidly and efficiently
Object transport, accordingly, it would be desirable to a kind of high-rise building elevator material-receiving device of design, in order to improve stationarity and the side of splicing
Just property.
Summary of the invention
The present invention is directed to existing technical problem, it is provided that a kind of construction of super highrise building elevator material-receiving device, it is therefore an objective to
After the safety of raising splicing and splicing, the convenience of transport, intends to solve the problem that prior art exists.
For achieving the above object, the present invention provides following technical scheme: a kind of construction of super highrise building elevator splicing fills
Putting, it includes right angle trigonometry steelframe, material receiving, elastic buffer member, rotation dish, hydraulic jack and locking expansion bolt,
It is characterized in that, the long right-angle side of described right angle trigonometry steelframe uses described locking expansion bolt to be fixedly installed on Super High and builds
On walling body, the two ends of the upper surface of described right angle trigonometry steelframe are fixedly installed multiple described elastic buffer member, described directly
The center of the upper surface of angle triangle steelframe is fixedly installed rotation dish, described rotation dish is fixedly installed hydraulic jack, institute
The center stating material receiving is fixedly installed on the top of described hydraulic jack, when needing to carry out the object to be transported of elevator
During splicing, described hydraulic jack is retracted, and the lower surface of described material receiving supports and is arranged on described elastic buffer member, when
After object splicing waiting, described hydraulic jack rises, and described material receiving is rotatable under the driving of rotating disk.
Further, as preferably, the hypotenuse of described right angle trigonometry steelframe welds with upper right-angle side right angle and is provided with hog frame,
It is fixedly installed auxiliary support on the construction wall of the lower section of described right angle trigonometry steelframe, hinged on described auxiliary support is provided with
Auxiliary hydraulic cylinder, the upper end thereof of described auxiliary hydraulic cylinder is arranged on the top of the hypotenuse of described right angle trigonometry steelframe, described bullet
Property Buffer Unit include tapered steel seat, rigidity retainer, elastic buffer supporting body, upper cylindrical seat and location steel bushing, wherein, described
The lower tapered end of tapered steel seat is fixed support and is arranged on the upper right-angle side of described right angle trigonometry steelframe, arranges in described tapered steel seat
Having described rigidity retainer, in the circumference of the large awl end of described rigidity retainer, array is provided with multiple groove, in each groove
Being provided with elastic buffer supporting body, the upper surface of described elastic buffer carrier exceeds the large end face of described rigidity retainer, institute
Stating and be fixedly installed location steel bushing on the lower surface of cylindrical seat, described location steel bushing is fastened in described rigidity retainer, with
Just fixing described elastic buffer supporting body, when splicing, the lower surface of described material receiving supports and is arranged on described upper cylindrical seat
Upper surface on.
Further, as preferably, described elastic buffer supporting body is elastomeric rubber bodies, and described high elastic rubber body
Inside it is provided with steel wire reinforcing mat.
Further, as preferably, on the lower surface between the upper surface of described material receiving and described elastic buffer member
It is provided with weight sensor, and described weight sensor is connected with alarm.
Further, as preferably, described material receiving is circular material receiving.
Further, as preferably, described rotation dish uses direct driving motor to drive.
Further, as preferably, the quantity of the groove on described rigidity retainer is 8-16.
Further, as preferably, present invention additionally comprises video monitoring module, described video monitoring module be arranged on described in connect
The top of material platform, in order to splicing process is monitored management.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention arranges elastic buffer supporting body by taper retainer, it is possible to increase more preferably buffering effect during splicing,
Meanwhile, rotation dish and hydraulic jack it are provided with, it is possible to after realizing splicing, object is directly transported to building, improve
The convenience of splicing and stability, it is ensured that the safety of Super High splicing, and, it is also provided with weight sensor and video prison
Control module, it is achieved that the real-time monitoring to splicing process, the safety further ensuring construction of super highrise building is carried out.
Accompanying drawing explanation
Fig. 1 is the structural representation of a kind of construction of super highrise building elevator material-receiving device of the present invention;
Fig. 2 is the structural representation of the elastic buffer member of a kind of construction of super highrise building elevator material-receiving device of the present invention;
Wherein, 1, high-rise building body of wall, 2, locking expansion bolt, 3, auxiliary support, 4, auxiliary hydraulic cylinder, 5, hog frame, 6,
Right angle trigonometry steelframe, 7, material receiving, 8, elastic buffer member, 9, hydraulic jack, 10, tapered steel seat, 11, rigidity keeps
Frame, 12, elastic buffer supporting body, 13, upper cylindrical seat, 14, location steel bushing, 15, rotation dish.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise
Embodiment, broadly falls into the scope of protection of the invention.
Referring to Fig. 1-2, the present invention provides a kind of technical scheme: a kind of construction of super highrise building elevator material-receiving device,
It includes right angle trigonometry steelframe 6, material receiving 7, elastic buffer member, rotation dish 15, hydraulic jack 9 and locking expansion bolt
2, it is characterised in that the long right-angle side of described right angle trigonometry steelframe 6 uses described locking expansion bolt 2 to be fixedly installed on superelevation
On layer construction wall 1, the two ends of the upper surface of described right angle trigonometry steelframe 6 are fixedly installed multiple described elastic buffer member,
The center of the upper surface of described right angle trigonometry steelframe 6 is fixedly installed rotation dish 15, and described rotation dish 15 is fixedly installed liquid
Pressure jack 9, the center of described material receiving 7 is fixedly installed on the top of described hydraulic jack, when needing elevator
When object to be transported carries out splicing, described hydraulic jack is retracted, and the lower surface of described material receiving supports and is arranged on described bullet
Property Buffer Unit on, after object splicing waiting, described hydraulic jack rises, and described material receiving is at rotating disk
Drive lower rotatable.
In the present embodiment, the hypotenuse of described right angle trigonometry steelframe welds with upper right-angle side right angle and is provided with hog frame 5, institute
Auxiliary support 3, hinged setting on described auxiliary support 3 it is fixedly installed on the construction wall of the lower section stating right angle trigonometry steelframe 6
Auxiliary hydraulic cylinder 4, the upper end thereof of described auxiliary hydraulic cylinder 4 is had to be arranged on the top of the hypotenuse of described right angle trigonometry steelframe 6, institute
State elastic buffer member and include tapered steel seat 10, rigidity retainer 11, elastic buffer supporting body 12, upper cylindrical seat 13 and location steel
Set 14, wherein, the lower tapered end of described tapered steel seat 10 is fixed support and is arranged on the upper right-angle side of described right angle trigonometry steelframe, institute
Being provided with described rigidity retainer 11 in stating tapered steel seat 10, in the circumference of the large awl end of described rigidity retainer 11, array is arranged
Having multiple groove, be provided with elastic buffer supporting body 12 in each groove, the upper surface of described elastic buffer carrier 12 exceeds
The large end face of described rigidity retainer 11, the lower surface of described upper cylindrical seat 13 is fixedly installed location steel bushing 14, described fixed
Position steel bushing 14 be fastened in described rigidity retainer 11, in order to fix described elastic buffer supporting body 12, when splicing, described in connect
The lower surface of material platform supports and is arranged on the upper surface of described upper cylindrical seat.
Wherein, in order to improve the bearing capacity of elastic caching supporting body, described elastic buffer supporting body is elastomeric rubber
It is provided with steel wire reinforcing mat in body, and described high elastic rubber body.Described material receiving and the upper table of described elastic buffer member
It is provided with weight sensor on lower surface between face, and described weight sensor is connected with alarm.Described material receiving is
Circular material receiving.In order to reduce the volume of rotation dish, improving rotating torque, described rotation dish uses direct driving motor to drive.Institute
The quantity stating the groove on rigidity retainer is 8-16.
Additionally, in order to carry out complete monitoring, improve the safety of construction, present invention additionally comprises video monitoring module, described
Video monitoring module is arranged on the top of described material receiving, in order to splicing process is monitored management.
The present invention arranges elastic buffer supporting body by taper retainer, it is possible to increase more preferably buffering effect during splicing
Really, meanwhile, rotation dish and hydraulic jack it are provided with, it is possible to after realizing splicing, object is directly transported to building, carry
The convenience of high splicing and stability, it is ensured that the safety of Super High splicing, and, it is also provided with weight sensor and regards
Frequently monitoring module, it is achieved that the real-time monitoring to splicing process, the safety further ensuring construction of super highrise building is carried out.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, permissible
Understand and these embodiments can be carried out multiple change without departing from the principles and spirit of the present invention, revise, replace
And modification, the scope of the present invention be defined by the appended.
Claims (8)
1. a construction of super highrise building elevator material-receiving device, it includes right angle trigonometry steelframe, material receiving, elastic buffer group
Part, rotation dish, hydraulic jack and locking expansion bolt, it is characterised in that the long right-angle side of described right angle trigonometry steelframe is adopted
Being fixedly installed on high-rise building body of wall with described locking expansion bolt, the two ends of the upper surface of described right angle trigonometry steelframe are solid
Surely being provided with multiple described elastic buffer member, the center of the upper surface of described right angle trigonometry steelframe is fixedly installed rotation dish,
Being fixedly installed hydraulic jack on described rotation dish, the center of described material receiving is fixedly installed on described hydraulic jack
Top, when needing the object to be transported of elevator is carried out splicing, described hydraulic jack is retracted, under described material receiving
Surface support is arranged on described elastic buffer member, and after object splicing waiting, described hydraulic jack rises, and
Described material receiving is rotatable under the driving of rotating disk.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described right angle
The hypotenuse of triangle steelframe welds with upper right-angle side right angle and is provided with hog frame, the construction wall of the lower section of described right angle trigonometry steelframe
On be fixedly installed auxiliary support, the hinged auxiliary hydraulic cylinder that is provided with, the upper end of described auxiliary hydraulic cylinder on described auxiliary support
The top of the hinged hypotenuse being arranged on described right angle trigonometry steelframe, described elastic buffer member includes that tapered steel seat, rigidity keep
Frame, elastic buffer supporting body, upper cylindrical seat and location steel bushing, wherein, the lower tapered end of described tapered steel seat is fixed support and is arranged on
On the upper right-angle side of described right angle trigonometry steelframe, being provided with described rigidity retainer in described tapered steel seat, described rigidity keeps
In the circumference of the large awl end of frame, array is provided with multiple groove, is provided with elastic buffer supporting body, described bullet in each groove
The upper surface of property buffer carrier exceeds the large end face of described rigidity retainer, and the lower surface of described upper cylindrical seat is fixedly installed
Location steel bushing, described location steel bushing is fastened in described rigidity retainer, in order to fixes described elastic buffer supporting body, works as splicing
Time, the lower surface of described material receiving supports and is arranged on the upper surface of described upper cylindrical seat.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 2, it is characterised in that: described elasticity
Buffering supporting body is elastomeric rubber bodies, and is provided with steel wire reinforcing mat in described high elastic rubber body.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described splicing
Weight sensor, and described weight sensor it is provided with on lower surface between the upper surface of platform and described elastic buffer member
It is connected with alarm.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described splicing
Platform is circular material receiving.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: described rotation
Dish uses direct driving motor to drive.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 2, it is characterised in that: described rigidity
The quantity of the groove on retainer is 8-16.
A kind of construction of super highrise building elevator material-receiving device the most according to claim 1, it is characterised in that: also include regarding
Frequently monitoring module, described video monitoring module is arranged on the top of described material receiving, in order to splicing process is monitored pipe
Reason.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610582732.5A CN106088602B (en) | 2016-07-23 | 2016-07-23 | A kind of construction of super highrise building lift material-receiving device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610582732.5A CN106088602B (en) | 2016-07-23 | 2016-07-23 | A kind of construction of super highrise building lift material-receiving device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106088602A true CN106088602A (en) | 2016-11-09 |
CN106088602B CN106088602B (en) | 2018-01-16 |
Family
ID=57448867
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610582732.5A Expired - Fee Related CN106088602B (en) | 2016-07-23 | 2016-07-23 | A kind of construction of super highrise building lift material-receiving device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106088602B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107269004A (en) * | 2017-07-03 | 2017-10-20 | 大连理工大学 | A kind of device and method constructed for green concrete |
CN107859339A (en) * | 2017-11-14 | 2018-03-30 | 中建三局第建设工程有限责任公司 | A kind of synchronous hoisting device and method for box beam support steel corbel |
CN107905379A (en) * | 2017-10-27 | 2018-04-13 | 中国建筑第八工程局有限公司 | Totally-enclosed layer construction method in high-rise building Core Walls Structure |
CN108840206A (en) * | 2018-09-14 | 2018-11-20 | 南通四建集团有限公司 | A kind of construction of super highrise building elevator material-receiving device |
CN108910760A (en) * | 2018-08-08 | 2018-11-30 | 北京鼎翰科技有限公司 | A kind of high-building construction elevator material-receiving device |
CN109100232A (en) * | 2018-09-06 | 2018-12-28 | 中建三局第三建设工程有限责任公司 | The experimental rig and application method of cone vertical bearing capacity are climbed for detecting bridge tower |
CN113833271A (en) * | 2021-09-06 | 2021-12-24 | 郝文涛 | A hold and hang device for construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB838244A (en) * | 1957-11-14 | 1960-06-22 | Ace Machinery Ltd | Improvements in or relating to power operated guided skip hoists |
CN104801625A (en) * | 2015-05-19 | 2015-07-29 | 中达电机股份有限公司 | Automatic material receiving device for punching machine |
CN204754248U (en) * | 2015-07-02 | 2015-11-11 | 中国建筑第八工程局有限公司 | Super high -rise building construction elevator regularization connects material platform |
CN204781975U (en) * | 2015-05-26 | 2015-11-18 | 中国建筑第八工程局有限公司 | Concrete buffering connects hopper |
CN204778237U (en) * | 2015-07-17 | 2015-11-18 | 中建八局第二建设有限公司 | Can have enough to meet need construction elevator layer door connects material platform |
-
2016
- 2016-07-23 CN CN201610582732.5A patent/CN106088602B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB838244A (en) * | 1957-11-14 | 1960-06-22 | Ace Machinery Ltd | Improvements in or relating to power operated guided skip hoists |
CN104801625A (en) * | 2015-05-19 | 2015-07-29 | 中达电机股份有限公司 | Automatic material receiving device for punching machine |
CN204781975U (en) * | 2015-05-26 | 2015-11-18 | 中国建筑第八工程局有限公司 | Concrete buffering connects hopper |
CN204754248U (en) * | 2015-07-02 | 2015-11-11 | 中国建筑第八工程局有限公司 | Super high -rise building construction elevator regularization connects material platform |
CN204778237U (en) * | 2015-07-17 | 2015-11-18 | 中建八局第二建设有限公司 | Can have enough to meet need construction elevator layer door connects material platform |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107269004A (en) * | 2017-07-03 | 2017-10-20 | 大连理工大学 | A kind of device and method constructed for green concrete |
CN107269004B (en) * | 2017-07-03 | 2019-10-22 | 大连理工大学 | A kind of device and method for green concrete construction |
CN107905379A (en) * | 2017-10-27 | 2018-04-13 | 中国建筑第八工程局有限公司 | Totally-enclosed layer construction method in high-rise building Core Walls Structure |
CN107859339A (en) * | 2017-11-14 | 2018-03-30 | 中建三局第建设工程有限责任公司 | A kind of synchronous hoisting device and method for box beam support steel corbel |
CN108910760A (en) * | 2018-08-08 | 2018-11-30 | 北京鼎翰科技有限公司 | A kind of high-building construction elevator material-receiving device |
CN109100232A (en) * | 2018-09-06 | 2018-12-28 | 中建三局第三建设工程有限责任公司 | The experimental rig and application method of cone vertical bearing capacity are climbed for detecting bridge tower |
CN109100232B (en) * | 2018-09-06 | 2023-12-05 | 中建三局第三建设工程有限责任公司 | Testing device for detecting vertical bearing capacity of climbing cone of bridge tower and using method |
CN108840206A (en) * | 2018-09-14 | 2018-11-20 | 南通四建集团有限公司 | A kind of construction of super highrise building elevator material-receiving device |
CN108840206B (en) * | 2018-09-14 | 2024-01-12 | 南通四建集团有限公司 | Material receiving device of super high-rise building construction lifter |
CN113833271A (en) * | 2021-09-06 | 2021-12-24 | 郝文涛 | A hold and hang device for construction |
Also Published As
Publication number | Publication date |
---|---|
CN106088602B (en) | 2018-01-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106088602A (en) | A kind of construction of super highrise building elevator material-receiving device | |
CN108019076B (en) | Construction method of large-diameter reinforced concrete silo and device for conical shell construction | |
CN208650862U (en) | A kind of anti-collapse suspension device of constructing tunnel | |
CN104213651B (en) | A kind of replaceable energy dissipation component of shear wall foundation and energy-dissipating structure | |
CN105971272A (en) | Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method | |
CN205000974U (en) | A tire formula automatic rising equipment rack for tunnel excavation construction | |
CN205242885U (en) | Lightweight concrete prefabricated staircase connection structure | |
CN105464217B (en) | A kind of adaptive slip rubber support and its replacing options | |
CN106368714A (en) | Tire type automatic lifting assembly rack for tunnel excavation construction | |
CN206999277U (en) | A kind of wallboard turning device | |
CN210407857U (en) | On-spot demonstration operation panel that electric power marketing was used | |
CN206693630U (en) | A kind of concreting servicing unit | |
CN214194611U (en) | High-strength foundation structure | |
CN106224645A (en) | The collector pipe structure conveniently transported and bury underground | |
CN217030199U (en) | Device for fixing pump pipe | |
CN211341789U (en) | Wall form reinforcing tool | |
CN204174938U (en) | A kind of concrete rotates carriage | |
CN211314232U (en) | Portable two lining platform trucks slant strutting arrangement | |
CN208378287U (en) | A kind of simple vertical transport equipment of architecture construction | |
CN205875410U (en) | A hang module system all for tube structure room panel construction | |
CN215593733U (en) | Building bridge reinforcing construction device | |
CN210118149U (en) | Anti-collapse supporting equipment for non-metal mine mining | |
CN206091681U (en) | Go up suspension type hanging wheel transmission | |
CN215402820U (en) | Spliced integral hoisting platform | |
CN211141359U (en) | Mechanical equipment hoisting frame for mine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20170329 Address after: 710054 School of management, Xi'an University of Science And Technology, Xi'an, Yanta Road, Shaanxi, China Applicant after: Xi'an University of Science and Technology Address before: 710054 School of management, Xi'an University of Science And Technology, Xi'an, Yanta Road, Shaanxi, China Applicant before: Shang Mei |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180116 Termination date: 20180723 |